CN206204727U - Prefabricated assembled inlet for stom water - Google Patents

Prefabricated assembled inlet for stom water Download PDF

Info

Publication number
CN206204727U
CN206204727U CN201620998331.3U CN201620998331U CN206204727U CN 206204727 U CN206204727 U CN 206204727U CN 201620998331 U CN201620998331 U CN 201620998331U CN 206204727 U CN206204727 U CN 206204727U
Authority
CN
China
Prior art keywords
bearing
fixed block
upper strata
stom water
prefabricated assembled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620998331.3U
Other languages
Chinese (zh)
Inventor
董永锋
龙福金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Billion Highway Maintenance Co Ltd
Original Assignee
Beijing Billion Highway Maintenance Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Billion Highway Maintenance Co Ltd filed Critical Beijing Billion Highway Maintenance Co Ltd
Priority to CN201620998331.3U priority Critical patent/CN206204727U/en
Application granted granted Critical
Publication of CN206204727U publication Critical patent/CN206204727U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses a kind of prefabricated assembled inlet for stom water, its drip irrigation device is to include the bottom bearing being superimposed with each other and upper strata bearing, hanging hole is formed between the bottom bearing and upper strata bearing to be used to install protection network, and then can prevent pedestrian and foreign body falling from entering well, so as to reduce potential safety hazard, reduce personal injury accident, and the protection network is connected firmly, it is difficult to be removed.

Description

Prefabricated assembled inlet for stom water
Technical field
The utility model is related to a kind of town road technical field of construction, and in particular, it is related to a kind of prefabrication and assembly construction Formula inlet for stom water.
Background technology
Civilian infrastructure construction is the ostentatious project in city, as the carrier of modern city, in urban development In its importance become increasingly conspicuous, civilian infrastructure construction can embody the modernization development level in city.
With the continuous propulsion of urban construction, the design increasingly science of urban drainage pipe network, prior art is:In road Both sides edge sets inlet for stom water, is arranged to urban pipe network surface gathered water by inlet for stom water.As Authorization Notice No. is Shown in a kind of rainwater inspection well for municipal roads disclosed in the Chinese utility model patent of CN203270763U, it include pit shaft, Ladder, the first adapter sleeve, well seat, two the second adapter sleeves, two rainwater branch pipes and expansion chambers are checked, the upper port of shown well seat is led to Cross the first adapter sleeve to be connected with pit shaft, the port of left and right two of shown well seat passes through first adapter sleeve and a rainwater respectively Branch pipe is connected, and expansion chamber is connected with the lower port of shown well seat, and shown inspection ladder is arranged on the inwall of pit shaft, the pit shaft It is F shaped steel reinforced concrete pipes.The rainwater inspection well for municipal roads also includes protection cage and protective cover, and the protection cage is consolidated Surely the upper end of pit shaft is connected to, protective cover is arranged on protection cage.
However, due to social security problem, the well lid well lid on street is stolen, such as:2003, Beijing Desheng was outdoors People Ding Hu Wests cell in 15 well lids be stolen, cell road hides trap everywhere.Sina's finance and economics news, 2012 5 Beijing time Month morning message on the 4th, New York municipality Thursday represents that a large amount of well cover for sewer are just stolen by burglar from the street of New York Walk, the hole of danger is left on highway and pavement.One spokesman's table of New York utility company Con Edison Show, at the beginning of 3 months since, existing more than 30 well lid in Brooker forest zone, queen area and Bronx area is stolen, and estimation is worked as by burglar Sold as old metal.These news are constantly reminding the importance of our road safeties.
In addition, the design of inlet for stom water also needs to consider the convenience of its installation such that it is able to reach rapid construction Purpose.Thus, a kind of security prefabricated assembled inlet for stom water higher is designed just into an important issue.
Utility model content
In view of the shortcomings of the prior art, the purpose of this utility model is that a kind of security of offer is higher, constructs more Plus easily prefabricated assembled inlet for stom water.
To achieve the above object, the utility model provides following technical scheme:A kind of prefabricated assembled inlet for stom water, including Bottom bearing and upper strata bearing annular in shape, the upper strata bearing is superimposed on the bottom bearing, the upper strata bearing and institute Some enclosed hanging holes are formed in both junctions after stating bottom bearing overlapping, the hanging hole is connected with protection network, described The link coordinated with the hanging hole is provided with protection network.
By using above-mentioned technical proposal, can be formed for mounting when prefabricated bottom base and upper strata bearing are coordinated The hanging hole of protection network, and hanging hole is enclosed, so protection network is difficult to be stolen, is easy to long-term raising security protection.And This fabricated structure so that the engineering time of the inlet for stom water is short.
Preferably, the inside lower end of the upper strata bearing is provided with the breach of ring-type, the roof of the breach sets oriented First fixed block of lower extension, the top surface of the bottom bearing is provided with the second fixed block coordinated with first fixed block, First fixed block matches somebody with somebody the hanging hole for being encircled into closing with second fixed block.
By using above-mentioned technical proposal, in construction, first the link of protection network can be set in the first fixed block Side, then assembles upper upper strata bearing so that the first fixed block and the second fixed block cooperatively form enclosed hanging hole.
Preferably, bottom of the top of second fixed block higher than first fixed block, and second fixed block Positioned at the inner side of first fixed block.
By using above-mentioned technical proposal, the first fixed block can form protective effect, also, first to the second fixed block Fixed block can form support to the second fixed block, and reinforcement effect is played to the second fixed block.
Preferably, being fixedly connected by fastener between the upper strata bearing and the bottom bearing.
By using above-mentioned technical proposal so that the connection between upper strata bearing and bottom bearing is more consolidated.
Preferably, the fastener includes the bolt being threadedly coupled with the bottom bearing through the upper strata bearing.
By using above-mentioned technical proposal, bolt can be connected through upper strata bearing with base, can by upper strata bearing and Bottom bearing is coupled together.
Preferably, being prefabricated with the swivel nut coordinated with the bolt in the bottom bearing.
By using above-mentioned technical proposal so that the connection of bolt is more stablized.
Preferably, the top surface of the upper strata bearing is provided with the putting hole placed for the head of the bolt.
By using above-mentioned technical proposal so that the top surface of upper strata bearing is more smooth.
Preferably, the protection network that the protection is made for steel wire.
By using above-mentioned technical proposal, the structural strength of protection network is higher, is difficult to be damaged.
In sum, the utility model has the advantages that compared to prior art:1. construction of the present utility model Short time limit;2. of the present utility model safe;3. the utility model is easy for installation.
Brief description of the drawings
Fig. 1 is the top view of embodiment;
Fig. 2 is the sectional view A-A of embodiment;
Fig. 3 is the axonometric drawing of embodiment;
Fig. 4 is the semi-cutaway of embodiment;
Fig. 5 is the explosive view of embodiment.
In figure:1st, upper strata bearing;11st, putting hole;12nd, perforate;13rd, the first fixed block;2nd, protection network;21st, link;3rd, spiral shell Bolt;4th, bottom bearing;41st, swivel nut;42nd, the second fixed block;5th, base soil layer;6th, lower floor's asphalt concrete layer;7th, upper strata pitch is mixed Solidifying soil layer.
Specific embodiment
The utility model is described in further detail below in conjunction with the accompanying drawings.
Embodiment:A kind of prefabricated assembled inlet for stom water, bottom bearing 4 referring to Fig. 1 and Fig. 2 including annular in shape and upper strata Bearing 1, upper strata bearing 1 is superimposed on bottom bearing 4, and the inner side of bottom bearing 4 and upper strata bearing 1 forms well head.Bottom bearing 4 Formed by concreting with upper strata bearing 1.It is base soil layer 5 in the bottom of bottom bearing 4, is located on the upper strata of base soil layer 5 The outside of bottom bearing 4 is provided with lower floor's asphalt concrete layer 6, and the top surface of lower floor's asphalt concrete layer 6 is located at bottom bearing 4 Under top surface, be provided with upper strata asphalt concrete layer 7 on lower floor's asphalt concrete layer 6, the top surface of upper strata asphalt concrete layer 7 with The top surface of upper strata bearing 1 is flushed.
Referring to Fig. 3, Fig. 4 and Fig. 5, wherein, the inside lower end of upper strata bearing 1 is provided with the breach of ring-type, the roof of breach The first fixed block 13 for extending downwardly is provided with, the top surface of bottom bearing 4 is provided with second coordinated with the first fixed block 13 and consolidates Determine block 42, the first fixed block 13 and the second fixed block 42 are with the hanging hole for being encircled into closing.First fixed block 13 and the second fixed block 42 are made of stainless steel, and prefabricated when upper strata bearing 1 is poured with bottom bearing 4.The top of the second fixed block 42 Higher than the bottom of the first fixed block 13, and the second fixed block 42 is located at the inner side of the first fixed block 13.
Protection network 2 is made up of steel wire, and several are provided with around protection network 2 for the link 21 with hanging hole cooperation, The link 21 is converted into and is welded and forms enclosed construction by the end bending of steel wire.
Circle-Array shows some perforation 12 on upper strata bearing 1, and the top of perforation 12 is provided with diameter greater than its diameter Putting hole 11, bolt 3 is equipped with perforation 12, and the head of bolt 3 is arranged in putting hole 11, and bolt 3 passes through upper strata bearing 1 It is threadedly coupled with bottom bearing 4.The inner periphery array of bottom bearing 4 have it is some with perforation 12 corresponding swivel nuts 41, the swivel nut 41 It is made of stainless steel, swivel nut 41 is prefabricated when bottom bearing 4 is poured.
The fabrication and installation process of the prefabricated assembled inlet for stom water is as follows, first with concreting formed upper strata bearing 1 with Bottom bearing 4, when upper strata bearing 1 is poured with bottom bearing 4, is inserted into the first fixed block 13, the bottom of in upper strata bearing 1 respectively Layer bearing 4 is inserted into the second fixed block 42 and swivel nut 41.After upper strata bearing 1 and bottom bearing 4 solidify, the first fixed block 13, Second fixed block 42 and swivel nut 41 also achieve fixation.Then when the inlet for stom water is manufactured, bottom bearing 4 need to be only arranged on On base soil layer 5, lower floor's asphalt concrete layer 6 is then laid, protection network 2 is hung over the inner side of the second fixed block 42, then will be upper Layer bearing 1 is arranged on bottom bearing 4, is threadedly coupled with swivel nut 41 through perforation 12 with bolt 3 and is realized upper strata bearing 1 and bottom Bearing 4 is fixedly connected.After completing being fixedly connected of upper strata bearing 1 and bottom bearing 4, in bottom bearing 4 and upper strata bearing 1 Outer ring laying upper strata asphalt concrete layer 7, you can complete the making of the inlet for stom water.
The above is only preferred embodiment of the present utility model, and protection domain of the present utility model is not limited merely to Above-described embodiment, all technical schemes belonged under the utility model thinking belong to protection domain of the present utility model.Should refer to Go out, for those skilled in the art, some improvement under the premise of the utility model principle is not departed from and Retouching, these improvements and modifications also should be regarded as protection domain of the present utility model.

Claims (8)

1. a kind of prefabricated assembled inlet for stom water, it is characterised in that:Including bottom bearing (4) and upper strata bearing (1) annular in shape, institute Upper strata bearing (1) is stated to be superimposed on the bottom bearing (4), the upper strata bearing (1) and the bottom bearing (4) overlap after Both junctions form some enclosed hanging holes, and the hanging hole is connected with protection network (2), are set on the protection network (2) There is the link (21) coordinated with the hanging hole.
2. prefabricated assembled inlet for stom water according to claim 1, it is characterised in that:Under the inner side of the upper strata bearing (1) End is provided with the breach of ring-type, and the roof of the breach is provided with the first fixed block (13) for extending downwardly, the bottom bearing (4) top surface be provided with first fixed block (13) coordinate the second fixed block (42), first fixed block (13) with Second fixed block (42) is with the hanging hole for being encircled into closing.
3. prefabricated assembled inlet for stom water according to claim 2, it is characterised in that:The top of second fixed block (42) Higher than the bottom of first fixed block (13), and second fixed block (42) is positioned at the interior of first fixed block (13) Side.
4. prefabricated assembled inlet for stom water according to claim 1, it is characterised in that:The upper strata bearing (1) and the bottom It is fixedly connected by fastener between layer bearing (4).
5. prefabricated assembled inlet for stom water according to claim 4, it is characterised in that:The fastener is included through on described The bolt (3) that layer bearing (1) is threadedly coupled with the bottom bearing (4).
6. prefabricated assembled inlet for stom water according to claim 5, it is characterised in that:It is prefabricated with the bottom bearing (4) The swivel nut (41) coordinated with the bolt (3).
7. prefabricated assembled inlet for stom water according to claim 5, it is characterised in that:The top surface of the upper strata bearing (1) sets It is equipped with the putting hole (11) placed for the head of the bolt (3).
8. prefabricated assembled inlet for stom water according to claim 1, it is characterised in that:The protection network is preventing that steel wire is made Protecting wire net (2).
CN201620998331.3U 2016-08-30 2016-08-30 Prefabricated assembled inlet for stom water Expired - Fee Related CN206204727U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620998331.3U CN206204727U (en) 2016-08-30 2016-08-30 Prefabricated assembled inlet for stom water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620998331.3U CN206204727U (en) 2016-08-30 2016-08-30 Prefabricated assembled inlet for stom water

Publications (1)

Publication Number Publication Date
CN206204727U true CN206204727U (en) 2017-05-31

Family

ID=58759870

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620998331.3U Expired - Fee Related CN206204727U (en) 2016-08-30 2016-08-30 Prefabricated assembled inlet for stom water

Country Status (1)

Country Link
CN (1) CN206204727U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111255049A (en) * 2020-03-21 2020-06-09 湖北省交通规划设计院股份有限公司 Pavement transverse drainage device and mounting method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111255049A (en) * 2020-03-21 2020-06-09 湖北省交通规划设计院股份有限公司 Pavement transverse drainage device and mounting method

Similar Documents

Publication Publication Date Title
CN105386464B (en) Inlet and outlet part for maintenance of intelligent urban underground comprehensive pipe gallery
CN107447657A (en) A kind of concealed deck drainage system
CN206204727U (en) Prefabricated assembled inlet for stom water
CN112343654A (en) Maintainable drainage system for extremely water-rich stratum tunnel and tunnel
CN209892228U (en) Underground comprehensive pipe gallery structure constructed by adopting underground excavation method
CN108360570A (en) Bituminous paving inspection shaft gug construction method
CN207314477U (en) The Stormwater Drainage System that road collection Water warfare becomes a mandarin
CN207582508U (en) A kind of permeable inspection well cover of eco-filtration
CN205443855U (en) Highway road surface with drainage water collection function
JP3107458U (en) Work floor for shaft construction and its mounting device
CN206352237U (en) A kind of new town road
CN209040163U (en) A kind of municipal works well lid
CN207749610U (en) The catch-basin of the anti-blocking anti-drop device of catch-basin and the application device
CN206721703U (en) Bang Shan highways with top protection structure
CN206800826U (en) A kind of anti-blocking, anti-creep overboard system
CN206189464U (en) Sewer pipe well with prevent weight measure safely
CN205804417U (en) A kind of permeable well lid of the new type colorful utilizing chats to prepare
CN214832901U (en) Assembled anti-settling concrete well ring
CN206070566U (en) Prestressed concrete multifunctional precast piping lane
CN206110191U (en) Well lid support of road inspection shaft
CN206428722U (en) A kind of multifunctional comprehensive underground pipe gallery
CN206189730U (en) Hook bolted connection node of whole afebril bridge plate wall of assembled concrete
CN204225257U (en) A kind of environment-friendly type prefabricated pair of case deep hole type catch pit
CN212271152U (en) Urban road well device
CN221276775U (en) Prefabricated two-sided drainage device of integration

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170531

Termination date: 20200830