WO2020244268A1 - Variable cross-section pipe gallery structure suitable for rapid construction and construction method therefor - Google Patents

Variable cross-section pipe gallery structure suitable for rapid construction and construction method therefor Download PDF

Info

Publication number
WO2020244268A1
WO2020244268A1 PCT/CN2020/078534 CN2020078534W WO2020244268A1 WO 2020244268 A1 WO2020244268 A1 WO 2020244268A1 CN 2020078534 W CN2020078534 W CN 2020078534W WO 2020244268 A1 WO2020244268 A1 WO 2020244268A1
Authority
WO
WIPO (PCT)
Prior art keywords
pipe gallery
construction
mold
side wall
section
Prior art date
Application number
PCT/CN2020/078534
Other languages
French (fr)
Chinese (zh)
Inventor
吴庆雄
陈荣刚
胡善华
杨益伦
陈洪毅
Original Assignee
福州大学
福建高速至信建设管理有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 福州大学, 福建高速至信建设管理有限公司 filed Critical 福州大学
Publication of WO2020244268A1 publication Critical patent/WO2020244268A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/10Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells

Definitions

  • the invention relates to a pipe gallery section structure suitable for rapid construction and a construction method thereof.
  • underground concrete pipe gallery structures such as municipal pipe gallery and underground passage generally adopt the form of integral cast-in-place or segmental prefabrication and on-site splicing.
  • the prefabricated pipe gallery can be quickly prefabricated and shortened the construction period, the length of the section limited by the lifting weight is shorter, resulting in more joints and poor waterproof performance. It is not applicable if the buried line has a height difference and a large corner change.
  • the design concepts and specifications of the relevant prefabricated pipe gallery are not yet fully mature; the pipe gallery is cast as a whole on site, because the structure has good waterproof and seismic performance, can adapt to complex structural cross-sections, and the relevant design specifications, construction techniques and processes are relatively mature and widely used application.
  • the traditional pipe gallery structure makes the cast-in-place formwork support system more complicated, and the installation and removal efficiency of the formwork is low.
  • the traditional cast-in-place construction technology uses manual labor to independently complete the various procedures of the cast-in-place in a small cabin, which seriously reduces the cast-in-place
  • the construction efficiency of the pipe gallery makes the construction process of the pipe gallery slow. Therefore, the relevant research and development of the structure of the pipe gallery and the rapid construction technology are becoming more and more important.
  • the purpose of the present invention is to provide a pipe gallery section structure suitable for rapid construction and its construction method, which can effectively eliminate the stress concentration phenomenon of the pipe gallery under the action of the top, lateral earth pressure and other external loads. It can also fully reduce its own weight, save materials and give full play to the characteristics of structural forces.
  • the technical scheme of the present invention is: a pipe gallery section structure suitable for rapid construction, including a top plate, a side wall and a bottom plate.
  • the top plate adopts a variable cross-section structure with a gradually changing section height.
  • the side walls are arranged on both sides of the top plate. A chamfer is set between the wall and the flat bottom plate, a top mold is set below the top plate to fit the top plate, and a side mold that fits the side wall is set below the top mold, and set between the top mold and the side mold There is a hinged structure.
  • variable-section roof with a gradually changing section height is formed by a circular curve transition at the junction of the side wall and the roof, and then a gradual curve transition to the middle span of the roof.
  • the side mold and the top mold are connected by a hinged structure to form an integral steel inner membrane with no corners, which is fully suitable for rapid construction of the pipe gallery.
  • the bottom plate and the side wall are in rectangular cross-sectional form, and the transition between the side wall and the bottom plate is a straight chamfered part.
  • Another technical solution provided by the present invention is a construction method of a variable cross-section pipe gallery structure suitable for rapid construction, including the pipe gallery cross-sectional structure suitable for rapid construction: (1) Carrying out the pipe gallery floor structure Construction: During the construction process, follow the traditional cast-in-situ pipe gallery construction method to complete site leveling, supporting pile construction, earth excavation and setting of horizontal bracing, pile foundation inspection, foundation pit acceptance, cushion laying, waterproof treatment, pipe gallery floor Structural pouring and maintenance; (2) Side wall steel reinforcement installation: Before installation, during the installation of the side wall steel reinforcement, the steel reinforcement is completed on the side wall reinforcement membrane frame in the steel processing shed and transported to the construction site.
  • the present invention has the beneficial effects: it can effectively eliminate the stress concentration phenomenon that occurs under the action of the top, lateral earth pressure and other external loads of the pipe gallery, and can also fully reduce its own weight, save materials and exert structural stress. Power characteristics.
  • Figure 1 is a schematic structural diagram of an embodiment of the present invention
  • Figure 2 is a schematic diagram of a template support according to an embodiment of the present invention.
  • a pipe gallery section structure suitable for rapid construction includes a top plate 300, a side wall 200 and a bottom plate 100.
  • the top plate 300 adopts a variable cross-section structure with a gradually changing section height, and the side wall 200 is provided On both sides of the top plate 300, a chamfered portion 400 is provided between the side wall 200 and the flat bottom plate 100.
  • a top mold 800 is provided below the top plate 300 to fit the top plate 300, and below the top mold 800 is provided a side wall 200
  • the laminated side mold 600 has a hinge structure 700 between the top mold 800 and the side mold 600.
  • the junction of the inner edge of the side wall 200 and the top plate 300 adopts a circular curve transition structure, which changes the traditional straight line chamfer transition form, which can effectively eliminate the pipe gallery from the top, lateral earth pressure and other external loads.
  • the end section height of the roof 300 structure is relatively large, and the mid-span section height is relatively small.
  • the negative bending moment at both ends is relatively large, and the positive bending moment in the middle is relatively large.
  • the matching of the small" force form can fully reduce its own weight, save materials and give full play to the structural force characteristics.
  • the side mold 600 and the top mold 800 are hingedly connected by the hinged structure 700 to form an integral steel inner film without bends, which is fully suitable for the rapid construction of the pipe gallery.
  • variable cross-section top plate 300 with a gradually changing section height is formed by a circular curve transition at the junction of the side wall 200 and the top plate 300, and then a gradual curve transition to the mid-span of the top plate 300.
  • variable cross-section top plate 300 are hingedly connected by a round curve corner mold to form an integral steel inner membrane without bends, which is fully suitable for rapid construction of the pipe gallery.
  • the bottom plate 100 and the side wall 200 are both rectangular in cross-section, and the side wall 200 and the bottom plate 100 are transitioned by a straight chamfer 400.
  • the gradual curve segment can be smoothly connected with the circular curve segment, and meets the force requirements of the top plate 300 structure.
  • the gradual curve can be a circular curve or a quadratic parabola.
  • a construction method of variable cross-section pipe gallery structure suitable for rapid construction including the described pipe gallery section structure suitable for rapid construction: (1) Construction of the pipe gallery bottom plate 100 structure: in the construction process, follow the traditional current Construction method of pouring pipe gallery: complete site leveling, supporting pile construction, earth excavation and setting of cross bracing, pile foundation inspection, foundation pit acceptance, cushion laying, waterproof treatment, pouring and maintenance of pipe gallery bottom 100 structure; (2) side Wall 200 steel reinforcement installation: Before installation, during the installation process of the side wall 200 steel reinforcement, the steel reinforcement is completed on the side wall 200 reinforcement membrane frame in the steel processing shed and transported to the construction site.
  • the steel frame is installed and positioned; (3)
  • the template 500 is installed: In the process of installing the template 500, first lay a self-propelled track on the bottom plate 100, and then the trolley moves into position and locks by itself, because the side wall 200 and the top plate 300 are smooth Curve transition, so the side mold and the top mold can be connected by the hinge structure 700 to form an integral steel inner film without bends.
  • the top mold is raised to the control elevation by the trolley column jack and fine-tuned to the side wall 200.
  • the inner position is locked by adjusting joints.
  • the side wall 200 formwork 500 is pushed by a lateral jack to rotate around the top hinge point to the vertical position of the side wall 200 and locked by the bottom brace.
  • the lock bolts of the inner and outer formwork 500 are released, the outer formwork 500 is removed, and then the vertical brace at the bottom of the inner formwork 500 is released, and the side jacks retract synchronously so that the side formwork 500 rotates around the top hinge point in the cabin to demold, and finally the trolley column
  • the vertical jack retracts so that the top mold is separated from the top plate 300, and the trolley and the overall inner membrane system move to the next construction section by themselves.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Oil, Petroleum & Natural Gas (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Sewage (AREA)

Abstract

The present invention relates to a pipe gallery cross-section structure suitable for rapid construction, comprising a top plate, side walls, and a bottom plate. A variable cross-section structure is used for the top plate of which the cross-section height changes gradually. The side walls are provided on two sides of the top plate. A chamfered portion is provided between the side wall and the flat bottom plate. A top mold attached to the top plate is provided below the top plate in the pipe gallery construction. A side mold attached to the side wall is provided below the top mold. A hinge structure is provided between the top mold and the side mold. The present invention also relates to a construction method for the pipe gallery cross-section structure suitable for rapid construction. According to the present invention, the structure of the variable cross-section top plate of which the cross-section height changes gradually can effectively eliminate the stress concentration phenomenon of the pipe gallery under the action of the top and lateral earth pressure and other external loads, and can also fully reduce the weight thereof, save materials, and exert the characteristics of structural force. Accordingly, a curved top mold matching the structure of the variable cross-section top plate is connected to the side mold by means of the hinge structure to form an integral steel inner membrane without bending angles, which is fully suitable for rapid construction of the pipe gallery.

Description

适用于快速施工的变截面管廊结构及其施工方法Variable section pipe gallery structure suitable for rapid construction and its construction method 技术领域Technical field
本发明涉及一种适用于快速施工的管廊截面结构及其施工方法。The invention relates to a pipe gallery section structure suitable for rapid construction and a construction method thereof.
背景技术Background technique
现代社会发展进步越来越快,城市市政基础设施建设越来越齐全,城市地下空间资源越来越狭小,空间资源愈发宝贵。在我国大部分城市,各种管线基本都是采用传统的直埋敷设方式,直埋敷设管线施工便捷,但是使用年限短,且各种不同类型的管线敷设杂乱无章,占据了大量地下空间,经常与城市的基本建设工程交叉,而出现敷设管线被损毁的现象。直埋敷设管线一旦出现损坏,需要开槽破路对管线进行检查修复,不仅会造成交通的拥堵,给市民的正常出行带来不便,也污染了周边环境,影响城市市容。为解决传统直埋敷设管线的弊端,充分合理地利用地下空间资源,近年来地下管廊工程建设在国内得到大力发展。The development and progress of modern society is faster and faster, the construction of urban municipal infrastructure is more and more complete, the urban underground space resources are getting narrower and smaller, and the space resources are becoming more and more precious. In most cities in my country, all kinds of pipelines are basically laid by traditional direct buried methods. Directly buried pipelines are convenient for construction, but their service life is short, and the laying of various types of pipelines is disorderly, occupying a lot of underground space. The city’s capital construction projects crossed, and the laying of pipelines was damaged. Once directly buried pipelines are damaged, they need to be grooved and broken for inspection and repair. This will not only cause traffic jams, bring inconvenience to citizens' normal travel, but also pollute the surrounding environment and affect the city's appearance. In order to solve the shortcomings of traditional directly buried pipelines and make full and reasonable use of underground space resources, in recent years, the construction of underground pipe corridors has been vigorously developed in China.
目前,市政管廊、地下通道等地下混凝土管廊结构一般采用整体现浇或节段预制、现场拼接的形式。其中预制管廊虽然能快速预制,缩短工期,但受吊装重量所限节段长度较短,导致接缝较多、防水性能较差,埋设线路若高差、转角变化过大也不适用,且相关预制管廊设计理念和规范尚且不完全成熟;管廊现场整体浇筑,因结构防水、抗震性能良好,能适应复杂的结构断面形式,且相关设计规范、施工技术和工艺较为成熟而被广泛的应用。At present, underground concrete pipe gallery structures such as municipal pipe gallery and underground passage generally adopt the form of integral cast-in-place or segmental prefabrication and on-site splicing. Although the prefabricated pipe gallery can be quickly prefabricated and shortened the construction period, the length of the section limited by the lifting weight is shorter, resulting in more joints and poor waterproof performance. It is not applicable if the buried line has a height difference and a large corner change. The design concepts and specifications of the relevant prefabricated pipe gallery are not yet fully mature; the pipe gallery is cast as a whole on site, because the structure has good waterproof and seismic performance, can adapt to complex structural cross-sections, and the relevant design specifications, construction techniques and processes are relatively mature and widely used application.
技术问题technical problem
但是传统的管廊结构形式使得现浇模板支撑系统较为复杂,安装、拆卸模板效率低,另外传统的现浇施工技术采用人工在狭小的舱室内独立完成现浇各道工序,严重降低了现浇管廊的施工效率,致使管廊的建设进程缓慢,因此对管廊结构形式、快速施工技术的相关研发显得愈发重要。However, the traditional pipe gallery structure makes the cast-in-place formwork support system more complicated, and the installation and removal efficiency of the formwork is low. In addition, the traditional cast-in-place construction technology uses manual labor to independently complete the various procedures of the cast-in-place in a small cabin, which seriously reduces the cast-in-place The construction efficiency of the pipe gallery makes the construction process of the pipe gallery slow. Therefore, the relevant research and development of the structure of the pipe gallery and the rapid construction technology are becoming more and more important.
技术解决方案Technical solutions
有鉴于此,本发明的目的在于提供了一种适用于快速施工的管廊截面结构及其施工方法,能有效消除管廊在顶部、侧向土压力和其他外荷载作用下发生的应力集中现象,还能充分减轻自重、节省材料并发挥结构受力特点。In view of this, the purpose of the present invention is to provide a pipe gallery section structure suitable for rapid construction and its construction method, which can effectively eliminate the stress concentration phenomenon of the pipe gallery under the action of the top, lateral earth pressure and other external loads. It can also fully reduce its own weight, save materials and give full play to the characteristics of structural forces.
本发明的技术方案是:一种适用于快速施工的管廊截面结构,包括顶板、侧墙和底板,所述顶板采用截面高度逐渐变化的变截面结构形式,侧墙设置于顶板两侧,侧墙与平直底板之间设置有倒角部,在顶板下方设置有与顶板贴合的顶模,在顶模下方设置有与侧墙贴合的侧模,在顶模和侧模之间设置有铰接结构。The technical scheme of the present invention is: a pipe gallery section structure suitable for rapid construction, including a top plate, a side wall and a bottom plate. The top plate adopts a variable cross-section structure with a gradually changing section height. The side walls are arranged on both sides of the top plate. A chamfer is set between the wall and the flat bottom plate, a top mold is set below the top plate to fit the top plate, and a side mold that fits the side wall is set below the top mold, and set between the top mold and the side mold There is a hinged structure.
进一步的,截面高度逐渐变化的变截面顶板,由侧墙与顶板交界处先经圆曲线过渡,然后以渐变曲线过渡至顶板跨中处所形成。Further, a variable-section roof with a gradually changing section height is formed by a circular curve transition at the junction of the side wall and the roof, and then a gradual curve transition to the middle span of the roof.
进一步的,所述侧模和顶模,通过铰接结构相连,形成无折角的整体钢内膜,充分适用于管廊的快速施工。Further, the side mold and the top mold are connected by a hinged structure to form an integral steel inner membrane with no corners, which is fully suitable for rapid construction of the pipe gallery.
进一步的,所述底板、侧墙均为矩形等截面形式,侧墙与底板间以直线倒角部进行过渡。Further, the bottom plate and the side wall are in rectangular cross-sectional form, and the transition between the side wall and the bottom plate is a straight chamfered part.
本发明提供的另一种技术方案是,一种适用于快速施工的变截面管廊结构的施工方法,包括所述的适用于快速施工的管廊截面结构:(1)对管廊底板结构进行施工:在施工过程中,按照传统现浇管廊施工方法完成场地平整、支护桩施工、土方开挖并设置横撑、桩基检测、基坑验收、垫层铺设、防水处理、管廊底板结构浇筑和养护;(2)侧墙钢筋安装:在安装之前,先在侧墙钢筋安装安装的过程中,在钢筋加工棚内的侧墙钢筋胎膜架上完成钢筋制作并运送至施工现场,借助吊车对侧墙钢筋骨架进行安装定位;(3)进行模板安装:在模板安装的过程中,首先在底板铺设自行轨道,然后台车自行移动就位并锁定,因侧墙与顶板间为圆滑曲线过渡,所以可将侧模与顶模间通过铰接结构相连形成无折角的整体钢内膜,立模过程中通过台车立柱千斤顶将顶模起升至控制标高并横向微调至侧墙内侧位置加调整节锁定,其次,侧墙模板利用侧向千斤顶外推使其绕顶部铰接点转动至侧墙竖向位置并通过底部撑杆锁定,再次,安装顶板钢筋及外模板并与内模顶、底部锁定;(4)混凝土浇筑与养护:待钢筋骨架及模板支设检验合格后浇筑混凝土并振捣密实,浇筑完成待混凝土初凝后进行整体覆盖并输送适宜温度的蒸汽或热水进行养护;(5)内外模板的拆除:待混凝土达到设计或相关规范规定拆模强度开始拆模,首先解除管廊外模板顶部对拉螺杆,同时将侧墙底部内外模板锁定螺栓解除,移除外模板,然后解除内模板底部竖向撑杆,侧向千斤顶同步回缩使得侧模板绕顶部铰接点向舱内转动而脱模,最后台车立柱竖向千斤顶回缩使得顶模与顶板脱开,台车及整体内膜系统自行移动至下一施工节段。Another technical solution provided by the present invention is a construction method of a variable cross-section pipe gallery structure suitable for rapid construction, including the pipe gallery cross-sectional structure suitable for rapid construction: (1) Carrying out the pipe gallery floor structure Construction: During the construction process, follow the traditional cast-in-situ pipe gallery construction method to complete site leveling, supporting pile construction, earth excavation and setting of horizontal bracing, pile foundation inspection, foundation pit acceptance, cushion laying, waterproof treatment, pipe gallery floor Structural pouring and maintenance; (2) Side wall steel reinforcement installation: Before installation, during the installation of the side wall steel reinforcement, the steel reinforcement is completed on the side wall reinforcement membrane frame in the steel processing shed and transported to the construction site. Use a crane to install and position the side wall reinforcement frame; (3) formwork installation: in the formwork installation process, first lay a self-propelled track on the bottom plate, and then the trolley moves into position and locks by itself, because the side wall and the top plate are smooth Curve transition, so the side mold and the top mold can be connected by a hinge structure to form an integral steel inner film without bends. During the mold erection process, the top mold is raised to the control elevation by the trolley column jack and fine-tuned to the inner side of the side wall. Add adjustment joints to lock. Secondly, the side wall formwork uses a lateral jack to push it to the vertical position of the side wall around the top hinge point and lock it by the bottom brace. Once again, install the top plate steel bar and the outer formwork and connect with the top of the inner formwork. Bottom locking; (4) Concrete pouring and curing: After the steel frame and formwork support are qualified, the concrete is poured and vibrated to compact it. After the initial setting of the concrete, the overall cover is completed and steam or hot water of suitable temperature is delivered for curing; (5) Removal of the internal and external formwork: When the concrete reaches the design or relevant specifications, the formwork will be demolished. First, release the top of the outer formwork of the pipe gallery, and release the locking bolts of the inner and outer formwork at the bottom of the side wall, and remove the outer formwork. Then the vertical support bar at the bottom of the inner formwork is lifted, and the lateral jacks retract synchronously to make the side formwork rotate around the top hinge point in the cabin to demold. Finally, the vertical jack of the trolley column retracts to make the top mold separate from the top plate, and the trolley And the whole inner membrane system moves to the next construction section by itself.
有益效果Beneficial effect
与现有技术相比,本发明的有益效果是:能有效消除管廊在顶部、侧向土压力和其他外荷载作用下发生的应力集中现象,还能充分减轻自重、节省材料并发挥结构受力特点。Compared with the prior art, the present invention has the beneficial effects: it can effectively eliminate the stress concentration phenomenon that occurs under the action of the top, lateral earth pressure and other external loads of the pipe gallery, and can also fully reduce its own weight, save materials and exert structural stress. Power characteristics.
附图说明Description of the drawings
图1为本发明实施例的结构示意图;Figure 1 is a schematic structural diagram of an embodiment of the present invention;
图2为本发明实施例的模板支撑示意图;Figure 2 is a schematic diagram of a template support according to an embodiment of the present invention;
图中:100-底板;200-侧墙;300-顶板; 400-倒角部;500-模板;600-侧模;700-铰接结构;800-顶模。In the picture: 100-bottom plate; 200-side wall; 300-top plate; 400-chamfer; 500-form plate; 600-side mold; 700-hinge structure; 800-top mold.
本发明的最佳实施方式The best mode of the invention
如图1~2所示,一种适用于快速施工的管廊截面结构,包括顶板300、侧墙200和底板100,所述顶板300采用截面高度逐渐变化的变截面结构形式,侧墙200设置于顶板300两侧,侧墙200与平直底板100之间设置有倒角部400,在顶板300下方设置有与顶板300贴合的顶模800,在顶模800下方设置有与侧墙200贴合的侧模600,在顶模800和侧模600之间设置有铰接结构700。所述的侧墙200与顶板300的内缘交界处采用圆曲线过渡的结构形式改变了传统的直线倒角过渡形式,可有效消除管廊在顶部、侧向土压力和其他外荷载作用下发生的应力集中现象,所述的变截面结构,顶板300结构的端部截面高度较大,跨中截面高度相对较小,与管廊结构“两端负弯矩较大,中间正弯矩相对较小”的受力形式匹配,能充分减轻自重、节省材料并发挥结构受力特点。通过铰接结构700将侧模600和顶模800铰接相连,形成无折角的整体钢内膜,充分适用于管廊的快速施工。As shown in Figures 1~2, a pipe gallery section structure suitable for rapid construction includes a top plate 300, a side wall 200 and a bottom plate 100. The top plate 300 adopts a variable cross-section structure with a gradually changing section height, and the side wall 200 is provided On both sides of the top plate 300, a chamfered portion 400 is provided between the side wall 200 and the flat bottom plate 100. A top mold 800 is provided below the top plate 300 to fit the top plate 300, and below the top mold 800 is provided a side wall 200 The laminated side mold 600 has a hinge structure 700 between the top mold 800 and the side mold 600. The junction of the inner edge of the side wall 200 and the top plate 300 adopts a circular curve transition structure, which changes the traditional straight line chamfer transition form, which can effectively eliminate the pipe gallery from the top, lateral earth pressure and other external loads. In the variable section structure, the end section height of the roof 300 structure is relatively large, and the mid-span section height is relatively small. Compared with the pipe gallery structure, the negative bending moment at both ends is relatively large, and the positive bending moment in the middle is relatively large. The matching of the small" force form can fully reduce its own weight, save materials and give full play to the structural force characteristics. The side mold 600 and the top mold 800 are hingedly connected by the hinged structure 700 to form an integral steel inner film without bends, which is fully suitable for the rapid construction of the pipe gallery.
本实施例中,截面高度逐渐变化的变截面顶板300,由侧墙200与顶板300交界处先经圆曲线过渡,然后以渐变曲线过渡至顶板300跨中处所形成。In this embodiment, the variable cross-section top plate 300 with a gradually changing section height is formed by a circular curve transition at the junction of the side wall 200 and the top plate 300, and then a gradual curve transition to the mid-span of the top plate 300.
本实施例中,变截面的顶板300现浇施工所对应的侧模和顶模,通过圆曲线角模铰接相连,形成无折角的整体钢内膜,充分适用于管廊的快速施工。In this embodiment, the side mold and the top mold corresponding to the cast-in-place construction of the variable cross-section top plate 300 are hingedly connected by a round curve corner mold to form an integral steel inner membrane without bends, which is fully suitable for rapid construction of the pipe gallery.
本实施例中,所述底板100、侧墙200均为矩形等截面形式,侧墙200与底板100间以直线倒角部400进行过渡。渐变线曲线段能与圆曲线段平顺相接,而且满足顶板300结构的受力要求,所述的渐变曲线可为圆曲线或二次抛物线等。In this embodiment, the bottom plate 100 and the side wall 200 are both rectangular in cross-section, and the side wall 200 and the bottom plate 100 are transitioned by a straight chamfer 400. The gradual curve segment can be smoothly connected with the circular curve segment, and meets the force requirements of the top plate 300 structure. The gradual curve can be a circular curve or a quadratic parabola.
一种适用于快速施工的变截面管廊结构的施工方法,包括所述的适用于快速施工的管廊截面结构:(1)对管廊底板100结构进行施工:在施工过程中,按照传统现浇管廊施工方法完成场地平整、支护桩施工、土方开挖并设置横撑、桩基检测、基坑验收、垫层铺设、防水处理、管廊底板100结构浇筑和养护;(2)侧墙200钢筋安装:在安装之前,先在侧墙200钢筋安装安装的过程中,在钢筋加工棚内的侧墙200钢筋胎膜架上完成钢筋制作并运送至施工现场,借助吊车对侧墙200钢筋骨架进行安装定位;(3)进行模板500安装:在模板500安装的过程中,首先在底板100铺设自行轨道,然后台车自行移动就位并锁定,因侧墙200与顶板300间为圆滑曲线过渡,所以可将侧模与顶模间通过铰接结构700相连形成无折角的整体钢内膜,立模过程中通过台车立柱千斤顶将顶模起升至控制标高并横向微调至侧墙200内侧位置加调整节锁定,其次,侧墙200模板500利用侧向千斤顶外推使其绕顶部铰接点转动至侧墙200竖向位置并通过底部撑杆锁定,再次,安装顶板300钢筋及外模板500并与内模顶、底部锁定;(4)混凝土浇筑与养护:待钢筋骨架及模板500支设检验合格后浇筑混凝土并振捣密实,浇筑完成待混凝土初凝后进行整体覆盖并输送适宜温度的蒸汽或热水进行养护;(5)内外模板500的拆除:待混凝土达到设计或相关规范规定拆模强度开始拆模,首先解除管廊外模板500顶部对拉螺杆,同时将侧墙200底部内外模板500锁定螺栓解除,移除外模板500,然后解除内模板500底部竖向撑杆,侧向千斤顶同步回缩使得侧模板500绕顶部铰接点向舱内转动而脱模,最后台车立柱竖向千斤顶回缩使得顶模与顶板300脱开,台车及整体内膜系统自行移动至下一施工节段。A construction method of variable cross-section pipe gallery structure suitable for rapid construction, including the described pipe gallery section structure suitable for rapid construction: (1) Construction of the pipe gallery bottom plate 100 structure: in the construction process, follow the traditional current Construction method of pouring pipe gallery: complete site leveling, supporting pile construction, earth excavation and setting of cross bracing, pile foundation inspection, foundation pit acceptance, cushion laying, waterproof treatment, pouring and maintenance of pipe gallery bottom 100 structure; (2) side Wall 200 steel reinforcement installation: Before installation, during the installation process of the side wall 200 steel reinforcement, the steel reinforcement is completed on the side wall 200 reinforcement membrane frame in the steel processing shed and transported to the construction site. The steel frame is installed and positioned; (3) The template 500 is installed: In the process of installing the template 500, first lay a self-propelled track on the bottom plate 100, and then the trolley moves into position and locks by itself, because the side wall 200 and the top plate 300 are smooth Curve transition, so the side mold and the top mold can be connected by the hinge structure 700 to form an integral steel inner film without bends. During the mold erection process, the top mold is raised to the control elevation by the trolley column jack and fine-tuned to the side wall 200. The inner position is locked by adjusting joints. Secondly, the side wall 200 formwork 500 is pushed by a lateral jack to rotate around the top hinge point to the vertical position of the side wall 200 and locked by the bottom brace. Once again, install the top plate 300 steel bars and the outer formwork 500 and locked with the top and bottom of the inner mold; (4) Concrete pouring and maintenance: After the steel frame and template 500 support inspection is passed, the concrete is poured and vibrated to compact it. After the pouring is completed, the concrete will be covered and the appropriate temperature will be delivered after the initial setting. (5) Demolition of the internal and external formwork 500: When the concrete reaches the design or relevant specifications, the demoulding strength is to be started. First, remove the top of the outer formwork 500 of the pipe gallery and pull the screw at the bottom of the side wall 200. The lock bolts of the inner and outer formwork 500 are released, the outer formwork 500 is removed, and then the vertical brace at the bottom of the inner formwork 500 is released, and the side jacks retract synchronously so that the side formwork 500 rotates around the top hinge point in the cabin to demold, and finally the trolley column The vertical jack retracts so that the top mold is separated from the top plate 300, and the trolley and the overall inner membrane system move to the next construction section by themselves.
上述操作流程及软硬件配置,仅作为本发明的较佳实施例,并非因此限制本发明的专利范围,凡是利用本发明说明书及附图内容所作的等同变换,或直接或间接运用在相关技术领域,均同理包括在本发明的专利保护范围内。The above-mentioned operation flow and hardware and software configuration are only preferred embodiments of the present invention, and do not therefore limit the scope of the present invention. Any equivalent transformation made by using the content of the description and drawings of the present invention, or directly or indirectly applied in related technical fields , The same reason is included in the scope of patent protection of the present invention.

Claims (5)

  1. 一种适用于快速施工的变截面管廊结构,包括顶板、侧墙和底板,其特征在于:所述顶板采用截面高度逐渐变化的变截面结构形式,侧墙设置于顶板两侧,侧墙与平直底板之间设置有倒角部,在管廊施工中顶板下方设置有与顶板贴合的顶模,在顶模下方设置有与侧墙贴合的侧模,在顶模和侧模之间设置有铰接结构。A variable cross-section pipe gallery structure suitable for rapid construction, comprising a top plate, a side wall and a bottom plate, and is characterized in that: the top plate adopts a variable cross-section structure with a gradually changing section height, and the side walls are arranged on both sides of the top plate. There is a chamfered portion between the flat bottom plates. In the construction of the pipe gallery, there is a top mold that is attached to the top board, and a side mold that is attached to the side wall is set below the top mold. Between the top mold and the side mold A hinge structure is provided between.
  2. 根据权利要求1所述的适用于快速施工的变截面管廊结构,其特征在于:截面高度逐渐变化的变截面顶板,由侧墙与顶板交界处先经圆曲线过渡,然后以渐变曲线过渡至顶板跨中处所形成。The variable cross-section pipe gallery structure suitable for rapid construction according to claim 1, characterized in that: the variable cross-section top slab with a gradually changing cross-section height first transitions from the side wall and the top slab through a circular curve, and then transitions to a gradual curve. The roof is formed at the mid-span.
  3. 根据权利要求2所述的适用于快速施工的变截面管廊结构,其特征在于:所述侧模和顶模,通过铰接结构相连,形成无折角的整体钢内膜,充分适用于管廊的快速施工。The variable cross-section pipe gallery structure suitable for rapid construction according to claim 2, characterized in that: the side mold and the top mold are connected by a hinged structure to form an integral steel inner membrane with no corners, which is fully suitable for the pipe gallery Fast construction.
  4. 根据权利要求3所述的适用于快速施工的变截面管廊结构,其特征在于:所述底板、侧墙均为矩形等截面形式,侧墙与底板间以直线倒角部进行过渡。The variable cross-section pipe gallery structure suitable for rapid construction according to claim 3, characterized in that: the bottom plate and the side walls are in rectangular cross-sectional forms, and the transition between the side walls and the bottom plate is a straight chamfered part.
  5. 一种适用于快速施工的变截面管廊结构的施工方法,包括如权利要求4所述的适用于快速施工的管廊截面结构,其特征在于:(1)对管廊底板结构进行施工:在施工过程中,按照传统现浇管廊施工方法完成场地平整、支护桩施工、土方开挖并设置横撑、桩基检测、基坑验收、垫层铺设、防水处理、管廊底板结构浇筑和养护;(2)侧墙钢筋安装:在安装之前,先在侧墙钢筋安装安装的过程中,在钢筋加工棚内的侧墙钢筋胎膜架上完成钢筋制作并运送至施工现场,借助吊车对侧墙钢筋骨架进行安装定位;(3)进行模板安装:在模板安装的过程中,首先在底板铺设自行轨道,然后台车自行移动就位并锁定,因侧墙与顶板间为圆滑曲线过渡,所以可将侧模与顶模间通过铰接结构相连形成无折角的整体钢内膜,立模过程中通过台车立柱千斤顶将顶模起升至控制标高并横向微调至侧墙内侧位置加调整节锁定,其次,侧墙模板利用侧向千斤顶外推使其绕顶部铰接点转动至侧墙竖向位置并通过底部撑杆锁定,再次,安装顶板钢筋及外模板并与内模顶、底部锁定;(4)混凝土浇筑与养护:待钢筋骨架及模板支设检验合格后浇筑混凝土并振捣密实,浇筑完成待混凝土初凝后进行整体覆盖并输送适宜温度的蒸汽或热水进行养护;(5)内外模板的拆除:待混凝土达到设计或相关规范规定拆模强度开始拆模,首先解除管廊外模板顶部对拉螺杆,同时将侧墙底部内外模板锁定螺栓解除,移除外模板,然后解除内模板底部竖向撑杆,侧向千斤顶同步回缩使得侧模板绕顶部铰接点向舱内转动而脱模,最后台车立柱竖向千斤顶回缩使得顶模与顶板脱开,台车及整体内膜系统自行移动至下一施工节段。A construction method for a variable section pipe gallery structure suitable for rapid construction, comprising the pipe gallery section structure suitable for rapid construction as claimed in claim 4, characterized in that: (1) construction of the pipe gallery floor structure: During the construction process, according to the traditional cast-in-situ pipe gallery construction method, the site leveling, supporting pile construction, earth excavation and setting of transverse bracing, pile foundation inspection, foundation pit acceptance, cushion laying, waterproof treatment, pipe gallery floor structure pouring and Maintenance; (2) Installation of side wall steel bars: Before installation, during the installation of side wall steel bars, the steel bars are produced on the side wall steel frame in the steel bar processing shed and transported to the construction site. Install and locate the side wall steel frame; (3) Install the formwork: In the process of formwork installation, first lay a self-propelled track on the bottom plate, and then move the trolley into position and lock it, because the side wall and the top plate are smoothly curved. Therefore, the side mold and the top mold can be connected by a hinged structure to form an integral steel inner film without bending angles. During the mold erection process, the top mold is raised to the control elevation by the trolley column jack and fine-tuned to the inner side of the side wall with adjustment joints. Lock, secondly, the side wall formwork is pushed out by the lateral jack to rotate around the top hinge point to the vertical position of the side wall and locked by the bottom brace. Once again, install the top plate reinforcement and the outer formwork and lock with the top and bottom of the inner form; (4) Concrete pouring and curing: After the steel frame and formwork support are qualified, the concrete is poured and vibrated to compact it. After the pouring is completed, the concrete will be covered as a whole and steam or hot water of suitable temperature is delivered for curing; (5) Removal of the inner and outer formwork: When the concrete reaches the design or relevant specifications, the formwork will be demolished. First, release the top of the outer formwork of the pipe gallery, and release the locking bolts of the inner and outer formwork at the bottom of the side wall, remove the outer formwork, and then release the inner formwork. The vertical support bar at the bottom of the formwork and the synchronous retraction of the side jacks make the side formwork rotate around the top hinge point in the cabin to demold. Finally, the vertical jack of the trolley column retracts to make the top die and the top plate separate, and the trolley and the whole The membrane system moves to the next construction section by itself.
PCT/CN2020/078534 2019-06-06 2020-03-10 Variable cross-section pipe gallery structure suitable for rapid construction and construction method therefor WO2020244268A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201910488919.2 2019-06-06
CN201910488919.2A CN110093948B (en) 2019-06-06 2019-06-06 Variable-section pipe gallery structure suitable for rapid construction and construction method thereof

Publications (1)

Publication Number Publication Date
WO2020244268A1 true WO2020244268A1 (en) 2020-12-10

Family

ID=67450463

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2020/078534 WO2020244268A1 (en) 2019-06-06 2020-03-10 Variable cross-section pipe gallery structure suitable for rapid construction and construction method therefor

Country Status (2)

Country Link
CN (1) CN110093948B (en)
WO (1) WO2020244268A1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863370A (en) * 2021-10-19 2021-12-31 鞍山三冶建筑工程有限公司 Rapid installation mechanism and construction method for pipe gallery prefabricated member

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110093948B (en) * 2019-06-06 2024-06-07 福州大学 Variable-section pipe gallery structure suitable for rapid construction and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05263457A (en) * 1992-03-18 1993-10-12 Asahi Concrete Works Co Ltd Connecting structure for box culvert in jacking method
KR20070082152A (en) * 2006-02-15 2007-08-21 정태화 The structure of precast concrete culvert
CN203684119U (en) * 2013-12-31 2014-07-02 中铁十二局集团第二工程有限公司 Integrated channel-type culvert die holder
CN206538790U (en) * 2017-03-03 2017-10-03 湖南五新模板有限公司 Interior mould trolley is used in a kind of cast-in-place pipe gallery construction
CN206888004U (en) * 2017-06-23 2018-01-16 新疆城建丝路建设有限公司 Prefabricated assembled single position in storehouse comprehensive pipe gallery structure
CN110093948A (en) * 2019-06-06 2019-08-06 福州大学 Variable cross-section Pipe rack and its construction method suitable for rapid construction

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6218180B2 (en) * 2014-06-20 2017-10-25 株式会社アルファシビルエンジニアリング Rectangular section propulsion method
CN105926674B (en) * 2016-04-15 2017-07-28 南京联众建设工程技术有限公司 High intensity Urban Underground pipe gallery
CN106869167A (en) * 2017-03-06 2017-06-20 南京联众建设工程技术有限公司 The bowed out box shape steel structure Urban Underground pipe gallery in section
CN108661670B (en) * 2018-05-03 2020-04-28 十九冶成都建设有限公司 Construction method for pipe gallery construction by using formwork trolley
CN210459289U (en) * 2019-06-06 2020-05-05 福州大学 Variable cross-section pipe gallery structure suitable for rapid construction

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05263457A (en) * 1992-03-18 1993-10-12 Asahi Concrete Works Co Ltd Connecting structure for box culvert in jacking method
KR20070082152A (en) * 2006-02-15 2007-08-21 정태화 The structure of precast concrete culvert
CN203684119U (en) * 2013-12-31 2014-07-02 中铁十二局集团第二工程有限公司 Integrated channel-type culvert die holder
CN206538790U (en) * 2017-03-03 2017-10-03 湖南五新模板有限公司 Interior mould trolley is used in a kind of cast-in-place pipe gallery construction
CN206888004U (en) * 2017-06-23 2018-01-16 新疆城建丝路建设有限公司 Prefabricated assembled single position in storehouse comprehensive pipe gallery structure
CN110093948A (en) * 2019-06-06 2019-08-06 福州大学 Variable cross-section Pipe rack and its construction method suitable for rapid construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113863370A (en) * 2021-10-19 2021-12-31 鞍山三冶建筑工程有限公司 Rapid installation mechanism and construction method for pipe gallery prefabricated member

Also Published As

Publication number Publication date
CN110093948B (en) 2024-06-07
CN110093948A (en) 2019-08-06

Similar Documents

Publication Publication Date Title
CN105908777B (en) A kind of pipe gallery sliding mould and its application method
CN104631512B (en) Hang modulus method after-pouring band beam-slab construction method
CN109487814A (en) Cast-in-place piping lane integrated moveable formwork jumbo construction method
WO2020244268A1 (en) Variable cross-section pipe gallery structure suitable for rapid construction and construction method therefor
CN103334356A (en) Bridge type precast reinforced concrete hidden beam slab pavement system and construction method thereof
CN110409492A (en) The combination assembled piping lane of one kind more structures containing superposed member and its construction method
CN210263131U (en) Assembled is from stagnant water underground pipe gallery structure
CN111608662A (en) Shaft oversized-diameter integral moving metal template
CN113481944B (en) Construction method of dam surface hole connection girder supporting structure
CN213143104U (en) Hoisting type finished product earth retaining enclosure device
CN212656260U (en) Assembled rail top air duct structure of underground station
CN106930391B (en) Cast-in-place drainage channel structure of top plate for formwork-free construction and construction method
CN112211402A (en) Anti-bank of pre-buried formula pouring die
CN205024719U (en) Pile foundation and integrated reverse construction vertical braces system of underground continuous wall
CN210459289U (en) Variable cross-section pipe gallery structure suitable for rapid construction
CN114263275B (en) Construction method for same-layer construction of high-rise assembled steel structure-core tube
CN210552011U (en) Take precast stair mould of concrete maintenance function
CN210256628U (en) Self-adaptive outer mold system for prefabricating concrete
CN110158627B (en) Foundation of prefabricated substation distribution device building and construction method
CN208294062U (en) A kind of concrete wall template and support combinations structure
CN106013234A (en) Construction method for underground comprehensive pipe rack
CN104908150A (en) Piping shaft manufacturing formwork and industrialized piping shaft production method
CN219450806U (en) Reinforced structure of retaining wall steel form
CN218990927U (en) Formwork support system for single-side formwork support on non-hardened ground
CN217480095U (en) Support system for constructing concrete pouring template of S-shaped double-slope dam

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 20818035

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 20818035

Country of ref document: EP

Kind code of ref document: A1