CN206385423U - Roadbed band synthesis is drawn, led, arranging, the structure for the facility that intercepts water - Google Patents

Roadbed band synthesis is drawn, led, arranging, the structure for the facility that intercepts water Download PDF

Info

Publication number
CN206385423U
CN206385423U CN201621267001.3U CN201621267001U CN206385423U CN 206385423 U CN206385423 U CN 206385423U CN 201621267001 U CN201621267001 U CN 201621267001U CN 206385423 U CN206385423 U CN 206385423U
Authority
CN
China
Prior art keywords
water
slope
metalling
arranging
infiltration
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621267001.3U
Other languages
Chinese (zh)
Inventor
刘东元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Engineering Co Ltd
Original Assignee
CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Co Ltd filed Critical CCCC First Highway Engineering Co Ltd
Priority to CN201621267001.3U priority Critical patent/CN206385423U/en
Application granted granted Critical
Publication of CN206385423U publication Critical patent/CN206385423U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Road Paving Structures (AREA)

Abstract

Roadbed band synthesis is drawn, led, arranging, the structure for the facility that intercepts water, and belongs to technical field of road construction.The structure includes infiltration slope, drainage blanket, slope of intercepting water, osculum, ponding ditch, particle size metalling, thin footpath metalling, soakaway trench, block water wall;Drainage blanket is horizontal structure, drainage blanket connection infiltration slope and slope of intercepting water;The centre of drainage blanket is provided with the osculum arranged vertically, and the bottom of osculum is connected with ponding ditch.The wall that blocks water is arranged on the bottom of slope portion that intercepts water, and the bottom on infiltration slope is disposed with particle size metalling, thin footpath metalling, soakaway trench, and soakaway trench is connected with ponding ditch.Infiltration slope, drainage blanket, the slope composition that intercepts water draw, led, arranging structure and effectively can absorb the surface water on road rapidly and drain into ponding ditch and export, in order to avoid cause surface gathered water and influence traffic safety, the wall that blocks water can be effectively blocked influence of the underground water to discharge structure, ensure the safety of road.

Description

Roadbed band synthesis is drawn, led, arranging, the structure for the facility that intercepts water
Technical field
The utility model is related to a kind of for rich in water, the pumping equipment of the roadbed band structure of sand, belonging to road construction skill Art field.
Background technology
For some special road sections of road construction, such as hairpin curve, geology be bad or high embankment etc., reply roadbed row Water system carries out integrated planning, comprehensive Design.The local irrigation projects for the treatment of are one of subgrade drainage comprehensive Design important Principle.For that purpose it is necessary to irrigation and drainage present situation and its planning intention first found out near roadbed, so as to while roadbed water damage is taken precautions against, Local water conservancy projects will not be damaged.In comprehensive Design, for the discharge of the surface water, set using drainings such as gutter, intercepting ditch It is standby, the hillside water and road bed moisture section that flow to roadbed are retained, nature cheuch, wasteland, ditch or low-lying land, row is introduced Go out outside roadbed scope.To especially gentle location, the drainage equipment such as nature cheuch and irrigation canals and ditches and culvert are made full use of, both closely Coordinate again each the division of labor, play its effectiveness, reach that draining is smooth, it is to avoid cause to wash away roadbed, will not be formed again alluvial and Endanger roadbed.
Processing to underground water, should consider with the discharge unification of the surface water, suit measures to local conditions, set necessary subdrainage to set (such as french drain) is applied, subdrainage irrigation canals and ditches are made full use of, the seepage in underground for jeopardizing roadbed is excluded with spring.
Drainage system comprehensive Design, answers the various discharge structure types of reasonable selection and position, appropriately determines drain function.This Outside, the linking of various drainage equipment should be also kept a close eye on, is allowed to constitute unified complete drainage system.For example, setting bridges and culverts When, its position, aperture, flowing water absolute altitude etc., the need for subgrade drainage should be able to being met.
Utility model content
The purpose of this utility model be to propose a kind of roadbed band integrate draw, lead, arranging, the structure for the facility that intercepts water, it is above-mentioned Structure adaptation comprehensive utilization diversion, water guide, draining, is cut in the special road section high containing sand, rich water, level of ground water of road construction The mode of water, effective and reasonable control is carried out by the water of roadbed band.
The technical solution adopted in the utility model is drawn, led, arranging for roadbed band synthesis, the structure for the facility that intercepts water, the structure bag Include infiltration slope 2, drainage blanket 3, slope 4 of intercepting water, osculum 5, ponding ditch 6, particle size metalling 7, thin footpath metalling 8, soakaway trench 9, Block water wall 10;Roadbed band synthesis is drawn, led, arranging, the structure setting for the facility that intercepts water is in the both sides of road 1;Seep water slope 2 and road 1 side connection, the angle of inclination on infiltration slope 2 is 10 ° -35 °.
Drainage blanket 3 is horizontal structure, the connection of drainage blanket 3 infiltration slope 2 and slope 4 of intercepting water;The centre of drainage blanket 3 is provided with vertical The osculum 5 of arrangement, the bottom of osculum 5 is connected with ponding ditch 6.
The intercept water angle of inclination on slope 4 is 10 ° -35 °, and the wall 10 that blocks water is arranged on the bottom of slope 4 of intercepting water, the bottom on slope 2 of seeping water Particle size metalling 7, thin footpath metalling 8, soakaway trench 9 are disposed with, soakaway trench 9 is connected with ponding ditch 6.
The surface on infiltration slope 2 is grass planting layer, and drainage blanket 3, slope 4 of intercepting water are plain concrete stone masonry construction.
The particle size metalling 7, thin footpath metalling 8, the oblique gradient of soakaway trench 9 and the angle of inclination phase on slope 2 of seeping water Deng.
The particle diameter of the particle size metalling 7 is 26.5mm-31.5mm.
The particle diameter of the thin footpath metalling 8 is 19mm-26.5mm.
Compared with prior art, the utility model has the advantages that.
1st, infiltration slope, drainage blanket, intercept water slope composition draw, lead, arrange structure can be effectively by the surface water on road Absorb rapidly and drain into ponding ditch and export, in order to avoid cause surface gathered water and influence traffic safety.
2nd, for the higher location of rich water and level of ground water, the wall that blocks water can be effectively blocked underground water to discharge structure Influence, ensures the safety of road.
3rd, the filtration and infiltration layer of particle size metalling, thin footpath metalling, soakaway trench composition, can be effectively to the ground on road Table water carries out layered filtration, absorption, excluded, it is ensured that the resistance to overturning of roadbed band.
Brief description of the drawings
Fig. 1 is structure chart of the present utility model.
In figure:1st, road, 2, infiltration slope, 3, drainage blanket, 4, slope of intercepting water, 5, osculum, 6, ponding ditch, 7, particle size rubble Layer, 8, thin footpath metalling, 9, soakaway trench, 10, block water wall.
Embodiment
As shown in figure 1, the structure of road 1 is:Grain formula bituminous concrete in 4cm;Cutting optimal:Grain formula pitch coagulation in 6cm Soil;Basic unit:10cm high-modulus asphalt rubbles.
Original structure is on the basis of owner requires, with reference to the design flow of AA high speed connecting lines, with reference to AA high speeds Selected by the construction experience on road.The design of difficult topical location subgrade drainage, it is necessary to difference situation, suits measures to local conditions.
Roadbed band synthesis is drawn, led, arranging, the structure for the facility that intercepts water, and the structure includes infiltration slope 2, drainage blanket 3, slope of intercepting water 4th, osculum 5, ponding ditch 6, particle size metalling 7, thin footpath metalling 8, soakaway trench 9, block water wall 10;The roadbed band integrate draw, lead, Arrange, the structure setting for the facility that intercepts water is in the both sides of road 1;Infiltration slope 2 is connected with the side of road 1, the inclination on slope 2 of seeping water Angle is 10 ° -35 °.
Drainage blanket 3 is horizontal structure, the connection of drainage blanket 3 infiltration slope 2 and slope 4 of intercepting water;The centre of drainage blanket 3 is provided with vertical The osculum 5 of arrangement, the bottom of osculum 5 is connected with ponding ditch 6.
The intercept water angle of inclination on slope 4 is 10 ° -35 °, and the wall 10 that blocks water is arranged on the bottom of slope 4 of intercepting water, the bottom on slope 2 of seeping water Portion is disposed with particle size metalling 7, thin footpath metalling 8, soakaway trench 9, and soakaway trench 9 is connected with ponding ditch 6.
The particle size metalling 7, thin footpath metalling 8, the oblique gradient of soakaway trench 9 and the angle of inclination phase on slope 2 of seeping water Deng.
The particle diameter of the particle size metalling 7 is 26.5mm-31.5mm.
The particle diameter of the thin footpath metalling 8 is 19mm-26.5mm.
Infiltration slope, drainage blanket, intercept water slope composition draw, lead, arrange structure can be effectively fast by the surface water on road Speed absorbs and drains into ponding ditch and export, in order to avoid cause surface gathered water and influence traffic safety.
For the higher location of rich water and level of ground water, the wall that blocks water can be effectively blocked shadow of the underground water to discharge structure Ring, ensure the safety of road.
Particle size metalling, thin footpath metalling, the filtration and infiltration layer of soakaway trench composition, can be effectively to the earth's surface on road Water carries out layered filtration, absorption, excluded, it is ensured that the resistance to overturning of roadbed band.

Claims (5)

1. roadbed band synthesis is drawn, led, arranging, the structure for the facility that intercepts water, it is characterised in that:The structure includes infiltration slope (2), draining Layer (3), slope of intercepting water (4), osculum (5), ponding ditch (6), particle size metalling (7), thin footpath metalling (8), soakaway trench (9), resistance Waterwall (10);The roadbed band integrate draw, lead, arranging, the structure setting of the facility that intercepts water road (1) both sides;Seep water slope (2) with The side connection of road (1), the angle of inclination of infiltration slope (2) is 10 ° -35 °;
Drainage blanket (3) is horizontal structure, drainage blanket (3) connection infiltration slope (2) and slope (4) of intercepting water;The centre of drainage blanket (3) is set There is the osculum (5) arranged vertically, the bottom of osculum (5) is connected with ponding ditch (6);
The intercept water angle of inclination on slope (4) is 10 ° -35 °, and the wall that blocks water (10) is arranged on slope of intercepting water (4) bottom, infiltration slope (2) Bottom is disposed with particle size metalling (7), thin footpath metalling (8), soakaway trench (9), and soakaway trench (9) is connected with ponding ditch (6) Connect.
2. roadbed band synthesis according to claim 1 is drawn, led, arranging, the structure for the facility that intercepts water, it is characterised in that:Infiltration is oblique The surface on slope (2) is grass planting layer, and drainage blanket (3), slope of intercepting water (4) are plain concrete stone masonry construction.
3. roadbed band synthesis according to claim 1 is drawn, led, arranging, the structure for the facility that intercepts water, it is characterised in that:It is described thick Footpath metalling (7), thin footpath metalling (8), the oblique gradient of soakaway trench (9) are equal with the angle of inclination of infiltration slope (2).
4. roadbed band synthesis according to claim 1 is drawn, led, arranging, the structure for the facility that intercepts water, it is characterised in that:It is described thick The particle diameter of footpath metalling (7) is 26.5mm-31.5mm.
5. roadbed band synthesis according to claim 1 is drawn, led, arranging, the structure for the facility that intercepts water, it is characterised in that:It is described thin The particle diameter of footpath metalling (8) is 19mm-26.5mm.
CN201621267001.3U 2016-11-24 2016-11-24 Roadbed band synthesis is drawn, led, arranging, the structure for the facility that intercepts water Expired - Fee Related CN206385423U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621267001.3U CN206385423U (en) 2016-11-24 2016-11-24 Roadbed band synthesis is drawn, led, arranging, the structure for the facility that intercepts water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621267001.3U CN206385423U (en) 2016-11-24 2016-11-24 Roadbed band synthesis is drawn, led, arranging, the structure for the facility that intercepts water

Publications (1)

Publication Number Publication Date
CN206385423U true CN206385423U (en) 2017-08-08

Family

ID=59486043

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621267001.3U Expired - Fee Related CN206385423U (en) 2016-11-24 2016-11-24 Roadbed band synthesis is drawn, led, arranging, the structure for the facility that intercepts water

Country Status (1)

Country Link
CN (1) CN206385423U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111021504A (en) * 2019-12-31 2020-04-17 深圳市华域环保科技有限公司 Drainage system in district is deposited to grit

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111021504A (en) * 2019-12-31 2020-04-17 深圳市华域环保科技有限公司 Drainage system in district is deposited to grit

Similar Documents

Publication Publication Date Title
CN106759825B (en) Construction method of sponge urban green land water storage system
CN210887246U (en) Roadbed slope protection structure
CN107989051B (en) Ecological slope protection system with combination of grid slope protection, sand well water seepage and water guide slope
CN106818164A (en) A kind of salt-soda soil arbor implantation methods
CN203613515U (en) LID (Low Impact Development)-type rainwater ditch
CN106193245B (en) A kind of paddy field underground reservoir and its construction method for sponge city
CN102383408B (en) Greening method for high water level impermeable saline and alkaline lands and greening system
CN207582619U (en) A kind of Rain Garden based on sponge city
CN206616662U (en) A kind of residential quarter sponge urban facilities system
CN206385423U (en) Roadbed band synthesis is drawn, led, arranging, the structure for the facility that intercepts water
CN102726141A (en) Saline-alkali soil improvement facility and method
CN211143522U (en) Planting roofing convenient to drainage and irrigation
CN104818734B (en) Control completely decomposed granite side slope damage by water waterproof and water drainage system and construction method thereof
CN216195256U (en) Ecological evaporation overflow tank
CN207739092U (en) Landscape ecology Pavement Construction
CN202679934U (en) Saline-alkali soil improvement facility
CN207228080U (en) Irrigation and drainage integrated channel
CN206903094U (en) A kind of garden landscape step
CN206034603U (en) Airport height fill construction three -dimensional drainage system
CN208981309U (en) A kind of punched-type protecting film runoff interception structure
CN209482083U (en) A kind of assembled gap porous pavement with rain water collecting system
CN203625739U (en) Embankment made of red sandstone filler
CN105544464B (en) A kind of clear beach material fill construction method of mountain area middle and small river
CN205954437U (en) Permeable pavement system that combines sponge city theory
CN108797700A (en) A kind of rain water collecting system and construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 100024 Beijing, Guanzhuang, Chaoyang District, Zhou

Patentee after: CHINA FIRST HIGHWAY ENGINEERING Co.,Ltd.

Address before: 100024 Beijing, Guanzhuang, Chaoyang District, Zhou

Patentee before: CCCC FIRST HIGHWAY ENGINEERING Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170808

Termination date: 20211124