CN108360570A - Bituminous paving inspection shaft gug construction method - Google Patents
Bituminous paving inspection shaft gug construction method Download PDFInfo
- Publication number
- CN108360570A CN108360570A CN201810279522.8A CN201810279522A CN108360570A CN 108360570 A CN108360570 A CN 108360570A CN 201810279522 A CN201810279522 A CN 201810279522A CN 108360570 A CN108360570 A CN 108360570A
- Authority
- CN
- China
- Prior art keywords
- gug
- bituminous paving
- prefabricated
- well lid
- inspection shaft
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/12—Manhole shafts; Other inspection or access chambers; Accessories therefor
- E02D29/128—Repairs of manhole shafts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/12—Manhole shafts; Other inspection or access chambers; Accessories therefor
- E02D29/14—Covers for manholes or the like; Frames for covers
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Road Repair (AREA)
- Road Paving Structures (AREA)
Abstract
The present invention discloses a bituminous paving inspection shaft gug construction method, acts on a bituminous paving, wherein the bituminous paving includes road surface and roadbed, includes the following steps:Prefabricated well is set;Interim well lid is anti-bias:It is laid with middle layer;Penetrate through the gug space;Dispose adjustable lifting die body system;Prepare gug circle;Steel well seat is installed;And installation well lid, the bituminous paving inspection shaft gug construction method match the anti-bias technology of interim well lid with adjustable lifting mould technology, have evaded the deficiency of traditional gug engineering method, improve construction efficiency, have preferable economic technology benefit.
Description
Technical field
The present invention relates to municipal road construction field, more particularly to a kind of bituminous paving inspection shaft gug construction method, institute
Inspection shaft gug construction method is stated in conjunction with the anti-bias technology of interim well lid and adjustable lifting mould technology.
Background technology
Become today of global concern in environmental protection, carries out bituminous paving laying project to the positive general trend of events of China's urban road, drip
Green road surface has the superiority such as anti-dust, pollution-free, noise reduction, beauty to be liked by vast urban construction person and people.
However it is exactly that underground utilities are more that urban road, which also has a big feature, which results in the quantity of road surface inspection shaft to increase sharply,
Especially seem that the rainwater sewage inspection well on driveway or the electric power telecommunication inspection manhole laying positioned at residential block are just special
Ground is more, these inspection shafts are that Municipal Infrastructure is indispensable, but also becomes difficulty in treatment when bituminous paving is laid with.
With the development of communication, motor vehicles increase to aggravate rolling to the inspection shaft on asphalt roads,
However bituminous paving haves the characteristics that compactness is inadequate, this results in the inspection shaft on bituminous paving in the work repeatedly of vehicular load
Under, under rainwater repeated action generally existing decline, the diseases such as damaged, passage around well, to cause road surface moisture to penetrate into, weight
The case where existing quality problems of appearing again.However the lower general who has surrendered of these inspection shafts brings many problems, one influences urban pavement
Beauty, since the recess of inspection shaft causes road surface rugged situation occur, two influence comfort level of driving a vehicle, when leading to car owner
When driving inspection shaft of the vehicle Jing Guo the decline, it will sink suddenly and the comfort level that influences to drive a vehicle, in some instances it may even be possible to safety can be caused
Accident.Such as when the sinking degree of certain inspection shafts is more serious, it may result in vehicle tyre and skid or be absorbed in, and
Cause immeasurable safety accident, three cause the quality problems of underground utilities, when inspection shaft recess or it is damaged when, at this time
The moisture on road surface either other substances can enter the underground utilities to aoxidize or corrosion underground utilities in addition some when
It waits substance and enters the underground utilities directly from the gap of side, and lead to underground utilities safety problem, four influence pavement structure
Stability.
However that there are construction efficiency is low for traditional gug engineering method, installation accuracy is low, and economy pays the problems such as big, also
It is to say, traditional gug engineering method causes the gug engineering phase longer due to construction problem, influences road surface normal operation, and safe
Precision is low.
In conclusion convenient there is an urgent need for inventing a kind of construction at present, installation accuracy is high, while the drip outstanding of economic technology benefit
Green road surface inspection shaft gug new paragon, to make up the deficiency of traditional gug engineering method.
Invention content
The purpose of the present invention is to provide a bituminous paving inspection shaft gug construction method, the bituminous paving inspection shaft liters
Well construction method matches the anti-bias technology of interim well lid with adjustable lifting mould technology, has evaded the deficiency of traditional gug engineering method, has carried
High construction efficiency has preferable economic technology benefit.
The purpose of the present invention is to provide a bituminous paving inspection shaft gug construction method, the interim anti-bias technology of well lid
To the interim well lid of fixation, well lid during decking and rolling is prevented to be subjected to displacement, improves installation accuracy.
The purpose of the present invention is to provide a bituminous paving inspection shaft gug construction method, close mesh is used above interim well lid
The metalling of net package substitutes cement stabilized macadam underlayment temporarily, excavates operation convenient for the later stage, while rubble is because using close mesh
Net package, easy to clean, construction are more convenient.
The purpose of the present invention is to provide a bituminous paving inspection shaft gug construction methods, using the adjustable lifting mould technology
Dispose gug circle, easily fill it is readily removable, improve construction efficiency and formwork quality it is guaranteed, technical benefits is notable.
The purpose of the present invention is to provide a bituminous paving inspection shaft gug construction method, the bituminous paving inspection shaft liters
The supplementary structure that well construction method is applied to can be recycled, and reduce construction cost.
The purpose of the present invention is to provide a bituminous paving inspection shaft gug construction method, the bituminous paving inspection shaft liters
Well construction method is suitable for the inspection shaft gug of flexible pavement and general road, i.e., applied widely.
The purpose of the present invention is to provide a bituminous paving inspection shaft gug construction method, the bituminous paving inspection shaft liters
Well construction method makes the inspection shaft gug construction become convenient, greatly improves construction efficiency, reduces construction cost.
The purpose of the present invention is to provide a bituminous paving inspection shaft gug construction method, the bituminous paving inspection shaft liters
Well construction method and the safe precision of gug structure are high, and accuracy is high, extends the service life of inspection shaft.
To realize the above-mentioned technical purpose, present invention employs following technical schemes:One bituminous paving inspection shaft gug is constructed
Method acts on a bituminous paving, wherein the bituminous paving includes road surface and roadbed, includes the following steps:
Prefabricated well is set:By prefabricated shaft construction to roadbed top surface design altitude, and pacify at the top of the prefabricated pit shaft
Fill prefabricated cover board;
Interim well lid is anti-bias:Interim well lid anti-bias structure center is disposed through the interim well that the prefabricated well covers
Lid, wherein the interim well lid anti-bias structure includes the fastener, push rod, mobile jib, elastic element and at least one auxiliary connect
Bar controls the fastener to strut auxiliary connecting rod, wherein inner wall of the auxiliary connecting rod against the prefabricated pit shaft;
It is laid with middle layer:It is laid with the steady underlayment of water, cement treated material and middle cutting optimal successively on the interim well lid;
Penetrate through the gug space:Take out metalling and the interim well lid anti-bias structure;
Dispose adjustable lifting die body system:Prefabricated punching block is set on the prefabricated cover board, and formation pours area, in the pre-manufactured steel
Embedded adjustable hanging mould structure in mould;
Prepare gug circle:The casting concrete in the hanging mould structure forms the gug circle pouring area;
Steel well seat is installed:In gug circle top surface installation well seat and accurate adjustment well seat height journey;And
Well lid is installed:Well lid is installed after the completion of the construction of well seat.
In some embodiments, in the anti-bias step of interim well lid, the push rod is connected to the mobile jib with can pushing,
The push rod and the elastic element are placed in the mobile jib, and the push rod passes through the elastic element and the auxiliary connecting rod
Connection, the activity of the push rod control the stretching, extension of the auxiliary connecting rod by the elastic element.
In some embodiments, the push rod pass through the interim well lid prefabricated hole, screw the fastener until
Inner wall of the auxiliary connecting rod against the prefabricated pit shaft.
In some embodiments, the laying middle layer further comprises the steps:
It is laid with the steady base of water:The steady base of water described in making, making are completed above the roadbed and the interim well lid
Afterwards, well location is identified, cleaning Stabilizing Materials are to vacate one first gug space;
It is laid with cement treated material:Continue making cement treated material on the steady base of water, after the completion of making, identifies well location, cleaning is steady
Fixed material is to vacate the second gug space;And
Cutting optimal in laying:Continue cutting optimal in making on cement treated material, after the completion of making, identifies well location, cleaning paving
If material is to vacate third gug space.
In some embodiments, the laying middle layer further comprises the steps:
First gug space, second gug space and third gug space penetrate through each other, and horizontal
Section aperture position size is identical, collectively constitutes a cylindric gug space.
In some embodiments, in placement adjustable lifting die body system step, the hanging mould structure includes vertical sleeve, horizontal
To sleeve, rod-adjurstable, horizontal hanger rod and anchor rib, wherein the vertical sleeve is fixed on the horizontal hanger rod, it is described perpendicular
The transverse sleeves are set to sleeve outer wall, the rod-adjurstable is set to the transverse sleeves, and the horizontal hanger rod passes through institute
It states anchor rib and is fixed on the middle cutting optimal.
In some embodiments, it can be adjusted including shrapnel and stem, the length of the rod-adjurstable in the vertical sleeve
Section, the rod-adjurstable connect the stem by the shrapnel, when the stem is inserted into the vertical sleeve, the adjustable support
Bar holds out against the prefabricated punching block.
In some embodiments, embedded adjustable hanging mould structure further comprises the steps:The fixed vertical sleeve in
The horizontal hanger rod, the horizontal hanger rod are fixed on the middle cutting optimal by the anchor rib, to the vertical sleeve interpolation
Enter the stem, holds out against the rod-adjurstable in the prefabricated punching block.
In some embodiments, the gug circle pour elevation be design road surface elevation subtract well lid thickness subtract it is reserved
Space thickness layer.
In some embodiments, when excavating the first gug space, the metalling wrapped up using Dense mesh screen is backfilled to
The design crest level of the steady base of water.
Description of the drawings
Fig. 1 is that one embodiment of the invention utilizes applying after the completion of the bituminous paving inspection shaft gug construction method
Work figure.
Fig. 2 is that the interim well lid in the bituminous paving inspection shaft gug construction method of one embodiment of the invention is anti-bias
The schematic diagram of application structure of technology.
Fig. 3 is the construction schematic diagram of the bituminous paving inspection shaft gug construction method of the embodiment of the present invention.
Fig. 4 is the adjustable lifting mould technology of the bituminous paving inspection shaft gug construction method of the embodiment of the present invention
Schematic diagram of application structure.
Fig. 5 is the method flow signal of the bituminous paving inspection shaft gug construction method of the embodiment of the present invention
Figure.
In figure:The prefabricated pit shafts of 1-;The interim well lids of 2-;3- fasteners;4- push rods;5- elastic elements;The prefabricated cover boards of 6-;The roads 7-
Bed;8- mobile jibs;9- auxiliary connecting rods;10- Dense mesh screens;11- metallings;The steady underlayment of 12- water;13- cement treated materials;In 14- below
Layer;15- anchor ribs;16- gug circles;17- sunpenders;18- fixed rings;19- stems;20- shrapnels;The vertical sleeves of 21-;22- is lateral
Sleeve;23- rod-adjurstables;The prefabricated punching blocks of 24-;25- limit fasteners;26- hinged shafts;27- well lids;28- steel well seats;29- lower margins
Bolt;30- designs road surface.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, the every other embodiment that those of ordinary skill in the art are obtained belong to what the present invention protected
Range.
It will be understood by those skilled in the art that the present invention exposure in, term " longitudinal direction ", " transverse direction ", "upper",
The orientation of the instructions such as "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom" "inner", "outside" or position are closed
System is to be based on the orientation or positional relationship shown in the drawings, and is merely for convenience of description of the present invention and simplification of the description, without referring to
Show or imply that signified device or element must have a particular orientation, with specific azimuth configuration and operation, therefore above-mentioned art
Language is not considered as limiting the invention.
It is understood that term " one " is interpreted as " at least one " or " one or more ", i.e., in one embodiment,
The quantity of one element can be one, and in a further embodiment, the quantity of the element can be multiple, and term " one " is no
It can be interpreted as the limitation to quantity.
In order to solve problems in the prior art, the present invention provides a bituminous paving inspection shaft gug construction method, wherein institute
Bituminous paving inspection shaft gug construction method is stated in conjunction with the anti-bias technology of interim well lid and adjustable lifting mould technology, has evaded traditional gug
The deficiency of engineering method improves the construction efficiency of gug, has preferable economic technology benefit.
Inspection shaft refers to just setting outside one residential (ranges such as residential area, public building area, plant area) interior pipeline buried
Diameter is not higher than the well head of certain altitude no more than certain size, the depth of burying, is used for inspection building adjunct, for example seem position
Inspection shaft in being used for rainwater sewage inspection well on driveway or positioned at residential block for laying electric power telecommunication line.And pitch
Road surface includes road surface and roadbed, wherein supporting body of the roadbed as road surface, the pressure on road surface, roadbed are come from carrying
It is set to the following certain size in road surface.That is, the inspection shaft is formed on asphalt roads, wherein the inspection shaft runs through
The space more than roadbed and unicom building adjunct and road surface, it is however generally that, inspection shaft height level is in preset design
Road surface.
The present invention provides a bituminous paving inspection shaft gug method, and the bituminous paving inspection shaft gug construction method includes
Following steps:
Place prefabricated well:Surveying setting-out is completed first in construction, the construction of prefabricated pit shaft 1 to roadbed top surface is designed high
Journey, and prefabricated cover board 2 is installed at the top of the prefabricated pit shaft 1.
Specifically, the height of height and test roadbed 7 of the roadbed 7 apart from design road surface 30 is first measured in the step
Degree, selects the suitable prefabricated pit shaft 1 and the prefabricated pit shaft 1 is set in the built-in space of inspection shaft, wherein described
Prefabricated pit shaft 1 abuts the inner wall of the roadbed 7, and the top of the prefabricated pit shaft 1 is constructed to design roadbed elevation of top surface, described pre-
1 inside of pit shaft processed defines a cylinder well space.
In addition the prefabricated cover board 2 is set in the top of the prefabricated pit shaft 1, the side of the prefabricated cover board 2 also abuts
The inner wall of the roadbed 7, and the prefabricated cover board 2 highly exactly can be placed on the prefabricated well when the prefabricated cover board 2
When on cylinder 1, the top surface level of the prefabricated cover board 2 is in 7 top surface of the roadbed.
The prefabricated cover board 2 is hollow circular ring shape structure, that is to say, that 2 inside of the prefabricated cover board is absolutely empty in defining one
Between, the hollow space is implemented as annular shape, and the size of the annular shape is according to the inspection shaft and the prefabricated pit shaft 1
Change and changes, in one embodiment of this invention, a diameter of 500mm of the hollow space, the model of the prefabricated pit shaft 1
For DN700.
When the prefabricated cover board 2 is set to the prefabricated pit shaft 1, the hollow space penetrates through cylinder well space,
And cylinder well space described in unicom and roadbed environment above.In one embodiment of this invention, the opening of the prefabricated cover board 2
Area is not more than the opening area of the prefabricated pit shaft 1, and the prefabricated cover board 2 and the prefabricated pit shaft 1 are symmetrical
Structure is symmetrical arranged along a central axes.
Interim well lid is anti-bias:The interim well lid anti-bias structure center is disposed through facing on the prefabricated well lid 6
When well lid, control fastener 3 to strut auxiliary connecting rod 9, wherein inner wall of the auxiliary connecting rod 9 against the prefabricated pit shaft 1.
Specifically, an interim well lid 2 by center symmetric setting on the prefabricated well lid 6, wherein the interim well lid 2
Upper formation prefabricated hole, wherein the prefabricated hole is arranged centered on the center of the interim well lid 2.That is, described
Interim well lid 2 is also implemented as a hollow circular ring structure, and the prefabricated hole is its hollow structure.It is worth noting that, working as institute
When stating interim well lid 2 and being placed on the prefabricated well lid 6, the central axes of the interim well lid 2 and the prefabricated hole coincide with
The central axes of the prefabricated well lid 6, in an embodiment of the present invention, the size of the reserving hole is 50mm.
The interim well lid anti-bias structure includes fastener 3, and push rod 4, mobile jib 8, elastic element 5 and at least one auxiliary connect
Bar 9, wherein the push rod 4 and the elastic element 5 are placed in the mobile jib 8, the auxiliary connecting rod 9 is connected to the mobile jib
9 other end, and symmetrically distributed around centered on the mobile jib 9, one end of the elastic element 5 is connected to the push rod
4, the other end is connected to the auxiliary connecting rod 9, and the auxiliary connecting rod 9 forms secondary surface after strutting.
Specifically, the elastic element 5 is set to the mobile jib 8, and described in one end connection of the elastic element 5
4 other end of push rod connects the auxiliary connecting rod 9, and when the push rod 4 is far from the mobile jib 8, the elastic element 5 is in nature
State, at this point, the auxiliary connecting rod 9 is shunk close to the mobile jib 8, two when the push rod 4 is close to the mobile jib 8, the bullet
Property element 5 by the push rod 4 push and be extruded, the auxiliary connecting rod 9 is opened around centered on the mobile jib 8.
In addition, the fastener 3 is set to one end of the push rod 4, the size of the push rod 4 is matched with the pre-manufactured hole
Hole, so that the push rod 4 may pass through the interim well lid 2, and the fastener 3 is set on the push rod 4 with tight
Gu the push rod 4 and the interim well lid 2, in an embodiment of the present invention, the fastener 3 are a bolt.In addition, passing through
Screwing on the fastener 3 can push the push rod 4 to strut the auxiliary connecting rod 9, anti-bias to play the role of interim well.
In summary, the mobile jib 5 passes through the prefabricated hole and passes through the fastener 3 and the interim well lid 2
Connection, since the central axes of the prefabricated hole coincide with the central axes of the prefabricated pit shaft 1, the also position of the described therefore described mobile jib 8
In on the central axes, screwing the fastener 3 to push the push rod 4, the work that the push rod 4 passes through the elastic element 5
It is anti-to play interim well lid 2 with strutting the auxiliary connecting rod 9 until the auxiliary connecting rod 9 is against the inner wall of the prefabricated pit shaft 1
Inclined effect improves structural strength, and in an embodiment of the present invention, the supporting surface that the auxiliary connecting rod 9 is formed is a diameter of
700mm。
It is laid with middle layer:Be laid with the steady underlayment 12 of water successively on the interim well lid 2, cement treated material 13 and in below
Layer 14.
The step of being laid with middle layer can be divided into the steady base of laying water 12 again:On the roadbed 7 and the interim well lid 2
The steady base 12 of water described in the making of face after the completion of making, identifies well location, cleaning Stabilizing Materials are to vacate one first gug space.
Specifically, in the step, the steady base 12 of water is cement stabilized macadam underlayment, that is, it is steady to be laid with cement
Fixed material is on the roadbed 7 and the interim well lid 2, to form the steady base of certain thickness water 12.And it is completed in making
Afterwards, survey crew goes out well location with coordinates logo, defines first gug space, digs out the stabilization in the gug space in time
Material.
In an embodiment of the present invention, the first gug space orientation be width from the outside 250-350mm of the borehole wall, preferably
300mm stablizes base 12 described in depth penetration to 2 top of interim well lid, that is to say, that need to dig out first gug in time
The size in space, the design that the metalling 11 in addition wrapped up using Dense mesh screen 11 in excavation section is backfilled to the steady base of water 12 are risen
Journey.
The step of being laid with middle layer can be divided into again is laid with cement treated material 13:The continuation making cement treated material on the steady base 12 of water
13, after the completion of making, well location is identified, cleaning Stabilizing Materials are to vacate the second gug space.
The construction procedure of the step is same as being laid with the steady base 12 of water, the difference is that, paver difference is described
The height of cement treated material 13 is controlled in 150-200mm, preferably 180mm.
Similarly, the step of being laid with middle layer can be divided into cutting optimal 14 in laying again:Continue in making on cement treated material 13
Cutting optimal 14 after the completion of making, identifies well location, and cleaning is laid with material to vacate third gug space.
The construction procedure of the step is same as being laid with stable base 12, the difference is that, paver difference is described
The height of middle cutting optimal 14 is controlled in 100-150mm, preferably 120mm.
After being laid with the middle layer, including step:
Penetrate through the gug space:Take out the metalling 11 and the interim well lid anti-bias structure.
Stabilizing Materials are constantly taken out in the construction process and are laid with material to form first gug space, the second gug space
And third gug space, wherein first gug space, the second gug space and third gug space breakthrough form each other
At a cylindric gug space, that is to say, that first gug space, the second gug space, third gug space it is transversal
Face controls in the same vertical plane, their cross section is identical, including position, area etc..
After the middle layer and the gug space are formed, the bituminous paving inspection shaft gug method packet
It includes:
Dispose adjustable lifting die body system:Prefabricated punching block 24 is set in the prefabricated steel 6, it is embedding in the prefabricated punching block 24
Enter adjustable hanging mould structure.
Specifically, the adjustable steel mold includes prefabricated punching block 24, wherein the pre-manufactured steel mould 24 is hollow circle tube
Shape is placed in the prefabricated steel 6, to define a die space in the gug space, and it is of note that described
The central axes of prefabricated punching block 24 correspond to the central axes of the prefabricated pit shaft 1 always.
The adjustable hanging mould structure includes vertical sleeve 21, transverse sleeves 22, rod-adjurstable 23, horizontal hanger rod 17 and anchor
Gu muscle 15, wherein the vertical sleeve 21 is fixed on the horizontal hanger rod 17, the transverse direction is arranged in 21 outer wall of vertical sleeve
Sleeve 22, the rod-adjurstable 23 are set to the space in the transverse sleeves 22, and the horizontal hanger rod 17 passes through the anchoring
Muscle 15 is fixed on the middle cutting optimal 14.
In addition, including shrapnel and stem 19 in the vertical sleeve 21, the length of the rod-adjurstable 23 can be conditioned, institute
State rod-adjurstable 23 and the stem 19 connected by the shrapnel, when the stem 19 is inserted into the vertical sleeve 21, it is described can
Strut 23 is adjusted to hold out against the prefabricated punching block 24.
Specifically, the both ends of the transverse direction trapeze 17 are fixed on the middle cutting optimal 14, in the embodiment of the present invention
In, the horizontal hanger rod 17 is fixed on the middle cutting optimal 14 by the anchor rib 15.The vertical sleeve 21 is perpendicular to institute
It states horizontal hanger rod 17 and is fixed on the horizontal line sunpender 17, be located on the central axes of the prefabricated punching block 24.
The transverse sleeves 22 and the vertical sleeve 21 are connected and are communicated, and the rod-adjurstable 23 is set to the transverse direction
In sleeve 22, and the adjustable in length of the rod-adjurstable 23, limit fastener 25 is set, wherein described on the rod-adjurstable 23
Limit fastener 25 is placed on the rod-adjurstable 23 with the length of the fixation rod-adjurstable 23.
Include shrapnel in the vertical sleeve 21, the shrapnel is connect with the rod-adjurstable 23, when the stem 19 is inserted
After entering in the vertical sleeve 21, the stem 19 compresses the rod-adjurstable 23 and the prefabricated punching block by the shrapnel
24。
In other words, embedded adjustable hanging mould structure further comprises the steps:The fixed vertical sleeve 21 is in the cross
To sunpender 17, the horizontal hanger rod 17 is fixed on the middle cutting optimal 14 by the anchor rib 15, to the vertical sleeve 21
It is interior to be inserted into the stem 19, the rod-adjurstable 23 is held out against in the prefabricated punching block 24.
After the adjustable hanging mould structure is placed in the gug space, further comprise the steps:
Prepare gug circle:The casting concrete in the hanging mould structure forms the gug circle 16 in encapsulating layer.
Specifically, in the step:C25 concrete is poured in mould to described hang, and vibration compacting, wherein the coagulation
Soil enters the position between the prefabricated punching block 24 and the middle layer by the hanging mould structure, wherein the gug circle pours
Elevation h=design road surface elevation-well lid thickness -20mm are built, the gaps 20m are at least stayed in well seat bottom with concrete surface, certainly here
20mm conditions without limitation, and scheme as priority.This highly be used to finely tune well lid elevation, before waiting for concrete initial set, in advance
Bury φ 18mm foundation bolts three or four.The outer diameter of the gug circle is more than the outer diameter of prefabricated pit shaft, pre- in the gug circle
Bury vertical foundation bolt.
In addition after the gug circle 16 shapes, the adjustable hanging mould structure is taken out, and include the following steps:
Steel well seat is installed:In 16 top surface of gug circle installation well seat 28 and accurate adjustment well seat height journey.
During the accurate adjustment of the well seat 28, intersecting parallels hanging wire, the outer 2~3m of the hanging wire ranging from borehole wall, after mixing up are taken
Timely tightening nuts are answered, after determining that nut does not loosen, the remaining exposed ground bolt of excision pours C25 microliths coagulation around well lid
Soil, and cover, maintenance of sprinkling water.Wherein the well seat 28 is formed on the gug circle 16 and relies on the middle layer.
Well lid is installed:Well lid 27 is installed after the completion of the construction of well seat.
In an embodiment of the present invention, the well lid 27 is connected to the design road surface by hinged shaft 26, that is to say, that institute
The elevation for stating well seat 28 coordinates the position of the well lid 27 so that when well lid 27 is set on the well seat 28, the well lid
27 face levels are in the design road surface 30.
The present invention is not limited to above-mentioned preferred forms, anyone can show that other are various under the inspiration of the present invention
The product of form, however, make any variation in its shape or structure, it is every that there is skill identical or similar to the present application
Art scheme, is within the scope of the present invention.
Claims (10)
1. a bituminous paving inspection shaft gug construction method, acts on a bituminous paving, wherein the bituminous paving includes road surface
And roadbed, which is characterized in that the bituminous paving inspection shaft gug construction method includes the following steps:
Prefabricated well is set:By prefabricated shaft construction to roadbed top surface design altitude, and it is pre- in the installation of the top of the prefabricated pit shaft
Cover board processed;
Interim well lid is anti-bias:Interim well lid anti-bias structure center is disposed through the interim well lid that the prefabricated well covers,
Described in interim well lid anti-bias structure include the fastener, push rod, mobile jib, elastic element and at least an auxiliary connecting rod, control
The fastener is made to strut auxiliary connecting rod, wherein inner wall of the auxiliary connecting rod against the prefabricated pit shaft;
It is laid with middle layer:It is laid with the steady underlayment of water, cement treated material and middle cutting optimal successively on the interim well lid;
Penetrate through the gug space:Take out metalling and the interim well lid anti-bias structure;
Dispose adjustable lifting die body system:Prefabricated punching block is set on the prefabricated cover board, and formation pours area, in the prefabricated punching block
Embedded adjustable hanging mould structure;
Prepare gug circle:The casting concrete in the hanging mould structure forms the gug circle pouring area;
Steel well seat is installed:In gug circle top surface installation well seat and accurate adjustment well seat height journey;And
Well lid is installed:Well lid is installed after the completion of the construction of well seat.
2. bituminous paving inspection shaft gug construction method according to claim 1, which is characterized in that the interim well lid is anti-
In inclined step, the push rod and the elastic element are placed in the mobile jib, and the auxiliary connecting rod is set to the mobile jib one
End, the push rod are connect by the elastic element with the auxiliary connecting rod, and the activity of the push rod passes through the elastic element
Control the stretching, extension of the auxiliary connecting rod.
3. bituminous paving inspection shaft gug construction method according to claim 2, which is characterized in that the push rod passes through institute
The prefabricated hole for stating interim well lid screws the fastener until the auxiliary connecting rod is against the inner wall of the prefabricated pit shaft, shape
At an auxiliary support face.
4. bituminous paving inspection shaft gug construction method according to claim 1, which is characterized in that the laying middle layer
Further comprise the steps:
It is laid with the steady base of water:The steady base of water described in making above the roadbed and the interim well lid, after the completion of making, mark
Know well location, cleaning Stabilizing Materials are to vacate one first gug space;
It is laid with cement treated material:Continue making cement treated material on the steady base of water, after the completion of making, identifies well location, clear up Stabilizing Materials
To vacate the second gug space;And
Cutting optimal in laying:Continue cutting optimal in making on cement treated material, after the completion of making, identifies well location, cleaning is laid with material
To vacate third gug space.
5. bituminous paving inspection shaft gug construction method according to claim 4, which is characterized in that the laying middle layer
Further comprise the steps:
First gug space, second gug space and third gug space penetrate through each other, and cross section
Aperture position size is identical, collectively constitutes a cylindric gug space.
6. bituminous paving inspection shaft gug construction method according to claim 1, which is characterized in that the placement adjustable lifting
In die body system step, the adjustable hanging mould structure includes vertical sleeve, transverse sleeves, rod-adjurstable, horizontal hanger rod and anchoring
Muscle, wherein the vertical sleeve is fixed on the horizontal hanger rod, the vertical sleeve outer wall is arranged the transverse sleeves, it is described can
Strut is adjusted to be set to the transverse sleeves, the horizontal hanger rod is fixed on the middle cutting optimal by the anchor rib.
7. bituminous paving inspection shaft gug construction method according to claim 6, which is characterized in that in the vertical sleeve
Including shrapnel and stem, the length of the rod-adjurstable can be conditioned, and the rod-adjurstable connects the core by the shrapnel
Column, when the stem is inserted into the vertical sleeve, the rod-adjurstable holds out against the prefabricated punching block.
8. bituminous paving inspection shaft gug construction method according to claim 7, which is characterized in that embedded adjustable lifting mould knot
Structure further comprises the steps:For the fixed vertical sleeve in the horizontal hanger rod, the horizontal hanger rod passes through the anchoring
Muscle is fixed on the middle cutting optimal, and the stem is inserted into the vertical sleeve, holds out against the rod-adjurstable in described prefabricated
Punching block.
9. bituminous paving inspection shaft gug construction method according to claim 1, which is characterized in that the gug circle pours
It is that design road surface elevation subtracts well lid thickness and subtracts reserved space thick layer to build elevation.
10. bituminous paving inspection shaft gug construction method according to claim 4, which is characterized in that excavating described the
When one gug space, the metalling wrapped up using Dense mesh screen is backfilled to the design crest level of the steady base of the water.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810279522.8A CN108360570B (en) | 2018-03-30 | 2018-03-30 | Lifting construction method for asphalt pavement inspection well |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810279522.8A CN108360570B (en) | 2018-03-30 | 2018-03-30 | Lifting construction method for asphalt pavement inspection well |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108360570A true CN108360570A (en) | 2018-08-03 |
CN108360570B CN108360570B (en) | 2020-11-20 |
Family
ID=63001985
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810279522.8A Active CN108360570B (en) | 2018-03-30 | 2018-03-30 | Lifting construction method for asphalt pavement inspection well |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108360570B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110820808A (en) * | 2018-08-10 | 2020-02-21 | 山东中宏路桥建设有限公司 | Method for installing rain sewage well cover on asphalt pavement |
CN111733887A (en) * | 2020-06-15 | 2020-10-02 | 中国一冶集团有限公司 | Construction method of asphalt concrete road inspection well first-rising structure |
CN113863383A (en) * | 2021-09-18 | 2021-12-31 | 上海二十冶建设有限公司 | Temporary covering tool for wellhead of inspection well |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104787469A (en) * | 2014-01-17 | 2015-07-22 | 蒋桂岁 | Foldable inner support device |
CN206448295U (en) * | 2017-02-09 | 2017-08-29 | 惠安德尔美机械有限公司 | A kind of Safety manhole cover of town road |
CN107386329A (en) * | 2017-09-14 | 2017-11-24 | 中国水利水电第五工程局有限公司 | A kind of pit shaft mould plate supporting device and its peace tear method open |
-
2018
- 2018-03-30 CN CN201810279522.8A patent/CN108360570B/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104787469A (en) * | 2014-01-17 | 2015-07-22 | 蒋桂岁 | Foldable inner support device |
CN206448295U (en) * | 2017-02-09 | 2017-08-29 | 惠安德尔美机械有限公司 | A kind of Safety manhole cover of town road |
CN107386329A (en) * | 2017-09-14 | 2017-11-24 | 中国水利水电第五工程局有限公司 | A kind of pit shaft mould plate supporting device and its peace tear method open |
Non-Patent Citations (1)
Title |
---|
王爱莲: "谈检查井升井施工方法", 《山西建筑》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110820808A (en) * | 2018-08-10 | 2020-02-21 | 山东中宏路桥建设有限公司 | Method for installing rain sewage well cover on asphalt pavement |
CN111733887A (en) * | 2020-06-15 | 2020-10-02 | 中国一冶集团有限公司 | Construction method of asphalt concrete road inspection well first-rising structure |
CN113863383A (en) * | 2021-09-18 | 2021-12-31 | 上海二十冶建设有限公司 | Temporary covering tool for wellhead of inspection well |
Also Published As
Publication number | Publication date |
---|---|
CN108360570B (en) | 2020-11-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109972659B (en) | Novel municipal inspection well structure and construction method | |
CN109898535A (en) | Prefabricated assembled upper pipe working well prestressing force open caisson and assembling method | |
CN106759496B (en) | Anti-settling inspection shaft changes the outfit technique | |
CN102644295A (en) | Construction method for preventing peripheral and local sedimentation of road surface inspection well | |
CN103343544A (en) | Construction method for large-scale open caisson | |
CN106049196B (en) | Flexible pile combines ballastless track roadbed construction method with stake raft with section | |
CN106981855B (en) | High-speed railway base cable trough system | |
CN108360570A (en) | Bituminous paving inspection shaft gug construction method | |
CN110295627B (en) | Construction method of road inspection well | |
CN103774687A (en) | Single-pipe tower prefabricated spiral steel pipe pile foundation | |
CN110004991A (en) | Underground structure anti-floating system and construction method based on raised type tangs plate | |
CN104652495B (en) | Internal support of foundation pit column and base plate node waterproof construction technology | |
CN109750571A (en) | A kind of road landslide emergency and permanent supporting and retaining system integral structure and construction method | |
CN110485266A (en) | A kind of road-bridge transition section road structure and construction method based on waste tire | |
CN208121816U (en) | The constructing structure of bituminous pavement inspection shaft gug | |
CN101768960B (en) | Bored concrete pile construction method of permafrost layer | |
CN103276645B (en) | Precast pile, beam and slab renovation technology for diseases of existing line tunnel base | |
CN110144784A (en) | The town road and its construction method constructed based on prestressed concrete plate stake | |
CN205874851U (en) | Ballastless track roadbed structure is made up with stake raft with section to flexible stake | |
CN112012763B (en) | Construction method of double-layer primary support multi-arch tunnel structure | |
CN102644266B (en) | Method utilizing fracture anchor rod piles for reinforcing soft soil stratum pavements in abutment areas | |
CN212128696U (en) | Road bridge links up mixed light dirt road bed structure of section bubble | |
RU2422581C1 (en) | Method to repair and construct arterial highways | |
CN207828722U (en) | A kind of protection structure for crossing over karez suitable for Xinjiang region roadbed | |
CN110374141A (en) | The construction method of inspection shaft is perfused after a kind of precast module type |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |