CN207513060U - A kind of cylinder stone material dry suspending wall construction - Google Patents

A kind of cylinder stone material dry suspending wall construction Download PDF

Info

Publication number
CN207513060U
CN207513060U CN201721620492.XU CN201721620492U CN207513060U CN 207513060 U CN207513060 U CN 207513060U CN 201721620492 U CN201721620492 U CN 201721620492U CN 207513060 U CN207513060 U CN 207513060U
Authority
CN
China
Prior art keywords
stone material
stainless steel
concrete column
adapting piece
structural concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721620492.XU
Other languages
Chinese (zh)
Inventor
刘建华
王艺萍
方浩波
寇字
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI KANGYE BUILDING DECORATION ENGINEERING Co Ltd
Original Assignee
SHANGHAI KANGYE BUILDING DECORATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI KANGYE BUILDING DECORATION ENGINEERING Co Ltd filed Critical SHANGHAI KANGYE BUILDING DECORATION ENGINEERING Co Ltd
Priority to CN201721620492.XU priority Critical patent/CN207513060U/en
Application granted granted Critical
Publication of CN207513060U publication Critical patent/CN207513060U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is related to a kind of cylinder stone material dry suspending wall constructions, including structural concrete column, stone material, structural concrete column top periphery is provided with furred ceiling, on structural concrete column side, lower part is equipped with multiple pre-buried iron plates, pre-buried iron plate is fixed on by setscrew on structural concrete column, supporting rod is welded on pre-buried iron plate, channel steel is installed on the outside of supporting rod, channel steel is arranged vertically, angle steel is welded on the outside of channel steel, angle steel is surrounded with a circle along structural concrete column periphery, stainless steel adapting piece is equipped with by stainless steel fastening bolt on angle steel, stainless steel adapting piece is in the L-type that outside is folded upward at, stone material is in hollow cylindrical, the inner wall of stone material is equipped with and the matched card slot of stainless steel adapting piece, stone material is mounted on by card slot on stainless steel adapting piece;The utility model compared with the existing technology, with improving work efficiency, the technology intermission for saving waiting cement mortar initial set the time, protects construction environment, reduces the pollution of cement mortar.

Description

A kind of cylinder stone material dry suspending wall construction
[technical field]
The utility model is related to technical field of buildings, specifically a kind of cylinder stone material dry suspending wall construction.
[background technology]
At present, it is a kind of design wind of the common elegant of building decoration using stone decoration bolumn cap, suspension column, shaft Lattice, sedate, dignified, secured, durable impression that effect gives.Traditional wet combining construction method is in the stone material being fixed temporarily The back side and the method for base face joints cement mortar bonding, principle are stone material and base until after cement mortar final set consolidation Form entirety.This method effect is low, forbids to collide before final set, easily generates the mass defect of hollowing.
[utility model content]
The purpose of this utility model seeks to solve above-mentioned deficiency and provide a kind of cylinder stone material dry suspending wall construction, improves Work efficiency, with saving the technology intermission that waits for cement mortar initial set time, construction environment is protected, reduces cement mortar It is low and the problems such as be also easy to produce hollowing to avoid conventional method effect for pollution.
A kind of cylinder stone material dry suspending wall construction is designed to achieve the above object, including structural concrete column 10, stone material 1, institute It states structural concrete column 10 to be cast on ground, 10 top periphery of structural concrete column is provided with furred ceiling 12, described 10 side upper and lower part of structural concrete column is equipped with multiple pre-buried iron plates 8, and the pre-buried iron plate 8 is fixed on by setscrew 9 On structural concrete column 10, supporting rod 7 is welded on the pre-buried iron plate 8, the supporting rod 7 is horizontally disposed, the supporting rod 7 Outside is equipped with channel steel 6, and the channel steel 6 is arranged vertically, and 6 top of channel steel is extended at furred ceiling 12,6 edge of channel steel At least two are circumferentially provided with, 6 outside of channel steel is welded with angle steel 5, and the angle steel 5 is surround along 10 periphery of structural concrete column It is provided with a circle, stainless steel adapting piece 3, the stainless steel adapting piece is equipped with by stainless steel fastening bolt 4 on the angle steel 5 3 it is circumferentially arranged have multiple, the stainless steel adapting piece 3 is in the L-type that is folded upward at of outside, and the stone material 1 is in hollow cylindrical, The inner wall of the stone material 1 be equipped with 3 matched card slot of stainless steel adapting piece, the stone material 1 is mounted on stainless by card slot On steel fastener 3.
Further, ground stone 11, the stone material 1 and ground stone 11 are equipped on the ground of 1 lower section of stone material Between be hung on stone material 2 13, the stone material 2 13 is in the shaped hollow round table of symmetrical above and below, intermediate outwardly convex, the stone material two Stone material lines 2 are provided between 13 and stone material 1.
Further, the stone material 2 13 passes through pre-buried two 8b of iron plate, two 7b of supporting rod, angle steel with structural concrete column 10 Two 5b, two 3b connections of stainless steel adapting piece, pre-buried two 8b of iron plate are fixed on 10 bottom of structural concrete column by setscrew 9 Portion is welded with two 7b of supporting rod on pre-buried two 8b of iron plate, and two 7b of supporting rod is horizontally disposed, outside two 7b of supporting rod Side is welded with angle steel two 5b, two 5b of angle steel and is surrounded with a circle, the angle steel along 10 bottom periphery of structural concrete column The L-type that stainless steel adapting piece two 3b, two 3b of stainless steel adapting piece are folded upward in outside, the stone material are installed on two 5b 2 13 inner walls are equipped with the card slot two that is connected with two 3b of stainless steel adapting piece, the stone material 2 13 by card slot two mount in On two 3b of stainless steel adapting piece.
Further, the stone material lines 2 are set as top circumferentially arranged with a circle, the outside wall surface of the stone material lines 2 The arc that outwardly convex, intermediate vertical arrangement, lower part are recessed inwardly.
The utility model is compared with the existing technology, structure novel, simple, and reasonable design is applied with traditional wet combining operation Work method is compared, with not only increasing work efficiency, the technology intermission for the saving waiting cement mortar initial set time, and protect and apply Work environment reduces the pollution of cement mortar;Moreover, the utility model processing and fabricating is installed, stone operation side is hung in level land construction Just, quality control is convenient and reliable, reduces high-rise working and vertically carries the difficulty of cement mortar and reduce for upper track work The product protection measure of sequence shortens the influence time of next procedure, improves the comprehensive benefit of enterprise and society;In addition, this Technical solution described in utility model can make a limited amount steelframe displacement facing arrangement according to integral layout, be conducive to the overall situation Organic unity coordinate, be worthy of popularization.
[description of the drawings]
Fig. 1 is the structure diagram of the utility model;
Fig. 2 is the close-up schematic view of the utility model;
Fig. 3 is the vertical view at another embodiment top stone material of the utility model;
Fig. 4 is the vertical view at another embodiment bottom stone material lines and stone material two of the utility model;
In figure:1st, stone material 2, stone material lines 3, stainless steel adapting piece 3b, stainless steel adapting piece 24, stainless steel fastening Bolt 5, angle steel 5b, angle steel 26, channel steel 7, supporting rod 7b, supporting rod 28, pre-buried iron plate 8b, pre-buried iron plate 29, Setscrew 10, structural concrete column 11, ground stone 12, furred ceiling 13, stone material two.
[specific embodiment]
The utility model is made below in conjunction with the accompanying drawings further explained below:
As shown in drawings, the utility model includes:Structural concrete column 10, stone material 1, structural concrete column 10 are cast in ground On face, 10 top periphery of structural concrete column is provided with furred ceiling 12, and 10 side upper and lower part of structural concrete column is equipped with more A pre-buried iron plate 8, pre-buried iron plate 8 are fixed on by setscrew 9 on structural concrete column 10, and branch is welded on pre-buried iron plate 8 Strut 7, supporting rod 7 is horizontally disposed, and 7 outside of supporting rod is equipped with channel steel 6, and channel steel 6 is arranged vertically, and 6 top of channel steel extends to day At flower furred ceiling 12, channel steel 6 is circumferentially arranged at least two, and 6 outside of channel steel is welded with angle steel 5, and angle steel 5 is along structural concrete column 10 peripheries are surrounded with a circle, and stainless steel adapting piece 3, stainless steel connection are equipped with by stainless steel fastening bolt 4 on angle steel 5 Part 3 is circumferentially arranged the L-type multiple, stainless steel adapting piece 3 is folded upward in outside, and stone material 1 is in hollow cylindrical, stone material 1 Inner wall be equipped with 3 matched card slot of stainless steel adapting piece, stone material 1 is mounted on by card slot on stainless steel adapting piece 3.
Wherein, ground stone 11 is equipped on the ground of 1 lower section of stone material, stone is hung between stone material 1 and ground stone 11 Material 2 13, stone material 2 13 are in the shaped hollow round table of symmetrical above and below, intermediate outwardly convex, are provided between stone material 2 13 and stone material 1 Stone material lines 2, stone material lines 2 are circumferentially arranged with a circle, and the outside wall surface of stone material lines 2 is set as top outwardly convex, centre is hung down The arc that straight arrangement, lower part are recessed inwardly;Stone material 2 13 passes through pre-buried two 8b of iron plate, supporting rod two with structural concrete column 10 7b, two 5b of angle steel, two 3b connections of stainless steel adapting piece, pre-buried two 8b of iron plate are fixed on structural concrete column by setscrew 9 10 bottoms are welded with two 7b of supporting rod on pre-buried two 8b of iron plate, and two 7b of supporting rod is horizontally disposed, are welded on the outside of two 7b of supporting rod Two 5b of angle steel, two 5b of angle steel are surrounded with a circle along 10 bottom periphery of structural concrete column, are equipped on two 5b of angle steel stainless Two 3b of steel fastener, two 3b of stainless steel adapting piece are in the L-type that outside is folded upward at, and 2 13 inner wall of stone material is equipped with to be connected with stainless steel The card slot two that two 3b of fitting is connected, stone material 2 13 are mounted by card slot two on two 3b of stainless steel adapting piece.
Cylinder stone material dried hanging hang structure described in the utility model mainly includes four embedded part, steelframe, connector, stone material portions Point, pre-buried iron plate is to be attached to base for post layer with mild steel expansion bolt, and for the connection of steelframe supporting rod and channel steel, steelframe supports stone The load of material, stainless steel adapting piece are the stress points that steelframe is connect with stone material.It is just that ornamental stone is cladding by above-mentioned structure On steelframe, the load on steelframe bears, on ground and base for post layer, to form stable stress system.During operation, tying first Structure concrete column finds out the installation site of pre-buried iron plate, and pre-buried iron plate is fixed with setscrew, welds supporting rod, installation channel steel and Angle steel is connect with stainless steel fastening screw with stainless steel adapting piece, finally installs stone material and stone material lines.
The utility model can pop up stone facing line on the ground, according to stone facing line, determine steel according to plan-position The position of column is erected, fabrication and installation built-in fitting makes iron embedded part along eminence equidistance on base for post layer;Erecting and welding steelframe is stood Column, and according to stone material height welding steel structure transverse horizontal angle steel (angle steel is in intermediate uniformly drilling);Find horizontal facing position accurately, Stone material to be installed, calibrates its horizontal vertical degree, installation connecting element notes special stone material glue with stone material inside edge groove, links with steelframe, Forbid to collide before stone material adhesive curing, after being horizontally mounted from left to right, successively installation is complete from bottom to up.
In the utility model, the stone material on structural concrete column top and the stone material lines of bottom and stone material two, center It can also be centrally disposed for bias, as shown in attached drawing 3 and attached drawing 4, i.e. bowing respectively at the stone material of top with structural concrete column Vertical view at view and bottom stone material lines and stone material two.
The utility model is simultaneously not limited to the embodiments described above, and other any spirit without departing from the utility model are real Matter with made under principle change, modification, replacement, combine, simplification, should be equivalent substitute mode, be included in this practicality Within novel protection domain.

Claims (4)

1. a kind of cylinder stone material dry suspending wall construction, it is characterised in that:Including structural concrete column (10), stone material (1), the structure Concrete column (10) is cast on ground, and structural concrete column (10) top periphery is provided with furred ceiling (12), described Structural concrete column (10) side upper and lower part is equipped with multiple pre-buried iron plates (8), and the pre-buried iron plate (8) passes through setscrew (9) it is fixed on structural concrete column (10), supporting rod (7), supporting rod (7) water is welded on the pre-buried iron plate (8) Plain cloth is put, and channel steel (6) is equipped on the outside of the supporting rod (7), and the channel steel (6) is arranged vertically, channel steel (6) the top extension To furred ceiling (12), the channel steel (6) is circumferentially arranged at least two, and angle steel is welded on the outside of the channel steel (6) (5), the angle steel (5) is surrounded with a circle along structural concrete column (10) periphery, tight by stainless steel on the angle steel (5) Fixing bolt (4) is equipped with stainless steel adapting piece (3), and the stainless steel adapting piece (3) is circumferentially arranged multiple, the stainless steel The L-type that connector (3) is folded upward in outside, the stone material (1) are equipped in hollow cylindrical, the inner wall of the stone material (1) With stainless steel adapting piece (3) matched card slot, the stone material (1) is mounted on by card slot on stainless steel adapting piece (3).
2. cylinder stone material dry suspending wall construction as described in claim 1, it is characterised in that:On ground below the stone material (1) Ground stone (11) is equipped with, stone material two (13), the stone material two are hung between the stone material (1) and ground stone (11) (13) in the shaped hollow round table of symmetrical above and below, intermediate outwardly convex, stone material is provided between the stone material two (13) and stone material (1) Lines (2).
3. cylinder stone material dry suspending wall construction as claimed in claim 2, it is characterised in that:The stone material two (13) and structure coagulation Earth pillar (10) is connected by pre-buried iron plate two (8b), supporting rod two (7b), angle steel two (5b), stainless steel adapting piece two (3b), institute It states pre-buried iron plate two (8b) and structural concrete column (10) bottom, the pre-buried iron plate two (8b) is fixed on by setscrew (9) On be welded with supporting rod two (7b), the supporting rod two (7b) is horizontally disposed, and angle steel is welded on the outside of the supporting rod two (7b) Two (5b), the angle steel two (5b) are surrounded with a circle, the angle steel two (5b) along structural concrete column (10) bottom periphery On stainless steel adapting piece two (3b), the L-type that the stainless steel adapting piece two (3b) is folded upward in outside, the stone material are installed Two (13) inner walls are equipped with the card slot two being connected with stainless steel adapting piece two (3b), and the stone material two (13) passes through card slot two It mounts on stainless steel adapting piece two (3b).
4. cylinder stone material dry suspending wall construction as claimed in claim 3, it is characterised in that:The stone material lines (2) circumferentially set There is a circle, the outside wall surface of the stone material lines (2) is set as top outwardly convex, intermediate vertical is arranged, lower part is recessed inwardly Arc.
CN201721620492.XU 2017-11-28 2017-11-28 A kind of cylinder stone material dry suspending wall construction Expired - Fee Related CN207513060U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721620492.XU CN207513060U (en) 2017-11-28 2017-11-28 A kind of cylinder stone material dry suspending wall construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721620492.XU CN207513060U (en) 2017-11-28 2017-11-28 A kind of cylinder stone material dry suspending wall construction

Publications (1)

Publication Number Publication Date
CN207513060U true CN207513060U (en) 2018-06-19

Family

ID=62541683

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721620492.XU Expired - Fee Related CN207513060U (en) 2017-11-28 2017-11-28 A kind of cylinder stone material dry suspending wall construction

Country Status (1)

Country Link
CN (1) CN207513060U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109944389A (en) * 2019-03-26 2019-06-28 中国建筑第八工程局有限公司 It is installed on the edge list and its construction method of structure floor

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109944389A (en) * 2019-03-26 2019-06-28 中国建筑第八工程局有限公司 It is installed on the edge list and its construction method of structure floor

Similar Documents

Publication Publication Date Title
CN107130757A (en) Large autoclaved lightweight aerated concrete slab component
CN202017346U (en) Late poured band hanging formwork structure
CN104153495B (en) A kind of attachment structure of Multi-function light concrete curtain wall
CN101906858B (en) Seamless installation process for polyline artistic GRC (Glass-fiber Reinforced Composite) board
CN207513060U (en) A kind of cylinder stone material dry suspending wall construction
CN204001309U (en) A kind of syndeton of Multi-function light concrete curtain wall
CN106522364B (en) 'garland' steel structure system for stadium periphery and installation process thereof
CN211228887U (en) Bracing column base node is used in timber structure building decoration
CN207934332U (en) Assembled architecture with steel Special-Shaped Column
CN207988159U (en) A kind of assembled watertight building
CN106193589A (en) Concrete superelevation heavy type beam and superimposed sheet combinative structure method for supporting
CN207110035U (en) Assembled steel tendon concrete frame structure based on steel plate connection joint
CN203412312U (en) Thermal-insulating integrated template wallboard construction building
CN105155846A (en) Construction method for arc-shaped reinforced concrete stand
CN213115585U (en) Stable form bearing structure that building engineering used
CN209114681U (en) A kind of outdoor dry-hang stone and ground intersection node structure
CN207988356U (en) A kind of waterproof connecting structure of shaped steel column and wallboard
CN105625719A (en) Tensile sheet structure aluminum alloy formwork early-dismantling system and construction method thereof
CN202745081U (en) Large-size rubble concrete settlement joint template system
CN206554500U (en) Steel structure concrete, which is poured, uses adjustable transverse support bar
CN106988520B (en) Construction method and support system for high-rise suspension structure
CN109944324A (en) Steel concrete combo box trestle and the combination assembled structural system of reinforced concrete frame column
CN201962894U (en) Suspension structure for building wall
CN204001289U (en) There is the light steel keel partition that carries the arm of encorbelmenting
CN204252494U (en) Reduce deviation building structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180619

Termination date: 20181128