CN105672656A - Construction method of exterior hidden frame supported glass curtain wall - Google Patents

Construction method of exterior hidden frame supported glass curtain wall Download PDF

Info

Publication number
CN105672656A
CN105672656A CN201410665209.XA CN201410665209A CN105672656A CN 105672656 A CN105672656 A CN 105672656A CN 201410665209 A CN201410665209 A CN 201410665209A CN 105672656 A CN105672656 A CN 105672656A
Authority
CN
China
Prior art keywords
column
glass
crossbeam
installing
curtain wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410665209.XA
Other languages
Chinese (zh)
Inventor
杨清江
陈乐�
李慧敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MCC5 Group Shanghai Corp Ltd
Original Assignee
MCC5 Group Shanghai Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC5 Group Shanghai Corp Ltd filed Critical MCC5 Group Shanghai Corp Ltd
Priority to CN201410665209.XA priority Critical patent/CN105672656A/en
Publication of CN105672656A publication Critical patent/CN105672656A/en
Pending legal-status Critical Current

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

Provided is a construction method of an exterior hidden frame supported glass curtain wall. The glass of the exterior hidden frame supported glass curtain wall is installed outside a vertical keel and placed on a transverse keel. All vertical frameworks of a framework system are firmly connected with pre-buried iron accessories in structural concrete. The construction method is characterized by comprising following steps: a, examining a main body structure and pre-buried iron accessories; b, installing supports and columns; c, installing crossbeams; d, installing rock wool; e, installing glass press blocks; f, installing glass boards and g gluing and caulking. The construction method of the exterior hidden frame supported glass curtain wall has following advantages: the construction method is standardized and reasonable in design of construction steps, easy in operation, quick in construction speed, safe and reliable in engineering quality, short working period and valuable economic benefit.

Description

The full concealed frame glass curtain wall construction method of exterior wall
Technical field
The present invention relates to a kind of Glass Curtain Wall Construction method, specifically, be a kind of full concealed frame glass curtain wall construction method of exterior wall.
Background technology
Glass curtain wall, refer to that be made up of with glass support system, relative agent structure can have certain displacement ability, do not share agent structure institute building external envelope structure the affected or decorating structure. Body of wall has monolayer and double glazing two kinds, and glass curtain wall is the construction wall trailing of a kind of novelty attractive in appearance, is the marked feature in modernism skyscraper epoch.
The feature of glass curtain wall:
1) handsome in appearance: facade effect is enriched, lines sense is strong, graceful, harmonious, smooth, and appreciative value is high. The inboard of curtain wall glass outer is coated with coloured metal coating, and from the appearance full wafer exterior wall is just as mirror, mirrors wherein by the scenery of sky and surrounding, and during light change, colors of image is bright-colored, with countless changes. Under the reflection of light, indoor are not by strong illumination, and vision is soft.
2) safe and reliable: structure construction fully takes into account the impact on curtain wall such as deadweight, wind load.
3) be conducive to environmental protection, save the energy.
4) easy for installation, detachable, easy to maintenance.
5) glass curtain wall can reduce the environmental pollution such as dust, waste water compared with the construction of other finishing material.
But, in Glass Curtain Wall Construction, Problems existing is also a lot, and such as glass breaking, structure glue lost efficacy, glass curtain wall fire protecting performance is poor, glass curtain wall supporting construction lost efficacy, and device for fixing glass curtain wall lost efficacy, structure glue Construction on Environment and equipment requirements are higher, as there being temperature and humidity control etc.
Therefore, current domestic built or be still in the stage lack of standardization building the construction of exterior wall full concealed frame glass curtain wall, there is a lot of not science, irrational place, manufacturing process is numerous and diverse, manufacturing cost is high.
Therefore the construction of known exterior wall full concealed frame glass curtain wall also exists above-mentioned all inconvenience and problem.
Summary of the invention
The purpose of the present invention, is in that to propose a kind of full concealed frame glass curtain wall construction method of exterior wall.
For achieving the above object, the technical solution of the present invention is:
A kind of full concealed frame glass curtain wall construction method of exterior wall, the glass of the full concealed frame glass curtain wall of exterior wall is arranged on outside vertical keel, being shelved in lateral keel, the vertical framework of every of frame system is all firmly connected with the embedded iron parts in structural concrete, it is characterised in that comprise the following steps:
A, agent structure, built-in fitting inspection:
(1) about built-in fitting, the inspection of upper lower deviation
First by surveying and locating personnel by the location line bullet of bearing on the body construction, be easy to workmen carry out checking, record, check that whether built-in fitting centrage is consistent with the location line of bearing, line is positioned by cross, check about built-in fitting, upper and lower deviation, if deviation great Bao design department propose built-in fitting amendment scheme;
(2) inspection of structural bearings
After the location line bullet of bearing is good, draws vertical steel wire at structure place according to external control net, and x wire is as installing control line; Check absolute altitude and the built-in fitting size of structure, inspection size is recorded, feeds back to technician and quality person;
(3) built-in fitting is if any deviation, will adopt rearmounted, and fix with chemical bolt, and typical construction form is carried out pull-out test;
The installation of b, bearing and column
(1) connection of bearing and column
Consider safety and the operability of construction and installation, first bearing is coupled together with handware bolt and column by column before the mounting in floor, bearing and column contact position add isolating pad, it is prevented that potential difference is corroded, the area that the area of isolating pad can not contact with perpendicular material less than connector; After connection, tie up with rope and hang out floor, then carry out installation in place;
(2) column is installed and is regulated
Hang out after floor until column, bearing is connected by T-bolt with built-in fitting, first bolt is placed in groove, rotate 90oAfter again bolt is screwed to 6 points tight, carry out the adjustment of top to bottom, left and right, front and rear; Tighten again after meeting the requirements on inspection, just, left and right control within 2-3mm;
(3) lattice of column is installed and is controlled
The installation of column is adjusted installing according to vertical steel straight line and horizontal fish silk thread, until being respectively of the required size, column carries out the inspection of axial deviation after installing, otherwise can affect the installation of horizontal material;
(4) after bottom column installs, when installing last layer column, sleeve is installed between two columns and stays and meet 15mm, in order to flexible; Between two columns, gluing seals, it is prevented that rainwater is invaded;
C, crossbeam are installed
(1), after column installs, first corner brace is inserted into the two ends of crossbeam, is carried on a shoulder pole by crossbeam, be then fixed on column with bolt by crossbeam before installing by crossbeam; Position, hole on the Kong Weiyu column of corner brace adopts interference fits, the size in hole big 0.1~0.2 millimeter than screw diameter;
(2) between crossbeam and column, carry out heat treatment, whole crossbeam size should than lattice size short 4~4.5mm, 2mm antinoise shaping piece is installed at crossbeam two ends;
(3) crossbeam is in installation process, and the height at crossbeam two ends should control within the scope of ± 1mm, and the same face absolute altitude deviation is not more than 3mm;
D, rock wool are installed
The first region polishing of 150mm*150mm on backboard, is then bonded in nail on backboard, then by nail sealant sealing, finally fixes rock wool again on backboard;
E, glass briquetting are installed
(1) being unkitted before glass plate, be first fixed on crossbeam, column by glass briquetting, being generally tightened to pressing plate has assemblage gap, after glass plate is installed, left and right, adjusts up and down, adjusts and complete is tightened by bolt again;
(2) the secondary frame of the glass plate of hidden frame is fixed on aluminum alloy frame by briquetting, and the installation of briquetting should meet designing requirement, and briquetting is no less than 300mm, and is not more than 300mm from edges of boards 100mm arrangement pitch, connects fastening with bolt back-off;
F, glass plate are installed
(1) transport of glass tower crane is to after having the floor of operation platform, again through the position that manpower transport to each floor needs, carries out every block of glass when installing, transports to institute's installation site with manual sucker again by manpower;
(2) after briquetting is installed, carry out the installation of glass plate, glass plate is hung on crossbeam lightly and moves left and right, be pushed in briquetting, be adjusted according to vertical lattice wire, tight a bolt after adjusting;
(3) glass plate is installed according to plate numbering figure, must not be interchangeable by the plate that difference is numbered in work progress, the relation of outer plate in simultaneously noting, it is prevented that glass produces color variations after installing;
G, gluing filleting
Glass plate checks that whether whole plate face is smooth vertical and horizontal after installing, and clogs foam rods and carry out gluing after passed examination;
(1) fully clean gap between sheet material, should not have water, oil stain, dust and other impurities, should fully clean adhesive surface, be dried;
(2) thickness of gluing is the 1/2 of seam width, and gluing must be uniform, continuous, full, and frictioning must smooth, and joint does not stay concavo-convex, lines defect; Silicone construction sealant bonds on seam planted agent two opposite, does not answer three bondings;
(3) paper of taping is firmly closely knit, and corner and joint connect smooth and easy and be close to edges of boards. Adhesive tape is not allow for dehiscing, coming off when pasting, not straight phenomenon;
(4), after gluing, in time adhesive tape should be cleaned out when glue is quick-drying, and the glue surface damaged when immediately treating because of tear tape;
(5) what the thickness of gluing should not be beaten is too thin or too thick, and colloid surface should be smooth, smooth, and cleaning glass is without dirt; Bind, edge sealing, back cover should firmly attractive in appearance, do not seep water, the water bound should be arranged inwards;
(6), after gluing, in time the glue polluting plate face is cleaned out.
The full concealed frame glass curtain wall construction method of exterior wall of the present invention can also be further achieved by the following technical measures.
Aforesaid method, wherein said lattice is installed in controlling, and axial deviation controls within the scope of ± 1mm, and between perpendicular material, lattice size Control is at ± 1mm.
Aforesaid method, wherein said sleeve is vertically connected with intubating length and cannot be less than 200mm.
Aforesaid method, wherein said glass plate in an installation, adjacent two cell board difference of height < 1mm, stitch width ± 1mm.
After adopting technique scheme, the full concealed frame glass curtain wall construction method of exterior wall of the present invention has the advantage that
1, construction procedure design specification is reasonable, simple to operate, speed of application is fast;
2, construction quality is safe and reliable, the reduction of erection time, and economic benefit is valuable, and the practice of construction duration shortens 50 days than time limit for contract, thus produces direct economic benefit and is: saves 50 days * 300 yuan/(man day)=495000 yuan of labour cost 33 people *; Equipment leasing and depreciation cost: 50 days * 1500 yuan/days=75000 yuan; Management 50 days * 600 yuan/(man day)=630000 yuan of cost 21 people *, also create favorable conditions for project construction in later period;
3, contribute for exploiting the overseas market.
Accompanying drawing explanation
Fig. 1 is the built-in fitting detection schematic diagram of the embodiment of the present invention;
Fig. 2 is two column vertical expansion joint schematic diagrams of the embodiment of the present invention;
Fig. 3 is that the crossbeam of the embodiment of the present invention is at scheme of installation;
Fig. 4 be the glass plate of the embodiment of the present invention in mounting and adjusting process, adjacent two cell board differences of height control schematic diagrams.
In figure: 1 built-in fitting, 2 longitudinal lattice lines of ink marker, the 3 transverse dividing lines of ink marker, 4 sleeves, 5 fluid sealants, 6 columns, 7 crossbeams, 8 glass plates.
Detailed description of the invention
Below in conjunction with embodiment and accompanying drawing thereof, the present invention is illustrated further.
Embodiment 1
Within 2014, Fire Department of Kuwait control building project structure form is reinforced concrete frame structure, and superstructure is G+6 layer, construction area 22000 square metres, and exterior wall is full concealed frame glass curtain wall, and exterior wall glass curtain wall area is 4200 square meters. The full concealed frame glass curtain wall sequence of construction of exterior wall of the present invention: installation → crossbeam of structure, the inspection → unwrapping wire of built-in fitting, ejection column frame bar, horizontal line → bearing and column installs → the lightning-arrest installation → glass installation → gluing of installation → insulation → interlayer fire prevention → concealment acceptance → glass briquetting, cleaning.
The full concealed frame glass curtain wall construction method of exterior wall of the present invention, the structure of the full concealed frame glass curtain wall of exterior wall be in advance with structure glue by glass bonding on instrument bezel, seal with structure sealant between instrument bezel, the sash of aluminium alloy element composition fixes instrument bezel, the upper ledge of instrument bezel hangs on the crossbeam of the whole sash system of aluminium alloy, glass is clear hollow plated film minute surface reflecting glass, instrument bezel and aluminium alloy sash system are all hidden after glass, aluminum alloy frame is can't see from outside, form a large-area direct reflection screen curtain wall, the whole load of curtain wall passes to aluminum alloy frame by glass by glue, it is characterized in that comprising the following steps:
A, agent structure, built-in fitting inspection:
Fig. 1 is the built-in fitting detection schematic diagram of the embodiment of the present invention.
(1) about built-in fitting, the inspection of upper lower deviation
First by surveying and locating personnel by the location line bullet of bearing on constructure body structure, be easy to workmen carry out checking, record, check that whether built-in fitting centrage is consistent with the location line of bearing, line is positioned by cross, check about built-in fitting, upper and lower deviation, if deviation great Bao design department propose built-in fitting amendment scheme;
(2) inspection of structural bearings
After the location line bullet of bearing is good, draws vertical steel wire at structure place according to external control net, and x wire is as installing control line; Check absolute altitude and the built-in fitting size of structure, inspection size is recorded, feeds back to technician and quality person;
(3) built-in fitting is if any deviation, will adopt rearmounted, and fix with chemical bolt, and typical construction form is carried out pull-out test;
The installation of b, bearing and column
(1) connection of bearing and column
Consider safety and the operability of construction and installation, first bearing is coupled together with handware bolt and column by column before the mounting in floor, bearing and column contact position add isolating pad, it is prevented that potential difference is corroded, the area that the area of isolating pad can not contact with perpendicular material less than connector; After connection, tie up with rope and hang out floor, then carry out installation in place. (curtain wall is for facing limit operation, it is prevented that high-altitude junk)
(2) column is installed and is regulated
Fig. 2 is two column vertical expansion joint schematic diagrams of the embodiment of the present invention.
Hang out after floor until column, bearing is connected by T-bolt with embedded part, first bolt is placed in groove, rotate 90. After again bolt is screwed to 6 points tight, carry out the adjustment of top to bottom, left and right, front and rear. Tighten again after meeting the requirements on inspection, just, left and right control within 2 3mm;
(3) lattice of column is installed and is controlled
The installation of column is adjusted installing according to vertical steel straight line and horizontal fish silk thread, until being respectively of the required size, column carries out the inspection of axial deviation after installing, and axial deviation controls within the scope of ± 1mm, between perpendicular material, lattice size Control is at ± 1mm, otherwise can affect the installation of horizontal material.
(4) after bottom column installs, when installing last layer column, sleeve is installed between two columns and stays and meet 15mm, in order to flexible. It is complete that adjustment installed by column, and between two columns, gluing seals, it is prevented that rainwater is invaded. It is vertically connected with sleeve intubating length and cannot be less than 200mm;
C, crossbeam are installed
Fig. 3 is that the crossbeam of the embodiment of the present invention is at scheme of installation.
(1) column carries out the installation of crossbeam after all installing, and before crossbeam is not installed, first corner brace is inserted into the two ends of crossbeam, is carried on a shoulder pole by crossbeam. Then it is fixed by bolts on column. Crossbeam bears the weight of glass, is easily generated torsion, thus the Kong Weiying of position, hole on column, corner brace adopts interference fits, the size in hole big 0.1~0.2 millimeter than screw diameter.
(2) noise can be produced owing to aluminium alloy curtain wall expands with heat and contract with cold, this factor is considered in design, between crossbeam and column, carry out heat treatment, whole crossbeam size should than lattice size short 4~4.5mm, 2mm antinoise shaping piece (2mm seam or gluing process) is installed at crossbeam two ends.
(3) crossbeam is in installation process, and the height at crossbeam two ends should control within the scope of ± 1mm. The same face absolute altitude deviation is not more than 3mm;
D, rock wool are installed
The first region polishing of 150mm*150mm on backboard, is then bonded in nail on backboard, then by nail sealant sealing, finally fixes rock wool again on backboard;
E, glass briquetting are installed
(1) being unkitted before glass plate, be first fixed on crossbeam, column by glass briquetting, being generally tightened to pressing plate has assemblage gap, after glass plate is installed, left and right, adjusts up and down, adjusts and complete is tightened by bolt again.
(2) the secondary frame of the glass plate of hidden frame is fixed on aluminum alloy frame by briquetting, and the installation of briquetting should meet designing requirement, and briquetting is no less than 300mm, and is not more than 300mm from edges of boards 100mm arrangement pitch, connects fastening with bolt back-off;
F, glass plate are installed
Fig. 4 be the glass plate of the embodiment of the present invention in mounting and adjusting process, adjacent two cell board differences of height control schematic diagrams.
(1) transport of glass tower crane is to after having the floor (the 3rd layer and the 5th layer) of operation platform, again through the position that manpower transport to each floor needs, carries out every block of glass when installing, with manual sucker pass through manpower transporting to installation site;
(2) after briquetting is installed, carry out the installation of glass plate, glass plate is hung on crossbeam lightly and moves left and right, be pushed in briquetting, be adjusted according to vertical lattice wire, tight a bolt after adjusting.
(3) glass plate is in mounting and adjusting process, and adjacent two cell board differences of height control at < 1mm, and seam width controls at ± 1mm.
(4) glass plate is installed according to plate numbering figure, must not be interchangeable by the plate that difference is numbered in work progress. The relation of outer plate in simultaneously noting, it is prevented that glass produces color variations after installing;
G, gluing filleting
Glass plate checks that whether whole plate face is smooth vertical and horizontal after installing, and clogs foam rods and carry out gluing after passed examination.
(1) fully clean gap between sheet material, should not have water, oil stain, dust and other impurities, should fully clean adhesive surface, be dried.
(2) thickness of gluing is the 1/2 of seam width. Gluing must uniformly, and continuous full frictioning must smooth. Joint does not stay the defects such as concavo-convex, lines. Silicone construction sealant bonds on seam planted agent two opposite, does not answer three bondings
(3) paper of taping is firmly closely knit, and corner and joint connect smooth and easy and be close to edges of boards. The phenomenons such as adhesive tape is not allow for dehiscing, coming off when pasting, not straight.
(4), after gluing, in time adhesive tape should be cleaned out when glue is quick-drying, and the glue surface damaged when immediately treating because of tear tape.
(5) what the thickness of gluing should not be beaten is too thin or too thick. And colloid surface should be smooth, smooth, cleaning glass is without dirt. Bind, edge sealing, back cover should firmly attractive in appearance, do not seep water, the water bound should be arranged inwards.
(6) after gluing, in time the glue polluting plate face is cleaned out, complete the full concealed frame glass curtain wall construction of exterior wall.
The present invention has substantive distinguishing features and significant technological progress, the exterior wall full concealed frame glass curtain wall construction method of the present invention according to construction drawing in processing factory by required vertical, horizontal aluminum alloy frame batch machining terminates, after building owner's body structure construction terminates, the position of the embedded iron parts according to early stage concrete structure outer wall carries out city's roads again, after calibrating position, again vertical aluminum alloy frame stainless steel bolt is fixed, then further according to drawing position, horizontal aluminum alloy frame is installed, then glass and sealing joint strip are installed, last again with sealant sealing, thus forming full built-in-frame type glass curtain. the construction procedure design specification of the exterior wall full concealed frame glass curtain wall construction method of the present invention is reasonable, simple to operate, speed of application fast, and direct economic benefit is notable, also contributes for exploiting the overseas market.
The full concealed frame glass curtain wall construction method of exterior wall of the present invention is used in Fire Department of Kuwait control building engineering in 2014, and effect is notable, and construction quality and progress obtain praising highly of owner, and the continuation cooperation for both sides is laid a good foundation.Adopt this technique to also reduce our construction cost simultaneously, reach intended cost objective, remarkable in economical benefits.
Above example is used for illustrative purposes only, but not limitation of the present invention, person skilled in the relevant technique, without departing from the spirit and scope of the present invention, it is also possible to make various conversion or change. Therefore, all equivalent technical schemes also should belong to scope of the invention, should be limited by each claim.

Claims (4)

1. the full concealed frame glass curtain wall construction method of exterior wall, the glass of the full concealed frame glass curtain wall of exterior wall is arranged on outside vertical keel, being shelved in lateral keel, the vertical framework of every of frame system is all firmly connected with the embedded iron parts in structural concrete, it is characterised in that comprise the following steps:
A, agent structure, built-in fitting inspection:
(1) about built-in fitting, the inspection of upper lower deviation
First by surveying and locating personnel by the location line bullet of bearing on the body construction, be easy to workmen carry out checking, record, check that whether built-in fitting centrage is consistent with the location line of bearing, line is positioned by cross, check about built-in fitting, upper and lower deviation, if deviation great Bao design department propose built-in fitting amendment scheme;
(2) inspection of structural bearings
After the location line bullet of bearing is good, draws vertical steel wire at structure place according to external control net, and x wire is as installing control line; Check absolute altitude and the built-in fitting size of structure, inspection size is recorded, feeds back to technician and quality person;
(3) built-in fitting is if any deviation, will adopt rearmounted, and fix with chemical bolt, and typical construction form is carried out pull-out test;
The installation of b, bearing and column
(1) connection of bearing and column
Consider safety and the operability of construction and installation, first bearing is coupled together with handware bolt and column by column before the mounting in floor, bearing and column contact position add isolating pad, it is prevented that potential difference is corroded, the area that the area of isolating pad can not contact with perpendicular material less than connector; After connection, tie up with rope and hang out floor, then carry out installation in place;
(2) column is installed and is regulated
Hang out after floor until column, bearing is connected by T-bolt with built-in fitting, first bolt is placed in groove, rotate 90oAfter again bolt is screwed to 6 points tight, carry out the adjustment of top to bottom, left and right, front and rear; Tighten again after meeting the requirements on inspection, just, left and right control within 2-3mm;
(3) lattice of column is installed and is controlled
The installation of column is adjusted installing according to vertical steel straight line and horizontal fish silk thread, until being respectively of the required size, column carries out the inspection of axial deviation after installing, otherwise can affect the installation of horizontal material;
(4) after bottom column installs, when installing last layer column, sleeve is installed between two columns and stays and meet 15mm, in order to flexible; Between two columns, gluing seals, it is prevented that rainwater is invaded;
C, crossbeam are installed
(1), after column installs, first corner brace is inserted into the two ends of crossbeam, is carried on a shoulder pole by crossbeam, be then fixed on column with bolt by crossbeam before installing by crossbeam; Position, hole on the Kong Weiyu column of corner brace adopts interference fits, the size in hole big 0.1~0.2 millimeter than screw diameter;
(2) between crossbeam and column, carry out heat treatment, whole crossbeam size should than lattice size short 4~4.5mm, 2mm antinoise shaping piece is installed at crossbeam two ends;
(3) crossbeam is in installation process, and the height at crossbeam two ends should control within the scope of ± 1mm, and the same face absolute altitude deviation is not more than 3mm;
D, rock wool are installed
The first region polishing of 150mm*150mm on backboard, is then bonded in nail on backboard, then by nail sealant sealing, finally fixes rock wool again on backboard;
E, glass briquetting are installed
(1) being unkitted before glass plate, be first fixed on crossbeam, column by glass briquetting, being generally tightened to pressing plate has assemblage gap, after glass plate is installed, left and right, adjusts up and down, adjusts and complete is tightened by bolt again;
(2) the secondary frame of the glass plate of hidden frame is fixed on aluminum alloy frame by briquetting, and the installation of briquetting should meet designing requirement, and briquetting is no less than 300mm, and is not more than 300mm from edges of boards 100mm arrangement pitch, connects fastening with bolt back-off;
F, glass plate are installed
(1) transport of glass tower crane is to after having the floor of operation platform, again through the position that manpower transport to each floor needs, carries out every block of glass when installing, transports to institute's installation site with manual sucker again by manpower;
(2) after briquetting is installed, carry out the installation of glass plate, glass plate is hung on crossbeam lightly and moves left and right, be pushed in briquetting, be adjusted according to vertical lattice wire, tight a bolt after adjusting;
(3) glass plate is installed according to plate numbering figure, must not be interchangeable by the plate that difference is numbered in work progress, the relation of outer plate in simultaneously noting, it is prevented that glass produces color variations after installing;
G, gluing filleting
Glass plate checks that whether whole plate face is smooth vertical and horizontal after installing, and clogs foam rods and carry out gluing after passed examination;
(1) fully clean gap between sheet material, should not have water, oil stain, dust and other impurities, should fully clean adhesive surface, be dried;
(2) thickness of gluing is the 1/2 of seam width, and gluing must be uniform, continuous, full, and frictioning must smooth, and joint does not stay concavo-convex, lines defect; Silicone construction sealant bonds on seam planted agent two opposite, does not answer three bondings;
(3) paper of taping is firmly closely knit, and corner and joint connect smooth and easy and be close to edges of boards;
Adhesive tape is not allow for dehiscing, coming off when pasting, not straight phenomenon;
(4), after gluing, in time adhesive tape should be cleaned out when glue is quick-drying, and the glue surface damaged when immediately treating because of tear tape;
(5) what the thickness of gluing should not be beaten is too thin or too thick, and colloid surface should be smooth, smooth, and cleaning glass is without dirt; Bind, edge sealing, back cover should firmly attractive in appearance, do not seep water, the water bound should be arranged inwards;
(6), after gluing, in time the glue polluting plate face is cleaned out.
2. the full concealed frame glass curtain wall construction method of exterior wall as claimed in claim 1, it is characterised in that described lattice is installed in controlling, axial deviation controls within the scope of ± 1mm, and between perpendicular material, lattice size Control is at ± 1mm.
3. the full concealed frame glass curtain wall construction method of exterior wall as claimed in claim 1, it is characterised in that described sleeve is vertically connected with intubating length and cannot be less than 200mm.
4. the full concealed frame glass curtain wall construction method of exterior wall as claimed in claim 1, it is characterised in that described glass plate in an installation, adjacent two cell board difference of height < 1mm, stitch width ± 1mm.
CN201410665209.XA 2014-11-20 2014-11-20 Construction method of exterior hidden frame supported glass curtain wall Pending CN105672656A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410665209.XA CN105672656A (en) 2014-11-20 2014-11-20 Construction method of exterior hidden frame supported glass curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410665209.XA CN105672656A (en) 2014-11-20 2014-11-20 Construction method of exterior hidden frame supported glass curtain wall

Publications (1)

Publication Number Publication Date
CN105672656A true CN105672656A (en) 2016-06-15

Family

ID=56945118

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410665209.XA Pending CN105672656A (en) 2014-11-20 2014-11-20 Construction method of exterior hidden frame supported glass curtain wall

Country Status (1)

Country Link
CN (1) CN105672656A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503454A (en) * 2017-08-14 2017-12-22 中建八局第三建设有限公司 Super large width bend glass curtain wall mechanization installation method
CN109296120A (en) * 2018-09-29 2019-02-01 重庆鲁能开发(集团)有限公司 A kind of U-shaped glass curtain wall system and construction method of angular position seamless connection
CN112900710A (en) * 2021-01-28 2021-06-04 龙强建工有限公司 Curtain wall construction method
CN114232901A (en) * 2021-12-31 2022-03-25 中铁五局集团有限公司 Construction method of steel structure canopy roof curtain wall of traffic hub station platform
CN114233013A (en) * 2022-01-06 2022-03-25 北京城建集团有限责任公司 Glass canopy construction method
CN115434441A (en) * 2022-08-31 2022-12-06 上海宝冶集团有限公司 Construction method of 3d printed wall decoration composite material acoustic board
CN115434465A (en) * 2022-10-14 2022-12-06 安徽新基建有限公司 Glass curtain wall mounting construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005171529A (en) * 2003-12-08 2005-06-30 Shimizu Corp Execution method of glass curtain wall
CN103306409A (en) * 2013-05-16 2013-09-18 一禾科技发展(上海)有限公司 Hidden frame glass curtain wall installation structure and hidden frame glass curtain wall installation method
CN103758355A (en) * 2014-02-20 2014-04-30 成军 Hollow glass no-auxiliary-frame installation method of hidden frame glass curtain wall

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005171529A (en) * 2003-12-08 2005-06-30 Shimizu Corp Execution method of glass curtain wall
CN103306409A (en) * 2013-05-16 2013-09-18 一禾科技发展(上海)有限公司 Hidden frame glass curtain wall installation structure and hidden frame glass curtain wall installation method
CN103758355A (en) * 2014-02-20 2014-04-30 成军 Hollow glass no-auxiliary-frame installation method of hidden frame glass curtain wall

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张立新: "《建筑工程施工组织设计编制与案例精选 土木工程施工组织设计》", 31 May 2007 *
武树春 石川: "《《建设工程施工现场安全资料管理规程》配套用书 (上册) 建设与监理单位安全资料编制范例》", 30 November 2007 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503454A (en) * 2017-08-14 2017-12-22 中建八局第三建设有限公司 Super large width bend glass curtain wall mechanization installation method
CN109296120A (en) * 2018-09-29 2019-02-01 重庆鲁能开发(集团)有限公司 A kind of U-shaped glass curtain wall system and construction method of angular position seamless connection
CN109296120B (en) * 2018-09-29 2023-11-28 重庆鲁能开发(集团)有限公司 U-shaped glass curtain wall system with seamless connection at corner position and construction method
CN112900710A (en) * 2021-01-28 2021-06-04 龙强建工有限公司 Curtain wall construction method
CN114232901A (en) * 2021-12-31 2022-03-25 中铁五局集团有限公司 Construction method of steel structure canopy roof curtain wall of traffic hub station platform
CN114233013A (en) * 2022-01-06 2022-03-25 北京城建集团有限责任公司 Glass canopy construction method
CN115434441A (en) * 2022-08-31 2022-12-06 上海宝冶集团有限公司 Construction method of 3d printed wall decoration composite material acoustic board
CN115434465A (en) * 2022-10-14 2022-12-06 安徽新基建有限公司 Glass curtain wall mounting construction method

Similar Documents

Publication Publication Date Title
CN105672656A (en) Construction method of exterior hidden frame supported glass curtain wall
CN103711262B (en) A kind of curved surface aluminum-magnesium-manganese alloy roof plate system construction method
CN103726597B (en) Adopt the frame type cell curtain wall of auxiliary mounting deck and profile of tooth corner brace and profile of tooth bearing
CN204001323U (en) Waterproof combined curtain wall
CN101725227A (en) Integral construction method for heat preservation and decoration of outer wall
CN106481098A (en) A kind of novel movable room
CN107762010A (en) A kind of installation method and its curtain wall system of modular architectural curtain wall system
CN203174952U (en) Bonding and hanging type thin-plastered external wall insulation system
CN109184056A (en) Curtain wall construction and its construction method with light trough
CN205840076U (en) Combined lightweight exterior wall assembly
CN112900703A (en) Assembled low-energy-consumption curtain wall system and construction method thereof
CN104294975B (en) A kind of aluminum facade attachment means
CN105298145B (en) The vertical external sunshade welding construction method of frame concealed curtain wall
CN103206091A (en) Construction method of U-shaped glass curtain wall
CN203334488U (en) Connection structure of glass plate of cable-net-type glass curtain wall and a steel cable
CN112392165B (en) Building heat-insulation outer wall structure and construction method thereof
CN105464299B (en) A kind of gable waterproof construction
CN108316595B (en) Combined installation process for heat-insulation decorative plate
CN101225683B (en) Method for connecting and installing unit curtain walls
CN211369128U (en) External wall heat preservation waterproof system
CN209066673U (en) Curtain wall construction with light trough
CN209260996U (en) A kind of fiber cement board external wall system
CN209040375U (en) A kind of fiber cement board external wall system top structure
CN102434062B (en) Split door pocket and installation method thereof
CN111206737A (en) Wall connecting piece of plug-in type low-carbon heat-preservation energy-saving plate

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160615