CN210712964U - Bilateral-shaped basement shear wall post-cast strip plugging member - Google Patents

Bilateral-shaped basement shear wall post-cast strip plugging member Download PDF

Info

Publication number
CN210712964U
CN210712964U CN201921245527.5U CN201921245527U CN210712964U CN 210712964 U CN210712964 U CN 210712964U CN 201921245527 U CN201921245527 U CN 201921245527U CN 210712964 U CN210712964 U CN 210712964U
Authority
CN
China
Prior art keywords
precast slab
wall
shaped
aluminium
stupefied
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921245527.5U
Other languages
Chinese (zh)
Inventor
厉天数
张建忠
吴刚
洪佳杰
陈建峰
章国胜
曹克文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Xinsheng Construction Group Co ltd
Original Assignee
Zhejiang Xinsheng Construction Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Xinsheng Construction Group Co ltd filed Critical Zhejiang Xinsheng Construction Group Co ltd
Priority to CN201921245527.5U priority Critical patent/CN210712964U/en
Application granted granted Critical
Publication of CN210712964U publication Critical patent/CN210712964U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Building Environments (AREA)

Abstract

The utility model discloses a bilateral-shaped basement shear wall post-cast strip plugging member, which comprises an outer wall precast slab, an inner wall combined slab and a split bolt used for connecting the outer wall precast slab and the inner wall combined slab, wherein the outer wall precast slab comprises a C-shaped precast slab, an internal thread sleeve arranged at the inner side of the C-shaped precast slab, a positioning bulge arranged at the top of the C-shaped precast slab and a positioning groove arranged at the bottom of the C-shaped precast slab and matched with the positioning bulge; interior wall compoboard includes aluminum plate, aluminium stupefied frame and aluminium stupefied crosspiece, aluminium stupefied frame constitutes the compoboard skeleton jointly with aluminium stupefied crosspiece, aluminum plate fixes and sets up on the compoboard skeleton, aluminium stupefied crosspiece is last to be equipped with the preformed hole in the position department that corresponds with the internal thread sleeve. The utility model has the advantages that: the basement shear wall post-cast strip plugging member is composed of an outer wall prefabricated plate, split bolts and an inner wall combined plate, and is simple in structure, easy to manufacture and convenient to construct.

Description

Bilateral-shaped basement shear wall post-cast strip plugging member
Technical Field
The utility model relates to a building engineering basement structure field especially relates to a bilateral basement shear force wall post-cast strip shutoff component of stereotyping.
Background
With the continuous development of the building industry, the number of post-cast strips penetrating downwards from the shear wall of a middle-high basement of an ultra-long structure is more and more, the post-cast strips are temporary construction joints reserved at corresponding positions of a foundation slab, a wall and a beam according to design or construction specification requirements in order to prevent harmful cracks of a cast-in-place concrete structure due to uneven temperature and shrinkage in the building construction, the structure is temporarily divided into a plurality of parts, the construction joints are poured and tamped after a plurality of times after the internal shrinkage of the components, and the structure is connected into a whole. At present, in the construction process of a basement, in order to avoid shrinkage and cracking of a shear wall of the basement after concrete is poured, a post-cast strip is usually arranged on a wall body of the shear wall, and the traditional method for sealing the post-cast strip of the shear wall is that seven groups of arc-shaped brick moulding beds are used for sealing and retaining soil at the outer side of an outer wall at the post-cast strip and are used as a side template for formal plugging of the post-cast strip, and a single-side formwork is required to be adopted for a side template in the city of the post-cast strip. Because the number of layers of the basement reaches 3-4 layers at present, the layer height is higher, the masonry brick moulding bed keeps soil, the height is higher, reinforcement needs to be planted on the basement shear walls on the two sides of the post-cast strip, the stability of the brick moulding bed is difficult to guarantee, the construction process is complex, the construction period is long, and when the concrete is poured on the post-cast strip, one side of the post-cast strip in a room needs to be supported by a single face, the construction difficulty is high, and the quality is difficult to guarantee. Moreover, the safety is difficult to be ensured, and safety accidents are easy to happen.
SUMMERY OF THE UTILITY MODEL
In order to solve the problem that exists among the prior art, the utility model provides a reasonable in structure, design benefit's basement shear force wall post-cast strip shutoff component of bilateral design.
The technical scheme of the utility model as follows:
a bilateral-shaped basement shear wall post-cast strip blocking member is characterized by comprising an outer wall precast slab, an inner wall combined slab and a split bolt for connecting the outer wall precast slab and the inner wall combined slab, wherein the outer wall precast slab comprises a C-shaped precast slab, an internal thread sleeve arranged on the inner side of the C-shaped precast slab, a positioning bulge arranged at the top of the C-shaped precast slab and a positioning groove arranged at the bottom of the C-shaped precast slab and matched with the positioning bulge; interior wall compoboard includes aluminum plate, aluminium stupefied frame and aluminium stupefied crosspiece, aluminium stupefied frame constitutes the compoboard skeleton jointly with aluminium stupefied crosspiece, aluminum plate is fixed to be set up on the compoboard skeleton, aluminium stupefied crosspiece is gone up and is being equipped with the preformed hole in the position department that corresponds with the internal thread sleeve, to stay bolt one end and internal thread sleeve fixed connection, the other end passes the preformed hole and fixes on the interior wall compoboard through the nut.
The bilateral-shaped basement shear wall post-cast strip plugging member is characterized in that the cross section of the C-shaped precast slab is C-shaped, and criss-cross distribution ribs are arranged inside the C-shaped precast slab and used for improving the strength of the precast slab.
The bilateral-shaped basement shear wall post-cast strip plugging member is characterized in that a water stopping groove is formed in one side, attached to a shear wall, of the C-shaped precast slab, and a water stopping rubber strip is arranged in the water stopping groove.
The bilateral-shaped basement shear wall post-cast strip plugging member is characterized in that hanging rings are arranged on two sides of the top of a C-shaped precast slab, and hanging ring grooves are formed in the positions, corresponding to the hanging rings, of the bottom of the C-shaped precast slab.
The bilateral-shaped basement shear wall post-cast strip plugging member is characterized in that the split bolt comprises a double-headed screw and a nut, and a water-stopping steel sheet is arranged in the middle of the double-headed screw.
The utility model has the advantages that:
1) the basement shear wall post-cast strip plugging member is composed of an outer wall prefabricated plate, split bolts and an inner wall combined plate, and is simple in structure, easy to manufacture and convenient to construct.
2) The internal thread sleeve is preset on the outer wall prefabricated plate, and the split bolt and the inner wall composite board are connected in a split mode, so that the connection is convenient, the structural stability is high, a semi-circular brick-built well is used as a retaining wall instead of a post-cast strip, the waterproof and backfill operation process of the post-cast strip is not affected, the backfill quality and the waterproof construction quality are ensured, and the construction period of the basement outer wall is shortened.
3) The outer wall prefabricated slab is manufactured by using the residual concrete in the concrete pouring process of the basement structure, so that the waste of materials is reduced, and the inner wall composite slab can be repeatedly used and meets the green construction requirement advocated by the nation.
Drawings
FIG. 1 is the construction drawing of the whole building of the utility model;
FIG. 2 is a schematic view of the overall structure of the present invention;
FIG. 3 is a schematic view of the three-dimensional structure of the outer wall prefabricated slab of the present invention;
FIG. 4 is a schematic view of the plane structure of the prefabricated panel of the present invention;
fig. 5 is a schematic structural view of the inner wall composite board of the present invention;
FIG. 6 is a schematic view of the split bolt structure of the present invention;
in the figure: 1-exterior wall precast slab, 11-C type precast slab, 12-positioning protrusion, 13-positioning groove, 14-water stop rubber strip, 15-lifting ring, 16-lifting ring groove, 17-internal thread sleeve, 2-split bolt, 21-double-head screw, 22-thread, 23-water stop steel sheet, 24-nut, 3-interior wall composite board, 31 aluminum plate, 32-aluminum ridge crosspiece, 33 preformed hole, 34-aluminum ridge frame and 4-shear wall.
Detailed Description
The invention is further described with reference to the accompanying drawings.
As shown in fig. 1 to 6, the double-side-shaped basement shear wall post-cast strip plugging member comprises an outer wall precast slab 1, a C-shaped precast slab 11, a positioning protrusion 12, a positioning groove 13, a water stop rubber strip 14, a hanging ring 15, a hanging ring groove 16, an internal thread sleeve 17, a split bolt 2, a double-headed screw 21, a thread 22, a water stop steel sheet 23, a nut 24, an inner wall composite slab 3, an aluminum plate 31, an aluminum ridge crosspiece 32, a reserved hole 33 and an aluminum ridge frame 34.
Example (b):
the bilateral-shaped basement shear wall post-cast strip plugging member comprises an outer wall prefabricated plate 1, an inner wall composite plate 3 and a split bolt 2 arranged between the outer wall prefabricated plate 1 and the inner wall composite plate 3, wherein the outer wall prefabricated plate 1 and the inner wall composite plate can be fixed at the positions of two sides of a shear wall 4 through the split bolt 2.
The outer wall precast slab is arranged on the outer side of the shear wall of the basement and comprises a C-shaped precast slab 11, a strip-shaped protrusion 12, a strip-shaped groove 13, a water stop rubber strip 14, a hanging ring 15, a hanging ring groove 16 and a sleeve 17. The cross section of the C-shaped precast slab 11 is C-shaped, and criss-cross distribution ribs are arranged inside the C-shaped precast slab 11 with two side surfaces forming a slope of 45 degrees and used for improving the strength of the precast slab; the positioning bulge 12 is of a strip structure, is arranged at the upper end of the C-shaped precast slab 11, is cast in situ together with the C-shaped precast slab 11, and is mainly used for effective centering connection of the upper C-shaped precast slab 11 and the lower C-shaped precast slab 11; the lower end of the C-shaped precast slab 11 corresponding to the positioning protrusion 12 is provided with a positioning groove 13 for matching with the upper positioning protrusion 12 of another C-shaped precast slab 11, so that the upper and lower C-shaped precast slabs 11 are effectively and fixedly connected.
The water stop rubber strip 14 is arranged in a water stop groove on the contact surface of the C-shaped precast slab 11 and the outer side of the shear wall, and is used for preventing water seepage of the vertical side surface when backfilling and preventing slurry leakage when concrete is poured in a post-pouring zone. The hanging rings 15 are composed of HPB300 with the diameter of 8mm, and are vertically embedded in two sides of the upper part of the C-shaped precast slab 11 in the longitudinal direction, so that the hoisting and installation are convenient. And a hanging ring groove 16 is arranged at the bottom of the C-shaped precast slab 11, and the position, size and depth of the hanging ring groove 16 are matched with those of the hanging ring 15. The four internal thread sleeves 17 are uniformly and symmetrically pre-arranged on the middle surface of the inner side of the C-shaped precast slab 11, so that the outer wall precast slab 1 can be conveniently and fixedly connected integrally.
The inner wall composite board 3 is composed of an aluminum plate 31, an aluminum ridge frame, an aluminum ridge crosspiece and a preformed hole 33. The aluminum plate 31 is matched with the outer wall prefabricated plate 1 in size, the thickness is preferably 15-30mm, and the phenomenon of mold expansion caused when concrete is poured between the inner wall aluminum alloy composite plate 3 and the outer wall prefabricated plate 1 is avoided. The total of the 4 aluminum corrugated frames 34 and the 2 aluminum corrugated crosspieces 32 is six, 60 x 80 is adopted, the aluminum corrugated with the wall thickness of 6-8mm (the inner wall composite board 3 adopts the aluminum corrugated frames to keep the vertical state without the help of external force, and is convenient for construction), the 4 aluminum corrugated frames 34 are welded and arranged on the outer side of the aluminum plate 31, and the 2 aluminum corrugated crosspieces 32 are in the middle of the aluminum plate 31, so that the inner wall composite board 3 forms a frame type integral structure with stable stress. The preformed holes 33 are uniformly and symmetrically arranged on the aluminum ridge crosspiece and penetrate through the aluminum plate 31, and the preformed holes 33 mainly serve for being matched with the split bolts 2.
The split bolt 2 is composed of a double-headed screw 21, a nut 24 and a water stop steel sheet 23. The size of the double-threaded screw 21 meets the requirement of being matched with the internal thread sleeve 17, the threads 22 are arranged at two ends of the double-threaded screw 21, and the length of the threads 22 meets the requirement of site construction; the water stop steel sheet 23 is arranged in the middle of the double-headed screw 21 and is used for preventing water in the concrete from permeating along the direction of the double-headed screw 21. The nuts 24 are matched with the two ends of the double-head screw 21 for use, and are used for oppositely pulling and fixing the inner wall composition board together.

Claims (5)

1. The double-side-shaped basement shear wall post-cast strip blocking member is characterized by comprising an outer wall precast slab (1), an inner wall combined slab (3) and a split bolt (2) for connecting the outer wall precast slab (1) and the inner wall combined slab (3), wherein the outer wall precast slab (1) comprises a C-shaped precast slab (11), an internal thread sleeve (17) arranged on the inner side of the C-shaped precast slab (11), a positioning bulge (12) arranged at the top of the C-shaped precast slab (11) and a positioning groove (13) arranged at the bottom of the C-shaped precast slab (11) and matched with the positioning bulge (12); interior wall compoboard (3) include aluminum plate (31), aluminium stupefied frame (34) and aluminium stupefied crosspiece (32), aluminium stupefied frame (34) constitute the compoboard skeleton jointly with aluminium stupefied crosspiece (32), aluminum plate (31) are fixed to be set up on the compoboard skeleton, aluminium stupefied crosspiece (32) are gone up and are being equipped with preformed hole (33) with internal thread sleeve (17) correspondence position department, to stay bolt (2) one end and internal thread sleeve (17) fixed connection, the other end passes preformed hole (33) and fixes on interior wall compoboard (3) through nut (24).
2. The plugging member for the rear pouring belt of the bilateral-shaped shear wall of the basement according to claim 1, wherein the cross section of the C-shaped precast slab (11) is C-shaped, and criss-cross distribution ribs are arranged inside the C-shaped precast slab (11) to improve the strength of the precast slab.
3. The plugging member for the late poured band of the shear wall of the bilateral fixed basement according to claim 1, wherein a water stopping groove is formed in one side of the C-shaped precast slab (11) which is attached to the shear wall (4), and a water stopping rubber strip (14) is arranged in the water stopping groove.
4. The double-sided shaped basement shear wall post-cast strip blocking member according to claim 1, wherein hanging rings (15) are arranged at two sides of the top of the C-shaped precast slab (11), and hanging ring grooves (16) are arranged at the bottom of the C-shaped precast slab (11) at positions corresponding to the hanging rings (15).
5. The double-sided shaped basement shear wall post-cast strip blocking member according to claim 1, wherein the split bolt (2) comprises a double-threaded screw (21) and a nut (24), and a water stop steel sheet (23) is arranged in the middle of the double-threaded screw (21).
CN201921245527.5U 2019-08-02 2019-08-02 Bilateral-shaped basement shear wall post-cast strip plugging member Active CN210712964U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921245527.5U CN210712964U (en) 2019-08-02 2019-08-02 Bilateral-shaped basement shear wall post-cast strip plugging member

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921245527.5U CN210712964U (en) 2019-08-02 2019-08-02 Bilateral-shaped basement shear wall post-cast strip plugging member

Publications (1)

Publication Number Publication Date
CN210712964U true CN210712964U (en) 2020-06-09

Family

ID=70966413

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921245527.5U Active CN210712964U (en) 2019-08-02 2019-08-02 Bilateral-shaped basement shear wall post-cast strip plugging member

Country Status (1)

Country Link
CN (1) CN210712964U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112112295A (en) * 2020-09-08 2020-12-22 中建四局第五建筑工程有限公司 Reinforcing construction method for post-cast strip of post-sealed outer wall

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112112295A (en) * 2020-09-08 2020-12-22 中建四局第五建筑工程有限公司 Reinforcing construction method for post-cast strip of post-sealed outer wall

Similar Documents

Publication Publication Date Title
US7882669B2 (en) Composite concrete shear wall for heat insulation
WO2017197853A1 (en) Insulation precast wall and prefabricated building
CN108360712A (en) A kind of assembled steel reinforced concrete shear force wall and its construction method
CN108396711B (en) Detachable gravity dam and construction and dismantling method thereof
CN112127356A (en) Assembled grid underground continuous wall of dry-type connection
CN108951840B (en) Method for constructing arc-shaped outer wall of basement based on single-side formwork support of shaped support
CN113944240A (en) Fixed prefabricated structure for sealing basement outer wall post-cast strip in advance and construction method thereof
CN111663681A (en) Assembled wall body connecting structure and construction method thereof
CN210712964U (en) Bilateral-shaped basement shear wall post-cast strip plugging member
CN108643133B (en) Detachable arch dam and construction and dismantling method thereof
CN112112295A (en) Reinforcing construction method for post-cast strip of post-sealed outer wall
CN209989847U (en) Shear force wall post-cast strip prefabricated plate closing device
CN216787229U (en) Basement outer wall post-cast strip assembled shutoff steel sheet structure
CN214220178U (en) Prefabricated disassembly-free side mold and adjustable supporting system for one-step molding of floor water retaining strip
CN212452765U (en) Two-in-one underground pipe gallery structure
CN210002441U (en) Box-type top plate structure for large-span urban tunnel
CN209798958U (en) Pouring system for drainage ditch of bottom plate post-cast strip and shaping hanging die for drainage ditch
CN112324009A (en) Precast concrete hollow heat-insulation wall structure and construction process
CN105839824B (en) Shed deckhead construction method
CN208201923U (en) A kind of armpit Angle formwork overlapping assembled comprehensive pipe gallery structure
CN221001655U (en) Retaining member for masonry and pouring of filled wall constructional column
CN214144234U (en) Precast concrete hollow heat-insulation wall structure
CN216340279U (en) Prefabricated form removal-free concrete hollow wall structure
CN220318582U (en) Well wall construction template of municipal administration tube well
CN113958033A (en) Construction method of assembled prefabricated wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A kind of sealing component of basement shear wall with post cast strip

Effective date of registration: 20200819

Granted publication date: 20200609

Pledgee: Industrial and Commercial Bank of China Limited Hangzhou Banshan sub branch

Pledgor: ZHEJIANG XINSHENG CONSTRUCTION GROUP Co.,Ltd.

Registration number: Y2020330000621

PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20211026

Granted publication date: 20200609

Pledgee: Industrial and Commercial Bank of China Limited Hangzhou Banshan sub branch

Pledgor: ZHEJIANG XINSHENG CONSTRUCTION GROUP Co.,Ltd.

Registration number: Y2020330000621

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A bilateral shaped post cast strip plugging member for basement shear wall

Effective date of registration: 20211111

Granted publication date: 20200609

Pledgee: Industrial and Commercial Bank of China Limited Hangzhou Banshan sub branch

Pledgor: ZHEJIANG XINSHENG CONSTRUCTION GROUP Co.,Ltd.

Registration number: Y2021330002221

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20221201

Granted publication date: 20200609

Pledgee: Industrial and Commercial Bank of China Limited Hangzhou Banshan sub branch

Pledgor: ZHEJIANG XINSHENG CONSTRUCTION GROUP Co.,Ltd.

Registration number: Y2021330002221

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A kind of sealing component with double side shaped post cast strip for basement shear wall

Effective date of registration: 20221214

Granted publication date: 20200609

Pledgee: Industrial and Commercial Bank of China Limited Hangzhou Banshan sub branch

Pledgor: ZHEJIANG XINSHENG CONSTRUCTION GROUP Co.,Ltd.

Registration number: Y2022330003664

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20231204

Granted publication date: 20200609

Pledgee: Industrial and Commercial Bank of China Limited Hangzhou Banshan sub branch

Pledgor: ZHEJIANG XINSHENG CONSTRUCTION GROUP Co.,Ltd.

Registration number: Y2022330003664

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A double-sided fixed post pouring sealing component for basement shear walls

Effective date of registration: 20231222

Granted publication date: 20200609

Pledgee: Industrial and Commercial Bank of China Limited Hangzhou Banshan sub branch

Pledgor: ZHEJIANG XINSHENG CONSTRUCTION GROUP Co.,Ltd.

Registration number: Y2023330003083

PE01 Entry into force of the registration of the contract for pledge of patent right