CN110409492A - A multi-structure combined assembled pipe gallery with superimposed components and its construction method - Google Patents
A multi-structure combined assembled pipe gallery with superimposed components and its construction method Download PDFInfo
- Publication number
- CN110409492A CN110409492A CN201910616098.6A CN201910616098A CN110409492A CN 110409492 A CN110409492 A CN 110409492A CN 201910616098 A CN201910616098 A CN 201910616098A CN 110409492 A CN110409492 A CN 110409492A
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- cast
- place
- pipe gallery
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 29
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 71
- 239000010959 steel Substances 0.000 claims abstract description 71
- 239000007787 solid Substances 0.000 claims abstract description 32
- 238000009415 formwork Methods 0.000 claims description 11
- 230000002787 reinforcement Effects 0.000 claims description 6
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 4
- 229910000576 Laminated steel Inorganic materials 0.000 claims description 3
- 239000004576 sand Substances 0.000 claims description 3
- 238000000034 method Methods 0.000 description 9
- 238000010586 diagram Methods 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 2
- 230000007613 environmental effect Effects 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 230000005641 tunneling Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/10—Tunnels or galleries specially adapted to house conduits, e.g. oil pipe-lines, sewer pipes ; Making conduits in situ, e.g. of concrete ; Casings, i.e. manhole shafts, access or inspection chambers or coverings of boreholes or narrow wells
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Chemical & Material Sciences (AREA)
- Oil, Petroleum & Natural Gas (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明属于地下综合管廊工程领域,具体是一种含叠合构件多结构组合装配式管廊及其施工方法。装配式管廊包括设置在现浇底板上的实芯预制内墙,实芯预制内墙设置在现浇底板中部的两侧,实芯预制内墙侧面设置有斜撑,两侧的实芯预制内墙顶部之间安装有预制钢筋桁架叠合顶板,预制钢筋桁架叠合顶板上侧为现浇结构顶板;现浇管廊包括设置在现浇底板一侧的现浇外墙,现浇外墙与实芯预制内墙之间设置现浇结构顶板;半装配式管廊包括设置在现浇底板另一侧的现浇外墙,现浇外墙内外侧设置双面预制夹芯外墙板,内侧的双面预制夹芯外墙板上安装有斜撑,双面预制夹芯外墙板与实芯预制内墙之间安装有预制钢筋桁架叠合顶板。
The invention belongs to the field of underground comprehensive pipe gallery engineering, in particular to a multi-structure assembled pipe gallery with superimposed components and a construction method thereof. The prefabricated pipe gallery includes a solid prefabricated interior wall set on the cast-in-place floor. The solid prefabricated interior wall is arranged on both sides of the middle part of the cast-in-place floor. A prefabricated steel bar truss superimposed roof is installed between the tops of the inner walls, and the upper side of the prefabricated steel bar truss superimposed roof is a cast-in-place structural roof; The cast-in-place structural roof is set between the solid prefabricated inner wall; the semi-fabricated pipe gallery includes a cast-in-place outer wall set on the other side of the cast-in-place base plate, and double-sided prefabricated sandwich outer wall panels are set on the inner and outer sides of the cast-in-place outer wall. Diagonal braces are installed on the inner double-sided prefabricated sandwich outer wall panels, and prefabricated steel truss laminated roofs are installed between the double-sided prefabricated sandwich outer wall panels and the solid prefabricated inner walls.
Description
技术领域technical field
本发明属于地下综合管廊工程领域,具体是一种含叠合构件多结构组合装配式管廊及其施工方法。The invention belongs to the field of underground comprehensive pipe gallery engineering, in particular to a multi-structure assembled pipe gallery with superimposed components and a construction method thereof.
背景技术Background technique
近年来,我国城市化进程不断加快,城市综合实力不断增强,对外交流日益增多,城市地下空间不断被开发,综合管廊的重要性越来越被人们认识。如何提高生产效率、降低安全隐患、降低人力成本、节能环保,减少污染成为现阶段主要的研究重点。In recent years, my country's urbanization process has been accelerating, the city's comprehensive strength has been continuously enhanced, foreign exchanges have increased, urban underground spaces have been continuously developed, and the importance of comprehensive utility corridors has become more and more recognized. How to improve production efficiency, reduce potential safety hazards, reduce labor costs, save energy and protect the environment, and reduce pollution has become the main research focus at this stage.
目前我国综合管廊的建设施工中,除特殊需求采用盾构法和顶管法之外,大部分工程均采用明挖法施工,其中明挖法施工又分为传统现浇混凝土和装配式法施工。现浇混凝土施工,其主要缺点为施工周期长、人工需求量大、施工现场环保压力大、安全风险大等,无法满足“四节一环保”的绿色建造要求。装配式综合管廊的主要构件在工厂预制、主体结构在现场拼装成形,整个建造过程可显著减少现场作业,减少人工、减少污染、降低成本,从而实现绿色建造的目标。但由于地下管廊荷载的复杂多变及防水的要求,地下综合管廊的预制装配施工比建筑工程的类型更多样、技术更先进、要求更严格。就目前国内装配式管廊技术还不是很成熟,对于装配式管廊施工质量还有待研究,因此必须研究一种能够有效解决目前城市地下综合管廊施工周期短、结构和防水性能要求高问题的施工方法。At present, in the construction of comprehensive pipe corridors in my country, except for the shield tunneling method and pipe jacking method for special needs, most of the projects are constructed by the open-cut method, and the open-cut method is divided into traditional cast-in-place concrete and prefabricated methods construction. The main disadvantages of cast-in-place concrete construction are long construction period, large labor demand, high environmental protection pressure on the construction site, and high safety risks, etc., which cannot meet the green construction requirements of "four sections and one environmental protection". The main components of the prefabricated comprehensive pipe gallery are prefabricated in the factory, and the main structure is assembled and formed on site. The entire construction process can significantly reduce on-site operations, reduce labor, reduce pollution, and reduce costs, thereby achieving the goal of green construction. However, due to the complex and changeable load of the underground pipe gallery and the waterproof requirements, the prefabricated assembly construction of the underground comprehensive pipe gallery is more diverse in types, more advanced in technology, and stricter in requirements than construction projects. At present, the domestic prefabricated pipe gallery technology is not very mature, and the construction quality of the prefabricated pipe gallery has yet to be studied. Therefore, it is necessary to study a method that can effectively solve the problems of short construction period and high requirements on structure and waterproof performance of the current urban underground comprehensive pipe gallery. Construction method.
发明内容Contents of the invention
本发明为了解决城市地下综合管廊在结构形式复杂和防水性能要求高的情况下,如何快速完成施工的问题,提供一种含叠合构件多结构组合装配式管廊及其施工方法。In order to solve the problem of how to quickly complete the construction of the urban underground comprehensive pipe gallery with complex structural forms and high waterproof performance requirements, the present invention provides a multi-structure assembled pipe gallery with superimposed components and a construction method thereof.
本发明采取以下技术方案:一种含叠合构件多结构组合装配式管廊,包括现浇管廊、装配式管廊以及半装配式管廊,装配式管廊包括设置在现浇底板上的实芯预制内墙,实芯预制内墙设置在现浇底板中部的两侧,实芯预制内墙侧面设置有斜撑,两侧的实芯预制内墙顶部之间安装有预制钢筋桁架叠合顶板,预制钢筋桁架叠合顶板上侧为现浇结构顶板;现浇管廊包括设置在现浇底板一侧的现浇外墙,现浇外墙与实芯预制内墙之间设置现浇结构顶板;半装配式管廊包括设置在现浇底板另一侧的现浇外墙,现浇外墙内外侧设置双面预制夹芯外墙板,内侧的双面预制夹芯外墙板上安装有斜撑,双面预制夹芯外墙板与实芯预制内墙之间安装有预制钢筋桁架叠合顶板,预制钢筋桁架叠合顶板上侧为现浇结构顶板。The present invention adopts the following technical solutions: a multi-structure combined assembled pipe gallery with superimposed components, including a cast-in-place pipe gallery, a prefabricated pipe gallery and a semi-fabricated pipe gallery. Solid prefabricated interior walls, the solid prefabricated interior walls are set on both sides of the middle part of the cast-in-place floor, the sides of the solid prefabricated interior walls are provided with diagonal braces, and the tops of the solid prefabricated interior walls on both sides are stacked with prefabricated steel trusses Roof, the upper side of the prefabricated steel truss superimposed roof is the cast-in-place structure roof; the cast-in-place pipe gallery includes the cast-in-place outer wall set on one side of the cast-in-place bottom plate, and the cast-in-place structure is set between the cast-in-place outer wall and the solid prefabricated inner wall Roof; the semi-fabricated pipe gallery includes a cast-in-place exterior wall set on the other side of the cast-in-place bottom plate, double-sided prefabricated sandwich exterior wall panels are installed on the inner and outer sides of the cast-in-place exterior wall, and the inner double-sided prefabricated sandwich exterior wall panels are installed There are diagonal braces, and a prefabricated steel truss superimposed roof is installed between the double-sided prefabricated sandwich exterior wall panels and the solid prefabricated interior walls, and the upper side of the prefabricated steel truss superimposed top is a cast-in-place structural roof.
进一步的,装配式管廊以及半装配式管廊一侧的现浇底板内预埋有预制钢筋桁架叠合底板,预制钢筋桁架叠合底板上设置斜撑支架,斜撑支架与斜撑的一端铰接,斜撑的另一端与实芯预制内墙连接。Further, the prefabricated steel truss superimposed floor is pre-embedded in the cast-in-place bottom plate on one side of the prefabricated pipe gallery and the semi-fabricated pipe gallery, and the prefabricated steel truss superimposed floor is provided with a diagonal brace, and one end of the diagonal brace and the diagonal brace Hinged, the other end of the brace is connected to the solid precast interior wall.
进一步的,实芯预制内墙安装在支架上,支架预埋在现浇底板内。Further, the solid prefabricated inner wall is installed on the bracket, and the bracket is pre-buried in the cast-in-place base plate.
进一步的,现浇外墙外侧安装有双面预制夹芯外墙板。Further, double-sided prefabricated sandwich exterior wall panels are installed on the outside of the cast-in-place exterior wall.
进一步的,双面预制夹芯外墙板顶部设有吊点,双面预制夹芯外墙板下部设置观测孔,双面预制夹芯外墙板底部两侧设置止水钢板。Further, the top of the double-sided prefabricated sandwich exterior wall panel is provided with hanging points, the lower part of the double-sided prefabricated sandwich exterior wall panel is provided with observation holes, and the two sides of the bottom of the double-sided prefabricated sandwich exterior wall panel are provided with water-proof steel plates.
进一步的,现浇底板内设置有缆线仓、积水仓和热力仓。Further, a cable bin, a water storage bin and a heat bin are arranged in the cast-in-place bottom plate.
进一步的,斜撑支架包括钢筋腿,钢筋腿底部预埋在预制钢筋桁架叠合底板内,钢筋腿顶部焊接挂钩。Further, the diagonal bracing bracket includes a steel bar leg, the bottom of the steel bar leg is pre-embedded in the laminated bottom plate of the prefabricated steel bar truss, and the top of the steel bar leg is welded with a hook.
一种含叠合构件多结构组合装配式管廊的施工方法,包括以下步骤,A construction method for a multi-structure assembled pipe gallery with superimposed components, comprising the following steps,
S100~底板吊装:在垫层上铺10mm厚细砂找平,将预制钢筋桁架叠合底板吊装就位,进行现浇底板部位的钢筋绑扎;S100~Bottom plate hoisting: Lay 10mm thick fine sand on the cushion for leveling, hoist the prefabricated steel bar truss laminated bottom plate in place, and carry out steel bar binding on the cast-in-place bottom plate;
S200~支座加工:用角钢根据底板的高度和预制墙板厚度焊接成方形支架,并在中间加设一道角钢加强;S200~Support processing: Use angle steel to weld square brackets according to the height of the bottom plate and the thickness of the prefabricated wall panels, and add an angle steel reinforcement in the middle;
S300~墙板吊装:将双面预制夹芯墙安装至外墙部位,实芯预制墙安装至内墙处,安装完成后采用斜撑进行固定,焊接双面预制夹芯墙板块间的止水钢板;S300~Wall panel hoisting: Install the double-sided prefabricated sandwich wall to the outer wall, and the solid prefabricated wall to the inner wall. steel plate;
S400~现浇外墙及混凝土施工:将现浇外墙按照图纸要求进行钢筋绑扎、止水钢板安装以及模板支设,完成后进行混凝土浇筑,外墙混凝土浇筑高度位于止水钢板中间;S400~Cast-in-place external wall and concrete construction: Bind the steel bars, install water-stop steel plates and formwork support for the cast-in-place external wall according to the requirements of the drawings, and then pour concrete after completion.
S500~顶板支撑体系:混凝土凝固后进行现浇外墙模板安装和满堂脚手架搭设,最后在无预制叠合钢筋桁架叠合顶板部位进行模板安装;S500~Roof support system: After the concrete is solidified, install the cast-in-place exterior wall formwork and erect scaffolding for the whole hall, and finally install the formwork at the laminated roof part without prefabricated laminated steel truss;
S600~顶板吊装:将预制钢筋桁架叠合顶板吊装至搭设完成的支撑体系上;S600~Roof hoisting: hoisting the laminated roof of the prefabricated steel truss to the erected supporting system;
S700~现浇顶板施工:在预制钢筋桁架叠合顶板上绑扎上层钢筋和现浇结构部位的钢筋,最后进行混凝土浇筑。S700~Construction of cast-in-place roof: Bind the upper steel bars and the steel bars of the cast-in-place structure on the prefabricated steel truss superimposed roof, and finally pour concrete.
与现有技术性相比 ,本发明具有以下特点和有益效果:Compared with the prior art, the present invention has the following characteristics and beneficial effects:
(1)本发明是利用了现浇结构性能好的特点,应用于管廊舱体较大和需节点受力要求高的部位,以保证结构的安全性和耐久性;(1) The present invention utilizes the characteristics of good performance of the cast-in-place structure, and is applied to the parts where the cabin body of the pipe gallery is large and requires high stress on the joints, so as to ensure the safety and durability of the structure;
(2)本发明的墙体应用了叠合式预制构件和全预制构件,节省了墙体钢筋绑扎和模板支设的时间,同时也保证了混凝土的浇筑和养护质量;(2) The wall of the present invention uses superimposed prefabricated components and fully prefabricated components, which saves the time for wall reinforcement binding and formwork support, and also ensures the quality of concrete pouring and maintenance;
(3)双面预制夹芯墙的应用,保证了外墙的防水质量,既有常规式的止水钢板保证施工缝的防水,又有预制和现浇双重混凝土来确保防水质量;(3) The application of double-sided prefabricated sandwich walls ensures the waterproof quality of the exterior walls. There are not only conventional waterproof steel plates to ensure the waterproof of construction joints, but also prefabricated and cast-in-place concrete to ensure waterproof quality;
(4)顶板应用了预制钢筋桁架叠合顶板,此顶板节省了顶板模板安装时间和顶板钢筋下层筋的绑扎时间,加快了施工进度。(4) The prefabricated steel truss laminated roof is applied to the roof, which saves the installation time of the roof formwork and the binding time of the lower reinforcement of the roof, and speeds up the construction progress.
附图说明Description of drawings
图1是本发明的结构示意图;Fig. 1 is a structural representation of the present invention;
图2是双面预制夹芯外墙板示意图;Fig. 2 is a schematic diagram of a double-sided prefabricated sandwich exterior wall panel;
图3是预制钢筋桁架叠合底板示意图;Fig. 3 is a schematic diagram of a prefabricated reinforced truss laminated floor;
图4是斜支撑环大样图示意图;Fig. 4 is a schematic diagram of a large sample diagram of an oblique support ring;
图中:1-预制钢筋桁架叠合底板,2-现浇底板,3-支架,4-双面预制夹芯外墙板,5-实芯预制内墙,6-斜撑,7-现浇外墙,8-预制钢筋桁架叠合顶板,9-现浇结构顶板,10-斜撑支架,11-缆线仓,12-积水仓,13-热力仓,14-吊点,15-观测孔,16-止水钢板,17-钢筋腿,18-挂钩。In the figure: 1-prefabricated reinforced truss laminated base plate, 2-cast-in-place base plate, 3-bracket, 4-double-sided prefabricated sandwich exterior wall panel, 5-solid prefabricated inner wall, 6-diagonal brace, 7-cast-in-place External wall, 8-prefabricated steel truss superimposed roof, 9-cast-in-place structure roof, 10-diagonal bracing bracket, 11-cable warehouse, 12-water storage warehouse, 13-thermal warehouse, 14-hanging point, 15-observation Hole, 16-waterproof steel plate, 17-reinforced leg, 18-hook.
具体实施方式Detailed ways
如图1所示,一种含叠合构件多结构组合装配式管廊,包括现浇管廊、装配式管廊以及半装配式管廊。As shown in Figure 1, a multi-structure combined assembled pipe gallery with superimposed components includes a cast-in-place pipe gallery, a prefabricated pipe gallery and a semi-fabricated pipe gallery.
装配式管廊包括设置在现浇底板2上的实芯预制内墙5,实芯预制内墙5设置在现浇底板2中部的两侧,实芯预制内墙5侧面设置有斜撑6,两侧的实芯预制内墙5顶部之间安装有预制钢筋桁架叠合顶板8,预制钢筋桁架叠合顶板8上侧为现浇结构顶板9。The prefabricated pipe gallery includes a solid prefabricated inner wall 5 arranged on the cast-in-place floor 2, the solid prefabricated inner wall 5 is arranged on both sides of the middle part of the cast-in-place floor 2, and the side of the solid prefabricated inner wall 5 is provided with diagonal braces 6, A prefabricated steel bar truss laminated roof 8 is installed between the tops of the solid prefabricated inner walls 5 on both sides, and the upper side of the prefabricated steel bar truss laminated roof 8 is a cast-in-place structural roof 9 .
现浇管廊包括设置在现浇底板2一侧的现浇外墙7,现浇外墙7与实芯预制内墙5之间设置现浇结构顶板9。The cast-in-place pipe gallery includes a cast-in-place outer wall 7 arranged on one side of the cast-in-place bottom plate 2 , and a cast-in-place structural roof 9 is arranged between the cast-in-place outer wall 7 and the solid prefabricated inner wall 5 .
半装配式管廊包括设置在现浇底板2另一侧的现浇外墙7,现浇外墙7内外侧设置双面预制夹芯外墙板4,内侧的双面预制夹芯外墙板4上安装有斜撑6,双面预制夹芯外墙板4与实芯预制内墙5之间安装有预制钢筋桁架叠合顶板8,预制钢筋桁架叠合顶板8上侧为现浇结构顶板9。The semi-fabricated pipe gallery includes a cast-in-place exterior wall 7 arranged on the other side of the cast-in-place base plate 2. The inner and outer sides of the cast-in-place exterior wall 7 are provided with double-sided prefabricated sandwich exterior wall panels 4, and the inner double-sided prefabricated sandwich exterior wall panels 4 is installed with diagonal braces 6, and a prefabricated steel truss laminated roof 8 is installed between the double-sided prefabricated sandwich exterior wall panel 4 and the solid prefabricated interior wall 5, and the upper side of the prefabricated steel truss laminated roof 8 is a cast-in-place structural roof 9.
装配式管廊以及半装配式管廊一侧的现浇底板2内预埋有预制钢筋桁架叠合底板1,预制钢筋桁架叠合底板1上设置斜撑支架10,斜撑支架10与斜撑6的一端铰接,斜撑6的另一端与实芯预制内墙5连接。The cast-in-place floor 2 on one side of the prefabricated pipe gallery and the semi-fabricated pipe gallery is pre-embedded with a prefabricated steel truss laminated floor 1, and the prefabricated steel truss laminated floor 1 is provided with a diagonal brace 10, and the diagonal brace 10 and the diagonal brace One end of 6 is hinged, and the other end of diagonal brace 6 is connected with solid prefabricated inner wall 5 .
实芯预制内墙5安装在支架3上,支架3预埋在现浇底板2内。现浇外墙7外侧安装有双面预制夹芯外墙板4。如图2所示,双面预制夹芯外墙板4顶部设有吊点14,双面预制夹芯外墙板4下部设置观测孔15,双面预制夹芯外墙板4底部两侧设置止水钢板16。现浇底板2内设置有缆线仓11、积水仓12和热力仓13。The solid prefabricated inner wall 5 is installed on the support 3, and the support 3 is pre-buried in the cast-in-place base plate 2. A double-sided prefabricated sandwich exterior wall panel 4 is installed on the outside of the cast-in-place exterior wall 7 . As shown in Figure 2, the top of the double-sided prefabricated sandwich exterior wall panel 4 is provided with a lifting point 14, the lower part of the double-sided prefabricated sandwich exterior wall panel 4 is provided with an observation hole 15, and the bottom of the double-sided prefabricated sandwich exterior wall panel 4 is provided on both sides. Waterproof steel plate 16. The cast-in-place bottom plate 2 is provided with a cable bin 11 , a water storage bin 12 and a heat bin 13 .
如图3、4所示,斜撑支架10包括钢筋腿17,钢筋腿17底部预埋在预制钢筋桁架叠合底板1内,钢筋腿17顶部焊接挂钩18。As shown in Figures 3 and 4, the diagonal brace 10 includes steel bar legs 17, the bottom of the steel bar legs 17 is pre-embedded in the laminated bottom plate 1 of the prefabricated steel bar truss, and the top of the steel bar legs 17 is welded with a hook 18.
一种含叠合构件多结构组合装配式管廊的施工方法,包括以下步骤,A construction method for a multi-structure assembled pipe gallery with superimposed components, comprising the following steps,
S100~底板吊装:在垫层上铺10mm厚细砂找平,将预制钢筋桁架叠合底板1吊装就位,进行现浇底板2部位的钢筋绑扎。S100~Bottom plate hoisting: Lay 10mm thick fine sand on the cushion for leveling, hoist the prefabricated steel truss laminated bottom plate 1 into place, and bind the steel bars at the cast-in-place bottom plate 2.
S200~支座加工:用8#角钢根据底板的高度和预制墙板厚度焊接成方形支架3,并在中间加设一道角钢加强。S200~Support processing: Use 8# angle steel to weld square bracket 3 according to the height of the bottom plate and the thickness of the prefabricated wall board, and add an angle steel reinforcement in the middle.
S300~墙板吊装:将双面预制夹芯墙4安装至外墙部位,实芯预制墙5安装至内墙处,安装完成后采用斜撑6进行固定,焊接双面预制夹芯墙4板块间的止水钢板。S300~Wall panel hoisting: Install the double-sided prefabricated sandwich wall 4 to the outer wall, and the solid prefabricated wall 5 to the inner wall. After the installation is completed, use the diagonal brace 6 to fix it, and weld the double-sided prefabricated sandwich wall 4 panels Waterproof steel plate between.
S400~现浇外墙及混凝土施工:将现浇外墙7按照图纸要求进行钢筋绑扎、止水钢板安装以及模板支设,完成后进行混凝土浇筑,外墙混凝土浇筑高度位于止水钢板中间。S400~Cast-in-place external wall and concrete construction: according to the requirements of the drawings, the cast-in-place external wall 7 shall be bound with steel bars, installed with water-stop steel plates and formwork support.
S500~顶板支撑体系:混凝土凝固后进行现浇外墙模板安装和满堂脚手架搭设,最后在无预制叠合钢筋桁架叠合顶板部位进行模板安装。S500~Roof support system: After the concrete is solidified, install the cast-in-place formwork for the exterior wall and erect scaffolding for the whole hall, and finally install the formwork on the laminated roof of the non-prefabricated laminated steel truss.
S600~顶板吊装:将预制钢筋桁架叠合顶板8吊装至搭设完成的支撑体系上。S600~Roof hoisting: hoist the prefabricated steel bar truss superimposed roof 8 to the erected supporting system.
S700~现浇顶板施工:在预制钢筋桁架叠合顶板8上绑扎上层钢筋和现浇结构部位的钢筋,最后进行混凝土浇筑。S700~Construction of cast-in-place roof: Bind the upper steel bars and the steel bars of the cast-in-place structure on the prefabricated steel truss laminated roof 8, and finally pour concrete.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910616098.6A CN110409492A (en) | 2019-07-09 | 2019-07-09 | A multi-structure combined assembled pipe gallery with superimposed components and its construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910616098.6A CN110409492A (en) | 2019-07-09 | 2019-07-09 | A multi-structure combined assembled pipe gallery with superimposed components and its construction method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN110409492A true CN110409492A (en) | 2019-11-05 |
Family
ID=68360785
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201910616098.6A Pending CN110409492A (en) | 2019-07-09 | 2019-07-09 | A multi-structure combined assembled pipe gallery with superimposed components and its construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN110409492A (en) |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110748066A (en) * | 2019-11-27 | 2020-02-04 | 山东德建集团有限公司 | A support-free laminated board including truss and truss processing device and method |
| CN111945777A (en) * | 2020-08-21 | 2020-11-17 | 福建荣冠环境建设集团有限公司 | Strengthen many storehouses of waterproof type utility tunnel |
| CN112031027A (en) * | 2020-09-30 | 2020-12-04 | 福州大学 | UHPC-RC combined overlapped assembly type comprehensive pipe gallery structure and construction method thereof |
| CN115354692A (en) * | 2022-09-20 | 2022-11-18 | 中南大学 | Modular underground comprehensive pipe gallery ventilation opening and assembling method thereof |
| CN116122190A (en) * | 2023-04-13 | 2023-05-16 | 山西建投建筑产业有限公司 | Construction structure and construction process for assembled integral multi-cabin drainage box culvert |
Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| ES2394569A1 (en) * | 2010-03-10 | 2013-02-01 | Prefabricados Tecnyconta S.L. | Method for the construction of lower steps and lower step built with said method (Machine-translation by Google Translate, not legally binding) |
| CN106245674A (en) * | 2016-08-01 | 2016-12-21 | 中建五局第三建设有限公司 | Hollow wallboard mixed prefabricated assembly type comprehensive pipe gallery and construction method thereof |
| CN206052777U (en) * | 2016-08-31 | 2017-03-29 | 长沙远大住宅工业集团股份有限公司 | Overlapping assembled underground pipe gallery wallboard positioner |
| CN207348095U (en) * | 2017-10-25 | 2018-05-11 | 湖南远大工程设计有限公司 | The special bearing diagonal component of piping lane |
| CN108755758A (en) * | 2018-07-10 | 2018-11-06 | 上海二十冶建设有限公司 | The construction method of full prefabrication and assembly construction superposed type empty stomach wallboard underground pipe gallery |
| CN109056815A (en) * | 2018-10-22 | 2018-12-21 | 中建科技有限公司 | Pipe gallery construction method |
| CN208501735U (en) * | 2018-07-20 | 2019-02-15 | 中盈远大(常州)装配式建筑有限公司 | Prefabricated piping lane |
| CN109403373A (en) * | 2018-01-26 | 2019-03-01 | 中铁四局集团建筑工程有限公司 | A kind of splitting method of superimposed assembled pipe gallery |
| CN210529752U (en) * | 2019-07-09 | 2020-05-15 | 中铁三局集团建筑安装工程有限公司 | Contain coincide component multi-structure combination assembled piping lane |
-
2019
- 2019-07-09 CN CN201910616098.6A patent/CN110409492A/en active Pending
Patent Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| ES2394569A1 (en) * | 2010-03-10 | 2013-02-01 | Prefabricados Tecnyconta S.L. | Method for the construction of lower steps and lower step built with said method (Machine-translation by Google Translate, not legally binding) |
| CN106245674A (en) * | 2016-08-01 | 2016-12-21 | 中建五局第三建设有限公司 | Hollow wallboard mixed prefabricated assembly type comprehensive pipe gallery and construction method thereof |
| CN206052777U (en) * | 2016-08-31 | 2017-03-29 | 长沙远大住宅工业集团股份有限公司 | Overlapping assembled underground pipe gallery wallboard positioner |
| CN207348095U (en) * | 2017-10-25 | 2018-05-11 | 湖南远大工程设计有限公司 | The special bearing diagonal component of piping lane |
| CN109403373A (en) * | 2018-01-26 | 2019-03-01 | 中铁四局集团建筑工程有限公司 | A kind of splitting method of superimposed assembled pipe gallery |
| CN108755758A (en) * | 2018-07-10 | 2018-11-06 | 上海二十冶建设有限公司 | The construction method of full prefabrication and assembly construction superposed type empty stomach wallboard underground pipe gallery |
| CN208501735U (en) * | 2018-07-20 | 2019-02-15 | 中盈远大(常州)装配式建筑有限公司 | Prefabricated piping lane |
| CN109056815A (en) * | 2018-10-22 | 2018-12-21 | 中建科技有限公司 | Pipe gallery construction method |
| CN210529752U (en) * | 2019-07-09 | 2020-05-15 | 中铁三局集团建筑安装工程有限公司 | Contain coincide component multi-structure combination assembled piping lane |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110748066A (en) * | 2019-11-27 | 2020-02-04 | 山东德建集团有限公司 | A support-free laminated board including truss and truss processing device and method |
| CN111945777A (en) * | 2020-08-21 | 2020-11-17 | 福建荣冠环境建设集团有限公司 | Strengthen many storehouses of waterproof type utility tunnel |
| CN111945777B (en) * | 2020-08-21 | 2022-02-22 | 福建荣冠环境建设集团有限公司 | Strengthen many storehouses of waterproof type utility tunnel |
| CN112031027A (en) * | 2020-09-30 | 2020-12-04 | 福州大学 | UHPC-RC combined overlapped assembly type comprehensive pipe gallery structure and construction method thereof |
| CN115354692A (en) * | 2022-09-20 | 2022-11-18 | 中南大学 | Modular underground comprehensive pipe gallery ventilation opening and assembling method thereof |
| CN116122190A (en) * | 2023-04-13 | 2023-05-16 | 山西建投建筑产业有限公司 | Construction structure and construction process for assembled integral multi-cabin drainage box culvert |
| CN116122190B (en) * | 2023-04-13 | 2023-06-27 | 山西建投建筑产业有限公司 | Construction structure and construction process for assembled integral multi-cabin drainage box culvert |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110409492A (en) | A multi-structure combined assembled pipe gallery with superimposed components and its construction method | |
| CN101694110B (en) | Beam-column joint connection structure and its construction method | |
| CN105089178B (en) | A kind of pre-splicing Standard formula building of prefabricated steel reinforced concrete shear walls | |
| CN204826308U (en) | Structure assembly type structure is pieced together in advance to prefabricated shaped steel concrete shear force wall | |
| CN108775084B (en) | Steel-concrete composite prefabricated beam and prefabricated column connection structure and construction method | |
| CN108612315A (en) | A kind of assembled mixed structure Frame-Shear Wall building system and construction method | |
| CN107191000A (en) | The temporary support of telescopic in height regulation reinforces combination steel construction | |
| CN207017483U (en) | The full precast shear wall structural system of regenerative steel skeleton | |
| CN107654021A (en) | A kind of assembling prefabricated reinforced concrete column and assembled combination frame building system | |
| CN208251372U (en) | A kind of assembled steel reinforced concrete shear force wall | |
| CN103122691A (en) | Tower crane standard knot bearing upper air supporting formwork steel platform structure and construction method | |
| CN110359487A (en) | A kind of fabricated construction side wall prefabricated component and its with arch sheet connecting structure | |
| CN216042835U (en) | A layering device for a high-rise frame structure with lightweight wall panels | |
| CN213204915U (en) | Overweight overhanging suspended component supporting system of super high-rise residential conversion layer | |
| CN210737607U (en) | A hang braced system for reverse construction method beam slab construction | |
| CN211421637U (en) | A connection structure of a prefabricated gutter | |
| CN111663566A (en) | Underground cylindrical reinforced concrete combined outer wall structure and construction method | |
| CN111519659A (en) | Integrated comprehensive pipe gallery | |
| CN112960566B (en) | Construction method of built-in tower crane of super high-rise building | |
| CN212224168U (en) | A double-sided superimposed guide wall | |
| CN209686923U (en) | Round tube combined support device and steel construction temporary construction support device | |
| CN210529752U (en) | Contain coincide component multi-structure combination assembled piping lane | |
| CN207122021U (en) | Assembled bolt connection concrete-filled steel tube shear wall | |
| CN110258642A (en) | A kind of open-cut composite assembly underground structure and its construction method | |
| CN218479532U (en) | Assembled post-cast strip closing device |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191105 |