CN104652612A - Embedded pipe structure based on fabricated structure - Google Patents
Embedded pipe structure based on fabricated structure Download PDFInfo
- Publication number
- CN104652612A CN104652612A CN201410847549.4A CN201410847549A CN104652612A CN 104652612 A CN104652612 A CN 104652612A CN 201410847549 A CN201410847549 A CN 201410847549A CN 104652612 A CN104652612 A CN 104652612A
- Authority
- CN
- China
- Prior art keywords
- wall
- pipe
- kinds
- reserved
- building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Rod-Shaped Construction Members (AREA)
Abstract
The invention relates to an embedded pipe structure based on a fabricated structure. The embedded pipe structure comprises various vertical embedded pipes; the various vertical embedded pipes are arranged between an outer wall and an inner wall of a building and are directly embedded to reserved positions of various box bodies in the vertical direction; when the various vertical embedded pipes are under the ground, a pipe embedding groove is reserved on a basic plane below a decoration skirting line of the inner wall; various vertical embedded pipes are directly inserted into the pipe embedding groove; the various vertical embedded pipes are in contact with a wall column, a beam or a steel structure keel in the vertical direction between the inner wall and the outer wall of the building; a junction box is reserved at each of both left and right sides of the wall column, the beam or the steel structure keel; holes are reserved in the corresponding positions on the wall column, the beam or the steel structure keel; after field splicing, the reserved positions of the left and right junction boxes are connected. The embedded pipe structure has the characteristics of reasonable structural arrangement, attractive field effect, capability of avoiding secondary excavation decoration, saving of a field construction period, saving of construction cost and the like.
Description
Technical field
What the present invention relates to is a kind of built-in pipe structure based on fabricated structure, belongs to the building technology field of intelligent substation.
Background technology
Capital construction portion of State Grid Corporation of China proposes the requirement of construction standard dispensing formula intelligent substation, the design and construction standard of unified standard dispensing formula intelligent substation, realize " standardized designs, batch production processing, assembling construction ", follow the principle of " safety, applicability, versatility, the economy " coordinating and unifying, carry out using fabricated structure in transformer station.The application of fabricated structure, can reduce scene " wet trade ", improves mechanized construction range of application, reduces field workforce and drops into, reduce site safety risk, improve engineering construction quality, technological level.
Fabricated structure machines by factory, realizes Assembling.Generally, building sheet material machines by factory, to on-the-spot splicing, needs in substation field subsequent construction for facilities such as electric, the ground connection in building, fire-fightings, there will be like this and significantly expose pipe laying, affect attractive in appearance and increase site work amount.
Shown in Fig. 1,2, for built-in pipe structural configuration on inner wall panel in conventional fabricated structure, it comprises an assembled wallboard and forms interior wall 3 and exterior wall 1, after conventional fabricated structure builds up, interior wall 3 is buried underground all kinds of casings 5 of all kinds of pipe laying 4 to direct screening interior wall, and this mode needs secondary perforate, fluting, and secondary perforate, the improper quality problems that may occur of slot treatment, outward appearance is coarse ugly, and subsequent construction vestige is obvious.
For realization batch production processing truly, assembling construction, reduce site operation workload and construction period, a large amount of hydroelectric line, reserved opening are buried underground in factory, avoid traditional structure system hydropower installation construct may occur secondary perforate, fluting, and secondary perforate, the improper quality problems that may occur of slot treatment.
Summary of the invention
The object of the invention is the deficiency overcoming prior art existence, and provide a kind of reasonable structural arrangement, spot effect attractive in appearance, secondary excavation can be avoided to fit up, save the site operation cycle, save construction cost, and the built-in pipe structure based on fabricated structure of fabricated structure built-in pipe pre-buried, on-the-spot complement in advance can be met.
The object of the invention is to have come by following technical solution, a kind of built-in pipe structure based on fabricated structure, it comprises all kinds of perpendicularly buried pipe, and described all kinds of perpendicularly buried pipes are arranged between the exterior wall of building and interior wall, and vertical direction directly buries the reserved location to all kinds of casing; When described all kinds of perpendicularly buried pipes are to below ground, reserved pipe laying groove on base surface below described inner wall decoration skirting, all kinds of perpendicularly buried pipe directly inserts described pipe laying groove.
The vertical direction of described all kinds of perpendicularly buried pipe between inner wall of building and exterior wall runs into wall column, crossbeam or steel structure keel, in an each side reserved junction box of wall column, crossbeam or steel structure keel, correspondence position preformed hole on wall column, crossbeam or steel structure keel, connects the reserved location of left and right junction box after on-the-spot splicing.
The exterior wall of described building adopts lightgage steel joist+rock cotton board+FC plate, and interior wall adopts lightgage steel joist+rock cotton board+FC plate, and described all kinds of perpendicularly buried pipes are drawn from the water power such as lighting case, headstock casing, to respective destination.
The invention belongs to and improve the one of prior art, it has connection and reasonable arrangement, spot effect is attractive in appearance, and secondary excavation can be avoided to fit up, and saves the site operation cycle, saves the features such as construction cost.
Accompanying drawing explanation
Fig. 1 is the schematic diagram of built-in pipe on inner wall panel of conventional fabricated structure.
Fig. 2 is the top view of built-in pipe on inner wall panel of conventional fabricated structure.
Fig. 3 be in fabricated structure of the present invention within the walls pipe laying at the connection detail of wall column annex.
Fig. 4 is pipe laying pipe laying top view in the vertical direction within the walls in fabricated structure of the present invention.
Fig. 5 is the connection detail of pipe laying and ground pipe laying junction within the walls in fabricated structure of the present invention.
Detailed description of the invention
Label in figure is: 1. exterior wall, 2. steel structure keel, 3. interior wall, 4. all kinds of pipe laying, 5. all kinds of casing, 6. inner wall decoration skirting, 7. pipe laying groove, 8. junction box, 9. reserving hole in structural beams within the walls.
Below in conjunction with drawings and Examples, the present invention is further illustrated.Shown in Fig. 3-5, a kind of built-in pipe structure based on fabricated structure, it comprises all kinds of perpendicularly buried pipe 4, and described all kinds of perpendicularly buried pipes 4 are arranged between the exterior wall 1 of building and interior wall 2, and vertical direction directly buries the reserved location to all kinds of casing 5; During described all kinds of perpendicularly buried pipe 4 to below ground, reserved pipe laying groove 7 on base surface below described inner wall decoration skirting 6, pipe laying groove 7 place described in all kinds of perpendicularly buried pipe 4 directly inserts.
The vertical direction of described all kinds of perpendicularly buried pipe 4 between inner wall of building and exterior wall runs into wall column, crossbeam or steel structure keel 2, in an each side reserved junction box of wall column, crossbeam or steel structure keel 2, correspondence position preformed hole 9 on wall column, crossbeam or steel structure keel 2, connects the reserved location of left and right junction box after on-the-spot splicing.
The exterior wall of described building adopts lightgage steel joist+rock cotton board+FC plate, and interior wall adopts lightgage steel joist+rock cotton board+FC plate, and described all kinds of perpendicularly buried pipes 4 are drawn from the water power such as lighting case, headstock casing, to respective destination.
Embodiment:
Shown in Fig. 3,4, all kinds of perpendicularly buried pipe 4 is arranged between described exterior wall 1 and interior wall 2 by the present invention, and vertical direction directly buries the reserved location to all kinds of casing 5; During described all kinds of perpendicularly buried pipe 4 to below ground, reserved pipe laying groove 7 on base surface below described inner wall decoration skirting 6, pipe laying groove 7 place described in all kinds of perpendicularly buried pipe 4 directly inserts.
Shown in Fig. 5, originally be it by all kinds of horizontal coiled pipe 4 when passing through described steel structure keel 2, described junction box within the walls 8 is reserved in steel structure keel 2 both sides, simultaneously reserve preformed hole 9 in described structural beams at the horizontal correspondence position of junction box 8 within the walls, after on-the-spot splicing, the reserved location of left and right junction box is connected.
The present invention is for solving built-in pipe installation question within the walls, adopt new design method, reserved location when described all kinds of pipe layings 4 being arranged in body of wall Production design, can avoid later-stage secondary perforate, embed pipe with trough, also can avoid the not corresponding problem cannot installing threading of pipe laying simultaneously.
Claims (3)
1. the built-in pipe structure based on fabricated structure, it comprises all kinds of perpendicularly buried pipe, it is characterized in that described all kinds of perpendicularly buried pipes (4) are arranged between the exterior wall (1) of building and interior wall (2), vertical direction directly buries the reserved location to all kinds of casing (5); When described all kinds of perpendicularly buried pipes (4) are to below ground, reserved pipe laying groove (7) on the base surface of described inner wall decoration skirting (6) below, pipe laying groove (7) place described in all kinds of perpendicularly buried pipe (4) directly inserts.
2. the built-in pipe structure based on fabricated structure according to claim 1, it is characterized in that the vertical direction of described all kinds of perpendicularly buried pipe (4) between inner wall of building and exterior wall runs into wall column, crossbeam or steel structure keel (2), in an each side reserved junction box of wall column, crossbeam or steel structure keel (2), the upper correspondence position preformed hole (9) of wall column, crossbeam or steel structure keel (2), connects the reserved location of left and right junction box after on-the-spot splicing.
3. the built-in pipe structure based on fabricated structure according to claim 1 and 2, it is characterized in that the exterior wall (1) of described building adopts lightgage steel joist+rock cotton board+FC plate, interior wall (3) adopts lightgage steel joist+rock cotton board+FC plate, described all kinds of perpendicularly buried pipes (4) are drawn from the water power such as lighting case, headstock casing, to respective destination.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410847549.4A CN104652612A (en) | 2014-12-29 | 2014-12-29 | Embedded pipe structure based on fabricated structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410847549.4A CN104652612A (en) | 2014-12-29 | 2014-12-29 | Embedded pipe structure based on fabricated structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104652612A true CN104652612A (en) | 2015-05-27 |
Family
ID=53244199
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410847549.4A Pending CN104652612A (en) | 2014-12-29 | 2014-12-29 | Embedded pipe structure based on fabricated structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104652612A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106245777A (en) * | 2016-09-30 | 2016-12-21 | 江苏旭华圣洛迪建材有限公司 | The installation method of a kind of assembled house and assembled house |
CN110359580A (en) * | 2019-08-19 | 2019-10-22 | 常州工程职业技术学院 | Prefabricated assembled composite steel concrete column component node connection structure and method for protecting support |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4665546A (en) * | 1985-03-13 | 1987-05-12 | Reliance Comm/Tec Corporation | Modular distribution frame assembly |
CN2174513Y (en) * | 1993-12-22 | 1994-08-17 | 张启予 | Light assembling type combined house |
CN1251877A (en) * | 1998-10-17 | 2000-05-03 | 德拉格医疗技术股份有限公司 | Distributing channel |
CN2856237Y (en) * | 2005-05-20 | 2007-01-10 | 任丙辉 | Light-weight mounting II-type light-weight steel member for building |
CN101016759A (en) * | 2007-01-12 | 2007-08-15 | 杨建平 | Fiver cement board grouting wall and construction method therefor |
CN204662667U (en) * | 2014-12-29 | 2015-09-23 | 浙江省电力设计院 | Built-in pipe structure based on fabricated structure |
-
2014
- 2014-12-29 CN CN201410847549.4A patent/CN104652612A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4665546A (en) * | 1985-03-13 | 1987-05-12 | Reliance Comm/Tec Corporation | Modular distribution frame assembly |
CN2174513Y (en) * | 1993-12-22 | 1994-08-17 | 张启予 | Light assembling type combined house |
CN1251877A (en) * | 1998-10-17 | 2000-05-03 | 德拉格医疗技术股份有限公司 | Distributing channel |
CN2856237Y (en) * | 2005-05-20 | 2007-01-10 | 任丙辉 | Light-weight mounting II-type light-weight steel member for building |
CN101016759A (en) * | 2007-01-12 | 2007-08-15 | 杨建平 | Fiver cement board grouting wall and construction method therefor |
CN204662667U (en) * | 2014-12-29 | 2015-09-23 | 浙江省电力设计院 | Built-in pipe structure based on fabricated structure |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106245777A (en) * | 2016-09-30 | 2016-12-21 | 江苏旭华圣洛迪建材有限公司 | The installation method of a kind of assembled house and assembled house |
CN106245777B (en) * | 2016-09-30 | 2018-12-04 | 南京旭华圣洛迪新型建材有限公司 | A kind of installation method and assembled house of assembled house |
CN110359580A (en) * | 2019-08-19 | 2019-10-22 | 常州工程职业技术学院 | Prefabricated assembled composite steel concrete column component node connection structure and method for protecting support |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203420403U (en) | Infilled wall construction structure based on wire box and wire tube mounting precasting building blocks | |
CN202190047U (en) | Fabricated steel ground cable channel | |
CN105762728A (en) | Method for pre-burying of strong and weak electricity box and electrical tubing | |
CN104652612A (en) | Embedded pipe structure based on fabricated structure | |
CN204662667U (en) | Built-in pipe structure based on fabricated structure | |
CN203473210U (en) | Wall and top cover connecting structure of cabin unit | |
CN205677114U (en) | Installation node for assembled inside casing light partition wall | |
CN204238193U (en) | Underground Hydro-electric Power Station fitting structure | |
CN203188682U (en) | Light and environment-friendly assembly type combined enclosure | |
CN206376495U (en) | A kind of skirting line structure | |
CN211898960U (en) | Assembled concrete building connection structure | |
CN204387499U (en) | The water power piping network installation device of indoor integrated finishing | |
CN208518183U (en) | Assembled type pipe prefabricated components | |
CN211200797U (en) | Steel bar formwork integrated wall body assembled electrical system | |
CN203452335U (en) | Water and electricity installation structure for constructional engineering | |
CN205329903U (en) | Assembled shear force wall hollow core slab line arrangment structure | |
CN210867100U (en) | Shielding spool slot for electrical system | |
CN218549428U (en) | Cylindrical lower wire box with expansion tongue | |
CN216344297U (en) | Pipeline node tee junction spare | |
CN204185997U (en) | A kind of constructability installs the steel structure column of wallboard | |
CN219690879U (en) | Assembled wall of pipeline separation | |
CN216641093U (en) | Novel prefabricated superimposed sheet and floor | |
CN204662889U (en) | A kind of end socket skirting ornamental strip with distribution trough | |
CN204662890U (en) | A kind of external corner skirting wire ornamental strip with distribution trough | |
CN204552153U (en) | Leakproof integral vacuum toilet |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information |
Address after: Hangzhou City, Zhejiang province 310012 GUCUI Road No. 68 Applicant after: Energy source in China construction group Zhejiang Province Power Design Institute Co., Ltd Address before: Hangzhou City, Zhejiang province 310012 GUCUI Road No. 68 Applicant before: Zhejiang Electric Power Design Inst. |
|
COR | Change of bibliographic data | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20150527 |
|
RJ01 | Rejection of invention patent application after publication |