CN206299900U CN201621371678.1U CN201621371678U CN206299900U CN 206299900 U CN206299900 U CN 206299900U CN 201621371678 U CN201621371678 U CN 201621371678U CN 206299900 U CN206299900 U CN 206299900U
Authority
CN
China
Prior art keywords
bors
oeuveres
pipeline
shaped steel
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621371678.1U
Other languages
Chinese (zh)
Inventor
顾文康
杨阳
唐伟栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Installation Engineering Group Co Ltd
Original Assignee
Shanghai Installation Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Installation Engineering Group Co Ltd filed Critical Shanghai Installation Engineering Group Co Ltd
Priority to CN201621371678.1U priority Critical patent/CN206299900U/en
Application granted granted Critical
Publication of CN206299900U publication Critical patent/CN206299900U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a kind of shaped steel Two bors d's oeuveres combined bracket installed for electrical and mechanical comprehensive pipeline, Two bors d's oeuveres shaped steel can increase whole support by force intensity, linked together by by multiple supports, support unification arrangement can be accomplished, save shaped steel consumption, the space shared by support can be greatly reduced simultaneously, lifting overall space is highly, in addition, cross-arm is set up by one or more pipeline for connecting two vertical edges of the U-shaped framework, the number of lines for needing to set up can arbitrarily be increased, solve large-scale electromechanical comprehensive pipeline layout unreasonable, maintenance is difficult, the big problem of shaped steel consumption.

Description

For the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed
Technical field
The utility model is related to a kind of shaped steel Two bors d's oeuveres combined bracket installed for electrical and mechanical comprehensive pipeline.
Background technology
Civil buildings are general at positions such as the public aisle of basement large space, giant mechanical and electrical equipment computer rooms, and water power wind is all kinds of Electromechanical pipeline species is more, bore is big, dense arrangement, traditional common practices be using the single shape steel bracket of each electromechanical pipeline or Single pattern for spelling comprehensive support, it is contemplated that the shape steel bracket of selection weight bearing power in itself, such way is to shaped steel expense Larger, in same electromechanical pipeline section, shape steel bracket need to take substantial amounts of Section Space, cause electromechanical pipeline to arrange difficult, whole Body space absolute altitude is relatively low.
Utility model content
The purpose of this utility model is to provide a kind of shaped steel Two bors d's oeuveres combined bracket installed for electrical and mechanical comprehensive pipeline, energy Enough solve the problems, such as that large-scale electromechanical comprehensive pipeline layout is unreasonable, maintenance is difficult, shaped steel consumption is big.
To solve the above problems, the utility model provides a kind of shaped steel Two bors d's oeuveres joint branch installed for electrical and mechanical comprehensive pipeline Frame, including:
The multiple supports for linking together, each support is welded by Two bors d's oeuveres shaped steel, and each support includes U-shaped framework One or more pipeline with two vertical edges for connecting the U-shaped framework sets up cross-arm.
Further, in the above-mentioned shaped steel Two bors d's oeuveres combined bracket installed for electrical and mechanical comprehensive pipeline, the Two bors d's oeuveres shaped steel It is Two bors d's oeuveres channel-section steel.
Further, in the above-mentioned shaped steel Two bors d's oeuveres combined bracket installed for electrical and mechanical comprehensive pipeline, the U-shaped framework Formed using No. 16 channel-section steel Two bors d's oeuveres.
Further, in the above-mentioned shaped steel Two bors d's oeuveres combined bracket installed for electrical and mechanical comprehensive pipeline, the pipeline sets up Cross-arm is formed using 10 or No. 12 channel-section steel Two bors d's oeuveres.
Further, in the above-mentioned shaped steel Two bors d's oeuveres combined bracket installed for electrical and mechanical comprehensive pipeline, the U-shaped framework The free end of two vertical edges be also associated with the first steel plate.
Further, in the above-mentioned shaped steel Two bors d's oeuveres combined bracket installed for electrical and mechanical comprehensive pipeline, first steel plate It is embedded in structural beams or structure floor in advance.
Further, in the above-mentioned shaped steel Two bors d's oeuveres combined bracket installed for electrical and mechanical comprehensive pipeline, first steel plate Free end with two vertical edges of the U-shaped framework is connected by setscrew.
Further, in the above-mentioned shaped steel Two bors d's oeuveres combined bracket installed for electrical and mechanical comprehensive pipeline, the pipeline sets up The second steel plate is welded with joint face between two channel-section steels of cross-arm.
Further, in the above-mentioned shaped steel Two bors d's oeuveres combined bracket installed for electrical and mechanical comprehensive pipeline, second steel plate Cross-arm is set up in the pipeline to be set by predetermined interval, the pipeline sets up and be provided with unwelded second steel plate on cross-arm Pipeline hoop.
Further, in the above-mentioned shaped steel Two bors d's oeuveres combined bracket installed for electrical and mechanical comprehensive pipeline, the pipeline hoop It is U-shaped anchor ear.
Further, in the above-mentioned shaped steel Two bors d's oeuveres combined bracket installed for electrical and mechanical comprehensive pipeline, second steel plate It is No. 20 steel plates
Compared with prior art, Two bors d's oeuveres shaped steel can increase whole support by force intensity, connected by by multiple supports Together, support unification arrangement can be accomplished, shaped steel consumption is saved, while the space shared by support can be greatly reduced, lifting is whole Body spatial altitude, in addition, one or more pipeline of two vertical edges by connecting the U-shaped framework sets up cross-arm, can be with Any to increase the number of lines for needing to set up, the large-scale electromechanical comprehensive pipeline layout of solution is unreasonable, maintenance is difficult, shaped steel consumption Big problem.It is first right with reference to electromechanical pipeline installation specification during using Two bors d's oeuveres shaped steel combined bracket pattern of the present utility model Electromechanical each systematic pipeline such as airduct, water pipe, crane span structure carries out reasonably optimizing arrangement, then by the conjuncted Two bors d's oeuveres branch of synthesis to selecting Frame carries out Overall Analysis, load and calculates, checks, and analysis draws electrical and mechanical comprehensive pipeline in the suitable shaped steel choosing of each cross section place Type and support spacing, provide the Two bors d's oeuveres support shop detail drawing on each position according to this, are installed after prefabricated processing in batching is unified, peace The shape steel bracket of dress both meets functional requirement, and support unification arrangement can be accomplished again, shaped steel consumption is saved, while branch can be greatly reduced Space shared by frame, lifting overall space can highly, for example lift the public aisle of basement large space, giant mechanical and electrical equipment machine The position such as room overall space height and perception effect, Two bors d's oeuveres support can fabrication and installation in batch, can effectively be saved compared with pipeline independent rack About section steel material consumption, improves construction efficiency.
Brief description of the drawings
Fig. 1 is the structure of the shaped steel Two bors d's oeuveres combined bracket installed for electrical and mechanical comprehensive pipeline of the embodiment of the utility model one Figure;
Fig. 2 is the structure top view of Fig. 1;
Fig. 3 is the amplification assumption diagram at the A of Fig. 2.
Specific embodiment
To enable above-mentioned purpose of the present utility model, feature and advantage more obvious understandable, below in conjunction with the accompanying drawings and tool Body implementation method is described in further detail to the utility model.
As shown in Figures 1 to 3, the utility model provides a kind of shaped steel Two bors d's oeuveres joint branch installed for electrical and mechanical comprehensive pipeline Frame, including:
The multiple supports for linking together, each support is welded by Two bors d's oeuveres shaped steel, and each support includes U-shaped framework 1 sets up cross-arm 2 with one or more pipeline of two vertical edges of the connection U-shaped framework 1.Here, Two bors d's oeuveres shaped steel can increase Plus whole support by force intensity, linked together by by multiple supports, support unification arrangement can be accomplished, save shaped steel and use Amount, while the space shared by support can be greatly reduced, lifting overall space highly, in addition, by connecting the U-shaped framework Two vertical edges one or more pipeline set up cross-arm, can arbitrarily increase need set up number of lines, solve large scale computer Electric comprehensive pipeline layout is unreasonable, the problem that maintenance is difficult, shaped steel consumption is big.Combined using Two bors d's oeuveres shaped steel of the present utility model During support pattern, with reference to electromechanical pipeline installation specification, each systematic pipeline first electromechanical to airduct, water pipe, crane span structure etc. is closed Reason is optimized the arrangement of, and is then carried out Overall Analysis, load calculating by the conjuncted Two bors d's oeuveres support of synthesis selected, is checked, point Analysis show that electrical and mechanical comprehensive pipeline, in the suitable shaped steel type selecting of each cross section place and support spacing, is provided double on each position according to this Support shop detail drawing is spelled, is installed after prefabricated processing in batching is unified, the shape steel bracket of installation both meets functional requirement, can accomplish again Support unification arrangement, overall perception effect is good, and pipeline arrangement is clear in order, and system maintenance operations are easy, saves shaped steel consumption, together When can greatly reduce space shared by support, lifting overall space can highly, for example be lifted the public aisle of basement large space, The position such as giant mechanical and electrical equipment computer room overall space height and perception effect, Two bors d's oeuveres support can fabrication and installation in batch, it is only compared with pipeline Staking can effectively save section steel material consumption, raising construction efficiency.Full weld 4 is connected between Two bors d's oeuveres shaped steel in Fig. 1.
In the embodiment of the utility model one, the Two bors d's oeuveres shaped steel is Two bors d's oeuveres channel-section steel, each on the market such that it is able to convenient selection Plant the channel-section steel of model.
In the embodiment of the utility model one, the U-shaped framework is formed using No. 16 channel-section steel Two bors d's oeuveres, so as to ensure that support is whole Body by force intensity.
In the embodiment of the utility model one, the pipeline is set up cross-arm and is formed using 10 or No. 12 channel-section steel Two bors d's oeuveres, is being saved On the basis of channel-section steel, the demand for setting up different types of pipeline is met.
In the embodiment of the utility model one, as shown in Fig. 1 to 2, two free ends of vertical edge of the U-shaped framework 1 are also The first steel plate 3 is connected with, during for support to be connected with beam or structure floor, increases the stress surface of connection.First steel plate, Can improve steel plate and receive force intensity and shape steel bracket bearing capacity in structure construction stage pre-buried positioning.
In the embodiment of the utility model one, first steel plate is embedded in structural beams or structure floor in advance, to improve steel plate By force intensity and shape steel bracket bearing capacity.
In the embodiment of the utility model one, first steel plate leads to two free ends of vertical edge of the U-shaped framework Setscrew connection is crossed, to ensure bonding strength.
In the embodiment of the utility model one, as shown in Figures 2 and 3, the pipeline sets up the company between two channel-section steels of cross-arm 2 Be welded with the second steel plate 5 in junction, the steel plate respectively with the contact surface full weld of described two channel-section steels, so as to further increase pipe Coil holder set cross-arm by force intensity.
In the embodiment of the utility model one, as shown in Figures 2 and 3, second steel plate 5 sets up cross-arm 2 and presses in the pipeline Predetermined interval is set, and the pipeline to set up and be provided with pipeline hoop at unwelded second steel plate on cross-arm, is embraced by pipeline Hoop can avoid the installation site of pipeline hoop with fixed -piping, second steel plate.
In the embodiment of the utility model one, second steel plate is No. 20 steel plates, to increase bonding strength.
In the embodiment of the utility model one, the pipeline hoop is U-shaped anchor ear, to coordinate the circular pipe of needs fixation Shape.
In sum, Two bors d's oeuveres shaped steel can increase whole support by force intensity, linked together by by multiple supports, Support unification arrangement can be accomplished, shaped steel consumption is saved, while the space shared by support can be greatly reduced, lifting overall space is high Degree, in addition, one or more pipeline of two vertical edges by connecting the U-shaped framework sets up cross-arm, can arbitrarily increase The number of lines for setting up is needed, the large-scale electromechanical comprehensive pipeline layout of solution is unreasonable, maintenance is difficult, shaped steel consumption is big asks Topic.During using Two bors d's oeuveres shaped steel combined bracket pattern of the present utility model, with reference to electromechanical pipeline installation specification, first to airduct, Electromechanical each systematic pipeline such as water pipe, crane span structure carries out reasonably optimizing arrangement, then enters by the conjuncted Two bors d's oeuveres support of synthesis selected Row Overall Analysis, load are calculated, checked, analysis draw electrical and mechanical comprehensive pipeline in the suitable shaped steel type selecting of each cross section place and Support spacing, provides the Two bors d's oeuveres support shop detail drawing on each position according to this, is installed after prefabricated processing in batching is unified, installation Shape steel bracket both meets functional requirement, and support unification arrangement can be accomplished again, shaped steel consumption is saved, while support institute can be greatly reduced The space of occupancy, lifting overall space can highly, for example lift the public aisle of basement large space, giant mechanical and electrical equipment computer room etc. Position overall space height and perception effect, Two bors d's oeuveres support can fabrication and installation in batch, can effectively save type compared with pipeline independent rack Steel material consumption, improves construction efficiency
Each embodiment is described by the way of progressive in this specification, and what each embodiment was stressed is and other The difference of embodiment, between each embodiment identical similar portion mutually referring to.
Obviously, those skilled in the art can carry out various changes to utility model and modification is new without deviating from this practicality The spirit and scope of type.So, if it is of the present utility model these modification and modification belong to the utility model claim and its Within the scope of equivalent technologies, then the utility model is also intended to including including these changes and modification.

Claims (10)

1. it is a kind of for electrical and mechanical comprehensive pipeline install shaped steel Two bors d's oeuveres combined bracket, it is characterised in that including:
The multiple supports for linking together, each support is welded by Two bors d's oeuveres shaped steel, and each support includes U-shaped framework and company One or more pipeline for connecing two vertical edges of the U-shaped framework sets up cross-arm.
2. it is as claimed in claim 1 to be used for the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed, it is characterised in that described Two bors d's oeuveres shaped steel is Two bors d's oeuveres channel-section steel.
3. it is as claimed in claim 2 to be used for the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed, it is characterised in that described U-shaped framework is formed using No. 16 channel-section steel Two bors d's oeuveres.
4. it is as claimed in claim 2 to be used for the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed, it is characterised in that described Pipeline is set up cross-arm and is formed using 10 or No. 12 channel-section steel Two bors d's oeuveres.
5. it is as claimed in claim 1 to be used for the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed, it is characterised in that described The free end of two vertical edges of U-shaped framework is also associated with the first steel plate.
6. it is as claimed in claim 5 to be used for the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed, it is characterised in that described First steel plate is embedded in structural beams or structure floor in advance.
7. it is as claimed in claim 5 to be used for the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed, it is characterised in that described First steel plate is connected with the free end of two vertical edges of the U-shaped framework by setscrew.
8. it is as claimed in claim 1 to be used for the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed, it is characterised in that described The second steel plate is welded with joint face between two channel-section steels of pipeline erection cross-arm, second steel plate is No. 20 steel plates.
9. it is as claimed in claim 8 to be used for the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed, it is characterised in that described Second steel plate sets up cross-arm and is set by predetermined interval in the pipeline, and the pipeline sets up unwelded second steel plate on cross-arm Place is provided with pipeline hoop.
10. it is as claimed in claim 9 to be used for the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed, it is characterised in that institute Pipeline hoop is stated for U-shaped anchor ear.
CN201621371678.1U 2016-12-14 2016-12-14 For the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed Active CN206299900U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621371678.1U CN206299900U (en) 2016-12-14 2016-12-14 For the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621371678.1U CN206299900U (en) 2016-12-14 2016-12-14 For the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed

Publications (1)

Publication Number Publication Date
CN206299900U true CN206299900U (en) 2017-07-04

Family

ID=59213565

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621371678.1U Active CN206299900U (en) 2016-12-14 2016-12-14 For the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed

Country Status (1)

Country Link
CN (1) CN206299900U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106764075A (en) * 2016-12-14 2017-05-31 上海市安装工程集团有限公司 For the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106764075A (en) * 2016-12-14 2017-05-31 上海市安装工程集团有限公司 For the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed

Similar Documents

Publication Publication Date Title
CN201495027U (en) Hoisting tool for mill housing
CN104405071A (en) Structure and method for increasing height of corridor ceiling
CN206299900U (en) For the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed
CN203359755U (en) Assembly and lifting integrated device for anode plate
CN203877739U (en) Bracket for integrally lifting air ducts
CN106764075A (en) For the shaped steel Two bors d's oeuveres combined bracket that electrical and mechanical comprehensive pipeline is installed
CN203247868U (en) Large-span steel structure construction temporary supporting frame
CN209741895U (en) Connection structure of assembled elevator steel construction and base
CN107991172A (en) One kind is based on the more dimensional structure face shear box assemble methods of limited block combined type
CN101510679B (en) 110KV double-loop T connection steel pipe pole
CN208310204U (en) A kind of pedestal for elevator coupling beam formwork erection
CN103255837B (en) A kind of removable modular combination room
CN203640122U (en) Node structure of elevation difference of floor carrier plates of rebar trusses
CN204692751U (en) The interim hanging board of steel-structure factory building
CN211141292U (en) Special bracket for integral hoisting of air pipe
CN102777703A (en) Assembly type light pipeline hanger
CN104674951A (en) Automatic tripping device for hoisting large reinforced concrete prefabricated columns and beams
CN204662804U (en) A kind of assembled steel structure stair
CN209620622U (en) A kind of promotion platform
CN203891514U (en) Main transformer framework for omitting end support in substation
CN105350788A (en) Method for conducting suspension and equipment pipeline arrangement by means of auxiliary steel frame
CN212608999U (en) Be used for shaking table horizontal actuator to bury a stock group hoisting structure
CN203846794U (en) Adjustable support
CN103498510A (en) Steel-structure combined pillar
CN105040991B (en) The supporting construction and method for supporting of large-span steel segmental hoisting