CN205777600U - Batter post installs auxiliary support apparatus - Google Patents
Batter post installs auxiliary support apparatus Download PDFInfo
- Publication number
- CN205777600U CN205777600U CN201620603505.1U CN201620603505U CN205777600U CN 205777600 U CN205777600 U CN 205777600U CN 201620603505 U CN201620603505 U CN 201620603505U CN 205777600 U CN205777600 U CN 205777600U
- Authority
- CN
- China
- Prior art keywords
- batter post
- stay cord
- anchor ear
- support column
- fixedly connected
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The utility model discloses a kind of batter post and auxiliary support apparatus is installed, including being separately positioned on the support means on batter post top and being arranged on the stabilising arrangement of batter post bottom, described support means includes can banding anchor ear I on described batter post, the lower section being positioned at anchor ear I is provided with support column, the top of described support column is articulated and connected with described anchor ear I, and the bottom of described support column can abut on the ground;Described stabilising arrangement include can banding anchor ear II on described batter post, the left and right sides being positioned at anchor ear II is respectively arranged with stay cord, and one end of stay cord is fixedly connected on described anchor ear II, the other end of stay cord can fix connection ground on.This utility model simple in construction, easy to use, make batter post during installing, be no longer influenced by the restriction of support means, accomplish the controllability at angle of inclination, shorten construction period, improve efficiency of construction.
Description
Technical field
This utility model relates to construction support means, is specifically related to a kind of batter post and installs auxiliary support apparatus.
Background technology
At present, the configuration design of the public buildings such as large stadium is more and more unique, different modeling, its total figure modelling generally in
Existing " V " shape shape, outer loop pillar is being not to be vertically arranged simultaneously, but presents outward-dipping state, and outer dip angle is relatively big, this
Batter post structure construction and installation when, formed local overall time solid memder self often cannot be relied on to realize self-supporting
Weight, but needing, temporary support is set and has assisted.Each batter post is generally required for bracing frame and individually supports, and props up
Support was accomplished by installation before batter post lifts often and puts in place.But during bracing frame makes and sets up, be to tiltedly
The angle of inclination of post pre-sets, and is lifted on bracing frame by batter post and is supported, the finally two ends to batter post
Install.But bracing frame is in the angle of inclination of default batter post, deviation somewhat occurs, then batter post is lifted on bracing frame
After, may result in batter post two ends cannot install, it is necessary to is again adjusted the predetermined angle of batter post on bracing frame, and regulated
Journey is complicated, wastes time and energy, reduces efficiency of construction, it is impossible to meets duration demand.
Utility model content
For above-mentioned the deficiencies in the prior art, technical problem to be solved in the utility model is: how to provide the one can
Being adjusted with the angle of inclination to batter post, shorten construction period, the batter post improving efficiency of construction installs auxiliary support apparatus.
In order to solve above-mentioned technical problem, this utility model have employed following technical scheme:
A kind of batter post installs auxiliary support apparatus, it is characterised in that: include the support means being separately positioned on batter post top
Be arranged on the stabilising arrangement of batter post bottom, described support means include can banding anchor ear I on described batter post, be positioned at and embrace
The lower section of hoop I is provided with support column, and the top of described support column is articulated and connected with described anchor ear I, and the bottom of described support column can
Abut on the ground;Described stabilising arrangement include can banding anchor ear II on described batter post, be positioned at the left and right two of anchor ear II
Side is respectively arranged with stay cord, and one end of stay cord is fixedly connected on described anchor ear II, and the other end of stay cord can be fixedly connected on
On ground.
In this utility model, support means and stabilising arrangement, before lifting, are the most first arranged on tiltedly by batter post
On post, it is utilized respectively anchor ear I and anchor ear II banding on batter post.Then with crane by batter post, support means and stabilising arrangement
Together slinging, utilize crane, first vertical so pass through the hinge on anchor ear I on the ground by vertical for support column, batter post can be
The top of support column relatively rotates, and makes support column while supporting batter post, additionally it is possible to adjust the angle of inclination of batter post
Joint, meets the angle of inclination of batter post.Additionally the left and right directions of batter post can be carried out by two stay cords in stabilising arrangement respectively
It is strained and fixed, enables the two ends of batter post to be directed at corresponding installation position, finally install.Thus it is no longer influenced by supporting
The restriction of device, can be adjusted the angle of inclination of batter post, shorten construction period, improve efficiency of construction.
As optimization, the bottom thread of described support column is combined with length adjustment device, and described length adjustment device includes
Base, the top of base is provided with threaded post along its axial direction, and the left and right sides of base is respectively fixedly connected with is easy to gripping
Handle, the bottom of described support column is provided with along its axis direction can be with the screwed hole of described threaded post threaded engagement.Because
Support arrangement is before batter post lifts, and is fixed on the ground on batter post, then get up with support means handling at batter post
After, it is possible to occurring that support column length is too short, batter post cannot turn to the situation at corresponding angle of inclination, if again by batter post and
Support means is placed and is readjusted installation site on ground, will result in the prolongation of construction period.It is positioned at support column bottom thread
The base coordinated, it is possible to whole bearing height is lowered in the rotation in screwed hole and threaded post, it is not necessary to readjust support again
The installation site of device, the engineering time of shortening, improves efficiency of construction.
As optimization, the bottom of described base is fixedly connected with the base plate being horizontally disposed with and being coaxially disposed with described base,
The bottom surface of described base plate is bonded with one layer of rubber blanket.It is more stable that horizontally disposed base plate can make support column place on bottom surface,
And then make the batter post being articulated and connected with support column more stable, preferably it is directed at corresponding installation position.Additionally base plate bottom surface
Rubber blanket can provide bigger frictional force, it is to avoid support column is shifted over during supporting.
As optimization, described stabilising arrangement also includes the stay cord elevator dress being respectively fixedly connected with in anchor ear II left and right sides
Putting, one end of described stay cord is fixedly connected on described stay cord winding plant, and described stay cord winding plant can be to described stay cord
Carrying out rolling, described stay cord winding plant is additionally provided with can the elevator locking system of stay cord winding plant described in locking.?
In the case of not using, utilize stay cord winding plant by stay cord rolling, and when in use, it is also possible to make according to scene
By situation, pulling out the stay cord of different length, and utilize elevator locking system that stay cord winding plant is carried out locking, fixed pulling rope draws
Go out length, to adapt to different fixing points.
In sum, the beneficial effects of the utility model are: this utility model simple in construction, easy to use, make batter post
During installing, it is no longer influenced by the restriction of support means, accomplishes the controllability at angle of inclination, shorten construction period,
Improve efficiency of construction.
Accompanying drawing explanation
In order to make the purpose of utility model, technical scheme and advantage clearer, new to this practicality below in conjunction with accompanying drawing
Type is described in further detail, wherein:
Fig. 1 is structural representation of the present utility model;
Fig. 2 is for scheming wherein enlarged diagram at A.
Detailed description of the invention
The utility model is described in further detail below in conjunction with the accompanying drawings.
As depicted in figs. 1 and 2, the batter post in this detailed description of the invention installs auxiliary support apparatus, including being separately positioned on
The support means on batter post 1 top and be arranged on the stabilising arrangement of batter post 1 bottom, described support means include can banding described
Anchor ear I 2 on batter post 1, the lower section being positioned at anchor ear I 2 is provided with support column 3, and the top of described support column 3 is hinged with described anchor ear I 2
Connecting, the bottom of described support column 3 can abut on the ground;Described stabilising arrangement include can banding on described batter post 1
Anchor ear II 4, the left and right sides being positioned at anchor ear II 4 is respectively arranged with stay cord 5, and one end of stay cord 5 is fixedly connected on described anchor ear
On II 4, the other end of stay cord 5 can be fixedly connected on ground.
In this detailed description of the invention, the bottom thread of described support column 3 is combined with length adjustment device, described length adjustment
Device includes base 6, and the top of base 6 is provided with threaded post 11 along its axial direction, and the left and right sides of base 6 is respectively fixedly connected with
Having the handle 7 being easy to grip, the bottom of described support column 3 is provided with along its axis direction can be with described threaded post 11 threaded engagement
Screwed hole.
In this detailed description of the invention, the bottom of described base 6 is fixedly connected with and is horizontally disposed with and coaxially sets with described base 6
The base plate 8 put, the bottom surface of described base plate 8 is bonded with one layer of rubber blanket.
In this detailed description of the invention, described stabilising arrangement also includes being respectively fixedly connected with drawing in anchor ear II 4 left and right sides
Rope winding plant 9, one end of described stay cord 5 is fixedly connected on described stay cord winding plant 9, described stay cord winding plant 9 energy
Enough described stay cord 5 being carried out rolling, described stay cord winding plant 9 is additionally provided with can stay cord winding plant 9 described in locking
Elevator locking system.
During being embodied as, the end of described stay cord 5 is fixedly connected with clamping head 10, and clamping head 10 can facilitate
Quickly object is gripped, and then the left and right directions of batter post is fixed.
Finally illustrate, above example only in order to the technical solution of the utility model to be described and unrestricted, although logical
Cross and this utility model is described with reference to preferred embodiment of the present utility model, but those of ordinary skill in the art
Should be appreciated that and in the form and details it can be made various change, without departing from appended claims institute
The spirit and scope of the present utility model limited.
Claims (4)
1. a batter post installs auxiliary support apparatus, it is characterised in that: the support means that includes being separately positioned on batter post top and
Be arranged on the stabilising arrangement of batter post bottom, described support means include can banding anchor ear I on described batter post, be positioned at anchor ear
The lower section of I is provided with support column, and the top of described support column is articulated and connected with described anchor ear I, and the bottom of described support column can be supported
Connect on the ground;Described stabilising arrangement include can banding anchor ear II on described batter post, be positioned at the left and right sides of anchor ear II
Being respectively arranged with stay cord, one end of stay cord is fixedly connected on described anchor ear II, and the other end of stay cord can be fixedly connected on ground
On face.
Batter post the most according to claim 1 installs auxiliary support apparatus, it is characterised in that: the bottom thread of described support column
Being combined with length adjustment device, described length adjustment device includes base, and the top of base is provided with threaded post along its axial direction,
The left and right sides of base is respectively fixedly connected with the handle being easy to grip, and the bottom of described support column is provided with energy along its axis direction
Enough screwed holes with described threaded post threaded engagement.
Batter post the most according to claim 2 installs auxiliary support apparatus, it is characterised in that: the bottom of described base is fixing even
Being connected to the base plate being horizontally disposed with and being coaxially disposed with described base, the bottom surface of described base plate is bonded with one layer of rubber blanket.
Batter post the most according to claim 1 installs auxiliary support apparatus, it is characterised in that: described stabilising arrangement also includes point
Not being fixedly connected on the stay cord winding plant of anchor ear II left and right sides, one end of described stay cord is fixedly connected on described stay cord elevator
On device, described stay cord winding plant can carry out rolling to described stay cord, and described stay cord winding plant is additionally provided with can
The elevator locking system of stay cord winding plant described in locking.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620603505.1U CN205777600U (en) | 2016-06-20 | 2016-06-20 | Batter post installs auxiliary support apparatus |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620603505.1U CN205777600U (en) | 2016-06-20 | 2016-06-20 | Batter post installs auxiliary support apparatus |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205777600U true CN205777600U (en) | 2016-12-07 |
Family
ID=58132802
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620603505.1U Active CN205777600U (en) | 2016-06-20 | 2016-06-20 | Batter post installs auxiliary support apparatus |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205777600U (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108708557A (en) * | 2018-06-25 | 2018-10-26 | 中铁第四勘察设计院集团有限公司 | Movable inclined column installation equipment and method |
CN109356362A (en) * | 2018-11-13 | 2019-02-19 | 中冶建工集团有限公司 | Ash cake assists tools and the method using the tool making ash cake |
CN111519753A (en) * | 2020-05-06 | 2020-08-11 | 无锡锡晟建设有限公司 | Steel hoop supporting device for cast-in-situ reinforced concrete inclined cylinder |
CN113123606A (en) * | 2021-03-30 | 2021-07-16 | 中国建筑第八工程局有限公司 | Auxiliary supporting device for installing inclined column and construction method thereof |
CN116122602A (en) * | 2023-04-07 | 2023-05-16 | 北京城建集团有限责任公司 | V-shaped column auxiliary debugging and installing system and using method |
-
2016
- 2016-06-20 CN CN201620603505.1U patent/CN205777600U/en active Active
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108708557A (en) * | 2018-06-25 | 2018-10-26 | 中铁第四勘察设计院集团有限公司 | Movable inclined column installation equipment and method |
CN109356362A (en) * | 2018-11-13 | 2019-02-19 | 中冶建工集团有限公司 | Ash cake assists tools and the method using the tool making ash cake |
CN111519753A (en) * | 2020-05-06 | 2020-08-11 | 无锡锡晟建设有限公司 | Steel hoop supporting device for cast-in-situ reinforced concrete inclined cylinder |
CN113123606A (en) * | 2021-03-30 | 2021-07-16 | 中国建筑第八工程局有限公司 | Auxiliary supporting device for installing inclined column and construction method thereof |
CN116122602A (en) * | 2023-04-07 | 2023-05-16 | 北京城建集团有限责任公司 | V-shaped column auxiliary debugging and installing system and using method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205777600U (en) | Batter post installs auxiliary support apparatus | |
CN102359303B (en) | Extra-high voltage common circuit iron tower assembling method | |
CN208122265U (en) | A kind of external wall construction nacelle device | |
CN102425261B (en) | Large-span multiunit tensile membrane structure and installation construction method thereof | |
WO2020052291A1 (en) | Construction elevator wall-attaching frame mounting platform attached to steel platform formwork and method therefor | |
CN105421859A (en) | Electricity grid telegraph pole erecting device and construction method | |
CN109231023B (en) | Method for installing jib system of portal crane | |
CN103321416A (en) | Construction method for prestress of cable-stayed grid structure | |
CN208899886U (en) | Cantilever frame platform | |
CN107091008A (en) | A kind of adhesion type is from lifting pole | |
CN109826082B (en) | Construction method for installing decorative structure in multi-tower combined space of cable-stayed bridge | |
CN106865422A (en) | A kind of folded truss arm hanging device for installing maintenance of wind powered generator group | |
CN102493664A (en) | Non-bracket cable truss construction method for lifting entire body by obliquely drawing fixed jack | |
CN210316791U (en) | Ground-inserting telescopic pillar for travelling tent | |
CN202689517U (en) | Suspension type electric hanging basket support frame | |
CN203255914U (en) | Unit-typed curtain wall lifting device | |
CN107165269A (en) | A kind of method that use hanger structure installs high-altitude bolt-ball net frame | |
CN105819352A (en) | Detachable lifting device for door-like mast building and construction method of lifting device | |
CN115467505A (en) | Climbing system for overhead layer climbing frame | |
CN210393401U (en) | Hoisting and positioning device for stand column | |
CN112127616A (en) | Lifting climbing frame | |
CN103510742B (en) | Multifunctional rotary derrick | |
CN108518119B (en) | Portable power transmission pole maintenance tool and construction method | |
CN205973671U (en) | Hanging flower basket linkage | |
CN219771528U (en) | Wind power tower crane equipment with wind-resistant structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |