CN104929297B - A kind of decoration panel installation of ceiling technique - Google Patents

A kind of decoration panel installation of ceiling technique Download PDF

Info

Publication number
CN104929297B
CN104929297B CN201510433711.2A CN201510433711A CN104929297B CN 104929297 B CN104929297 B CN 104929297B CN 201510433711 A CN201510433711 A CN 201510433711A CN 104929297 B CN104929297 B CN 104929297B
Authority
CN
China
Prior art keywords
hanging part
shaped
decoration panel
shape
hanging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510433711.2A
Other languages
Chinese (zh)
Other versions
CN104929297A (en
Inventor
李诗全
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu superstar mingchuang curtain wall new material Co.,Ltd.
Original Assignee
Hundred Experians (foochow) Curtain Wall Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hundred Experians (foochow) Curtain Wall Engineering Co Ltd filed Critical Hundred Experians (foochow) Curtain Wall Engineering Co Ltd
Priority to CN201510433711.2A priority Critical patent/CN104929297B/en
Publication of CN104929297A publication Critical patent/CN104929297A/en
Application granted granted Critical
Publication of CN104929297B publication Critical patent/CN104929297B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Finishing Walls (AREA)

Abstract

The present invention provides a kind of Combined type suspended ceiling suspension member, including the second connector for connecting two pieces of adjacent decoration panels for hanging the first connector and part of decoration panel to be used in the edge of furred ceiling;First connector is Z-shaped piece or L-shaped hanging part;Second connector includesShape hanging part;The horizontal sides of L-shaped hanging part,Z-shaped hanging part is all mounted with the right side horizontal sides of shape hanging part, the upper end horizontal part left end of Z-shaped hanging part has extended downwardly hanging joint;The horizontal sides of L-shaped hanging part,Adjusting screw rod is installed, adjusting screw rod is located between the vertical portion of Z-shaped hanging part and hanging joint on the right side of shape hanging part in horizontal sides.The present invention has wide range of applications, hung available for an extension, nail, apply also for that tradition is T-shaped to mount system, the invention enables the use of stone ceiling more secure, design stress point is reasonable, four angles of stone material facilitate adjustment height, it is simple in construction, it can independently dismount, save artificial, operability high, it is cost-effective while improving degree of safety.

Description

A kind of decoration panel installation of ceiling technique
Technical field
The invention belongs to building ceiling design and construction field, and in particular to a kind of Combined type suspended ceiling suitable for stone ceiling Suspension member and installation of ceiling technique.
Background technology
In existing building curtain wall technology, stone curtain wall is made up of structural support, panel and hanger system, suspension member system System is the connector that panel is attached to structural support.Common hanger system has three kinds of T-shaped formula, back bolt type and small unit type.T Pattern connection is simple, low cost, using more.The utility model patent of Application No. 201220077278.5 provides a kind of tool There is the small unit type stone ceiling hanger system that dual safety is constructed, the system is arranged on crossbeam, by some set identical groups Part is constituted, and often covering component includes main suspension member and sub- suspension member, and crossbeam side surface is fixed in described main suspension member one end, and the other end is in hook Structure, sub- suspension member one end is corresponding with main suspension member hook structure end shape and is hung on thereon, and the sub- suspension member other end is plugged in injection In the notch of the back face of stone of dry-hang glue, back face of stone also pastes the fiberglass gridding cloth of one whole, is set in back face of stone Two reinforcement aluminum strips, strengthen aluminum strip for every and are glued with stone material and are bolted with two sub- suspension members.Mounting described by the utility model Method is inconvenient into adjusting up and down, it is difficult to ensure the flatness of stone ceiling, the required precision to technique is too high, causing can not model greatly Enclose popularization and application.
In existing stone curtain wall engineering, the most common form of stone ceiling have suitable for reading, the European moulding of window lower mouth, Bottom furred ceiling of cantilevered structure etc..Lithotome Density inhomogeneity even part kind quality is loose, and bending strength is poor, stone material After installation of ceiling, stone panel is broken to come off.Most of stone ceilings do not mount system reasonably, and particularly tradition is T-shaped Suspension member, one piece of stone material thickness 25MM, hangs up decorative panel of stone material of two pieces of sides provided with notch with T-shaped, problem exists originally A notch is also opened in only 25MM thickness, notch will at least reach that 4mm is thick, and the stone material thickness at stress point has pole with regard to very little Big potential safety hazard;Existing stone ceiling hanger system also has problems with or shortcoming:First, bad regulation, reason up and down The thickness for being stone material is not every piece all the same, the bad regulation of traditional mounting system in flatness;2nd, stone ceiling plate Block can not be dismounted independently;3rd, mounting method required precision is too high, causes cost of labor too high;4th, it is designed with dragon on common furred ceiling Bone structure layer, the problems such as directly improving material cost.
The content of the invention
The technical problems to be solved by the invention are a kind of novel adjustable stone material Combined type suspended ceiling suspension members, and the present invention is carried For Combined type suspended ceiling suspension member can allow the use more secure of stone ceiling, design stress point rationally, four of stone material Angle facilitate adjustment height, have a wide range of application, available for hang or it is cladding use, point hang cost it is low, dismounting facilitate.
The Combined type suspended ceiling suspension member that the present invention is provided, it is characterised in that:Including the first connector and the second connector;It is described Decoration panel is hung in the edge that first connector is used in furred ceiling, and second connector is used to connect two pieces of adjacent facings Plate;First connector is Z-shaped piece, or is L-shaped hanging part, and the vertical edge of the L-shaped hanging part offers hanging hole;Described Two connectors includeShape hanging part, shouldThe top of shape hanging part offers hanging hole;The water of the L-shaped hanging part Flat side,Z-shaped hanging part is all mounted with the right side horizontal sides of shape hanging part, a left side for the upper end horizontal part of the Z-shaped hanging part End has extended downwardly hanging joint;The horizontal sides of the L-shaped hanging part,It is fitted with the right side horizontal sides of shape hanging part Adjusting screw rod, the adjusting screw rod is located between the vertical portion of the Z-shaped hanging part and the hanging joint.
When carrying out stone ceiling, it can realize that adjacent stone panel is hung using a lifting point using the second connector Stress is hung, i.e., adjacent stone panel all passes throughShape hanging part falls on wall, saves the use of anchor pole, while so that Mounting process simplify, adjusting screw rod on the one hand serve prevent Z-shaped hanging part from L-shaped hanging part,It is sliding on shape hanging part Fall, on the other hand, can move up and down adjusting screw rod by turning adjusting screw rod, hung so as to adjust Z-shaped hanging part in L-shaped Fitting,Height on shape hanging part, realizes the adjustment to stone panel levelness.The furred ceiling suspension member user of the present invention Just, it is easy to be adjusted the installation accuracy of stone panel.
For only including the first connector of L-shaped hanging part, it is suitable for that the stone material in edge is installed, such as At 90 ° of corners, anchor pole is implanted on vertical wall in advance, anchor pole and plane-parallel, anchor pole perpendicular to the vertical portion of L-shaped hanging part simultaneously In hanging hole;For ease of directly by the connection of the anchor pole on the first connector and top wall, first connector The upper end of vertical portion of L-shaped hanging part be extended with horizontal hanging portion to the left, the hanging hole of the first connector is opened in the level On hanging portion.
For prevent Z-shaped hanging part from L-shaped hanging part,Slid on shape hanging part, the horizontal part of the L-shaped hanging part Right-hand member upwardly extended hanging joint, it is describedThe right-hand member of the right side horizontal part of shape hanging part has upwardly extended hanging joint, hangs After connecing, L-shaped hanging part,Hanging joint on shape hanging part can effectively prevent Z-shaped hanging part from dropping.
Due to L-shaped hanging part,Hanging joint is provided with shape hanging part, to prevent dropping for Z-shaped hanging part, this When, the function of preventing Z-shaped hanging part from dropping of adjusting screw rod can be desalinated, the installation site to adjusting screw rod is adjusted so that Z Shape hanging part be articulated in L-shaped hanging part,After on shape hanging part, the upper end of the adjusting screw rod on the L-shaped hanging part and Z The bottom contact of the hanging joint of shape hanging part;The hanging joint of the L-shaped hanging part is located at vertical portion and the Z of the Z-shaped hanging part It is described between the hanging joint of shape hanging partThe upper end of adjusting screw rod on shape hanging part and the hanging joint of Z-shaped hanging part Bottom is contacted;The hanging joint of second connector be located at vertical portion and the Z-shaped hanging part of the Z-shaped hanging part hanging joint it Between, because the hanging joint of Z-shaped hanging part is extended downwardly so that adjusting screw rod somewhat back-outs the extension that some can be with Z-shaped hanging part Junction contacts are also very time saving and energy saving when adjusting stone panel levelness.
The present invention also provides a kind of decoration panel installation of ceiling technique, comprises the following steps:
(1) L-shaped hanging part is arranged on using hanging hole and planted in advance on the anchor pole of wall;The horizontal part of L-shaped hanging part is pre- Adjusting screw rod is first installed, or after L-shaped hanging part is connected with anchor pole, then the installation regulation on the horizontal part of L-shaped hanging part Screw rod;
(2) by a Z-shaped hanging part be arranged on decoration panel the back side one end, wherein, the lower end horizontal part of Z-shaped hanging part with Decoration panel is connected;Second connector is arranged on to the other end of the decoration panel simultaneously, whereinThe left end level of shape hanging part Portion is connected with the decoration panel;
(3) Z-shaped hanging part is hung over to the right-hand member of L-shaped hanging part, wherein, the hanging joint of Z-shaped hanging part is located at L-shaped hanging part Vertical portion and adjusting screw rod on L-shaped hanging part between, or positioned at the vertical portion of L-shaped connector and L-shaped connector Hanging joint between;Pass throughHanging hole on shape hanging part is installed in pre- plant on the anchor pole of wall;Shape The right side horizontal part of hanging part is provided with adjusting screw rod, Huo Zhe in advanceAfter shape hanging part is connected with anchor pole, thenAdjusting screw rod is installed on the right side horizontal part of shape hanging part;
(4) by another Z-shaped hanging part be arranged on the second decoration panel the back side, wherein, the lower end horizontal part of Z-shaped hanging part with Second decoration panel is connected;Second connector is arranged on to the other end of the second decoration panel simultaneously, whereinA left side for shape hanging part End horizontal part is connected with the second decoration panel;
(5) the Z-shaped hanging part mentioned in (4) step is hung overOn the right-hand member horizontal part of shape hanging part, wherein, it is Z-shaped The hanging joint of hanging part is located atThe right vertical portion of shape hanging part is with being arranged onAdjusting screw rod on shape hanging part it Between, or be located atThe right vertical portion of shape hanging part withBetween the hanging joint of shape hanging part;
(6) the rest may be inferred, until when being installed to last block decoration panel, hung over its right-hand member on wall using Z-shaped piece, or Person, by Z-shaped hanging part be arranged on last block decoration panel the back side, then by Z-shaped hanging part hang in advance be arranged on wall on L-shaped hanging part on.
The present invention also provides a kind of decoration panel installation of ceiling technique, comprises the following steps:
(1) back side of Z-shaped piece and decoration panel is connected;Second connector is arranged on to the other end of the decoration panel simultaneously, WhereinThe left end horizontal part of shape hanging part is connected with the decoration panel;
(2) by Z-shaped piece,Shape hanging part is connected with the anchor pole planted in advance into wall, wherein,The right side of shape hanging part Side horizontal part is provided with adjusting screw rod, Huo Zhe in advanceAfter shape hanging part is connected with anchor pole, thenShape hanging part Right side horizontal part on adjusting screw rod is installed;
(3) Z-shaped hanging part is arranged on to the back side of the second decoration panel, wherein, the lower end horizontal part of Z-shaped hanging part and second Decoration panel is connected;Another second connector is arranged on to the other end of the second decoration panel simultaneously, whereinA left side for shape hanging part End horizontal part is connected with the second decoration panel;
(4) Z-shaped hanging part is hung overOn the right-hand member horizontal part of shape hanging part, wherein, the hanging joint of Z-shaped hanging part It is located atThe right vertical portion of shape hanging part is with being arranged onBetween adjusting screw rod on shape hanging part, or it is located at The right vertical portion of shape hanging part withBetween the hanging joint of shape hanging part;
(5) the rest may be inferred, until when being installed to last block decoration panel, hung over its right-hand member on wall using Z-shaped piece, or Person, by Z-shaped hanging part be arranged on last block decoration panel the back side, then by Z-shaped hanging part hang in advance be arranged on wall on L-shaped hanging part on.
When being installed to last block decoration panel, the right side of the decoration panel also needs to install one piece of the 3rd facing normal thereto One horizontal part of Z-shaped piece, is first connected by plate with the right-hand member of last block decoration panel, recycles Z-shaped piece vertical portion to pacify the Z-shaped piece Mounted in planting in advance on the anchor pole of wall, wherein, the Z-shaped piece vertical portion is parallel with gravity direction, finally, will offer the of notch Three decoration panels are hung on another horizontal part of Z-shaped piece.
Z-shaped hanging part is hung overAfter the right side horizontal part of shape hanging part, left and right adjusts the position of Z-shaped hanging part, with The gap between adjacent stone panel is adjusted, and/or the upper of the adjusting screw rod is finely tuned through the gap between adjacent decoration panel Lower position, so that the levelness between adjusting decoration panel.
The Combined type suspended ceiling suspension member that the present invention is provided can be used for point to hang, nail is hung (centre does not set keel);It can also be applied to Tradition is T-shaped to mount system, and centre is provided with keel, and anchor pole is directly fixedly connected with the corresponding points on keel, had wide range of applications.This The there is provided Combined type suspended ceiling suspension member of invention can allow the use more secure of stone ceiling, design stress point rationally, stone Four angles of material facilitate adjustment height;The present invention is simple in construction, can independently dismount, and saves artificial, operability height, improves peace It is also cost-effective while whole step.
Brief description of the drawings
Fig. 1 is the structural representation of embodiment one;
Fig. 2 is the structural representation of embodiment two;
Fig. 3 is the structural representation of embodiment three;
Fig. 4 is example IV structural representation;
Fig. 5 is the structural representation of embodiment five;
Fig. 6 is enlarged drawing at I in Fig. 1;
Fig. 7 is enlarged drawing at II in Fig. 1;
Fig. 8 is enlarged drawing at III in Fig. 3;
Fig. 9 is enlarged drawing at IV in Fig. 2.
In figure:1-Shape hanging part;2-Z shape hanging parts;3- hanging joints one;4- adjusting screw rods;The horizontal hanging portions of 5-; 6- hanging joints three;7- hanging joints two;The vertical walls of 8-;The horizontal walls of 9-;10- stone panels;11- anchor poles;12- back of the body bolt;13-Z Word part;14-L shape hanging parts;The connectors of 15- first.
Embodiment
Embodiment one:
As shown in Fig. 1,6,7, the left end of the upper end horizontal part of Z-shaped hanging part 2 has extended downwardly hanging joint 1.
As shown in Fig. 1,7, the first connector 15 includes L-shaped hanging part 14, and the upper end of the vertical portion of L-shaped hanging part 14 is to the left It is extended with horizontal hanging portion 5, horizontal hanging portion 5 and offers hanging hole, the horizontal part of L-shaped hanging part 14 has upwardly extended mounting First 27, adjusting screw rod 4 is installed on the horizontal part of L-shaped hanging part 14.
As a shown in Figure 6, the second connector includesShape hanging part 1,The top of shape hanging part 1, which is offered, hangs Hanging hole,Adjusting screw rod 4 is installed on the right side horizontal part of shape hanging part 1.
In the present embodiment, 2 the first connectors and 2 the second connectors have been used, wherein, the second connector is used in two Block stone material junction, the first connector is used for the section start or tail end of furred ceiling, because on the one hand the second connector can be used for hanging Z-shaped hanging part is connect, on the other hand can also be connected with stone panel, is also just said, the anchor pole for installing the second connector can be simultaneously Two blocks of stone materials are hung, the use of anchor pole is reduced.
During construction, outwards constructed from corner, the first connector 15 is arranged on default on horizontal wall 9 by hanging hole On anchor pole 11 (anchor pole of the present invention both can be the parts such as common anchor pole or bolt), according to construction needs, Adjust the distance between the first connector 15 and horizontal wall 9;By the horizontal part of the lower end of Z-shaped hanging part 2, the second connectorThe right side horizontal part of shape hanging part 1 is connected by back of the body bolt 12 with stone panel 10, the second connector, the first connector point Not Wei Yu same stone panel two angles;Z-shaped hanging part is hung on the horizontal part of L-shaped hanging part 14 of the first connector, L Adjusting screw rod 4 on shape hanging part is located between the hanging joint 27 of the connector 15 of hanging joint one 3 and first of Z-shaped hanging part 2; WillShape hanging part is arranged on horizontal wall 9 on default anchor pole by hanging hole;Again by under second Z-shaped hanging part The horizontal part at end, secondThe right side horizontal part of shape hanging part 1 is connected by back of the body bolt 12 with stone panel 10, by the Z-type Hanging part is hung on previous piece of stone panelOn shape hanging part,Adjusting screw rod 4 on shape hanging part is located at Z-shaped , will between hanging part vertical portion and hanging joint 1Shape hanging part is arranged on default on horizontal wall 9 by hanging hole On anchor pole, as needed, by turning adjusting screw rod 4, the upper end of adjusting screw rod 4 is withstood on the upper end horizontal part of Z-shaped hanging part, Using moving up and down for adjusting screw rod 4, the height of stone panel is adjusted.The rest may be inferred, until installation of ceiling is completed;Due in tail End has used the first connector, when mounting the stone panel of caudal end, it is necessary to first hang the L-shaped for not mounting any stone panel Fitting is arranged on horizontal wall 9, then the Z-shaped hanging part for being provided with stone panel is hung on L-type hanging part.In two blocks of stone materials Panel junction, it is possible to need to adjust the gap between two pieces of stone panels, can be by moving left and right Z-shaped hanging part come real It is existing.In practice of construction, one piece of stone panel is generally required all carries out stress hanging on four angles.Because stone panel is general All than larger,Shape hanging part, Z-shaped hanging part are also larger, generally existTwo adjusting screw rods are set on shape hanging part, It is more convenient for adjusting flatness using two adjusting screw rods.
Embodiment two:
As shown in Fig. 2,9,2 the first connectors and 2 the second connectors have been used, wherein, the second connector is used in two Block stone material junction, the first connector is used for the section start or tail end of furred ceiling.Hanging is opened up on the vertical portion of L-shaped hanging part 14 Hole, the right-hand member of the horizontal part of L-shaped hanging part 14 has upwardly extended hanging joint 27;Adjusting screw rod 4 is located at the vertical of Z-shaped hanging part 2 Between portion and hanging joint 1.
The form of construction work of the present embodiment and embodiment one are basically identical, and difference is, due to being not provided with keel, L-shaped Hanging part 14 is arranged on vertical wall 8.
Embodiment three:
As shown in Fig. 3,8, the present embodiment has used 1 L-shaped hanging part, 2 the second connectors, 1 Z-shaped piece 13.L-shaped is hung The horizontal part right-hand member of fitting has upwardly extended hanging joint 27.The right-hand member of the right side horizontal part of shape hanging part 1 is upwardly extended There is hanging joint 36.
The form of construction work of the present embodiment and embodiment one are basically identical, and difference is, due to L-shaped hanging part, Shape hanging part is both provided with hanging joint, after mounting, and hanging joint two, hanging joint three are all located at vertical portion and the mounting of Z-shaped hanging part Between first, hanging joint two, hanging joint three serve the effect for preventing that Z-shaped hanging part from sliding, at this point it is possible to without adjusting screw rod Prevent the landing of Z-shaped hanging part, the upper end of adjusting screw rod 4 is contacted with the bottom of hanging joint two, hanging joint three, when need adjust stone During face plate flatness, adjusting screw rod is somewhat turned.It is also very simple with the form of construction work of rear-end Z-shaped piece 13, first One end of Z-shaped piece is connected with stone panel, then Z-shaped piece 13 is arranged on the anchor pole on horizontal wall 9.
Example IV:
The present embodiment and embodiment two are basically identical, and difference is:At the vertical wall in left side, hung using L-shaped The right-hand member of the horizontal part of fitting has not upwardly extended hanging joint two.At the also rear-end vertical wall of the present embodiment, one is utilized Individual Z-shaped piece 13 mounts two pieces of stone panels simultaneously, wherein, the stone panel of horizontal level is connected by back of the body bolt with Z-shaped piece, vertically Acclivitous skewed slot is offered on the stone panel of position, mount the Z-shaped piece of the stone panel corresponding site be fabricated to Upper inclined lattice framing, lattice framing is inserted mounting is realized in skewed slot, during construction, the furred ceiling stone panel peace of advanced row horizontal level Dress, i.e. be connected a horizontal part of Z-shaped piece with the stone panel back side, then by the vertical portion of Z-shaped piece installed in planting in advance into wall Anchor pole on, the vertical portion of Z-shaped piece is parallel with gravity direction, and the stone panel for offering inclined notch finally is hung over into Z-shaped piece On another horizontal part (be fabricated to and be inclined upwardly).
Embodiment five:
The present embodiment and embodiment three are basically identical, and difference is:In wall body vertical intersection, Z-shaped piece 13 is utilized Mounting is realized, is directly connected Z-shaped piece with stone panel, then Z-shaped piece is arranged on anchor pole.
For enhancing stability, L-shaped hanging part, Z-shaped piece,Shape hanging part, Z-shaped hanging part and stone panel installation portion Position can interstitital texture glue, L-shaped hanging part,The hitching position of shape hanging part and Z-shaped hanging part, which can set up crash roll, to be prevented Shake.

Claims (4)

1. a kind of decoration panel installation of ceiling technique, it is characterised in that comprise the following steps:
(1) L-shaped hanging part is arranged on using hanging hole and planted in advance on the anchor pole of wall;The horizontal part of L-shaped hanging part is pacified in advance Adjusting screw rod is installed, or adjusting screw rod is installed after L-shaped hanging part is connected with anchor pole, then on the horizontal part of L-shaped hanging part;
(2) a Z-shaped hanging part is arranged on to the one end at the back side of decoration panel, wherein, the lower end horizontal part and facing of Z-shaped hanging part Plate is connected;Second connector is arranged on to the other end of the decoration panel simultaneously, whereinThe left end horizontal part of shape hanging part with The decoration panel is connected;
(3) Z-shaped hanging part is hung over to the right-hand member of L-shaped hanging part, wherein, the hanging joint of Z-shaped hanging part is located at the perpendicular of L-shaped hanging part Between straight portion and adjusting screw rod on L-shaped hanging part, or positioned at the vertical portion of L-shaped connector and the extension of L-shaped connector Between joint;Pass throughHanging hole on shape hanging part is installed in pre- plant on the anchor pole of wall;Shape hanging part Right side horizontal part adjusting screw rod, Huo Zhe are installed in advanceAfter shape hanging part is connected with anchor pole, thenShape is mounted Adjusting screw rod is installed on the right side horizontal part of part;
(4) another Z-shaped hanging part is arranged on to the back side of the second decoration panel, wherein, the lower end horizontal part of Z-shaped hanging part and second Decoration panel is connected;Second connector is arranged on to the other end of the second decoration panel simultaneously, whereinThe left end water of shape hanging part Flat portion is connected with the second decoration panel;
(5) the Z-shaped hanging part mentioned in (4) step is hung overOn the right-hand member horizontal part of shape hanging part, wherein, Z-shaped mounting The hanging joint of part is located atThe right vertical portion of shape hanging part is with being arranged onBetween adjusting screw rod on shape hanging part, Or be located atThe right vertical portion of shape hanging part withBetween the hanging joint of shape hanging part;
(6) the rest may be inferred, until when being installed to last block decoration panel, hung over its right-hand member on wall using Z-shaped piece, or, Z-shaped hanging part is arranged on to the back side of last block decoration panel, then Z-shaped hanging part is hung over to the L being arranged in advance on wall On shape hanging part.
2. a kind of decoration panel installation of ceiling technique, it is characterised in that comprise the following steps:
(1) back side of Z-shaped piece and decoration panel is connected;Second connector is arranged on to the other end of the decoration panel simultaneously, whereinThe left end horizontal part of shape hanging part is connected with the decoration panel;
(2) by Z-shaped piece,Shape hanging part is connected with the anchor pole planted in advance into wall, wherein,The right side level of shape hanging part Portion is provided with adjusting screw rod, Huo Zhe in advanceAfter shape hanging part is connected with anchor pole, thenThe right side water of shape hanging part Adjusting screw rod is installed in flat portion;
(3) Z-shaped hanging part is arranged on to the back side of the second decoration panel, wherein, the lower end horizontal part and the second facing of Z-shaped hanging part Plate is connected;Another second connector is arranged on to the other end of the second decoration panel simultaneously, whereinThe left end water of shape hanging part Flat portion is connected with the second decoration panel;
(4) Z-shaped hanging part is hung overOn the right-hand member horizontal part of shape hanging part, wherein, the hanging joint of Z-shaped hanging part is located atThe right vertical portion of shape hanging part is with being arranged onBetween adjusting screw rod on shape hanging part, or it is located atShape is hung The right vertical portion of fitting withBetween the hanging joint of shape hanging part;
(5) the rest may be inferred, until when being installed to last block decoration panel, hung over its right-hand member on wall using Z-shaped piece, or, Z-shaped hanging part is arranged on to the back side of last block decoration panel, then Z-shaped hanging part is hung over to the L being arranged in advance on wall On shape hanging part.
3. decoration panel installation of ceiling technique as claimed in claim 1 or 2, it is characterised in that:When being installed to last block facing During plate, the right side of the decoration panel also needs to install one piece of the 3rd decoration panel normal thereto, first by a horizontal part of Z-shaped piece and finally The right-hand member connection of one piece of decoration panel, recycles Z-shaped piece vertical portion to be arranged on the Z-shaped piece and plants in advance on the anchor pole of wall, wherein, The Z-shaped piece vertical portion is parallel with gravity direction, finally, and the 3rd decoration panel for offering notch is hung over to another level of Z-shaped piece In portion.
4. decoration panel installation of ceiling technique as claimed in claim 1 or 2, it is characterised in that:Z-shaped hanging part is hung overShape After the right side horizontal part of hanging part, left and right adjusts the position of Z-shaped hanging part, to adjust the gap between adjacent decoration panel, and/or The upper-lower position of the adjusting screw rod is finely tuned through the gap between adjacent decoration panel, so that the level between adjusting decoration panel Degree.
CN201510433711.2A 2015-07-22 2015-07-22 A kind of decoration panel installation of ceiling technique Active CN104929297B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510433711.2A CN104929297B (en) 2015-07-22 2015-07-22 A kind of decoration panel installation of ceiling technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510433711.2A CN104929297B (en) 2015-07-22 2015-07-22 A kind of decoration panel installation of ceiling technique

Publications (2)

Publication Number Publication Date
CN104929297A CN104929297A (en) 2015-09-23
CN104929297B true CN104929297B (en) 2017-08-11

Family

ID=54116702

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510433711.2A Active CN104929297B (en) 2015-07-22 2015-07-22 A kind of decoration panel installation of ceiling technique

Country Status (1)

Country Link
CN (1) CN104929297B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105201121B (en) * 2015-09-30 2017-09-19 浙江亚厦装饰股份有限公司 A kind of Integral ceiling facing board mounting structure
CN105937286B (en) * 2016-06-29 2018-04-13 苏州金螳螂建筑装饰股份有限公司 A kind of adjustable aluminium sheet ceiling connecting structure
CN106368368B (en) * 2016-11-14 2018-07-03 陕西鼎盛装饰工程有限责任公司 Based on T-shaped and Z-type pendant stone material aluminium honeycomb composite plate ceiling construction method
CN107313548B (en) * 2017-06-26 2022-09-23 浙江未来加电子商务有限公司 Adjustable wall hanging device
CN108643969A (en) * 2018-04-11 2018-10-12 贵州开磷集团股份有限公司 A kind of hanging apparatus and the method that object is hung on roadway inner top panel
WO2020175000A1 (en) 2019-02-28 2020-09-03 パナソニックIpマネジメント株式会社 Ceiling panel
CN110847350A (en) * 2019-12-19 2020-02-28 葛斌斌 Keel-free ceiling suspended structure and construction method thereof
CN112252566B (en) * 2020-10-27 2021-11-05 怀化简美装饰设计工程有限公司 Wall corner suspended ceiling structure for interior decoration

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4920719A (en) * 1989-03-13 1990-05-01 Armstrong World Industries, Inc. Method and apparatus of positioning a new ceiling over an existing ceiling
US5598678A (en) * 1995-06-07 1997-02-04 Reynolds; Henry B. Ceiling devices
JPH10227093A (en) * 1997-02-17 1998-08-25 Toppan Printing Co Ltd Double ceiling backing method
CN103174275B (en) * 2011-12-21 2015-08-05 王云飞 Heat insulating decorative board hanging fastener component and mounting method thereof
CN102587551A (en) * 2012-03-05 2012-07-18 秦皇岛市中贤幕墙装饰工程有限公司 Small unit type stone ceiling hanging piece system with double-safety structure
CN202658822U (en) * 2012-06-27 2013-01-09 中建七局建筑装饰工程有限公司 Open-type ceiling board
CN103437472B (en) * 2013-07-19 2015-08-05 百益百利(福州)幕墙工程有限公司 Decorating building stone panel fixing device and construction method
CN103669671B (en) * 2013-12-29 2015-12-02 中国建筑第七工程局有限公司 Stone material cellular compound plate ceiling system
CN204850208U (en) * 2015-07-22 2015-12-09 百益百利(福州)幕墙工程有限公司 Modular furred ceiling pendant

Also Published As

Publication number Publication date
CN104929297A (en) 2015-09-23

Similar Documents

Publication Publication Date Title
CN104929297B (en) A kind of decoration panel installation of ceiling technique
CN206737222U (en) Cell cube section curtain wall installing device
CN102947519A (en) Variable fastener for fixing curtain wall
CN204126102U (en) A kind of sheet material fast-assembling ceiling structure
CN107327111A (en) A kind of dried hanging hang structure and finishing systems
CN105178495B (en) A kind of suspended ceiling keel system and its construction method
CN110424661A (en) The construction method of dry hanging granite plate
CN207988526U (en) The erecting by overhang of unit type curtain wall plate
CN108286319A (en) Furring tile cladding system and construction method
CN106760092B (en) Seamless hanging system for ceramic thin plate-glass composite plate
CN207003902U (en) A kind of decorative panel suspension member and Side fascia
CN205712911U (en) A kind of Stone-ceramic brick dry hanging article
CN209509297U (en) The assembled furred ceiling of decoration panel is plugged and fixed
CN207177178U (en) A kind of single hook sheet material metope hanger structure
CN106368368B (en) Based on T-shaped and Z-type pendant stone material aluminium honeycomb composite plate ceiling construction method
CN207122081U (en) A kind of dried hanging hang structure and finishing systems
CN204850208U (en) Modular furred ceiling pendant
CN2679267Y (en) 3-D regulatable connection structure of stone curtain wall
CN210917906U (en) Detachable ceiling edge keel system
CN208473060U (en) A kind of metal curtain wall
CN208563849U (en) Exterior wall cladding external corner connecting elements
CN203307971U (en) Unit type energy-saving pottery clay plate curtain wall
CN205077805U (en) Dry pendant mounting structure of wall
CN108385895A (en) A kind of fast-assembling walling system
CN211499622U (en) Ground overhead device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20201109

Address after: 233000 Xianghe Home Floor No.9, Xinhuai Road, Dongsheng Street, Longzihu District, Bengbu City, Anhui Province

Patentee after: Bengbu Qibang Science and Technology Information Consulting Co.,Ltd.

Address before: M9511 Industrial Park No. 18 Majiang road Mawei District 350015 in Fujian province Fuzhou City 4 floor 4 floor East

Patentee before: BAIYI BAILI (FUZHOU) CURTAIN WALL ENGINEERING Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210330

Address after: 213001 No. 536, Hehai West Road, Xinbei District, Changzhou City, Jiangsu Province

Patentee after: Jiangsu superstar mingchuang curtain wall new material Co.,Ltd.

Address before: 233000 No.9, 1st floor, Xianghe Jiayuan, Xinhuai Road, Dongsheng Street, Longzihu District, Bengbu City, Anhui Province

Patentee before: Bengbu Qibang Science and Technology Information Consulting Co.,Ltd.