CN110820808A - Method for installing rain sewage well cover on asphalt pavement - Google Patents

Method for installing rain sewage well cover on asphalt pavement Download PDF

Info

Publication number
CN110820808A
CN110820808A CN201810906380.3A CN201810906380A CN110820808A CN 110820808 A CN110820808 A CN 110820808A CN 201810906380 A CN201810906380 A CN 201810906380A CN 110820808 A CN110820808 A CN 110820808A
Authority
CN
China
Prior art keywords
well
asphalt pavement
annular groove
well cover
height
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810906380.3A
Other languages
Chinese (zh)
Inventor
江磊
马科
张清华
卢山
陈旭亮
宋永飞
温波
吕德才
张湘云
姜炜
陈涛
徐洪波
李鑫
栾顺舟
周杰
皮志辉
闫立峰
董泉清
宋新立
王绍伟
皮志强
苗四生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG ZHONGHONG ROAD AND BRIDGE CONSTRUCTION CO Ltd
Original Assignee
SHANDONG ZHONGHONG ROAD AND BRIDGE CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG ZHONGHONG ROAD AND BRIDGE CONSTRUCTION CO Ltd filed Critical SHANDONG ZHONGHONG ROAD AND BRIDGE CONSTRUCTION CO Ltd
Priority to CN201810906380.3A priority Critical patent/CN110820808A/en
Publication of CN110820808A publication Critical patent/CN110820808A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/14Covers for manholes or the like; Frames for covers

Abstract

The invention relates to a method for installing a rain sewage well cover on an asphalt pavement, which comprises the following steps: (1) when the asphalt pavement is constructed, an annular groove is reserved around the well ring; (2) laying anti-settling reinforcing steel bars in the annular grooves; (3) the well lid is suspended by using the hoisting device, and the suspension height is adjusted until the height of the upper end surface of the well lid is consistent with the height of the road surface, so that the suspension state of the well lid is maintained; (4) and pouring concrete into the annular groove, curing, and removing the hanging device after the concrete reaches a preset strength. The invention has the advantages that: the method is simple in construction, the installed well cover is not settled, the well cover can pass through a vehicle with a large load, and the well cover is good in flatness and smooth to pass.

Description

Method for installing rain sewage well cover on asphalt pavement
Technical Field
The invention relates to a method for installing a rain sewage well cover on an asphalt pavement.
Background
The traditional method of the asphalt pavement rain sewage well cover is that after the base construction is finished, before the asphalt pavement construction, bricks, stones or concrete are used for lifting a well body well to a designed elevation, a well ring is placed, and then asphalt is paved. The technology has the advantages that the compaction degree of the asphalt cannot be controlled in advance, the well ring is often one or two centimeters higher or lower than the asphalt pavement, and is not flat, so that the vehicle cannot stably pass through the technology. And the well mouth can often be smashed by the vehicle, leads to the walling crib to sink or broken, influences the safety of passing.
Disclosure of Invention
In order to overcome the defects of the prior art, the invention provides a method for installing a rain sewage well cover on an asphalt pavement, and the technical scheme of the invention is as follows:
a method for installing a rain sewage well cover on an asphalt pavement comprises the following steps:
(1) when the asphalt pavement is constructed, an annular groove is reserved around the well ring;
(2) a lower civil grid layer, an anti-settling reinforcing steel bar and an upper civil grid layer are sequentially paved in the annular groove from bottom to top;
(3) the well lid is suspended by using the hoisting device, and the suspension height is adjusted until the height of the upper end surface of the well lid is consistent with that of the road surface, so that the suspension state of the well lid is maintained;
(4) and pouring concrete into the annular groove, covering the lower wood grid layer, the anti-settling reinforcing steel bars and the upper civil grid layer with the concrete, maintaining, and removing the suspension device after the concrete reaches a preset strength.
The distance between the outer edge of the annular groove and the walling crib is 30-50 cm.
The invention has the advantages that: the method is simple in construction, the installed well cover is not settled, the well cover can pass through an automobile, the flatness is good, and the passing is smooth.
Detailed Description
The invention will be further described with reference to specific embodiments, and the advantages and features of the invention will become apparent as the description proceeds. These examples are illustrative only and do not limit the scope of the present invention in any way. It will be understood by those skilled in the art that various changes in form and details may be made therein without departing from the spirit and scope of the invention, and that such changes and modifications may be made without departing from the spirit and scope of the invention.
The invention relates to a method for installing a rain sewage well cover on an asphalt pavement, which comprises the following steps:
(1) when the asphalt pavement is constructed, an annular groove is reserved around the well ring;
(2) a lower civil grid layer, an anti-settling reinforcing steel bar and an upper civil grid layer are sequentially paved in the annular groove from bottom to top;
(3) the well lid is suspended by using the hoisting device, and the suspension height is adjusted until the height of the upper end surface of the well lid is consistent with that of the road surface, so that the suspension state of the well lid is maintained;
(4) and pouring concrete into the annular groove, covering the lower wood grid layer, the anti-settling reinforcing steel bars and the upper civil grid layer with the concrete, maintaining, and removing the suspension device after the concrete reaches a preset strength.
The distance between the outer edge of the annular groove and the walling crib is 30-50 cm.
Through the process, the installed well lid is not settled, can pass through a loaded automobile, and is good in flatness and smooth to pass.

Claims (2)

1. The method for installing the asphalt pavement rainwater and sewage well cover is characterized by comprising the following steps of:
(1) when the asphalt pavement is constructed, an annular groove is reserved around the well ring;
(2) in the annular grooveA lower earth-wood grid layer, an anti-sedimentation reinforcing steel bar and an upper civil grid layer are sequentially laid from bottom to top;
(3) the well lid is suspended by using the hoisting device, and the suspension height is adjusted until the height of the upper end surface of the well lid is consistent with that of the road surface, so that the suspension state of the well lid is maintained;
(4) and pouring concrete into the annular groove, covering the lower wood grid layer, the anti-settling reinforcing steel bars and the upper civil grid layer with the concrete, maintaining, and removing the suspension device after the concrete reaches a preset strength.
2. The method for installing the rainwater and sewage well cover on the asphalt pavement according to claim 1, wherein the distance between the outer edge of the annular groove and the well ring is 30-50 cm.
CN201810906380.3A 2018-08-10 2018-08-10 Method for installing rain sewage well cover on asphalt pavement Pending CN110820808A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810906380.3A CN110820808A (en) 2018-08-10 2018-08-10 Method for installing rain sewage well cover on asphalt pavement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810906380.3A CN110820808A (en) 2018-08-10 2018-08-10 Method for installing rain sewage well cover on asphalt pavement

Publications (1)

Publication Number Publication Date
CN110820808A true CN110820808A (en) 2020-02-21

Family

ID=69541025

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810906380.3A Pending CN110820808A (en) 2018-08-10 2018-08-10 Method for installing rain sewage well cover on asphalt pavement

Country Status (1)

Country Link
CN (1) CN110820808A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101718101A (en) * 2009-11-19 2010-06-02 济南城建工程公司 Concrete integral pouring construction method and device for road inspection well
KR20100108786A (en) * 2009-03-30 2010-10-08 (주)한성 Manhole with mounting device of cover having height control function
CN104695300A (en) * 2015-02-06 2015-06-10 湖北益通建设股份有限公司 Process for lifting asphalt pavement inspection well and lifting structure
CN105133655A (en) * 2015-09-01 2015-12-09 深圳市建设(集团)有限公司 Construction method of well lid of road surface inspection well and auxiliary installation device
CN107313456A (en) * 2017-06-26 2017-11-03 中国建筑局(集团)有限公司 A kind of municipal inspection shaft and its anti-excavation construction method
CN108360570A (en) * 2018-03-30 2018-08-03 中大建设股份有限公司 Bituminous paving inspection shaft gug construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100108786A (en) * 2009-03-30 2010-10-08 (주)한성 Manhole with mounting device of cover having height control function
CN101718101A (en) * 2009-11-19 2010-06-02 济南城建工程公司 Concrete integral pouring construction method and device for road inspection well
CN104695300A (en) * 2015-02-06 2015-06-10 湖北益通建设股份有限公司 Process for lifting asphalt pavement inspection well and lifting structure
CN105133655A (en) * 2015-09-01 2015-12-09 深圳市建设(集团)有限公司 Construction method of well lid of road surface inspection well and auxiliary installation device
CN107313456A (en) * 2017-06-26 2017-11-03 中国建筑局(集团)有限公司 A kind of municipal inspection shaft and its anti-excavation construction method
CN108360570A (en) * 2018-03-30 2018-08-03 中大建设股份有限公司 Bituminous paving inspection shaft gug construction method

Similar Documents

Publication Publication Date Title
SG181210A1 (en) Reusable paving slab for temporary road andmethod for paving temporary road with the same
KR100869969B1 (en) Manhole repair method
CN102561690A (en) Construction method for supporting structures on two sides of post-cast strip by use of brick column
CN103334359B (en) Prefabricated reinforced concrete pavement plate and pavement construction method
CN204455749U (en) Prefabricated road surface block
CN107964874A (en) A kind of assembly concrete guardrail construction method
CN110820808A (en) Method for installing rain sewage well cover on asphalt pavement
CN103434933B (en) Large member hoisting in-position device and in-position method
CN103343503A (en) Bridge type wear-resistant pavement structure system with prefabricated reinforced concrete trough plate and construction method
CN204940033U (en) The anti-ponding paved road of a kind of undercurrent
CN205296197U (en) Prefabricated cushion cap of anticorrosive industry factory building concrete rim of a cup formula
CN107059531A (en) A kind of anti-settling pervious surface and its laying method
KR102358264B1 (en) Apparatus for adjusting iron lid and manhole construction method using the same
CN206512585U (en) A kind of adjustable box-structure viaduct of the gradient
US10794034B2 (en) Adapter frame
CN210561540U (en) But levelling device based on precast concrete pavement slab
CN102926403B (en) Roof construction method by cover-excavation method
CN210916851U (en) Leveling precast concrete pavement slab
CN209703545U (en) A kind of tower-crane foundation structure under underground garage bottom plate
CN206477363U (en) The road well head and well lid of a kind of trimeric structure
CN202559387U (en) Well lid with adjustable wellhole crossing height
CN206127790U (en) Expressway subgrade reinforced structure
KR100907040B1 (en) Height adjustable manhole
CN205313960U (en) Easy operation platform of shake, make level, quick travel is integrated
CN209941751U (en) Novel stone well lid

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination