CN206110735U - Automatically controlled integrated device of modular assembly formula skid -mounted - Google Patents

Automatically controlled integrated device of modular assembly formula skid -mounted Download PDF

Info

Publication number
CN206110735U
CN206110735U CN201621176346.8U CN201621176346U CN206110735U CN 206110735 U CN206110735 U CN 206110735U CN 201621176346 U CN201621176346 U CN 201621176346U CN 206110735 U CN206110735 U CN 206110735U
Authority
CN
China
Prior art keywords
wall
automatically controlled
room
controlled integrated
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621176346.8U
Other languages
Chinese (zh)
Inventor
姚广庆
顾毅华
宋树贵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PANJIN GUANGLIDA ELECTRIC Co Ltd
Original Assignee
PANJIN GUANGLIDA ELECTRIC Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PANJIN GUANGLIDA ELECTRIC Co Ltd filed Critical PANJIN GUANGLIDA ELECTRIC Co Ltd
Priority to CN201621176346.8U priority Critical patent/CN206110735U/en
Application granted granted Critical
Publication of CN206110735U publication Critical patent/CN206110735U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to an automatically controlled integrated device of modular assembly formula skid -mounted. The problem of the current automatically controlled integrated device of large -scale skid -mounted transportation difficulty has mainly been solved. Its characterized in that: room body main part is as an organic whole by wall body, base, the room cover concatenation fastening bolt of a plurality of skid -mounted functional modules, wall part adopts connecting bolt (4) connection as an organic whole through adorning in the inside L type connecting section steel (2) of a plurality of wall steel plate (8), weld in L type connecting section steel (2) wall steel plate (8), wall steel plate (8) inside set up wall insulation panel (7), base portion forms through a plurality of base shaped steel (1) concatenation, is connected with hoist and mount position sleeves (10) cooperation through toper guiding locating pin (12) between adjacent base shaped steel (1), the room cover through a plurality of horizontal rooms set a roof beam in place (16) form through connecting bolt (15) concatenation. This automatically controlled integrated device of modular assembly formula skid -mounted, hoist and mount are convenient with the transportation, and work efficiency is high.

Description

Modular assembled sledge fills automatically controlled integrated apparatus
Technical field
This utility model is related to technical field of electric equipment, and more particularly to a kind of Modular assembled sledge fills automatically controlled integration Device.
Background technology
Sledge in the market fills automatically controlled integrated apparatus or box-type substation is functionally more complete, and equipment amount increases, The overall dimensions for causing skid body or casing become big, easily occur the problem of ultra-wide superelevation overlength in transportation, hang to overall Dress and conveyer belt carry out very big impact.Troublesome poeration is lifted simultaneously, dangerous high, inefficiency.
The content of the invention
Technical problem to be solved in the utility model is to overcome exist in background technology existing large-scale sledge to fill automatically controlled one The problem of integral hoisting transport difficult is put in makeup, and is provided a kind of Modular assembled sledge and filled automatically controlled integrated apparatus, the module Change assembled sledge and fill automatically controlled integrated apparatus, lifting and convenient transportation, high working efficiency.
The invention for solving the technical problem can reach by following technical solution:The Modular assembled sledge fills automatically controlled one Body makeup is put, including room phosphor bodies, and the room phosphor bodies are filled body of wall, base, the fastening of room cover of functional module by some sledges Connect as one;The wall part is connected by connecting shaped steel loaded on the L-type inside some body of wall steel plates using connecting bolt It is integrated, the body of wall steel plate inside arranges wall insulated board;The base portion is spliced by some base shaped steel, phase It is connected with lifting positioning sleeve by taper guide positioning pin between adjacent base shaped steel;The room cover passes through some horizontal rooms Set a roof beam in place and be spliced;The phase next door is connected between setting a roof beam in place by room frame connecting bolt;Room cover top bolt has room lid Cover plate.
This utility model can have the advantages that compared with above-mentioned background technology:The Modular assembled sledge dress electricity Control integrated device, lifting and convenient transportation, greatly reduce cost of transportation.With it is simple and direct be easy to construction, intensity is good, versatility It is high with standardization level, the features such as interior trim surface is smooth, exterior trim is attractive in appearance.Can be according to using modular specification, standard batch Amount makes production, improves work efficiency.
Description of the drawings
Accompanying drawing 1 is structural representation of the present utility model;
Accompanying drawing 2 is this utility model base connector schematic diagram;
Accompanying drawing 3 is this utility model room cover attaching structure schematic diagram.
In figure:1- base shaped steel, 2-L types connection shaped steel, 3- sealing joint strips, 4- connecting bolts, 5- splicing seams trim panels, 6- Closely knit heat insulating stuffing, 7- wall insulated boards, 8- body of wall steel plates, 9- splicing seams outer plaques, 10- lifting positioning sleeves, 11- hangs Dress positioning sleeve baffle plate, 12- taper guide positioning pins, 13- is located by connecting bolt, 14- covering plate for house, 15- rooms frame connecting bolt, 16- Set a roof beam in place in room.
Specific embodiment:
Below in conjunction with the accompanying drawings the utility model is described in further detail:
Accompanying drawing 1 is combined shown in Fig. 2, Fig. 3, and the Modular assembled sledge fills automatically controlled integrated apparatus, including room phosphor bodies, The room phosphor bodies fill the body of wall of functional module, base, room lid splicing fastening bolt and are connected in one by some sledges;The wall part Connected as one using connecting bolt 4 by connecting shaped steel 2 loaded on the L-type inside some body of wall steel plates 8, the body of wall steel plate 8 Connect shaped steel 2 by being welded to connect L-type, the L-type connection Mosaic face of shaped steel 2 is stained with sealing joint strip 3, for ensureing being completely embedded property; The inside of the body of wall steel plate 8 arranges wall insulated board 7, and between the splicing seams of neighboring walls warming plate 7 closely knit heat insulating stuffing 6 is filled, To ensure heat-insulation and heat-preservation, antifrost and condensation so that two module neighboring walls heat-insulation layers become an entirety;It is described adjacent Internal between wall insulated board 7 to arrange splicing seams trim panel 5, the outside of neighboring walls steel plate 8 arranges splicing seams outer plaque 9, to ensure Intensity;The base portion is spliced by some base shaped steel 1, is oriented to by special taper between adjacent pans shaped steel 1 and is determined Position pin 12 is connected with special hoisting positioning sleeve 10 and completes the guiding of sledge dress functional module, positions and be connected so that overall to spell All correspondence is accurate for dress location hole;The termination of special hoisting positioning sleeve 10 is provided with lifting baffle plate 11, mounts in order to hoisting rope;It is described The bolt 13 that is located by connecting between special taper guide positioning pin 12 and special hoisting positioning sleeve 10 by being placed in guide positioning pin It is fixedly connected;
The room cover is set a roof beam in place by some horizontal rooms and 16 is spliced;The phase next door is set a roof beam in place between 16 by room frame Connecting bolt 15 connects;Room cover top bolt has covering plate for house 14, and the termination of the covering plate for house 14 1 is Π types, another Termination is c-type;Π types head is mutually overlapped so as to form labyrinth laminated arrangement, the covering plate for house with adjacent covering plate for house 14C types termination End casing in 14 is connected using bolt mode with room bobbin beam;The labyrinth stacked structure being capable of more effectively waterproof.
It is described to fill the body of wall of functional module, base, room cover splicing fastening bolt by some sledges and be connected in and be integrally formed entirety Room body device.
The Modular assembled sledge fill each functional module of automatically controlled integrated apparatus according to drawing and technological requirement through group to, After all process steps such as welding, inspection, basecoat paint, internal wall thermal insulating, finish paint spraying, inspection are fully completed, scene is transported to Carry out assembled work.Check whether the putting position of each functional module is correct before assembled.Comprise the following steps that:
1st, base is positioned and is connected
When each functional module is assembled, its distance is gradually furthered using drafting tool.Special taper guide positioning pin 12 is worn Trumpet type circular hole and the precise match of special hoisting positioning sleeve 10 outside the center of special hoisting positioning sleeve 10 are crossed, reaches what is be oriented to and position Purpose.The bolt 13 that is located by connecting is tightened makes base shaped steel near seamless.By some guide-localization external member precise match, each work( Energy module is tightened after being close to by connecting bolt, causes base splicing to complete.
2nd, the splicing of wall frame
Sealing joint strip should be sticked at connecting-type steel surface before each functional module base splicing, be started after base splicing firmly The splicing operation of body of wall.Shaped steel fastening will be connected with connecting bolt 4, with the closely knit heat insulating stuffing of piece by the seam inside splicing seams Gap is filled up, and upholstery is carried out with the tapping of splicing seams trim panel or staking, and the tapping of splicing seams outer plaque or staking are in body of wall steel plate Outer surface is reaching extraneous adornment effect.
3rd, the splicing of room lid
After the completion of the base of each functional module splices with wall frame, start the splicing operation of covering plate for house.From skid body or case The side of formula transformer station starts to install the room lid after segmentation one by one.Make the partitioning portion of each piece of room lid and the top of wall frame Connection fastening.Overlap with the partitioning portion of front portion room lid when the partitioning portion of another piece of room lid is installed, form labyrinth stacking Formula structure, while being tightened with connecting bolt.Room cap-shaped is caused into an entirety.
The Modular assembled sledge fills automatically controlled integrated apparatus, is that former large-scale sledge is filled into automatically controlled integrated apparatus by function Module carries out being divided into some small-sized sledges to fill functional module, and then small-sized sledge dress functional module is assembled into the sledge of complete function Filling automatically controlled integrated apparatus. the small-sized sledge dress functional module wall and ceiling electrical equipment connecting line adopt heavy-duty connector Connection, prefabricated in factory to complete, scene only needs to complete the grafting of plug and socket.This utility model Modular assembled sledge Automatically controlled integrated apparatus are filled, solves the problems, such as that large-scale sledge fills automatically controlled integrated apparatus or box-type substation transport difficult, significantly Reduce cost of transportation, with it is simple and direct be easy to construction, good intensity, versatility and standardization level are high, interior trim surface is smooth, The features such as exterior trim is attractive in appearance.Work, using modularity, normalization, the production of standardization batch making, can be improved according to user function demand Make efficiency.This utility model so that user function demand is no longer restricted by device profile and transport, can preferably complete user Demand.

Claims (5)

1. a kind of Modular assembled sledge fills automatically controlled integrated apparatus, including room phosphor bodies, it is characterised in that:The room body master Body fills the body of wall of functional module, base, room cover and is fastenedly connected and is integrated by some sledges;If the wall part is by being loaded on Dry wall body steel plate(8)Internal L-type connection shaped steel (2) adopts connecting bolt(4)Connect as one, the body of wall steel plate(8)It is interior Portion arranges wall insulated board(7);The base portion is spliced by some base shaped steel (1), between adjacent pans shaped steel (1) By taper guide positioning pin(12)With lifting positioning sleeve(10)It is connected;The room cover is set a roof beam in place by some horizontal rooms (16)It is spliced;The phase next door is set a roof beam in place(16)Between pass through room frame connecting bolt(15)Connection;Room cover top bolt It is connected to room lid cover plate(14).
2. Modular assembled sledge according to claim 1 fills automatically controlled integrated apparatus, it is characterised in that:It is described adjacent Wall insulated board(7)Closely knit heat insulating stuffing is filled between splicing seams(6), neighboring walls warming plate(7)Between internal splicing seams are set Trim panel(5), neighboring walls steel plate(8)Outside arranges splicing seams outer plaque(9).
3. Modular assembled sledge according to claim 1 fills automatically controlled integrated apparatus, it is characterised in that:The L-type Connection shaped steel(2)Mosaic face is stained with sealing joint strip(3).
4. Modular assembled sledge according to claim 1 fills automatically controlled integrated apparatus, it is characterised in that:The lifting Positioning sleeve(10)Termination welding lifting baffle plate(11);The taper guide positioning pin(12)With lifting positioning sleeve(10)Between by putting The bolt that is located by connecting in guide positioning pin(13)It is fixedly connected.
5. Modular assembled sledge according to claim 1 fills automatically controlled integrated apparatus, it is characterised in that:The room lid Plate(14)One termination is Π types, and another termination is c-type;Adjacent covering plate for house(14)Between Π types termination mutually overlap with c-type termination So as to form labyrinth laminated arrangement;The covering plate for house(14)In end casing be connected with room bobbin beam using bolt mode.
CN201621176346.8U 2016-11-02 2016-11-02 Automatically controlled integrated device of modular assembly formula skid -mounted Active CN206110735U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621176346.8U CN206110735U (en) 2016-11-02 2016-11-02 Automatically controlled integrated device of modular assembly formula skid -mounted

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621176346.8U CN206110735U (en) 2016-11-02 2016-11-02 Automatically controlled integrated device of modular assembly formula skid -mounted

Publications (1)

Publication Number Publication Date
CN206110735U true CN206110735U (en) 2017-04-19

Family

ID=58524642

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621176346.8U Active CN206110735U (en) 2016-11-02 2016-11-02 Automatically controlled integrated device of modular assembly formula skid -mounted

Country Status (1)

Country Link
CN (1) CN206110735U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108894177A (en) * 2018-08-06 2018-11-27 上海宝冶集团有限公司 Sled sled racing track modularization assembling and hanging method
CN112919382A (en) * 2019-12-05 2021-06-08 柏诚工程股份有限公司 Manufacturing and mounting method of electrical modularization

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108894177A (en) * 2018-08-06 2018-11-27 上海宝冶集团有限公司 Sled sled racing track modularization assembling and hanging method
CN112919382A (en) * 2019-12-05 2021-06-08 柏诚工程股份有限公司 Manufacturing and mounting method of electrical modularization

Similar Documents

Publication Publication Date Title
CN104074267B (en) Dismantled and assembled sledge steel loading structure mobile field camp
CN206110735U (en) Automatically controlled integrated device of modular assembly formula skid -mounted
CN104112832B (en) Chassis quick change battery box used for electric vehicle
CN102709369B (en) Tile solar photovoltaic module
CN204960122U (en) Prefabricated integrated PVC line box SIP wall body
CN204126320U (en) Apportion modular offshore boosting station
CN205212199U (en) Prefabricated cabin formula combination secondary equipment wiring structure
CN104631747A (en) L-shaped component system for mounting thermal-insulating and decorating integrated board
CN103541477A (en) Keel for dry hanging stone curtain wall and mounting method of keel
CN205290516U (en) Integral base water collector of machining center
CN103410237B (en) Integral building shielding and enclosing corrugated plate
CN206971521U (en) A kind of architectural construction of furred ceiling
CN101418600A (en) Large prefabricated substation double-layer steel sheet structure wall
CN202487808U (en) Wiring terminal
CN207170150U (en) A kind of dispensing heating, drying device
CN204662755U (en) The pre-buried brick of strong and weak electricity pipeline
CN204886075U (en) Prefabricated formula cable shaft
CN104652612A (en) Embedded pipe structure based on fabricated structure
CN207405779U (en) Detachable Liftable steel frame movable room
CN106284799A (en) A kind of assembly method of roof system
CN204662667U (en) Built-in pipe structure based on fabricated structure
CN202541398U (en) Multifunctional television relaying vehicle
CN205726719U (en) A kind of outdoor cabinet cabinet and outdoor cabinet
CN212114752U (en) Cable joint connects feeder pillar
CN207098407U (en) A kind of power transformation box with modularization waterproof and heat-insulating ceiling

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant