CN206308878U CN201621223142.5U CN201621223142U CN206308878U CN 206308878 U CN206308878 U CN 206308878U CN 201621223142 U CN201621223142 U CN 201621223142U CN 206308878 U CN206308878 U CN 206308878U
Authority
CN
China
Prior art keywords
suspension member
composite plate
stone material
material aluminium
aluminium honeycomb
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621223142.5U
Other languages
Chinese (zh)
Inventor
何党辉
李奕傧
梁帅
张亮
刘波
卢秦炜
张海刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Dingsheng Decoration Engineering Co Ltd
Original Assignee
Shaanxi Dingsheng Decoration Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Dingsheng Decoration Engineering Co Ltd filed Critical Shaanxi Dingsheng Decoration Engineering Co Ltd
Priority to CN201621223142.5U priority Critical patent/CN206308878U/en
Application granted granted Critical
Publication of CN206308878U publication Critical patent/CN206308878U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of based on T-shaped and Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, the hanging structure mounted including the ceiling joist below building roof and to constructed stone material aluminium honeycomb composite plate furred ceiling, hanging structure is arranged on ceiling joist;Stone material aluminium honeycomb composite plate furred ceiling includes multiple row stone material aluminium honeycomb composite plate, hanging structure includes two row outside suspension members and the T-shaped suspension member of multiple row, the T-shaped suspension member of a row is provided between adjacent two row stone material aluminium honeycomb composite plate, each T-shaped suspension member is installed between the two Z-type suspension members in left and right, and each T-shaped suspension member constitutes an assembly type suspension member with two Z-type suspension members positioned at its left and right sides;Suspension member on the outside of a row is provided with the outside of each column on the outside of composite plate.The utility model simple structure, reasonable in design and easy construction, using effect are good, and energy is easy, be rapidly completed stone material aluminium honeycomb composite plate ceiling construction process, and input cost is relatively low, and construction quality is easy to ensure.

Description

Based on T-shaped and Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure
Technical field
The utility model belongs to ceiling construction technical field, more particularly, to a kind of based on T-shaped and Z-type suspension member stone material aluminium Honeycomb composite plate ceiling construction structure.
Background technology
With continuing to develop for science and technology, architectural image tends to diversification, and traditional dry-hang stone furred ceiling technology has met Not large space, the technical requirements of large span stone ceiling construction.Stone material aluminium honeycomb composite plate ceiling material with impact resistance it is strong, The characteristic such as light weight, efficiency of construction are high, facing is attractive in appearance, is widely used in various large spaces surface-veneer engineered.Stone material aluminium honeycomb is answered Plywood is a kind of using aviation complex technique, very thin marble thin slice and honeycomb product laminating production is gone out a kind of new Dalle, also referred to as aluminium honeycomb-stone composite plate.At present, stone material cellular compound plate ceiling construction uses back bolt type and does mostly Extension method is constructed.Back bolt type dry-hanging method is to be drilled to after dovetail hole is combined with the swollen bolt of convex to be connected with keel again in back face of stone, and by Anyhow the keel of metallic support composition are fastened on major structure of construction by built-in fitting.But existing above-mentioned traditional back of the body bolt When formula dry-hanging method carries out stone material aluminium honeycomb composite plate ceiling construction, there is that work progress is complicated, input cost is high, low construction efficiency The problems such as.And nowadays, the unification of stone material aluminium honeycomb composite plate ceiling construction neither one, specification and specific construction method can Follow, thus be inevitably present that constructing operation is more random, lack of standardization, input cost is higher during practice of construction, construction effect The problems such as rate is relatively low, institute's construction molding stone material aluminium honeycomb composite plate furred ceiling is second-rate.
Utility model content
Technical problem to be solved in the utility model is to be directed to above-mentioned deficiency of the prior art, there is provided one kind is based on The T-shaped stone material aluminium honeycomb composite plate ceiling construction structure with Z-type suspension member, its simple structure, reasonable in design and easy construction, uses Effect is good, and energy is easy, be rapidly completed stone material aluminium honeycomb composite plate ceiling construction process, and input cost is relatively low, construction quality It is easy to ensure.
In order to solve the above technical problems, the technical solution adopted in the utility model is:It is a kind of based on T-shaped with Z-type suspension member Stone material aluminium honeycomb composite plate ceiling construction structure, it is characterised in that:Including the furred ceiling below the building roof for needing furred ceiling Keel and the hanging structure mounted to constructed stone material aluminium honeycomb composite plate furred ceiling, the hanging structure are arranged on furred ceiling dragon On bone;The stone material aluminium honeycomb composite plate furred ceiling includes multiple row in the parallel stone material aluminium honeybee laid and be respectively positioned in same level Honeycomb composite plate, stone material aluminium honeycomb composite plate described in multiple row carries out cloth from left to right along the transverse width direction of the building roof If stone material aluminium honeycomb composite plate described in each column is laid from front to back including polylith along the longitudinal length of the building roof Stone material aluminium honeycomb composite plate, the stone material aluminium honeycomb composite plate be rectangle;It is located in stone material aluminium honeycomb composite plate described in multiple row The one row stone material aluminium honeycomb composite plate of the leftmost side and the row stone material aluminium honeycomb composite plate positioned at the rightmost side are outer Side composite plate, all stone material aluminium honeycomb composite plates in stone material aluminium honeycomb composite plate described in multiple row except as noted outside the composite plate of side It is intermediate composite sheet;The hanging structure includes that two row outside suspension members and multiple row are laid and multiple to stone material aluminium honeycomb from left to right The T-shaped suspension member that plywood is mounted, a row T-shaped extension is provided between the adjacent two row stone material aluminium honeycomb composite plate Part, T-shaped suspension member described in each column includes that multiple longitudinal lengths along the building roof are laid in always from front to back T-shaped suspension member on line;Each described T-shaped suspension member be installed in left and right two Z-type suspension members between, each described T-shaped suspension member with Two Z-type suspension members positioned at its left and right sides constitute an assembly type suspension member;It is respectively provided with the outside of outside composite plate described in each column There is suspension member on the outside of a row, outside suspension member includes multiple longitudinal lengths along the building roof from front to back described in each column Lay outside suspension member on the same line;Stone material aluminium honeycomb composite plate described in same is carried out in T-shaped suspension member described in each column The quantity of the T-shaped suspension member for mounting is M, and wherein M is positive integer and M >=2;To described in same in outside suspension member described in each column The outside suspension member quantity that outside composite plate is mounted is M;The left and right sides of every piece of stone material aluminium honeycomb composite plate is equal A row are provided with for fixed outside suspension member or the pre-embedded bolt of Z-type suspension member, pre-embedded bolt described in each column include M it is individual by it is preceding extremely Pre-embedded bolt on the same line is laid afterwards;
The T-shaped suspension member is T-shaped and it includes horizonal base plate with the vertical installation being fixed on above horizonal base plate middle part Plate;The Z-type suspension member be zigzag and it include top board, the lower supporting plate positioned at the outer side-lower of top board and be connected to upper pressure Middle part connecting plate between plate and lower supporting plate, the top board and lower supporting plate are in horizontal layout, and the lower supporting plate leads to Pre-embedded bolt is crossed to be fixed on stone material aluminium honeycomb composite plate;Two upper pressures of the Z-type suspension member in each described assembly type suspension member Plate is press respectively against the horizonal base plate left and right sides top of T-shaped suspension member.
It is above-mentioned based on T-shaped with Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, it is characterized in that:The furred ceiling Keel are in level to laying and it passes through the hanging of multiple suspension rods on the building roof.
It is above-mentioned based on T-shaped with Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, it is characterized in that:The furred ceiling Keel are spliced with multiple tracks in longitudinal keel of parallel laying by multiple tracks in the lateral keel of parallel laying, longitudinal keel Laid along the longitudinal length of the building roof, longitudinal keel and the perpendicular laying of lateral keel;Multiple tracks institute State longitudinal keel to be laid in same level and the longitudinal keel shoe of its composition, lateral keel is laid in same described in multiple tracks On horizontal plane and its composition lateral keel frame, longitudinal keel are fastenedly connected with lateral keel described in multiple tracks described in per pass, described Longitudinal keel shoe is located at the lower section of the lateral keel frame;T-shaped suspension member is laid in same level described in multiple row, the T Vertical installing plate in type suspension member is fixedly mounted on longitudinal keel by connecting bolt, the multiple in T-shaped suspension member described in each column The T-shaped suspension member is each attached to along with longitudinal keel.
It is above-mentioned based on T-shaped with Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, it is characterized in that:Described in every piece The outside of outside composite plate is mounted on fixed structures by the M outside suspension member, and the fixed structures are described The framed side wallboard that side wall or the side wall outside on the outside of building roof, the ceiling joist, the building roof is set;Every piece institute The inner side for stating outside composite plate is mounted on the M being installed on the longitudinal keel T-shaped suspension member by the M Z-type suspension member On;Every piece of intermediate composite sheet by the 2M Z-type suspension member be mounted on the 2M being installed on longitudinal keel it is described T-shaped On suspension member.
It is above-mentioned based on T-shaped with Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, it is characterized in that:The longitudinal direction Keel and lateral keel are shaped steel, equal between longitudinal keel and lateral keel described in multiple tracks described in per pass in the ceiling joist It is fixedly connected with welding manner.
It is above-mentioned based on T-shaped with Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, it is characterized in that:The longitudinal direction Keel and lateral keel are Zinc-coated angle steel.
It is above-mentioned based on T-shaped with Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, it is characterized in that:The connection Bolt in horizontal layout and its be fixedly mounted on longitudinal keel, be provided with the vertical installing plate one for connecting bolt install And the vertical bolt adjustment hole that can be moved up and down for connecting bolt, the vertical bolt adjustment hole is elongate holes;
It is pre- that pre-embedded bolt in the stone material aluminium honeycomb composite plate furred ceiling on each piece of stone material aluminium honeycomb composite plate is furred ceiling Bolt is buried, the furred ceiling pre-embedded bolt is provided with a confession furred ceiling pre-embedded bolt in vertically to laying on the lower supporting plate The cross bolts adjustment hole that the furred ceiling pre-embedded bolt is moved left and right is installed and can supply, the cross bolts adjustment hole is length Bar hole and itself and the vertical perpendicular laying of bolt adjustment hole.
It is above-mentioned based on T-shaped with Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, it is characterized in that:The fixation Structures are framed side wallboard, and the framed side wallboard is located at the left side or right side of the stone material aluminium honeycomb composite plate furred ceiling, and framed side wallboard position In outside composite plate outside;The framed side wallboard in vertically to lay and its as described in polylith stone material aluminium honeycomb composite plate along institute The stone material aluminium honeycomb composite plate that the longitudinal length of construction building furred ceiling is laid from front to back is spliced, in the framed side wallboard Stone material aluminium honeycomb composite plate be wallboard composite plate;The bottom of every piece of wallboard composite plate is provided with M for fixed outer The pre-embedded bolt of pendant part, the pre-embedded bolt in the wallboard composite plate is wallboard pre-embedded bolt, the M wallboard pre-embedded bolt It is laid in same level;The outside suspension member is corner suspension member, and the corner suspension member is including outside fixed plate, positioned at institute State the inner side fixed plate on the inside of the fixed plate of outside and be connected to oblique between the outside fixed plate and the inner side fixed plate Connecting plate, the outside fixed plate in vertically to lay and it is fixed on the wallboard composite plate by the wallboard pre-embedded bolt On, the inner side fixed plate in horizontal layout and its be fixed in the outside composite plate by the furred ceiling pre-embedded bolt;Institute Oblique connecting plate is stated to incline gradually downward from outside to inside.
It is above-mentioned based on T-shaped with Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, it is characterized in that:The T-shaped extension Part and Z-type suspension member are aluminium alloy suspension member.
It is above-mentioned based on T-shaped with Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, it is characterized in that:Described M =2~4, the longitudinal length L≤1500mm of the stone material aluminium honeycomb composite plate;
As L≤600mm, M=2;As 600mm < L≤1000mm, M=3;As 1000mm < L≤1500mm, M= 4。
The utility model has advantages below compared with prior art:
1st, simple structure, reasonable in design and easy construction, input construction cost are relatively low.
2nd, the T-shaped suspension member and the simple structure of Z-type suspension member and processing and fabricating for being used are easy, can carry out batch production batch and add Work, crudy is easy to ensure.
3rd, the T-shaped suspension member and the reasonable in design of Z-type suspension member for being used, each T-shaped suspension member are installed in two Z in left and right Between type suspension member, each T-shaped suspension member constitutes an assembly type suspension member with two Z-type suspension members positioned at its left and right sides, thus It is attached using clamp mode between T-shaped suspension member and two Z-type suspension members in assembly type suspension member, not only simple installation, and energy Adjust easy, quick position and plate face flatness to mounted stone material aluminium honeycomb composite plate in vertical and horizontal direction It is whole, it is ensured that to mount the installation site accuracy and flatness of stone material aluminium honeycomb composite plate, increase substantially installation effectiveness, saving of labor It is time saving.
4th, the assembly type suspension member simple installation that is used, the installation quality of quick and stone material aluminium honeycomb composite plate are easy to protect Card, T-shaped suspension member is fixed on longitudinal keel in advance in assembly type suspension member, and Z-type suspension member is fixed on stone material aluminium honeycomb composite plate It is fixed on pre-embedded bolt, and simple installation.
5th, rotation angle position (coupling part i.e. between furred ceiling and framed side wallboard) is attached using corner suspension member, is used Corner hanger structure is simple, reasonable in design and simple installation is easy, using effect is good, and corner suspension member is directly anchored to stone material On pre-embedded bolt on aluminium honeycomb composite plate, simple installation is fixed.
6th, simple to operate, efficiency of construction is high, and the construction period is short, can effectively save engineering cost.
7th, stone material aluminium honeycomb composite plate is connected using T-shaped suspension member and Z-type suspension member with ceiling joist, Z-type suspension member and stone material aluminium Connected by pre-embedded bolt between honeycomb composite plate, and be attached by connecting bolt between T-shaped suspension member and ceiling joist, And prevent from sliding using skidproof buckle after setting adjustment hole regulating bolt position, and bolt fastening, form the space-load body of stabilization System.
8th, using effect is good and practical value is high, and the stone material aluminium honeycomb composite plate furred ceiling with construction molding is lightweight, damage Consumption less, environmental protection the features such as, be engaged with Z-type suspension member by T-shaped suspension member, make stone material aluminium honeycomb composite plate furred ceiling and furred ceiling imperial One stress system of entirety of bon e formation, efficiently solves the difficult construction problem of large span, large space stone ceiling facing.With biography The back bolt type dry-hanging method of system is compared, with simple to operate, efficiency of construction is high, plate regulation leeway is big, lightweight, after installation Many advantages, such as plate face whole structure is attractive in appearance.Also, when carrying out ceiling construction using the utility model, construction quality is easily controlled System, has accomplished environmental protection, green construction, and can effectively shorten the duration, reduces engineering cost.
9th, economic benefit and social benefit significantly, compared with using traditional ceiling construction process, save cost effectiveness (CE) substantially, 7200m such as is about to construction area2Building ceiling when being constructed, the cost of traditional suspension member is 5.7 yuan/, and this practicality The cost of new used suspension member (i.e. assembly type suspension member) construction building furred ceiling is 1.9 yuan/, with traditional suspension member construction furred ceiling Cost is 45.6 yuan/m2, the cost that suspension member (i.e. assembly type suspension member) construction building furred ceiling is used with the utility model is 16.2 Unit/m2;In addition, the labour cost of traditional construction technique is 176 yuan/m2, and labour cost of the present utility model is 135 yuan/m2.Using The utility model not only can completely show the lines glamour of lithotome, save mounting cost, effectively shorten the construction period, The ceiling construction project of the public places such as bank, commercial center, amusement can be effectively applied to, social benefit is notable.
10th, prospect is promoted the use of extensive and widely applicable, it is adaptable to which tier building is answered with stone material aluminium honeycomb in skyscraper The ceiling decoration engineering of plywood.
In sum, the utility model simple structure, reasonable in design and easy construction, using effect are good, can be easy, quick Stone material aluminium honeycomb composite plate ceiling construction process is completed, and input cost is relatively low, and construction quality is easy to ensure.
Below by drawings and Examples, the technical solution of the utility model is described in further detail.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model.
Fig. 2 is the use state of the utility model assembly type suspension member with reference to figure.
Description of reference numerals:
1-suspension rod;2-1-longitudinal direction keel;2-2-lateral keel;
3-T-shaped suspension member;3-1-horizonal base plate;3-2-vertical installing plate;
4-stone material aluminium honeycomb composite plate;5-outside suspension member;6-Z-type suspension member;
6-1-top board;6-2-lower supporting plate;6-3-middle part connecting plate;
7-framed side wallboard;8-connecting bolt;9-pre-embedded bolt;
10-horizontal keel;11-L-shaped suspension member;12-glue-line.
Specific embodiment
As shown in Figure 1 and Figure 2, the utility model includes being arranged on needs ceiling joist below the building roof of furred ceiling and right The hanging structure that constructed stone material aluminium honeycomb composite plate furred ceiling is mounted, the hanging structure is arranged on ceiling joist;Institute Stone material aluminium honeycomb composite plate furred ceiling is stated to be combined in the parallel stone material aluminium honeycomb laid and be respectively positioned in same level including multiple row Plate 4, stone material aluminium honeycomb composite plate 4 described in multiple row is laid from left to right along the transverse width direction of the building roof, often Arranging the stone material aluminium honeycomb composite plate 4 includes the stone that polylith is laid from front to back along the longitudinal length of the building roof Material aluminium honeycomb composite plate 4, the stone material aluminium honeycomb composite plate 4 is rectangle;It is located at most in stone material aluminium honeycomb composite plate 4 described in multiple row The one row stone material aluminium honeycomb composite plate 4 in left side and the row stone material aluminium honeycomb composite plate 4 positioned at the rightmost side are outer Side composite plate, all stone material aluminium honeycombs in stone material aluminium honeycomb composite plate 4 described in multiple row except as noted outside the composite plate of side are combined Plate 4 is intermediate composite sheet;The hanging structure includes that two row outside suspension members 5 and multiple row are laid and to stone material aluminium honeybee from left to right The T-shaped suspension member 3 that honeycomb composite plate 4 is mounted, is provided with described in a row between the adjacent two row stone material aluminium honeycomb composite plate 4 T-shaped suspension member 3, T-shaped suspension member 3 described in each column includes that multiple longitudinal lengths along the building roof are laid in from front to back T-shaped suspension member 3 on same straight line;Each described T-shaped suspension member 3 is installed between the two Z-type suspension members 6 in left and right, and each is described T-shaped Suspension member 3 constitutes an assembly type suspension member with two Z-type suspension members 6 positioned at its left and right sides;Outside composite plate described in each column Outside is provided with suspension member 5 on the outside of a row, and outside suspension member 5 includes multiple longitudinal lengths along the building roof described in each column Outside suspension member 5 on the same line is laid from front to back in direction;To stone material aluminium described in same in T-shaped suspension member 3 described in each column The quantity of the T-shaped suspension member 3 that honeycomb composite plate 4 is mounted is M, and wherein M is positive integer and M >=2;Outside described in each column M is to the quantity of outside suspension member 5 that outside composite plate described in same is mounted in suspension member 5;Every piece of stone material aluminium honeybee The left and right sides of honeycomb composite plate 4 is provided with a row for the pre-embedded bolt 9 of suspension member 5 or Z-type suspension member 6 on the outside of fixed, each column institute Stating pre-embedded bolt 9 includes the M pre-embedded bolt 9 laid from front to back on the same line;
The T-shaped suspension member 3 is T-shaped and it includes horizonal base plate 3-1 and is fixed on perpendicular above horizonal base plate 3-1 middle parts To installing plate 3-2;The Z-type suspension member 6 is for zigzag and it includes top board 6-1, the lower branch positioned at the outer side-lowers of top board 6-1 Fagging 6-2 and the middle part connecting plate 6-3, the top board 6-1 that are connected between top board 6-1 and lower supporting plate 6-2 and lower branch Fagging 6-2 is in horizontal layout, and the lower supporting plate 6-2 is fixed on stone material aluminium honeycomb composite plate 4 by pre-embedded bolt 9;Often The top board 6-1 of two Z-type suspension members 6 is press respectively against a horizonal base plate 3-1 left sides for T-shaped suspension member 3 in the individual assembly type suspension member Right both sides top.
In the present embodiment, the ceiling joist in level to lay and its pass through multiple suspension rods 1 and hang in the building On top.
In the present embodiment, as shown in figure 1, the ceiling joist by multiple tracks in parallel laying longitudinal keel 2-1 and multiple tracks It is spliced in the lateral keel 2-2 of parallel laying, longitudinal keel 2-1 enters along the longitudinal length of the building roof Row laying, longitudinal keel 2-1 and the perpendicular layings of lateral keel 2-2;Longitudinal direction keel 2-1 is laid in same described in multiple tracks On horizontal plane and its longitudinal keel shoe of composition, lateral keel 2-2 described in multiple tracks is laid in same level and its composition is horizontal To keel shoe, longitudinal direction keel 2-1 is fastenedly connected with lateral keel 2-2 described in multiple tracks described in per pass, longitudinal keel shoe position In the lower section of the lateral keel frame;T-shaped suspension member 3 is laid in same level described in multiple row, in the T-shaped suspension member 3 Vertical installing plate 3-2 is fixedly mounted on longitudinal keel 2-1 by connecting bolt 8, the multiple institutes in T-shaped suspension member 3 described in each column T-shaped suspension member 3 is stated to be each attached to along with longitudinal keel 2-1.
In the present embodiment, every piece of outside of the outside composite plate is mounted on fixed structure by the M outside suspension member 5 Build on thing, the fixed structures are the building roof, the ceiling joist, the side wall or described on the outside of the building roof The framed side wallboard 7 that side wall outside is set;Every piece of inner side of the outside composite plate is mounted on peace by the M Z-type suspension member 6 Loaded on the M T-shaped suspension member 3 on longitudinal keel 2-1;Every piece of intermediate composite sheet is by the 2M Z-type suspension member 6 It is mounted on the 2M T-shaped suspension member 3 being installed on longitudinal keel 2-1.
In the present embodiment, the structure and chi of all stone material aluminium honeycomb composite plates 4 in the stone material aluminium honeycomb composite plate furred ceiling Very little all same.
During practice of construction, the stone material aluminium honeycomb composite plate 4 typically have 800mm × 800mm, 600mm × 1200mm, The multiple specification such as 600mm × 1000mm, 600mm × 1500mm, the plate construction of stone material aluminium honeycomb composite plate 4 has to comply with table 1 Requirement:
The stone material aluminium honeycomb composite plate plate construction of table 1 requirement table
The quantity M of pre-embedded bolt 9 is installed on every piece of stone material aluminium honeycomb composite plate 4, it is compound according to stone material aluminium honeycomb The longitudinal length L of plate 4 is determined.
Described M=2~4, the longitudinal length L≤1500mm of the stone material aluminium honeycomb composite plate 4;
As L≤600mm, M=2;As 600mm < L≤1000mm, M=3;As 1000mm < L≤1500mm, M= 4。
In the present embodiment, L≤600mm, M=2.
During practice of construction, can accordingly be adjusted according to the longitudinal length L of stone material aluminium honeycomb composite plate 4, the value size to M It is whole.
Before practice of construction, it is possible to use BIM BIM and according to drawing, specification, atlas and relevant regulations, Drawing to constructed stone material aluminium honeycomb composite plate furred ceiling carries out Deepen Design, and to consider constructed stone material aluminium honeycomb The installation site of the equipment such as light fixture, Smoke Sensor, sprinkling equipment, air port double-edged fine-toothed comb on composite plate furred ceiling, to constructed stone material Each piece of stone material aluminium honeycomb composite plate 4 carries out typesetting respectively in aluminium honeycomb composite plate furred ceiling, and obtains typesetting figure, reaches structure and sets The purpose of reasonable and good appearance is counted, blanking processing is carried out to each piece of stone material aluminium honeycomb composite plate 4 further according to typesetting figure.
When reality is processed to each piece of stone material aluminium honeycomb composite plate 4, need to be in the backboard of stone material aluminium honeycomb composite plate 4 The pre-buried 2M in the face pre-embedded bolt 9.
In the present embodiment, longitudinal keel 2-1 and lateral keel 2-2 is shaped steel, per pass institute in the ceiling joist State and be fixedly connected with welding manner between longitudinal keel 2-1 and lateral keel 2-2 described in multiple tracks.
Also, longitudinal keel 2-1 and lateral keel 2-2 is Zinc-coated angle steel.
During practice of construction, longitudinal keel 2-1 and lateral keel 2-2 is Zinc-coated angle steel i.e. the two of angle steel of L50 × 4 Hem width degree is 50mm and its thickness is 4mm.
In the present embodiment, the horizontal stroke of the laying spacing of longitudinal keel 2-1 and stone material aluminium honeycomb composite plate 4 in the ceiling joist It is consistent to width.
For the position for setting access hole on constructed stone material aluminium honeycomb composite plate furred ceiling, also need that additional keel are installed.
In the present embodiment, the suspension rod 1 is metal suspension rod, with welding side between the metal suspension rod and lateral keel 2-2 Formula is fixedly connected, and the built-in fitting fixed for the metal suspension rod upper weld is provided with the building roof.
To reduce influence of the sinking amount of deflection of the ceiling joist to ceiling decoration smooth degree of layer, the furred ceiling dragon as far as possible The center section springing height of bone should be not less than 1/200 that room short span is the transverse width of the building roof.Also, Before actually carrying out stone material aluminium honeycomb composite plate installation, the line equipment constructed in stone material aluminium honeycomb composite plate furred ceiling is installed must Must complete.
In the present embodiment, 1 point of multiple rows of multiple row of multiple suspension rods is laid, and suspension rod 1 described in each column includes multiple edges The suspension rod 1 that the longitudinal length of the building roof is laid.
Spacing in suspension rod 1 described in each column between the front and rear two neighboring suspension rod 1 is 900mm~1200mm, described to hang Distance on the outside of the described ceiling joist of bar 1 is not to be exceeded 300mm, should otherwise increase suspension rod 1, when suspension rod 1 and stone material of constructing When line equipment in aluminium honeycomb composite plate furred ceiling is met, adjustment suspension centre is the installation position of suspension rod 1 to ensure furred ceiling quality.
In the present embodiment, between the suspension rod 1 and lateral keel 2-2 and between lateral keel 2-2 and longitudinal keel 2-1 Welding manner is used, and is welded and is formed the foot welding height of angle welding for 4mm~6mm, preservative treatment is done after full weld.
After the ceiling joist is installed, logical ray examination is drawn to check and accept the ceiling joist lower edge, and complete hidden work Journey is checked and accepted.
In the present embodiment, the T-shaped suspension member 3 and Z-type suspension member 6 are aluminium alloy suspension member.
In the present embodiment, the middle part connecting plate 6-3 is in vertically to laying.
Also, the vertical height of the middle part connecting plate 6-3 is identical with the thickness of slab of horizonal base plate 3-1.
In the present embodiment, the connecting bolt 8 in horizontal layout and its be fixedly mounted on longitudinal keel 2-1, it is described perpendicular The vertical bolt regulation that connecting bolt 8 is moved up and down is installed and can supplied for connecting bolt 8 to being provided with one on installing plate 3-2 Hole, the vertical bolt adjustment hole is elongate holes.
Pre-embedded bolt 9 in the stone material aluminium honeycomb composite plate furred ceiling on each piece of stone material aluminium honeycomb composite plate 4 is furred ceiling Pre-embedded bolt, the furred ceiling pre-embedded bolt is provided with a confession furred ceiling pre-buried in vertically to laying on the lower supporting plate 6-2 The cross bolts adjustment hole that the furred ceiling pre-embedded bolt is moved left and right, the cross bolts adjustment hole are installed and can supplied to bolt It is elongate holes and itself and the vertical perpendicular laying of bolt adjustment hole.
In the present embodiment, the vertical bolt adjustment hole is located at the middle part of vertical installing plate 3-2, the cross bolts regulation Hole position is in the middle part of lower supporting plate 6-2.
As shown in figure 1, in the present embodiment, the fixed structures are framed side wallboard 7, the framed side wallboard 7 is located at the stone material The left side or right side of aluminium honeycomb composite plate furred ceiling, and framed side wallboard 7 is located at outside composite plate outside;The framed side wallboard 7 is in perpendicular It is straight to lay and its as described in polylith stone material aluminium honeycomb composite plate 4 along institute's construction building furred ceiling longitudinal length from front to back The stone material aluminium honeycomb composite plate 4 of laying is spliced, and the stone material aluminium honeycomb composite plate 4 in the framed side wallboard 7 is wallboard composite plate; The bottom of every piece of wallboard composite plate is provided with the M pre-embedded bolt 9 for fixed outside suspension member 5, and the wallboard is combined Pre-embedded bolt 9 on plate is wallboard pre-embedded bolt, and the M wallboard pre-embedded bolt is laid in same level;It is described outer Pendant part 5 is corner suspension member, and the corner suspension member includes that outside fixed plate, the inner side on the inside of the outside fixed plate are consolidated Fixed board and the oblique connecting plate being connected between the outside fixed plate and the inner side fixed plate, the outside fixed plate is in perpendicular It is straight to laying and it is fixed in the wallboard composite plate by the wallboard pre-embedded bolt, the inner side fixed plate is in horizontal cloth And if it is fixed in the outside composite plate by the furred ceiling pre-embedded bolt;The oblique connecting plate from outside to inside gradually to Lower inclination.
When being constructed to constructed stone material aluminium honeycomb composite plate furred ceiling, comprise the following steps:
Step one, ceiling joist are installed:Ceiling joist is installed below the building roof for needing furred ceiling, the ceiling joist is in Level to lay and its pass through multiple suspension rods 1 and hang on the building roof;
Step 2, T-shaped suspension member are installed:The T-shaped suspension member 3 of multiple row, T described in multiple row are installed described in step one on ceiling joist Type suspension member 3 is laid in same level;
Vertical installing plate 3-2 in the T-shaped suspension member 3 is fixedly mounted on longitudinal keel 2-1 by connecting bolt 8, often The multiple described T-shaped suspension member 3 in the T-shaped suspension member 3 is arranged to be each attached to along with longitudinal keel 2-1;
Step 3, stone material aluminium honeycomb composite plate are installed:To described in each piece in constructed stone material aluminium honeycomb composite plate furred ceiling Stone material aluminium honeycomb composite plate 4 is installed respectively, obtains the stone material aluminium honeycomb composite plate furred ceiling of construction molding;
Every piece of outside of the outside composite plate is mounted on fixed structures by the M outside suspension member 5, described Fixed structures are that the building roof, the ceiling joist, the side wall on the outside of the building roof or side wall outside set The framed side wallboard 7 put;Every piece of inner side of the outside composite plate is mounted on by the M Z-type suspension member 6 and is installed on longitudinal keel On the M T-shaped suspension member 3 on 2-1;Every piece of intermediate composite sheet is mounted on by the 2M Z-type suspension member 6 and is installed on On the 2M T-shaped suspension member 3 on longitudinal keel 2-1;
Step 4, joint filling treatment:The stone material aluminium honeycomb composite plate of completion of being constructed in step 3 is hung using gap-filling glue Splicing seams in top between adjacent two pieces of stone material aluminium honeycomb composite plates 4 carry out joint filling treatment respectively.
In the present embodiment, before carrying out ceiling joist installation in step one, surveying setting-out is first carried out, released using spirit level The horizontal control lines and arch camber control line of ceiling joist.
When the installation of stone material aluminium honeycomb composite plate is carried out in step 3, to make simple installation, first at the scene to each block of stone material aluminium Honeycomb composite plate 4 carries out walkthrough, and each piece of stone material aluminium honeycomb composite plate 4 is numbered respectively, then again to stone material aluminium honeycomb Composite plate 4 carries out check mark installation one by one.
When the installation of stone material aluminium honeycomb composite plate is carried out in the present embodiment, in step 3, from left to right or from right to left to many The stone material aluminium honeycomb composite plate 4 is arranged to be installed respectively;To when stone material aluminium honeycomb composite plate 4 is installed described in each column, Block-by-block installation is carried out respectively to multiple stone material aluminium honeycomb composite plates 4 from front to back or from rear to preceding.
Thus, when actually carrying out the installation of stone material aluminium honeycomb composite plate, a branch point row carry out hanging wire installation.
In the present embodiment, to when intermediate composite sheet is installed every piece described in step 3, first by the intermediate composite sheet The 2M Z-type suspension member 6 of installation is press respectively against on the horizonal base plate 3-1 in the 2M T-shaped suspension member 3, then by upper downward The setting height(from bottom) of the whole 2M T-shaped suspension member 3 is adjusted to the vertical height of the intermediate composite sheet, and to the intermediate composite sheet Horizontal level carry out left and right adjustment, until the intermediate composite sheet is adjusted to the installation site being pre-designed;Treat that the centre is multiple Plywood is adjusted to the installation site being pre-designed, to for fixing the connecting bolt 8 of 2M T-shaped suspension members 3 and for solid The pre-embedded bolt 9 (i.e. described furred ceiling pre-embedded bolt) for determining the 2M T-shaped suspension member 3 is locked respectively.
Also, to for fixing the connecting bolt 8 of 2M T-shaped suspension members 3 and for fixing the 2M T-shaped suspension member 3 The furred ceiling pre-embedded bolt be locked respectively after, need to also distinguish on each connecting bolt 8 and each furred ceiling pre-embedded bolt Skidproof buckle is installed.
In the present embodiment, the pre-embedded bolt 9 is a diameter of Φ 8mm and length is the bolt of 40mm.
It is fastenedly connected using pre-embedded bolt 9 between the stone material aluminium honeycomb composite plate 4 and Z-type suspension member 6, Z-type suspension member 6 passes through T-shaped suspension member 3 is fixedly connected with longitudinal direction keel 2-1, by the vertical bolt adjustment hole and the cross bolts adjustment hole, The plate face flatness of each piece of stone material aluminium honeycomb composite plate 4 that can be to being installed carries out easy, quick regulation.
When the installation of stone material aluminium honeycomb composite plate is carried out in the present embodiment, in step 3, opened from one layer of the building roof Begin, a row stone material aluminium honeycomb composite plate 4 is first installed, then on the basis of the row stone material aluminium honeycomb composite plate 4, according to typesetting figure Each piece of stone material aluminium honeycomb composite plate 4 successively block-by-block retrusive is installed.
During practice of construction, a width of 4mm of seam of the splicing seams between adjacent two pieces of stone material aluminium honeycomb composite plates 4~ 6mm。
In the present embodiment, a width of 5mm of seam of the splicing seams, the splicing seams are that the special seam card controls of 5mm are used in plate stitch Seam is wide.When being installed to stone material aluminium honeycomb composite plate 4, to be checked with datum line, including horizontal direction and direction in length and breadth mark It is high, it is ensured that after the installation site of stone material aluminium honeycomb composite plate 4 is errorless, then connecting bolt 8 and pre-embedded bolt 9 to be tightened with anchor stone Material aluminium honeycomb composite plate 4, installs skidproof buckle afterwards, it is ensured that each piece of flatness of stone material aluminium honeycomb composite plate 4 installed, and protects The seam for demonstrate,proving the splicing seams is wide consistent, seam no visual difference of height.
In the present embodiment, set pre-embedded bolt 9 is in symmetrical laying on every piece of stone material aluminium honeycomb composite plate 4.
Thus, the laying spacing and T-shaped extension in T-shaped suspension member 3 described in each column of the China and foreign countries pendants part 5 of outside suspension member 5 described in each column The laying spacing of part 3 is consistent.On every piece of stone material aluminium honeycomb composite plate 4 installation position of pre-embedded bolt 9 with to the stone material aluminium The T-shaped suspension member 3 and/or the installation position of outside suspension member 5 that honeycomb composite plate 4 is mounted are consistent.
In the present embodiment, positioned at a row suspension rod 1 of the leftmost side and the row positioned at most rear side in suspension rod 1 described in multiple row The suspension rod 1 is outside suspension rod, and one level dragon for the fixation of framed side wallboard 7 is respectively and fixedly provided with the outside of outside suspension rod described in each column Bone 10, the horizontal keel 10 is in parallel laying with longitudinal keel 2-1.
The top of every piece of wallboard composite plate is provided with the M pre-embedded bolt 9 for fixed outside suspension member 5, every piece The pre-embedded bolt 9 being equipped with set by the wallboard composite plate top is wallboard fixing bolt, on each described wallboard fixing bolt An inner side suspension member is respectively and fixedly provided with, each described inner side suspension member inner side is provided with one and is fixed on level dragon by fastening bolt L-shaped suspension member 11 on bone 10, the inner side suspension member is in the Z-type suspension member 6 laid, the L-shaped suspension member 11 is installed on institute vertically State in the suspension member of inner side.
It is fastenedly connected by gap-filling glue between the wallboard composite plate bottom and the outside composite plate.Thus, when When the wallboard composite plate is identical with the material of the outside composite plate, the wallboard composite plate and the outside composite plate it Between junction using gluing process.
During practice of construction, when the wallboard composite plate is different from the material of the outside composite plate, the wallboard is combined Closed up using end cap or negative and positive angle closing in line junction between plate and the outside composite plate.
In the present embodiment, the outside suspension member 5 is aluminium alloy suspension member.
Also, the angle inclined between connecting plate and horizontal plane is 45 °.
When joint filling treatment is carried out in the present embodiment, in step 4, the gap-filling glue is uniformly injected into using glue rifle first described In splicing seams, then struck off with scraper plate immediately;The thickness of the gap-filling glue is 4mm~6mm in the splicing seams.
In the present embodiment, the gap-filling glue is sealing neutral silicone resin.
Before carrying out joint filling treatment in step 4, first clear up in the splicing seams and periphery debris, and in the splicing Protection glue band is pasted in the both sides of seam respectively, prevents from polluting the surface stone material of the splicing seams the week side of boss, and glue rifle to be employed is filled out described After seam glue is uniformly injected into the splicing seams and is struck off with scraper plate immediately, dismantle immediately the Protection glue band, the glue for ultimately forming Stitch 12 surfaces to smooth, centre is slightly recessed and without Zou's pleat.
After the completion of construction, the stone material aluminium honeycomb to construction molding according to building engineering construction quality acceptance standard is also needed Composite plate furred ceiling carries out an acceptance inspection,《Code for construction quality acceptance of building decoration》It is required that the flatness of the ceiling joist, rise Arch meets code requirement, and the flatness error of the ceiling joist is not more than 2mm, and the ceiling joist is along short span 1/200 Arch camber, the surrounding levelness of the ceiling joist is not more than 5mm, and the panel flatness of the stone material aluminium honeycomb composite plate furred ceiling is not More than 2mm, the discrepancy in elevation of adjacent two pieces of stone material aluminium honeycomb composite plates 4 is not more than 0.5mm, adjacent two pieces of stone material aluminium honeycombs The linearity of the splicing seams between composite plate 4 is not more than 2mm.
The above, is only preferred embodiment of the present utility model, and not the utility model is imposed any restrictions, every Any simple modification, change and the equivalent structure change made to above example according to the utility model technical spirit, still Belong in the protection domain of technical solutions of the utility model.

Claims (10)

1. a kind of based on T-shaped and Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, it is characterised in that:Including installing Ceiling joist below the building roof for needing furred ceiling and to mounting that constructed stone material aluminium honeycomb composite plate furred ceiling is mounted Structure, the hanging structure is arranged on ceiling joist;The stone material aluminium honeycomb composite plate furred ceiling includes that multiple row is in parallel laying And the stone material aluminium honeycomb composite plate (4) in same level is respectively positioned on, stone material aluminium honeycomb composite plate (4) is built along described described in multiple row The transverse width direction for building roof is laid from left to right, and stone material aluminium honeycomb composite plate (4) described in each column includes polylith edge The stone material aluminium honeycomb composite plate (4) that the longitudinal length of the building roof is laid from front to back, the stone material aluminium honeycomb is answered Plywood (4) is rectangle;A row stone material aluminium honeycomb in stone material aluminium honeycomb composite plate (4) described in multiple row positioned at the leftmost side is combined Plate (4) and the row stone material aluminium honeycomb composite plate (4) positioned at the rightmost side are outside composite plate, stone material aluminium honeybee described in multiple row All stone material aluminium honeycomb composite plates (4) in honeycomb composite plate (4) except as noted outside the composite plate of side are intermediate composite sheet;It is described Hanging structure includes that two row outside suspension member (5) and multiple row are laid and stone material aluminium honeycomb composite plate (4) is mounted from left to right T-shaped suspension member (3), be provided with a row T-shaped suspension member (3) between the adjacent two row stone material aluminium honeycomb composite plate (4), often Arranging the T-shaped suspension member (3) includes that multiple longitudinal lengths along the building roof are laid in same straight line from front to back On T-shaped suspension member (3);Each described T-shaped suspension member (3) is installed between the two Z-type suspension members (6) in left and right, each described T-shaped extension Part (3) constitutes an assembly type suspension member with two Z-type suspension members (6) positioned at its left and right sides;Outside composite plate described in each column Outside be provided with suspension member (5) on the outside of a row, outside suspension member (5) described in each column includes multiple along the vertical of the building roof Lay outside suspension member (5) on the same line from front to back to length direction;To same in T-shaped suspension member (3) described in each column The quantity of the T-shaped suspension member (3) that the stone material aluminium honeycomb composite plate (4) is mounted is M, and wherein M is positive integer and M >=2; M is to outside suspension member (5) quantity that outside composite plate described in same is mounted in outside suspension member (5) described in each column; The left and right sides of every piece of stone material aluminium honeycomb composite plate (4) is provided with a row for suspension member (5) or Z-type suspension member on the outside of fixed (6) pre-embedded bolt (9), pre-embedded bolt (9) described in each column includes the M pre-buried spiral shell laid from front to back on the same line Bolt (9);
The T-shaped suspension member (3) for it is T-shaped and it include horizonal base plate (3-1) and be fixed on horizonal base plate (3-1) middle part above Vertical installing plate (3-2);The Z-type suspension member (6) for zigzag and it include top board (6-1), positioned at top board (6-1) outside The lower supporting plate (6-2) of lower section and the middle part connecting plate (6-3) being connected between top board (6-1) and lower supporting plate (6-2), institute Top board (6-1) and lower supporting plate (6-2) are stated in horizontal layout, the lower supporting plate (6-2) is fixed by pre-embedded bolt (9) In on stone material aluminium honeycomb composite plate (4);Two top boards (6-1) of the Z-type suspension member (6) point in each described assembly type suspension member Horizonal base plate (3-1) left and right sides top of T-shaped suspension member (3) is not pressed in.
2. according to, based on T-shaped and Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, it is special described in claim 1 Levy and be:The ceiling joist in level to lay and its pass through multiple suspension rods (1) hanging on the building roof.
3. according to described in claim 1 or 2 based on T-shaped with Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, its It is characterised by:The ceiling joist is in the laterally imperial of parallel laying with multiple tracks in longitudinal keel (2-1) of parallel laying by multiple tracks Bone (2-2) is spliced, and longitudinal keel (2-1) are laid along the longitudinal length of the building roof, described vertical To keel (2-1) and lateral keel (2-2) perpendicular laying;Longitudinal keel (2-1) are laid in same level described in multiple tracks The upper and longitudinal keel shoe of its composition, lateral keel (2-2) described in multiple tracks is laid in same level and the horizontal dragon of its composition Skeleton, longitudinal keel (2-1) described in per pass are fastenedly connected with lateral keel described in multiple tracks (2-2), longitudinal keel shoe position In the lower section of the lateral keel frame;T-shaped suspension member (3) is laid in same level described in multiple row, the T-shaped suspension member (3) In vertical installing plate (3-2) be fixedly mounted on longitudinal keel (2-1) by connecting bolt (8), T-shaped suspension member described in each column (3) the multiple described T-shaped suspension member (3) in is each attached to along with longitudinal keel (2-1).
4. according to, based on T-shaped and Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, it is special described in claim 3 Levy and be:Every piece of outside of the outside composite plate is mounted on fixed structures by the M outside suspension member (5), institute It is the building roof, the ceiling joist, the side wall on the outside of the building roof or side wall outside to state fixed structures The framed side wallboard (7) of setting;Every piece of inner side of the outside composite plate be mounted on by the M Z-type suspension member (6) be installed on it is vertical To on the M T-shaped suspension member (3) on keel (2-1);Every piece of intermediate composite sheet is by the 2M Z-type suspension member (6) It is mounted on the 2M T-shaped suspension member (3) being installed on longitudinal keel (2-1).
5. according to, based on T-shaped and Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, it is special described in claim 3 Levy and be:Longitudinal keel (2-1) and lateral keel (2-2) are shaped steel, longitudinal direction dragon described in per pass in the ceiling joist It is fixedly connected with welding manner between bone (2-1) and lateral keel (2-2) described in multiple tracks.
6. according to, based on T-shaped and Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, it is special described in claim 5 Levy and be:Longitudinal keel (2-1) and lateral keel (2-2) are Zinc-coated angle steel.
7. according to, based on T-shaped and Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, it is special described in claim 3 Levy and be:The connecting bolt (8) in horizontal layout and its be fixedly mounted on longitudinal keel (2-1), the vertical installing plate One is provided with (3-2) the vertical bolt regulation that connecting bolt (8) is moved up and down is installed and can supplied for connecting bolt (8) Hole, the vertical bolt adjustment hole is elongate holes;
Pre-embedded bolt (9) in the stone material aluminium honeycomb composite plate furred ceiling on each piece of stone material aluminium honeycomb composite plate (4) is furred ceiling Pre-embedded bolt, the furred ceiling pre-embedded bolt is provided with a confession furred ceiling pre- in vertically to laying on the lower supporting plate (6-2) Bury bolt and install and can supply the cross bolts adjustment hole that the furred ceiling pre-embedded bolt is moved left and right, the cross bolts regulation Hole is elongate holes and itself and the vertical perpendicular laying of bolt adjustment hole.
8. according to, based on T-shaped and Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, it is special described in claim 4 Levy and be:The fixed structures are framed side wallboard (7), and the framed side wallboard (7) is positioned at the stone material aluminium honeycomb composite plate furred ceiling Left side or right side, and framed side wallboard (7) is positioned at outside composite plate outside;The framed side wallboard (7) in vertically to lay and its by The stone material aluminium that stone material aluminium honeycomb composite plate (4) described in polylith is laid from front to back along the longitudinal length of institute's construction building furred ceiling Honeycomb composite plate (4) is spliced, and the stone material aluminium honeycomb composite plate (4) in the framed side wallboard (7) is wallboard composite plate;Every piece institute The bottom for stating wallboard composite plate is provided with the M pre-embedded bolt (9) for fixed outside suspension member (5), the wallboard composite plate On pre-embedded bolt (9) be wallboard pre-embedded bolt, the M wallboard pre-embedded bolt is laid in same level;It is described outer Pendant part (5) is corner suspension member, and the corner suspension member includes that outside fixed plate, the inner side on the inside of the outside fixed plate are consolidated Fixed board and the oblique connecting plate being connected between the outside fixed plate and the inner side fixed plate, the outside fixed plate is in perpendicular It is straight to laying and it is fixed in the wallboard composite plate by the wallboard pre-embedded bolt, the inner side fixed plate is in horizontal cloth And if it is fixed in the outside composite plate by the furred ceiling pre-embedded bolt;The oblique connecting plate from outside to inside gradually to Lower inclination.
9. according to described in claim 1 or 2 based on T-shaped with Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, its It is characterised by:The T-shaped suspension member (3) and Z-type suspension member (6) are aluminium alloy suspension member.
10. according to described in claim 1 or 2 based on T-shaped with Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure, It is characterized in that:Described M=2~4, the longitudinal length L≤1500mm of the stone material aluminium honeycomb composite plate (4);
As L≤600mm, M=2;As 600mm < L≤1000mm, M=3;As 1000mm < L≤1500mm, M=4.
CN201621223142.5U 2016-11-14 2016-11-14 Based on T-shaped and Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure Active CN206308878U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621223142.5U CN206308878U (en) 2016-11-14 2016-11-14 Based on T-shaped and Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621223142.5U CN206308878U (en) 2016-11-14 2016-11-14 Based on T-shaped and Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure

Publications (1)

Publication Number Publication Date
CN206308878U true CN206308878U (en) 2017-07-07

Family

ID=59244015

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621223142.5U Active CN206308878U (en) 2016-11-14 2016-11-14 Based on T-shaped and Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure

Country Status (1)

Country Link
CN (1) CN206308878U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108517988A (en) * 2018-03-07 2018-09-11 北京建筑大学 A kind of non-big face stone material corner connection system
CN109577542A (en) * 2018-01-31 2019-04-05 钟兵 A kind of cement base very-high performance artificial slabstone ceiling structure and installation method
CN113356458A (en) * 2021-06-21 2021-09-07 北新集团建材股份有限公司 Ceiling member and ceiling board mounting method
CN115217295A (en) * 2022-08-09 2022-10-21 中国建筑第二工程局有限公司 High-rise large-span indoor suspended ceiling hoisting system and construction method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109577542A (en) * 2018-01-31 2019-04-05 钟兵 A kind of cement base very-high performance artificial slabstone ceiling structure and installation method
CN109577542B (en) * 2018-01-31 2021-10-26 钟兵 Cement-based ultrahigh-performance artificial stone slab ceiling structure and mounting method
CN108517988A (en) * 2018-03-07 2018-09-11 北京建筑大学 A kind of non-big face stone material corner connection system
CN113356458A (en) * 2021-06-21 2021-09-07 北新集团建材股份有限公司 Ceiling member and ceiling board mounting method
CN115217295A (en) * 2022-08-09 2022-10-21 中国建筑第二工程局有限公司 High-rise large-span indoor suspended ceiling hoisting system and construction method thereof
CN115217295B (en) * 2022-08-09 2023-09-01 中国建筑第二工程局有限公司 High-rise large-span indoor ceiling hoisting system and construction method thereof

Similar Documents

Publication Publication Date Title
CN206308878U (en) Based on T-shaped and Z-type suspension member stone material aluminium honeycomb composite plate ceiling construction structure
CN106368368B (en) Based on T-shaped and Z-type pendant stone material aluminium honeycomb composite plate ceiling construction method
CN107419870A (en) A kind of construction method for decorating panel cladding system and decoration panel cladding system
CN102947519A (en) Variable fastener for fixing curtain wall
CN104929297B (en) A kind of decoration panel installation of ceiling technique
CN108005276B (en) A kind of inner wall of building wall and its construction method
CN106049714B (en) Plastic-steel net combined light partition wall and construction method
CN105672656A (en) Construction method of exterior hidden frame supported glass curtain wall
CN105155846A (en) Construction method for arc-shaped reinforced concrete stand
CN206189716U (en) Assembled pendant is used to stone material aluminium honeycomb composite board furred ceiling
CN206941951U (en) A kind of combined wall board
CN208267265U (en) A kind of assembled curtain wall decoration rod structure
CN104294975B (en) A kind of aluminum facade attachment means
CN203961077U (en) The cladding system of open clay plate curtain wall
CN207829362U (en) A kind of Long-span Cantilever hyperboloid wood Decorative Construction device
CN205875486U (en) Give a new lease of life to light -duty board curtain wall construction structure of stone architectural concrete
CN205954910U (en) Beam column integration wallboard
CN1122129C (en) Construction method of indoor decoration with light wall board
CN103410334B (en) A kind of clay plate curtain wall construction method of installation
CN106567454A (en) Mounting method of oblique steel rib and concrete composite structure
CN207092300U (en) A kind of replaceable unit curtain wall system
CN207919819U (en) A kind of steel framework concrete partition
CN207513060U (en) A kind of cylinder stone material dry suspending wall construction
CN206513056U (en) Prefabricated porous plate end anti-slip ruggedized construction
CN205840071U (en) A kind of clay plate curtain wall plate seam integral type I shape connects assembly