CN206091288U - Concrete post -cast strip is propped up and is established device - Google Patents
Concrete post -cast strip is propped up and is established device Download PDFInfo
- Publication number
- CN206091288U CN206091288U CN201621140588.1U CN201621140588U CN206091288U CN 206091288 U CN206091288 U CN 206091288U CN 201621140588 U CN201621140588 U CN 201621140588U CN 206091288 U CN206091288 U CN 206091288U
- Authority
- CN
- China
- Prior art keywords
- concrete body
- cast strip
- concrete
- concrete structure
- post
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model discloses a concrete post -cast strip is propped up and is established device. Concrete post -cast strip is propped up and is established device is including fixing the steel sheet net at the concrete structure body and the 2nd concrete structure end of body respectively, form post -cast strip casting area between the concrete structure body and the 2nd concrete structure body, be equipped with many ejector pins between the tip of the concrete structure body and the tip of the 2nd concrete structure body, the tight top of one end of every ejector pin is in the tip department that a concrete structure personally experienced sth. Part of the body, and the tight top of the other end of this ejector pin is in the tip department of the 2nd concrete structure body, the tip of the concrete structure body and the equal pre -buried at least waterstop that has of the tip of the 2nd concrete structure body, the at least part of this waterstop stretches into post -cast strip casting area, link to each other through an at least pull rod is fixed between two adjacent ejector pins. The utility model discloses the size of having guaranteed waterstop position and concrete post -cast strip is accurate, and bulging die, indeformable not.
Description
Technical field
The utility model is related to a kind of late poured band and installs device, belongs to installing for architectural engineering late poured band
Apparatus field.
Background technology
When high-rise building design has annex, due to the load and stiffness difference of main building and annex it is larger, it will usually cause base
Plinth internal force and Foundation pressure are changed greatly, and excessive differential settlement occurs so as to cause basis.This relative settlement will cause
Larger shearing and moment of flexure, are likely to result under certain condition the even more big destruction of the cracking leak of base plate.
In order to solve the problems, such as settlement difference, movement joint or pouring after settlement are set generally between main building and annex.Typically
For, post-cast strip is referred in cast-in-place integral reinforced concrete structure, the provisional band shape seam only retained in construction period, is risen
To the effect of digestion sedimentation contraction distortion, according to requirement of engineering, after retaining certain hour, then become company with concreting is closely knit
Continue overall structure.
First, the setting of post-cast strip will increase construction workload, and higher requirement is it is also proposed to construction technology.Due to rear
Pour belt construction and be related to secondary operation, not only actually increase the complexity of construction technology, and influence whether to construct into
Degree, increase construction cost expense.
Secondly, with the fast development of national economy, building site an inch of land is an inch of gold, skyscraper is more and more more, and high level is built
During building foundation pit construction, in order to avoid Sand phenomenon during excavation of foundation pit, precipitation will be carried out, but thus be caused peripherally
Lower water level reduces causing adjacent building cracking, subsidence phenomenon to happen occasionally, and stops precipitation in advance and drop to a great extent
The probability that low above-mentioned accident occurs.
The problems such as deforming to solve the relative settlement between main structure body and podium, structure both shrinks deformation and temperature stress,
The mode of indwelling post-cast strip is used widely in architectural engineering.
At present, the device that installs of conventional architectural engineering late poured band mainly has plank sheathing formwork erection device, general
Logical expanded metal lath installs two kinds of device, and both modes deposit respective technological deficiency:
1)Plank sheathing installs device, is installed using plank, flitch steel pipe, inconvenient operation, high material consumption, and precision owes standard
Really, work consuming is time-consuming during form removal.
2)It is to install absolute altitude, position with reinforcing bar, expanded metal lath, steel pipe to be difficult to control to that ordinary steel expanded metals installs device, is especially existed
Mass defect is easily caused with post-cast strip steel plate water-stopping strip junction.
Chinese patent application CN201510032618.0 discloses a kind of post-cast strip exterior wall closure knot with elastic waterstop bar
Structure.It includes outer wall of basement, post-cast strip, wall outer side face, prefabricated cover plate;Described outer wall of basement, post-cast strip outside set
There is prefabricated cover plate, between outer wall of basement and prefabricated cover plate rubber fastening band is provided with;Horizontal steel is provided with inside described post-cast strip
Muscle, longitudinal reinforcement;Described preform lid intralamellar part sets cover plate embedded bar;Described outer wall of basement is with prefabricated cover plate by solid
Determine pull bar connection, and wall outer side face is bonding using waterproof mortar with prefabricated cover plate connection end portion.The patent easy construction, work
Low intensity, high working efficiency, and blocking-proof result is notable, impervious waterproof ability is strong.But patent position in construction is still difficult
To control, especially mass defect is still being easily caused with post-cast strip steel plate water-stopping strip junction.
Utility model content
The utility model aims to provide a kind of late poured band and installs device, and this installs device and can ensure that waterstop position
Put and late poured band size accurately, it is and not swollen mould, indeformable.
To achieve these goals, the technical scheme that the utility model is adopted is:
A kind of late poured band installs device, including be separately fixed at the first concrete body and the second concrete knot
The expanded metals in structure body end portion;Post-cast strip casting area is formed between first concrete body and the second concrete body;
It is structurally characterized in that, many tops are provided between the end of first concrete body and the end of the second concrete body
Bar, one end of every push rod is pressed closer in the end of the first concrete body, and the other end of the push rod is pressed closer in the second coagulation
The end of soil structured body;The end of first concrete body and the end of the second concrete body be embedded with to
A few waterstop, the waterstop is extending at least partially into the post-cast strip casting area;By extremely between adjacent two push rods
A few pull bar is fixedly linked.
Thus, expanded metals is fixed by push rod, then is strained and fixed connected two push rods with pull bar, thus, expanded metals, waterstop with
Concrete body pours integral, does not remove, it is ensured that the size of waterstop position and late poured band is accurate.
According to embodiment of the present utility model, further optimization can also be made to the utility model, below for optimization after
The technical scheme of formation:
Region is installed in order to increase, the end of the push rod and first concrete body or the second xoncrete structure
It is connected by bracketing between body.
Preferably, the waterstop is arranged between adjacent two bracketings.Thus, bracketing is clamped only under the pulling force of pull bar
Water band, it is ensured that the size of waterstop position and late poured band is accurate.
Preferably, two are provided between the end of first concrete body and the end of the second concrete body
Push rod.
Preferably, it is fixedly linked by two pull bars between adjacent two push rods.
Push rod length is adjusted for convenience, various sizes of post-cast strip is adapted to, and the push rod is length-adjustable adjustable
Push rod bolt.
Preferably, the pull bar is length-adjustable stay-bolt.
Preferably, the waterstop is steel plate water stopper.
For raising bonding strength, by pouring between first concrete body and the second concrete body
Build and be connected in the post-cast strip of post-cast strip casting area.Thus, expanded metals, waterstop and concrete body pour it is integral,
Do not remove.
By said structure, expanded metals of the present utility model, steel plate water stopper are not removed after installing, with concreting one
Rise.Bracketing is held out against with adjustable ejector rod screw rod and fix expanded metals, prevent casting and compacting of concrete effect from making expanded metals distending.Drawn with stay-bolt
Tight upper and lower two layers of adjustable ejector rod bolt, clamps steel plate water stopper, it is ensured that steel plate water stopper position and late poured band
Size is accurately, not swollen mould, indeformable.
Compared with prior art, the beneficial effects of the utility model are:The utility model guarantee steel plate water stopper position and
The size of post-cast strip accurately, has the advantages that not swollen mould, indeformable, easy to operate, low cost, safe and reliable, effect are good.
Description of the drawings
Fig. 1 is the structure principle chart of the utility model one embodiment.
In figure
1- expanded metals;2- push rods;3- bracketings;4- pull bars;5- waterstops;The concrete bodies of 6- first;The concrete of 7- second
Structure.
Specific embodiment
Below with reference to accompanying drawing and in conjunction with the embodiments describing the utility model in detail.It should be noted that not conflicting
In the case of, the feature in embodiment and embodiment in the utility model can be mutually combined.For sake of convenience, hereinafter such as
Occur " on ", D score, "left", "right" printed words, only represent it is consistent with the upper and lower, left and right direction of accompanying drawing itself, not to structure
Play restriction effect.
A kind of late poured band installs device, as shown in figure 1, including expanded metals 1(Preferably expanded metal lath), push rod 2(It is preferred that
For adjustable ejector rod bolt), bracketing 3, pull bar 4, steel plate water stopper 5.Wherein expanded metals 1 is separately fixed at the first concrete body
6 and the end of the second concrete body 7, pour after being formed between the concrete body 7 of first concrete body 6 and second
Band casting area;Two tops are provided between the end of the end of first concrete body 6 and the second concrete body 7
Bar 2, one end of every push rod 2 is pressed closer in the end of the first concrete body 6 by a bracketing 3, the push rod 2 it is another
End is pressed closer in the end of the second concrete body 7 by another bracketing 3;The end of first concrete body 6
A steel plate water stopper 5 is embedded with the end of the second concrete body 7, the part of the steel plate water stopper 5 is stretched into described
Post-cast strip casting area;It is fixedly linked by two pull bars 4 between adjacent two push rods 2.
The course of work of the present utility model is as follows:First concrete body 6 and the second concrete body 7 are installed first
The expanded metal lath of end lower, then installs one group of adjustable ejector rod bolt and bracketing, and by adjusting push rod bolt bracketing is held out against, and makes
Steel plate water stopper 5 accurately, is finally installed in the expanded metal lath position of the first concrete body 6 and the second concrete body 7, checks
Adjustment position, it is accurately rear fixed.
The expanded metal lath of the first concrete body 6 and the end upper of the second concrete body 7 is installed, is then installed another
Layer adjustable ejector rod bolt and bracketing, by adjusting upper strata push rod bolt bracketing is held out against, and makes top expanded metal lath position accurate;Finally
To be strained and fixed after upper and lower two groups of push rods bolt stay-bolt tightening nuts.
The content that above-described embodiment is illustrated should be understood to that these embodiments are only used for being illustrated more clearly that the utility model,
Rather than scope of the present utility model is limited, after the utility model has been read, those skilled in the art are new to this practicality
The modification of the various equivalent form of values of type each falls within the application claims limited range.
Claims (9)
1. a kind of late poured band installs device, including being separately fixed at the first concrete body(6)With the second concrete
Structure(7)The expanded metals of end(1);First concrete body(6)With the second concrete body(7)Between formed after
Pour band casting area;Characterized in that, first concrete body(6)End and the second concrete body(7)'s
Many push rods are provided between end(2), every push rod(2)One end press closer in the first concrete body(6)End, should
Push rod(2)The other end press closer in the second concrete body(7)End;First concrete body(6)End
Portion and the second concrete body(7)End be embedded with least one waterstop(5), the waterstop(5)It is at least part of
Stretch into the post-cast strip casting area;Adjacent two push rods(2)Between pass through at least one pull bar(4)It is fixedly linked.
2. late poured band according to claim 1 installs device, it is characterised in that the push rod(2)End with
First concrete body(6)Or second concrete body(7)Between pass through bracketing(3)It is connected.
3. late poured band according to claim 2 installs device, it is characterised in that the waterstop(5)It is arranged on
Adjacent two bracketings(3)Between.
4. late poured band according to claim 1 installs device, it is characterised in that first concrete body
(6)End and the second concrete body(7)End between be provided with two push rods(2).
5. late poured band according to claim 1 installs device, it is characterised in that adjacent two push rods(2)Between
By two pull bars(4)It is fixedly linked.
6. the late poured band according to one of claim 1-5 installs device, it is characterised in that the push rod(2)For
Length-adjustable adjustable ejector rod bolt.
7. the late poured band according to one of claim 1-5 installs device, it is characterised in that the pull bar(4)For
Length-adjustable stay-bolt.
8. the late poured band according to one of claim 1-5 installs device, it is characterised in that the waterstop(5)
For steel plate water stopper.
9. the late poured band according to one of claim 1-5 installs device, it is characterised in that first concrete
Structure(6)With the second concrete body(7)Between be connected by being cast in the post-cast strip of post-cast strip casting area.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621140588.1U CN206091288U (en) | 2016-10-20 | 2016-10-20 | Concrete post -cast strip is propped up and is established device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621140588.1U CN206091288U (en) | 2016-10-20 | 2016-10-20 | Concrete post -cast strip is propped up and is established device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206091288U true CN206091288U (en) | 2017-04-12 |
Family
ID=59975858
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621140588.1U Active CN206091288U (en) | 2016-10-20 | 2016-10-20 | Concrete post -cast strip is propped up and is established device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206091288U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111188355A (en) * | 2019-12-31 | 2020-05-22 | 湖北省路桥集团有限公司 | Super-gravity type anchorage shallow-buried foundation and construction method |
CN111593885A (en) * | 2019-02-20 | 2020-08-28 | 广西华业建筑工程有限公司 | Plug-in type composite post-cast strip side mold and construction method |
-
2016
- 2016-10-20 CN CN201621140588.1U patent/CN206091288U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111593885A (en) * | 2019-02-20 | 2020-08-28 | 广西华业建筑工程有限公司 | Plug-in type composite post-cast strip side mold and construction method |
CN111188355A (en) * | 2019-12-31 | 2020-05-22 | 湖北省路桥集团有限公司 | Super-gravity type anchorage shallow-buried foundation and construction method |
CN111188355B (en) * | 2019-12-31 | 2021-08-20 | 湖北省路桥集团有限公司 | Super-gravity type anchorage shallow-buried foundation and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208473116U (en) | A kind of partial precast assembly steel reinforced concrete holes in soffit beam | |
CN102383418A (en) | Anti-seismic prefabricated concrete solid square pile and production method thereof | |
CN206091288U (en) | Concrete post -cast strip is propped up and is established device | |
WO2020244268A1 (en) | Variable cross-section pipe gallery structure suitable for rapid construction and construction method therefor | |
CN205501843U (en) | Consolidate rigid framed arch bridge | |
CN205077525U (en) | Basement waterproof concrete bottom plate post -cast strip is with novel waterstop structure | |
CN104594389A (en) | Post-cast strip external wall plugging structure with elastic water stoppers | |
CN206928323U (en) | A kind of ring muscle fastens assembled pipe gallery | |
CN105442457A (en) | Construction structure and method for extending bridge floor plate bridge filled with fine sand | |
CN112627034A (en) | Synchronous construction method for turning over mold of high pier of bridge | |
CN106836559A (en) | Reinforced concrete wall structure capable of preventing cracking and construction method thereof | |
CN216617534U (en) | Tunnel concrete monolithic pouring support system | |
CN206529881U (en) | The constructing device of cushion cap and ground girder construction | |
CN206957198U (en) | Cast-in-situ template structure at a kind of sandwich exterior wall J-shaped wall of prefabricated concrete structure | |
CN206052565U (en) | A kind of beam-column type bracket | |
CN113605247B (en) | Flange type steel box arch springing consolidation structure and construction method | |
CN211250565U (en) | Pouring die for beam | |
CN210459289U (en) | Variable cross-section pipe gallery structure suitable for rapid construction | |
CN205382505U (en) | Board -like concrete air cooling platform basis of rib is erected in area | |
CN110005429B (en) | Box-type top plate structure of urban tunnel bifurcation | |
CN210439720U (en) | Reinforced structure for increasing cross section of concrete beam side | |
CN210712964U (en) | Bilateral-shaped basement shear wall post-cast strip plugging member | |
CN104908150B (en) | A kind of piping shaft making template and the method based on factorial praluction piping shaft | |
CN210002441U (en) | Box-type top plate structure for large-span urban tunnel | |
CN209854778U (en) | Post-cast strip support-free structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||