CN205677114U - Installation node for assembled inside casing light partition wall - Google Patents
Installation node for assembled inside casing light partition wall Download PDFInfo
- Publication number
- CN205677114U CN205677114U CN201620459836.2U CN201620459836U CN205677114U CN 205677114 U CN205677114 U CN 205677114U CN 201620459836 U CN201620459836 U CN 201620459836U CN 205677114 U CN205677114 U CN 205677114U
- Authority
- CN
- China
- Prior art keywords
- partition wall
- place
- node
- inside casing
- shaped steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a kind of installation node for assembled inside casing light partition wall, relate to construction steel structure field.The described installation node for assembled inside casing light partition wall, including lower node and upper node, wherein: described lower node include lower frame set a roof beam in place and be arranged at lower frame set a roof beam in place on rest, described rest includes gripper shoe, is positioned at the flat board above described gripper shoe and is positioned at base plate below described gripper shoe, described base plate is set a roof beam in place with lower frame and is connected, being provided with the first bolt hole on described flat board, described flat board bolt connects the bottom of partition wall;Described upper node include upper ledge set a roof beam in place and be arranged at upper ledge set a roof beam in place on shaped steel, the upper end of described shaped steel connects described upper ledge and sets a roof beam in place, and lower end is provided with the second bolt hole, and described shaped steel bolt connects the top of partition wall.The utility model can facilitate concrete inside casing partition wall to install fast and accurately, and operating efficiency and cost-effective is greatly improved.
Description
Technical field
The utility model relates to construction steel structure field, is specifically related to a kind of installation for assembled inside casing light partition wall
Node.
Background technology
Prefabricated assembled inside casing light partition wall is a kind of novel partition wall meeting building industrialization requirement.It is two pieces of lightweights
Concrete slab is connected to become entirety by joint bar, and fills sound insulation, moistureproof light material, and root between concrete slab
According to the requirement of stress, fire prevention and preheating embedding line, inner frame is set.The material of inner frame can be concrete, steel or aluminium alloy
Deng.Prefabricated assembled inside casing light partition wall is from heavy and light, and sound insulation, moisture effect are good, and without plate seam, body of wall realizes that factory is entirely prefabricated.This
Outward, owing to this partition wall has inner frame, wall integrity can be good, in face and is respectively provided with greater stiffness outside face.So this partition wall exists
Lifting or by outside face during accidental load effect, body of wall is not easy to crack, has good bearing capacity.Because possessing above-mentioned advantage,
Inside casing light partition wall has well application and market prospects in assembled architecture field.
Assembled inside casing light partition wall can be used for steel frame and concrete frame.But when at present this partition wall being installed, often
Again slot on beams of concrete after pouring or floor, then bury partition connectors underground.Such way destructible original structure
(such as causing crack, break reinforcing bar etc.), and construction inconvenience.In order to make this inside casing light partition wall at the construction field (site) accurately and rapidly
Install, answer the installation node of reasonable design partition wall.Node is reasonably installed operating efficiency and cost-effective can be greatly improved, be
The key problem in technology of prefabricated assembled partition wall.
Utility model content
The utility model provides one to install accurately and rapidly at the construction field (site), and operating efficiency and saving can be greatly improved
The installation node for assembled inside casing light partition wall of cost.
For solving above-mentioned technical problem, the utility model provides technical scheme as follows:
A kind of installation node for assembled inside casing light partition wall, including lower node and upper node, wherein:
Described lower node include lower frame set a roof beam in place and be arranged at lower frame set a roof beam in place on rest, described rest includes gripper shoe, position
Flat board above described gripper shoe and be positioned at the base plate below described gripper shoe, described base plate is set a roof beam in place with lower frame and is connected, described
Being provided with the first bolt hole on flat board, described flat board bolt connects the bottom of partition wall;
Described upper node include upper ledge set a roof beam in place and be arranged at upper ledge set a roof beam in place on shaped steel, the upper end of described shaped steel connects described
Upper ledge is set a roof beam in place, and lower end is provided with the second bolt hole, and described shaped steel bolt connects the top of partition wall.
Further, the bottom of partition wall is provided with the groove mating with described rest, with described first spiral shell in described groove
The corresponding position of keyhole is provided with internal thread sleeve.
Further, described gripper shoe is three pieces, takes the shape of the letter U and is arranged in the lower section of described flat board, the opening of described U-shaped towards
One side wall of partition wall.
Further, described first bolt hole is the slotted hole being parallel to partition wall metope, and described second bolt hole is vertical
Direction slotted hole.
Further, gap, described flat board and building are left between the lower limb that the upper surface of described partition wall and upper ledge are set a roof beam in place
Gap is left, equal filling flexible material in described gap and gap between the upper surface of plate.
Further, described lower frame is set a roof beam in place as lower girder steel, and described upper ledge is set a roof beam in place as upper girder steel, and the bottom of described gripper shoe is worn
It is located in the cast-in-place part of floor, and the top of described gripper shoe and lower girder steel lay respectively at the both sides of floor, described base plate
With bolts with the top flange of lower girder steel, the upper end of described shaped steel is with bolts with the lower flange of upper girder steel.
Further, described shaped steel is inverted " L " shaped steel, and the horizontal component of described inverted " L " shaped steel uses bolt with upper girder steel
Connecting, described second bolt hole is arranged at the vertical section of described inverted " L " shaped steel.
Further, described lower frame is set a roof beam in place as lower composite beam, and described upper ledge is set a roof beam in place as upper composite beam, described lower composite beam bag
Including lower composite beam pre-erection and the cast-in-place part of lower composite beam, described upper composite beam includes composite beam pre-erection and upper overlapping
The cast-in-place part of beam, the bottom of described gripper shoe is located in the cast-in-place part of lower composite beam and floor, the upper bit of described gripper shoe
In the upside of the cast-in-place part of described lower composite beam, described base plate is with bolts with lower composite beam pre-erection, described shaped steel
Upper end with bolts with upper composite beam pre-erection..
Further, described shaped steel is " Z " shaped steel, and the upper end of described " Z " shaped steel is with bolts with upper composite beam, institute
State the second bolt hole and be arranged at the lower end of described " Z " shaped steel.
Further, the inside casing of partition wall is provided with the dark beam of level and vertical sleeper, and described lower node and upper node are arranged at
The dark beam of described level and the point of intersection of vertical sleeper.
The utility model has the advantages that
Compared with prior art, the installation node for assembled inside casing light partition wall of the present utility model, lower node and
Upper node achieves light partition wall with partition wall bolt mode even respectively and installs fast and accurately in Vierendeel girder, and achieves
Partition wall is effectively connected with Vierendeel girder;Lower node, upper node and partition wall all can realize prefabricated in factory, meet building industrialization
Requiring, when installing partition wall without site operation weld seam, wet trade workload is little, and installation cost is low, and installation accuracy is high.
Brief description
Fig. 1 is Vierendeel girder installation node for assembled inside casing light partition wall of the present utility model when being steel-frame structure
The structural representation of lower node, wherein (a) is front view, and (b) is side view, and (c) is top view;
Fig. 2 is Vierendeel girder installation node for assembled inside casing light partition wall of the present utility model when being xoncrete structure
In the structural representation of lower node, wherein (a) is front view, and (b) is side view, and (c) is top view;
Fig. 3 is Vierendeel girder installation node for assembled inside casing light partition wall of the present utility model when being steel-frame structure
In the structural representation of upper node, wherein (a) is front view, and (b) is side view;
Fig. 4 is Vierendeel girder installation node for assembled inside casing light partition wall of the present utility model when being xoncrete structure
In the structural representation of upper node, wherein (a) is front view, and (b) is side view;
Fig. 5 is Vierendeel girder installation node for assembled inside casing light partition wall of the present utility model when being steel-frame structure
Arrangement schematic diagram;
Fig. 6 is that the Vierendeel girder shown in Fig. 5 is of the present utility model for assembled inside casing light partition wall when being steel-frame structure
Installation node partition wall I-I to II-II to cross-sectional view, wherein (a) is I-I sectional view, (b) be II-
II sectional view;
Fig. 7 is Vierendeel girder installation for assembled inside casing light partition wall of the present utility model when being concrete frame structure
The arrangement schematic diagram of node;
Fig. 8 is that the Vierendeel girder shown in Fig. 7 is of the present utility model for assembled inside casing lightweight when being concrete frame structure
Partition wall installation node partition wall I-I to II-II to cross-sectional view, wherein (a) is I-I sectional view, and (b) is
II-II sectional view.
Detailed description of the invention
For making the technical problems to be solved in the utility model, technical scheme and advantage clearer, below in conjunction with accompanying drawing
And specific embodiment is described in detail.
The utility model provides a kind of installation node for assembled inside casing light partition wall, as shown in Figures 1 to 8, bag
Include lower node 20 and upper node 30, wherein:
Lower node 20 includes that lower frame sets a roof beam in place the 4th, 8 and be arranged at the rest 5 that the 4th, lower frame sets a roof beam in place on 8, and the 2nd, rest 5 includes gripper shoe
Being positioned at the flat board 3 above gripper shoe 2 and being positioned at the base plate 1 below gripper shoe 2, base plate 1 and lower frame are set a roof beam in place and the 4th, 8 are connected, on flat board 3
Being provided with the first bolt hole 6, flat board 3 bolt connects the bottom of partition wall 14;
Upper node 30 includes that upper ledge sets a roof beam in place the 10th, 13 and be arranged at the shaped steel that the 10th, upper ledge set a roof beam in place on 13 the 9th, 12, shaped steel the 9th, 12
Upper end connects upper ledge and sets a roof beam in place the 10th, 13, and lower end is provided with the second bolt hole 11, and shaped steel the 9th, 12 bolts connect the top of partition walls 14.
Installation node for assembled inside casing light partition wall of the present utility model, lower node 20 and upper node 30 respectively with
Partition wall 14 bolt mode even achieves partition wall 14 and installs fast and accurately in Vierendeel girder, and achieves partition wall 14 and framework
Effective connection of beam;Lower node the 20th, upper node 30 and partition wall 14 all can realize prefabricated in factory, meet wanting of building industrialization
Asking, when installing partition wall 14 without site operation weld seam, wet trade workload is little, and installation cost is low, and installation accuracy is high.
As a kind of improvement of the present utility model, the bottom of partition wall 14 is preferably provided with the groove 17 mating with rest 5, recessed
In groove 17, the position corresponding with the first bolt hole 6 is provided with internal thread sleeve 7.The width of rest 5 can be more than bottom partition wall 14
The width of the dark beam of level 15, but less than the gross thickness of partition wall 14, play the effect of the whole face wall body supporting partition wall 14;Groove 17
Being arranged on the dark beam of the level bottom partition wall 14 15, and groove 17 having enough space rests 5, the width of groove 17 can
With the width 20~30mm more than rest 5, this structure is when installing partition wall 14, it is allowed to partition wall 14 direction in face occurs slightly
Sliding, improves partition wall 14 and lower frame and sets a roof beam in place the 4th, 8 success rate being connected, and this structure can make partition wall 14 under little shake effect
Do not ftracture, do not damage.
Preferably, gripper shoe 2 can be three pieces, takes the shape of the letter U and is arranged in the lower section of flat board 3, and the opening of U-shaped is towards partition wall 14
One side wall.This structure is easily installed bolt precision rest 5 and partition wall 14.
Further, the first bolt hole 6 is preferably parallel to the slotted hole of partition wall 14 metope, and the second bolt hole 11 is preferably
Vertical direction slotted hole.This slotted hole improve partition wall 14 and lower frame set a roof beam in place the 4th, 8 and partition wall 14 and upper ledge set a roof beam in place the 10th, 13 even
The success rate connecing.
Preferably, the upper surface of partition wall 14 and upper ledge set a roof beam in place the 10th, 13 lower limb between can leave gap 18, flat board 3
And gap 21 can be left between the upper surface of floor 19, equal filling flexible material in gap 18 and gap 21.The chi in gap 18
Very little can be about 10mm, and the size in gap 21 can be 20~30mm, and flexible material can be polyethylene rod, and this structure has
Limit to effect the displacement at vertical direction for the partition wall 14, and allow partition wall 14, at vertical direction, small size displacement occurs, thus improve
Partition wall 14 and upper ledge set a roof beam in place the 10th, 13 and partition wall 14 and lower frame set a roof beam in place the 4th, 8 success rate being connected, additionally this node structure power transmission
Mode is reasonable, can bear the accidental load of bigger metope compared to conventional node.
Another kind of improving as of the present utility model, the 4th, lower frame is set a roof beam in place 8 can be lower girder steel 4, and upper ledge is set a roof beam in place the 10th, 13 permissible
For upper girder steel 10, the bottom of gripper shoe 2 is located in the cast-in-place part of floor 19, and the top of gripper shoe 2 and 4 points of lower girder steel
Not being positioned at the both sides of floor 19, base plate 3 is with bolts with the top flange of lower girder steel 4, shaped steel the 9th, 12 upper end and upper girder steel
The lower flange of 10 is with bolts.This structure is applicable to when Vierendeel girder is steel-frame structure of the present utility model for assembling
Node installed by formula inside casing light partition wall.
Further, the 9th, shaped steel 12 be preferably inverted " L " shaped steel 9, and the horizontal component of inverted " L " shaped steel 9 uses with upper girder steel 10
Bolt connects, and the second bolt hole 11 is arranged at the vertical section of inverted " L " shaped steel 9.This structure is preferably corresponding at partition wall 14
Position arranges internal thread sleeve 7, in order to " L " shaped steel 9 and partition wall 14 use that bolt is fixing to be connected, and this node structure can compare equally
Conventional node can bear the accidental load of bigger metope.
Another kind of improving as of the present utility model, the 4th, lower frame is set a roof beam in place 8 can be lower composite beam 8, and upper ledge is set a roof beam in place the 10th, 13 can
Thinking upper composite beam 13, lower composite beam 8 includes lower composite beam pre-erection 81 and the cast-in-place part 82 of lower composite beam, upper composite beam 13
Including upper composite beam pre-erection 131 and the cast-in-place part of upper composite beam 132, it is cast-in-place that the bottom of gripper shoe 2 is located in lower composite beam
In part 82 and floor 19, the top of gripper shoe 2 is positioned at the upside of the cast-in-place part 82 of lower composite beam beam, base plate 3 and lower composite beam
Pre-erection 81 is with bolts, shaped steel the 9th, 12 upper end with upper composite beam beam prefabricated part 131 with bolts.This
Structure is applicable to when Vierendeel girder is concrete frame structure of the present utility model for assembled inside casing light partition wall installation node.
Further, the 9th, shaped steel 12 be preferably " Z " shaped steel 12, and the upper end of " Z " shaped steel 12 and upper composite beam 13 use bolt
Connecting, the second bolt hole 11 is arranged at the lower end of " Z " shaped steel 12.This structure be easy to " Z " shaped steel 12 and upper composite beam 13 and
Install fast and accurately between " Z " shaped steel 12 and partition wall 14.
It should be noted that the structure of lower node, upper node is in addition to using above-mentioned several preferred frame modes, also
Those skilled in the art can be used it is conceivable that the various structures meeting aforementioned principle, all do not affect the utility model technology
The realization of scheme.In addition, the emphasis of lower node, the quantity of upper node and the concern of position not the utility model, art technology
Personnel can be adjusted flexibly according to common knowledge and arrange.
Preferably, lower node 20 and upper node 30 can be arranged at the dark beam of level 15 of partition wall 14 inner frame and vertical sleeper
The point of intersection of 16.When Buried pipe in vertical sleeper 16, in order to avoid pipeline conflicts with installing node location, lower node 20 He
Upper node 30 can be arranged on the near intersections of the dark beam of level 15 and vertical sleeper 16.Installation node installation position of the present utility model
Put flexibly, the flexible arrangement of partition wall 14 can be coordinated.
Additionally, be also provided with on partition wall 14 for inverted " L " shaped steel 9 and the bolted interior silk braid of " Z " shaped steel 12
Cylinder 7, and it is provided with the inside depression fitted with inverted " L " shaped steel 9 and " Z " shaped steel 12 in internal thread sleeve 7 position.The utility model
Installation node installation finish after, will cave in floating with cement mortar or putty, more smooth U.S. of profile of junction can be made
See.
Further, prefabricated assembled inside casing light partition wall of the present utility model can use following installation steps:
1. the rest 5 of lower node 20 is connected to lower frame to set a roof beam in place the 4th, on 8;
2. set a roof beam in place at lower frame and the 4th, lay the prefabricated panel of floor 19 on 8;
3. partition wall 14 is connected by rest 5 and lower frame the 4th, 8 bolts of setting a roof beam in place;
4. the 9th, partition wall 14 by the shaped steel of upper node 30 12 is set a roof beam in place with upper ledge and the 10th, 13 to be connected;
5. water the cast-in-place part of build floor 19;
6. set a roof beam in place at partition wall 14 and upper ledge and the 10th, fill out in the gap 21 between the gap 18 between 13 and partition wall 14 and floor 19
Fill flexible material, and with cement mortar or putty by floating for the depression of partition wall metope.
To sum up, the utility model has the advantages that
1. the installation node for assembled inside casing light partition wall of the present utility model can facilitate inside casing light partition wall quick,
Install exactly.Without site operation weld seam during installation partition wall, wet trade workload is little, and installation cost is low, and installation accuracy is high.
2. the installation node for assembled inside casing light partition wall of the present utility model is applicable to partition wall inner frame material and is
The situation of concrete, steel or aluminium alloy.
3. being not necessarily to after pouring when installing node connector for assembled inside casing light partition wall of the present utility model
Slotting on beams of concrete or floor, not destroying original structure, easy construction is reasonable.
4. the installation node for assembled inside casing light partition wall of the present utility model and light partition wall all can be real in factory
Existing prefabricated, convenient transportation, meet the requirement of building industrialization.
5. the installation node for assembled inside casing light partition wall of the present utility model is connected reliably with inside casing light partition wall,
Mode of transfer force is reasonable.Compared to conventional node, the installation node for assembled inside casing light partition wall of the present utility model can hold
By bigger metope accidental load, and allow body of wall that sliding in a certain degree of face occurs, inside casing light partition wall can be made little
Do not ftracture under shake effect, do not damage.
6. the installation node mounting locations for assembled inside casing light partition wall of the present utility model is flexible, can coordinate lightweight
The flexible arrangement of partition wall.
7. the installation node for assembled inside casing light partition wall of the present utility model can make outside light partition wall junction
Shape is more smooth attractive in appearance.
The above is preferred embodiment of the present utility model, it is noted that for the ordinary skill of the art
For personnel, on the premise of without departing from principle described in the utility model, can also make some improvements and modifications, these improve
Also should be regarded as protection domain of the present utility model with retouching.
Claims (10)
1. the installation node for assembled inside casing light partition wall, it is characterised in that include lower node and upper node, its
In:
Described lower node include lower frame set a roof beam in place and be arranged at lower frame set a roof beam in place on rest, described rest includes gripper shoe, is positioned at institute
Stating the flat board above gripper shoe and being positioned at the base plate below described gripper shoe, described base plate is set a roof beam in place with lower frame and is connected, described flat board
On be provided with the first bolt hole, described flat board bolt connects the bottom of partition wall;
Described upper node include upper ledge set a roof beam in place and be arranged at upper ledge set a roof beam in place on shaped steel, the upper end of described shaped steel connects described upper ledge
Setting a roof beam in place, lower end is provided with the second bolt hole, and described shaped steel bolt connects the top of partition wall.
2. the installation node for assembled inside casing light partition wall according to claim 1, it is characterised in that the end of partition wall
Portion is provided with the groove mating with described rest, and in described groove, the position corresponding with described first bolt hole is provided with internal thread
Sleeve.
3. the installation node for assembled inside casing light partition wall according to claim 2, it is characterised in that described support
Plate is three pieces, takes the shape of the letter U and is arranged in the lower section of described flat board, and the opening of described U-shaped is towards a side wall of partition wall.
4. the installation node for assembled inside casing light partition wall according to claim 3, it is characterised in that described first
Bolt hole is the slotted hole being parallel to partition wall metope, and described second bolt hole is vertical direction slotted hole.
5. the installation node for assembled inside casing light partition wall according to claim 4, it is characterised in that described partition wall
Upper surface and the lower limb set a roof beam in place of upper ledge between leave gap, leave gap, institute between described flat board and the upper surface of floor
Equal filling flexible material in stating gap and gap.
6. the installation node for assembled inside casing light partition wall according to arbitrary in claim 1 to 5, its feature exists
Setting a roof beam in place as lower girder steel in, described lower frame, described upper ledge is set a roof beam in place as upper girder steel, and the bottom of described gripper shoe is located in floor, and
And the top of described gripper shoe and lower girder steel lay respectively at the both sides of floor, described base plate uses bolt with the top flange of lower girder steel
Connecting, the upper end of described shaped steel is with bolts with the lower flange of upper girder steel.
7. the installation node for assembled inside casing light partition wall according to claim 6, it is characterised in that described shaped steel
For inverted " L " shaped steel, the horizontal component of described inverted " L " shaped steel is with bolts with upper girder steel, and described second bolt hole is arranged at
The vertical section of described inverted " L " shaped steel.
8. the installation node for assembled inside casing light partition wall according to arbitrary in claim 1 to 5, its feature exists
Setting a roof beam in place as lower composite beam in, described lower frame, described upper ledge is set a roof beam in place as upper composite beam, and described lower composite beam includes that lower composite beam is prefabricated
Part and the cast-in-place part of lower composite beam, described upper composite beam includes composite beam pre-erection and the cast-in-place part of upper composite beam, institute
The bottom stating gripper shoe is located in the cast-in-place part of lower composite beam and floor, and the top of described gripper shoe is positioned at described lower composite beam
The upside of cast-in-place part, described base plate is with bolts with lower composite beam pre-erection, the upper end of described shaped steel and upper overlapping
Beam prefabricated part is with bolts.
9. the installation node for assembled inside casing light partition wall according to claim 8, it is characterised in that described shaped steel
For " Z " shaped steel, the upper end of described " Z " shaped steel is with bolts with upper composite beam, and described second bolt hole is arranged at described " Z "
The lower end of shaped steel.
10. the installation node for assembled inside casing light partition wall according to claim 1, it is characterised in that partition wall
Inside casing is provided with the dark beam of level and vertical sleeper, and described lower node and upper node are arranged at the dark beam of described level and vertical sleeper
Point of intersection.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620459836.2U CN205677114U (en) | 2016-05-19 | 2016-05-19 | Installation node for assembled inside casing light partition wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620459836.2U CN205677114U (en) | 2016-05-19 | 2016-05-19 | Installation node for assembled inside casing light partition wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205677114U true CN205677114U (en) | 2016-11-09 |
Family
ID=57436025
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620459836.2U Active CN205677114U (en) | 2016-05-19 | 2016-05-19 | Installation node for assembled inside casing light partition wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205677114U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106703257A (en) * | 2017-01-20 | 2017-05-24 | 广州赫来斯装饰材料有限公司 | Partition wall supporting device |
CN110777934A (en) * | 2019-10-31 | 2020-02-11 | 北京天邦巨成科技有限公司 | Supporting mechanism of crossbeam for building |
CN114981508A (en) * | 2020-03-19 | 2022-08-30 | 吉野石膏株式会社 | Connecting structure of partition wall and floor slab and construction method thereof |
-
2016
- 2016-05-19 CN CN201620459836.2U patent/CN205677114U/en active Active
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106703257A (en) * | 2017-01-20 | 2017-05-24 | 广州赫来斯装饰材料有限公司 | Partition wall supporting device |
CN106703257B (en) * | 2017-01-20 | 2018-11-06 | 广州赫来斯装配式建材科技有限公司 | A kind of partition wall support device |
CN110777934A (en) * | 2019-10-31 | 2020-02-11 | 北京天邦巨成科技有限公司 | Supporting mechanism of crossbeam for building |
CN110777934B (en) * | 2019-10-31 | 2020-07-28 | 北京天邦巨成科技有限公司 | Supporting mechanism of crossbeam for building |
CN114981508A (en) * | 2020-03-19 | 2022-08-30 | 吉野石膏株式会社 | Connecting structure of partition wall and floor slab and construction method thereof |
CN114981508B (en) * | 2020-03-19 | 2024-03-08 | 吉野石膏株式会社 | Connection structure of partition wall and floor slab and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101603336B (en) | Precast concrete short-pier shear wall with infilling wall panel and connecting method thereof | |
CN203834739U (en) | End steel board connection, positioning and assembly type shear wall structure | |
CN101608480B (en) | Manufacturing method of precast concrete short-limb shear wall provided with door windows | |
CN104179278A (en) | Hidden two-in-one dry type connection joint for prefabricated externally-hung wallboards | |
CN106049707A (en) | Prefabricated wall body, prefabricated house building and construction method | |
CN109403545B (en) | High-assembly-rate steel pipe concrete frame structure system and connection method | |
CN205677114U (en) | Installation node for assembled inside casing light partition wall | |
CN105220792A (en) | A kind of prefabricated concealed bracings energy-consuming shear wall and assemble method thereof | |
CN204112525U (en) | Band perps precast shear wall structure in strong concrete precast frame | |
CN111236416A (en) | Prefabricated reinforced concrete structure house and installation method thereof | |
CN205875472U (en) | A concrete inside casing partition wall installation node for steel frame | |
CN110748076B (en) | Prestressed steel pipe truss externally-hung wallboard and wall body manufactured and installed by using same | |
CN206707020U (en) | A kind of assembling type outer wall beam dry type connecting node | |
CN206189456U (en) | Three cabin piping lanes | |
CN206299015U (en) | Assembled composite floor | |
CN205444565U (en) | Wallboard connected node | |
CN212376009U (en) | Prefabricated assembled reinforced concrete structure house | |
CN213741807U (en) | Heavy stone curtain wall structure installed in pulling and hanging combination manner | |
CN205444570U (en) | Wallboard connected node | |
CN205742627U (en) | Node installed by inside casing light partition wall for concrete frame | |
CN103498512B (en) | A kind of assembled architecture wall beam stablizes syndeton | |
CN208202227U (en) | A kind of precast concrete composite beam composite inner wall | |
CN207905160U (en) | A kind of bindiny mechanism at prefabricated buildings corner | |
CN205894350U (en) | Prefabricated formula wall connection structure and utilize this connection structure's prefabricated formula housing construction | |
CN205921343U (en) | Cable pit cell cube and cable pit |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |