- CN206376514U CN206376514U CN201720012280.7U CN201720012280U CN206376514U CN 206376514 U CN206376514 U CN 206376514U CN 201720012280 U CN201720012280 U CN 201720012280U CN 206376514 U CN206376514 U CN 206376514U
- Authority
- CN
- China
- Prior art keywords
- scaffold
- vertical rod
- fixedly connected
- tool
- attached wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model provides a kind of tool climbing scaffold, including the multiple scaffold units mutually spliced;The scaffold unit includes:Attached wall supported rod erecting part, the attached wall supported rod erecting part is provided with attached wall slide rail;Multilayer scaffold board, is fixed on the attached wall supported rod erecting part, and the scaffold board has the splice ends mutually spliced with the adjacent scaffold unit.The utility model, which solves traditional scaffold, to carry out scene using steel tube fastener and sets up, and wastes time and energy, Mechanization Level is low, and quality control differs, the problem of higher to the skill set requirements of setting up workman.
Description
Technical field
The utility model is related to a kind of construction aid, and in particular to a kind of tool climbing scaffold.
Background technology
Scaffold is job site for operative and solves vertically and horizontally to transport the various supports set up;Common
Traditional scaffold is set up using the steel tube fastener scene of carrying out, the scaffold that this steel tube fastener is set up not only time-consuming expense
Power, Mechanization Level is low, and quality control differs, higher to the skill set requirements of setting up workman.As China largely modernizes
The appearance of heavy construction system, the need for fastener type steel pipe scaffold has not adapted to construction development, Devoting Major Efforts To Developing and is pushed away
Wide application new type scaffold is the task of top priority, particularly the outer protection coherent-wall scaffolding of high-rise and high-rise building.
Utility model content
To overcome the defect present in prior art, a kind of tool climbing scaffold is now provided, to solve traditional pin
Hand cradle carries out scene using steel tube fastener and set up, and wastes time and energy, Mechanization Level is low, and quality control differs, to setting up work
The problems such as skill set requirements of people are higher.
To achieve the above object there is provided a kind of tool climbing scaffold, including the multiple scaffold units mutually spliced;
The scaffold unit includes:
Attached wall supported rod erecting part, the attached wall supported rod erecting part is provided with attached wall slide rail;
Multilayer scaffold board, is fixed on the attached wall supported rod erecting part, and the scaffold board has and the adjacent pin hand
The splice ends that frame unit mutually splices.
Further, the attached wall supported rod erecting part includes the first vertical rod and the second vertical rod;The tool climbs pin hand
Frame is installed on external wall, and first vertical rod is located at the one of the close external wall of the tool climbing scaffold
Side, second vertical rod is located at the side of the remote external wall of the tool climbing scaffold, pin hand described in multilayer
Plate is connected between first vertical rod and second vertical rod.
Further, wall-attached supporting seat is installed, the attached wall slide rail is installed on the wall-attached supporting seat on the external wall
On.
Further, the scaffold unit also includes the first protective net frame, and first protective net frame is fixedly connected on
Between two pieces of adjacent scaffold boards and fit in second vertical rod.
Further, first protective net frame includes:Support body is protected, the protection support body is fixedly connected by connector
In the scaffold board;And the safety net on the protection support body.
Further, the connector includes:First fixed plate, is fixedly connected on the scaffold board;Second fixed plate, Gu
Surely the protection support body is connected to, first fixed plate is fixedly connected with second fixed plate;And floor of putting more energy into, connection
Between first fixed plate and second fixed plate.
Further, the scaffold unit also includes strengthening frame, and the strengthening frame is fixedly connected on first vertical rod,
The strengthening frame has the splicing side mutually spliced with the adjacent scaffold unit.
Further, the strengthening frame is truss-like strengthening frame.
Further, the scaffold unit also includes the triangle being connected between first vertical rod and the scaffold board
Support.
Further, the trivet includes:
First strut, is fixedly connected on first vertical rod;
Second strut, is fixedly connected on the bottom of the scaffold board;And
Hound, the hound skewed horizontal load is between first strut and second strut.
The beneficial effects of the utility model are that work can be achieved in the simple structure of tool climbing scaffold, its part
Factory's Prefabrication, and interchangeability is strong, simple installation, using reliable, and can realize the extension in multiple directions, applicability
By force.
Brief description of the drawings
Fig. 1 is the schematic diagram of the utility model tool climbing scaffold.
Fig. 2 is the schematic diagram of the scaffold unit of the utility model tool climbing scaffold.
Fig. 3 is enlarged diagram at A in Fig. 2.
Embodiment
Illustrate embodiment of the present utility model below by way of specific instantiation, those skilled in the art can be by this theory
Content disclosed by bright book understands other advantages of the present utility model and effect easily.The utility model can also be by addition
Different embodiments are embodied or practiced, and the various details in this specification can also be based on different viewpoints with answering
With, without departing from it is of the present utility model spirit under carry out various modifications or alterations.
Fig. 1 is the schematic diagram of the utility model tool climbing scaffold;Fig. 2 is that the utility model tool climbs pin hand
The schematic diagram of the scaffold unit of frame;Fig. 3 is enlarged diagram at A in Fig. 2.
Referring to figs. 1 to shown in Fig. 3, the utility model provides a kind of tool climbing scaffold, and tool climbs pin hand
Frame is installed on external wall, and tool climbing scaffold includes the multiple scaffold units 1 that can be mutually splicing together.
Scaffold unit 1 can horizontal, vertical or horizontal and Longitudinal Extension it is combined and spliced.
Scaffold unit 1 includes:Attached wall supported rod erecting part, multilayer scaffold board 13, the first protective net frame 14, trivet 15,
Second protective net frame 16, cross bar 17 and strengthening frame 18.Attached wall supported rod erecting part is provided with attached wall slide rail.Multilayer scaffold board is fixed
On attached wall supported rod erecting part, scaffold board 13 has the splice ends mutually spliced with adjacent scaffold unit.First protective net frame
14 are fixedly connected between adjacent two layers of scaffold board 13, and cross bar 17 is fixedly connected on the top of attached wall supported rod erecting part.Second
Protective net frame 16 is fixedly connected between cross bar 17 and the scaffold board 13 of top.
Attached wall supported rod erecting part includes the first vertical rod 11 and the second vertical rod 12.First vertical rod 11 is climbed pin hand positioned at tool
Frame is close to the side of external wall.Second vertical rod 12 is located at side of the tool climbing scaffold away from external wall.Two
One vertical rod 11 be arranged in parallel.First vertical rod 11 setting corresponding with the second vertical rod 12.Along the first vertical rod 11 and the second vertical rod
Multilayer scaffold board 13 is provided between 12.The level of scaffold board 13 is located between two first vertical rods 11 and two second vertical rods 12 and formed
It is available for workmen to walk and carry out the space of constructing operation.Scaffold board 13 has for being installed on the two of adjacent scaffold unit
Individual splice ends, energy implementation tool climbing scaffold is extending transversely to both sides.Two pieces of adjacent in vertical direction scaffold boards 13
Between be connected with the first protective net frame 14.Trivet 15 is provided between the bottom of scaffold board 13 and the first vertical rod 11.Cross bar 17
It is located at the top of two second vertical rods 12.The second protective net frame is fixedly connected between cross bar 17 and the scaffold board of top 13
16.First protective net frame 14, the second protective net frame 16 are fitted in the second vertical rod 12.It is additionally provided with two first vertical rods 11
Strengthening frame 18.Strengthening frame 18 has two splicing sides for being installed on adjacent scaffold unit, in tool climbing scaffold
Reinforcing in structure is carried out to two adjacent scaffold units when extending transversely, makes to connect more between two scaffold units
It is stable.
When installing tool climbing scaffold of the present utility model, the first vertical rod 11 is close to external wall.Along first
On the length direction of vertical rod 11, the first vertical rod 11 interval is opened up provided with the first mounting hole.In the length direction along the second vertical rod 12,
Second vertical rod 12 offers second mounting hole corresponding with the first mounting hole.Scaffold board 13 is horizontally arranged at the He of the first vertical rod 11
The platform walked and operated for workmen is formed between second vertical rod 12.
Scaffold board 13 includes rectangular box, the connecting rod being arranged between one group of relative short edge of rectangular box and is located at
Plate body on rectangular box.Rectangular box is made up of four cylinders with C-shaped configuration, and the cross section of cylinder is C-shaped.Cylinder can
With the lightweight material from C-type steel or channel-section steel etc, in order to lightweight.The 3rd installation is offered in the both sides of scaffold board 13
Hole.3rd mounting hole of the both sides of scaffold board 13 passes through fastener and the first mounting hole of the first vertical rod 11, the second vertical rod 12 respectively
The second mounting hole connection.
First protective net frame 14 includes protection support body and safety net.The upper and lower part of protection support body passes through connector respectively
141 are connected between two pieces of neighbouring scaffold boards 13.Connector 141 includes the first fixed plate, the second fixed plate and added
Strength floor.First fixed plate is fixedly connected on scaffold board 13;Second fixed plate is fixedly connected on protection support body, the first fixed plate with
Second fixed plate is fixedly connected, and the first fixed plate is perpendicular to the second fixed plate;Floor of putting more energy into is connected to the first fixed plate and second
Between fixed plate.Safety net is hung on protection support body.Protection support body includes the protection framework of rectangle and is located at protection framework
In M shape lever.The bottom and top of framework is protected to pass through connector 141 and two pieces of neighbouring scaffold boards 13 respectively
Connection.
Trivet 15 is located between the first vertical rod 11 and scaffold board 13.Trivet 15 include orthogonal first strut,
Second strut and hound.First strut is fixedly connected with the first vertical rod 11, and the bottom of the second strut and scaffold board 13 is fixed
Connection, hound skewed horizontal load is between the first strut and the second strut.Trivet 15 can be made using hollow square steel.First
Strut is arranged in the first vertical rod 11, and the second strut is arranged on the bottom of scaffold board 13.Trivet 15 is conducive to stable and firm
Connection between the column 11 of scaffold board 13 and first.
Cross bar 17 uses C-shaped configuration material similar to the rectangular box of scaffold board 13.Cross bar 17 is connected to two second and stood
The end of bar 12, forms more stable structure between two second vertical rods 12 made.
In order to ensure being arranged on the safety of workmen on the scaffold board 13 of top layer, in cross bar 17 and the scaffold board 13 of top layer
Between be additionally provided with the second protective net frame 16.Second protective net frame 16 is consistent with the structure of the first protective net frame 14.
In order to further strengthen the steadiness of the connection between scaffold unit 1, reinforcing is additionally provided with the first vertical rod 11
Frame 18.The length of strengthening frame 18 is identical with the length of scaffold board 13.Strengthening frame 18 is truss structure, is made of hollow square steel.
Strengthening frame 18 includes top boom, lower boom, brace and montant.Top boom and lower boom are separately mounted to two first vertical rods 11
On.Strengthening frame 18 has two relative splicing sides.Mutually splice with adjacent scaffold unit the splicing side of strengthening frame 18
Together.
Foldable drop in leaf is installed in the bottom of scaffold unit 1.Drop in leaf is hinged on the scaffold board of bottom
On 13.
In order to further improve the use scope of the utility model tool climbing scaffold, in the outside of the first vertical rod 11
Wall-attached supporting seat can be installed by being connected with attached wall slide rail, attached wall slide rail, then can combine to form a kind of attached scaffold.Further
, Lift-on/Lift-off System is equipped with this attached scaffold and then constitutes a kind of Combined type attached lifting scaffold.
In actual assembled tool climbing scaffold of the present utility model, scaffold board and reinforcing can be passed through in the horizontal
Frame, fixed Combination is into the scaffold length of needs, and the first vertical rod and the second vertical rod in single scaffold board horizontal length are according to need
Set one or two.
In vertical direction, the pin that multilayer scaffold board is combined into needs is installed by the lengthening of the first vertical rod and the second vertical rod
Hand cradle height.
The utility model tool climbing scaffold vertical height in theory is not limited, simply in actual production
When, limited by material therefor length, transport and installation, the product of limited level can only be produced.When being actually needed more levels
When can vertically connect combination at the scene.
The beneficial effects of the utility model are that work can be achieved in the simple structure of tool climbing scaffold, its part
Factory's Prefabrication, and interchangeability is strong, simple installation, using reliable, and can realize the extension in multiple directions, applicability
By force.
It should be noted that structure, ratio, size depicted in this specification institute accompanying drawings etc., only to coordinate
Content disclosed in bright book, so that those skilled in the art is understood with reading, being not limited to the utility model can implement
Qualifications, therefore do not have technical essential meaning, the modification of any structure, the change of proportionate relationship or the adjustment of size,
In the case where not influenceing the utility model effect that can be generated and the purpose that can reach, all should still it fall disclosed in the utility model
Technology contents can cover in the range of.Meanwhile, in this specification it is cited as " on ", " under ", "left", "right", " in
Between " and " one " etc. term, be merely convenient to understanding for narration, and be not used to limit the enforceable scope of the utility model, its
Relativeness is altered or modified, under without essence change technology contents, when being also considered as the enforceable category of the utility model.
The utility model is described in detail above in association with accompanying drawing embodiment, those skilled in the art can root
Many variations example is made to the utility model according to described above.Thus, some of embodiment details should not be constituted to this practicality
New restriction, the utility model regard the scope defined using appended claims as protection domain.
Claims (10)
1. a kind of tool climbing scaffold, it is characterised in that:Including the multiple scaffold units mutually spliced;The scaffold
Unit includes:
Attached wall supported rod erecting part, the attached wall supported rod erecting part is provided with attached wall slide rail;
Multilayer scaffold board, is fixed on the attached wall supported rod erecting part, and the scaffold board has and the adjacent scaffold list
The splice ends of first mutually splicing.
2. tool climbing scaffold according to claim 1, it is characterised in that:The attached wall supported rod erecting part includes the
One vertical rod and the second vertical rod;The tool climbing scaffold is installed on external wall, and first vertical rod is located at the work
The side of the close external wall of toolization climbing scaffold, second vertical rod is located at the tool climbing scaffold
Side away from the external wall, scaffold board described in multilayer is connected between first vertical rod and second vertical rod.
3. tool climbing scaffold according to claim 2, it is characterised in that:Attached wall is installed on the external wall
Bearing, the attached wall slide rail is installed on the wall-attached supporting seat.
4. tool climbing scaffold according to claim 3, it is characterised in that:The scaffold unit also includes first
Protective net frame, first protective net frame is fixedly connected between two pieces of adjacent scaffold boards and fits in described second and stands
Bar.
5. tool climbing scaffold according to claim 4, it is characterised in that first protective net frame includes:It is anti-
Retaining frame body, the protection support body is fixedly connected on the scaffold board by connector;And the peace on the protection support body
The whole network.
6. tool climbing scaffold according to claim 5, it is characterised in that the connector includes:First fixes
Plate, is fixedly connected on the scaffold board;Second fixed plate, is fixedly connected on the protection support body, first fixed plate and institute
The second fixed plate is stated to be fixedly connected;And floor of putting more energy into, it is connected between first fixed plate and second fixed plate.
7. tool climbing scaffold according to claim 2, it is characterised in that the scaffold unit also includes reinforcing
Frame, the strengthening frame is fixedly connected on first vertical rod, and the strengthening frame has mutually spells with the adjacent scaffold unit
The splicing side connect.
8. tool climbing scaffold according to claim 7, it is characterised in that the strengthening frame is reinforced for truss-like
Frame.
9. tool climbing scaffold according to claim 2, it is characterised in that the scaffold unit also includes connection
Trivet between first vertical rod and the scaffold board.
10. tool climbing scaffold according to claim 9, it is characterised in that the trivet includes:
First strut, is fixedly connected on first vertical rod;
Second strut, is fixedly connected on the bottom of the scaffold board;And
Hound, the hound skewed horizontal load is between first strut and second strut.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720012280.7U CN206376514U (en) | 2017-01-06 | 2017-01-06 | Tool climbing scaffold |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720012280.7U CN206376514U (en) | 2017-01-06 | 2017-01-06 | Tool climbing scaffold |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206376514U true CN206376514U (en) | 2017-08-04 |
Family
ID=59403392
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720012280.7U Active CN206376514U (en) | 2017-01-06 | 2017-01-06 | Tool climbing scaffold |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206376514U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110158941A (en) * | 2019-06-03 | 2019-08-23 | 李大泽 | Build aluminium alloy outrigger |
-
2017
- 2017-01-06 CN CN201720012280.7U patent/CN206376514U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110158941A (en) * | 2019-06-03 | 2019-08-23 | 李大泽 | Build aluminium alloy outrigger |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103711323B (en) | Utilize the anti-ceiling board construction method of portable tubular truss stage+module roofing | |
AU2010266835B2 (en) | A slab formwork system | |
CN204126230U (en) | Assembly scaffold unit | |
CN104674665B (en) | Large-spatial structures vestibule bridge installation method | |
CN101503908B (en) | Construction method for spacing suspension cable structural template support platform | |
CN207392716U (en) | A kind of tool-type suspension scaffold | |
CN206376514U (en) | Tool climbing scaffold | |
CN205134919U (en) | Modularization suspension type steel tubes clamps scaffold operation platform | |
CN104775606A (en) | Operation platform for prefabricated assembled residential building wall plate construction and construction method thereof | |
CN106351245A (en) | Tower crane foundation base and construction method thereof | |
CN209798542U (en) | safety construction assembled bent cap operation platform | |
CN103628692A (en) | Floor beam mounting bracket and use and construction method thereof | |
CN208184050U (en) | A kind of civilian villa liftable roof truss | |
CN207905389U (en) | Assembled is bolted reinforcing steel processing shed entirely | |
CN104195954B (en) | Overhead column erection without scaffolding platform and erection method thereof | |
CN205475706U (en) | Hanging rack system | |
CN205711695U (en) | Plate girder truss-like combinative structure construction bridge | |
CN111608377B (en) | Comprehensive construction method for building overhanging scaffold | |
CN204850517U (en) | System of pounding is prevented to spelling formula height -adjustable steel construction | |
CN207993340U (en) | Dismantled and assembled single storey industry workshop teaching mode | |
CN105464218B (en) | One kind landing truss bearing pin connecting joint structure | |
CN214785737U (en) | Scaffold for building | |
CN215007207U (en) | Assembled stair teaching aid is used in teaching | |
CN204531215U (en) | For the mobile truss of Standard Factory Room under tile construction | |
CN217812395U (en) | Pump line reinforcing apparatus |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20180720 Address after: 610500 699, Longhu Road, East Industrial Zone, Xindu District, Chengdu, Sichuan Patentee after: Zhongjian aluminum new material Chengdu Co., Ltd. Address before: 610073 18 E District, 51 Tengfei Avenue, Qingyang District, Chengdu, Sichuan. Patentee before: Zhongjian aluminium New Material Co Ltd |
|