CN206090817U - Steel construction assemblyization house - Google Patents
Steel construction assemblyization house Download PDFInfo
- Publication number
- CN206090817U CN206090817U CN201621026760.0U CN201621026760U CN206090817U CN 206090817 U CN206090817 U CN 206090817U CN 201621026760 U CN201621026760 U CN 201621026760U CN 206090817 U CN206090817 U CN 206090817U
- Authority
- CN
- China
- Prior art keywords
- steel
- basic part
- wall body
- floor
- house
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Building Environments (AREA)
Abstract
The utility model provides a steel construction assemblyization house. Steel construction assemblyization house includes steel structural framework, wall body board and floor, the wall body board reaches the floor is all located steel structural framework, steel structural framework includes steel basic part and steel connecting piece, the steel basic part passes through the steel connecting piece is connected, the steel basic part reaches steel connector assembly forms steel construction assemblyization house's skeleton texture. The utility model discloses a steel construction assemblyization house adopts steel structural framework, wall body board and floor separately prefabricated by the mill, has reduced work post and workman's quantity, has improved construction speed and has reduced engineering cost, the housing industrialization process has been promoted.
Description
Technical field
This utility model is related to building field, more particularly to a kind of steel construction assembling house.
Background technology
At present owned building and large equipment base are all tied up muscle, cast in situs, scene and are built by laying bricks or stones with live formwork, scene
Form operation.The work post being related to is more, and workload is little, long in time limit, and various materials and water resource waste are serious, cause cost significantly
Improve, impact of the noise, airborne dust produced by cast-in-place operation to environment is also very big.
Utility model content
Tie up muscle, cast in situs and cause work post many to solve existing building scene formwork, scene, workload is little, long in time limit,
Various materials and water resource waste are serious, and cost is increased substantially, and the noise produced by cast-in-place operation is big, shadow of the airborne dust to environment
The big technical problem of sound, this utility model provides a kind of steel structure frame, body of wall plate body and floor and separates by prefabrication, reduces
Work post and number of workers, improve speed of application, reduce construction costs, the steel construction assembling that noise is little, airborne dust without generation is few
Change house.
The storing with external circulating device that this utility model is provided includes steel structure frame, ash wall body plate and floor, the wall
Body plate and the floor are located at the steel structure frame, and the steel structure frame includes steel basic part and steel fastener, described
Steel basic part is connected by the steel fastener, and the steel basic part and the steel fastener are assembled to form the steel construction assembling
Change the framing structure of house.
In a kind of preferred embodiment of the steel construction assembling house that this utility model is provided, the ash wall body plate is steam pressure
Aerated concrete wall plate.
In a kind of preferred embodiment of the steel construction assembling house that this utility model is provided, the floor adds for steam pressure
Gas concrete slab.
In a kind of preferred embodiment of the steel construction assembling house that this utility model is provided, the steel structure frame is also
Including the integrated basis of low layer steel building, the low layer steel building is integrated basic located at the steel construction assembling house
Opposing floor portion.
In a kind of preferred embodiment of the steel construction assembling house that this utility model is provided, the steel basic part includes
Upright steel basic part, horizontal steel basic part and roof steel basic part, pass through the horizontal base steel between the upright steel basic part
Plinth part and the steel fastener connect, and are connected by the steel fastener between the horizontal steel basic part, the roof base steel
Plinth part is connected by the steel fastener with the upright steel basic part.
In a kind of preferred embodiment of the steel construction assembling house that this utility model is provided, the ash wall body plate is located at institute
Upright steel basic part is stated, the floor is located at the horizontal steel basic part.
Relative to prior art, steel construction assembling house of the present utility model has following beneficial effect:
Separated by prefabrication using steel structure frame, ash wall body plate and floor, reduce work post and number of workers, improve
Speed of application reduces construction costs;Promote Process of Housing Industrialization.Live formwork, scene is avoided to tie up muscle, cast in situs shape
Formula operation, the work post being related to is few, and workload is big, short time limit, and various materials and water resource waste are few, and cost is greatly lowered, existing
Pour noise produced by operation, airborne dust few.Batch production makes, and assembled in situ dry construction prevents resource, waste of material, has
Sharp environmental conservation, material-saving saves artificial, lowers labor intensity, and speed of application is fast, reduces construction costs.
Description of the drawings
Technical scheme in order to be illustrated more clearly that this utility model embodiment, below will be to needed for embodiment description
The accompanying drawing to be used is briefly described, it should be apparent that, drawings in the following description are only some realities of the present utility model
Example is applied, for those of ordinary skill in the art, on the premise of not paying creative work, can be with according to these accompanying drawings
Other accompanying drawings are obtained, wherein:
Fig. 1 is the structural representation of the preferred embodiment of steel construction assembling house one that this utility model is provided.
Specific embodiment
Below in conjunction with the accompanying drawing in this utility model embodiment, the technical scheme in this utility model embodiment is carried out
Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of the present utility model, rather than whole
Embodiment.Based on the embodiment in this utility model, those of ordinary skill in the art are not under the premise of creative work is made
The all other embodiment for being obtained, belongs to the scope of this utility model protection.
Fig. 1 is referred to, is the structural representation of the preferred embodiment of steel construction assembling house one that this utility model is provided.
The steel construction assembling house 1 includes steel structure frame 11, ash wall body plate 12 and floor 13.The ash wall body plate 12 and
The floor 13 is located at the steel structure frame 11.The ash wall body plate 12 is steam-pressing aero-concrete ash wall body plate.The floor
13 is autoclaved aerated concrete slab.
The steel structure frame 11 includes steel basic part 111, steel fastener 112 and the integrated basis of low layer steel building
113.The steel basic part 111 is connected by the steel fastener 112, and the steel basic part 111 and the steel fastener 112 are filled
With the framing structure for forming the steel construction assembling house 1.The low layer steel building integrated basic 113 is located at the steel
The opposing floor portion of Standard house 1.
The steel basic part 111 includes upright steel basic part 1111, horizontal steel basic part 1112 and roof steel basic part
1113.Connected by the horizontal steel basic part 1112 and the steel fastener 112 between the upright steel basic part 1111, institute
State and connected by the steel fastener 112 between horizontal steel basic part 1112, the roof steel basic part 1113 passes through the steel
Connector 112 is connected with the upright steel basic part 1111.
The ash wall body plate 12 is located at the upright steel basic part 1111, and the floor 13 is located at the horizontal steel basic part
1112。
Steel construction assembling house 1 of the present utility model has following beneficial effect:
Separated by prefabrication using steel structure frame 11, ash wall body plate 12 and floor 13, reduce work post and number of workers,
Improve speed of application and reduce construction costs;Promote Process of Housing Industrialization.Live formwork, scene is avoided to tie up muscle, scene
Form operation is poured, the work post being related to is few, workload is big, short time limit, various materials and water resource waste are few, and cost significantly drops
Low, the noise, airborne dust produced by cast-in-place operation is few.Batch production makes, assembled in situ dry construction, prevents resource, material wave
Take, favorable environment protection, material-saving saves artificial, lowers labor intensity, and speed of application is fast, reduces construction costs.
Embodiment of the present utility model is the foregoing is only, the scope of the claims of the present utility model is not thereby limited, it is every
The equivalent structure made using this utility model description and accompanying drawing content or equivalent flow conversion, or be directly or indirectly used in
Other related technical fields, are included in the same manner in scope of patent protection of the present utility model.
Claims (6)
1. a kind of steel construction assembling house, it is characterised in that including steel structure frame, ash wall body plate and floor, the ash wall body plate
And the floor is located at the steel structure frame, the steel structure frame includes steel basic part and steel fastener, the base steel
Plinth part is connected by the steel fastener, and the steel basic part and the steel fastener are assembled to form the steel construction assembling and live
The framing structure of residence.
2. steel construction assembling house according to claim 1, it is characterised in that the ash wall body plate is steam pressurized coagulation
Native ash wall body plate.
3. steel construction assembling house according to claim 1, it is characterised in that the floor is steam-pressing aero-concrete
Plate.
4. steel construction assembling house according to claim 1, it is characterised in that the steel structure frame also includes low layer
The integrated basis of steel building, the integrated basic relative bottom located at the steel construction assembling house of the low layer steel building
Portion.
5. steel construction assembling house according to claim 1, it is characterised in that the steel basic part includes upright base steel
Plinth part, horizontal steel basic part and roof steel basic part, by the horizontal steel basic part and institute between the upright steel basic part
Steel fastener connection is stated, is connected by the steel fastener between the horizontal steel basic part, the roof steel basic part passes through
The steel fastener is connected with the upright steel basic part.
6. steel construction assembling house according to claim 5, it is characterised in that the ash wall body plate is located at the upright steel
Basic part, the floor is located at the horizontal steel basic part.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621026760.0U CN206090817U (en) | 2016-08-31 | 2016-08-31 | Steel construction assemblyization house |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621026760.0U CN206090817U (en) | 2016-08-31 | 2016-08-31 | Steel construction assemblyization house |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206090817U true CN206090817U (en) | 2017-04-12 |
Family
ID=58475068
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621026760.0U Expired - Fee Related CN206090817U (en) | 2016-08-31 | 2016-08-31 | Steel construction assemblyization house |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206090817U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107419801A (en) * | 2017-04-17 | 2017-12-01 | 浙江普天集成房屋有限公司 | A kind of assembled individual layer ALC wood connecting building and its construction method and ALC board manufacturing methods |
-
2016
- 2016-08-31 CN CN201621026760.0U patent/CN206090817U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107419801A (en) * | 2017-04-17 | 2017-12-01 | 浙江普天集成房屋有限公司 | A kind of assembled individual layer ALC wood connecting building and its construction method and ALC board manufacturing methods |
CN107419801B (en) * | 2017-04-17 | 2019-11-12 | 浙江普天集成房屋有限公司 | A kind of assembled single layer ALC wood connecting building and its construction method and ALC board manufacturing method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107143034A (en) | A kind of assembly concrete frame structure beam column rigid connection node | |
CN203769239U (en) | Flat artificial stone and curtain wall thereof | |
CN103216024A (en) | Self-heat-preservation mortar-free block masonry shear wall system and construction method thereof | |
CN105003020A (en) | Ceramsite concrete metal net rack light wallboard and splicing structure thereof | |
CN108532796A (en) | Assembly concrete shear wall and face inner beam rigid connection node and construction method | |
CN206090817U (en) | Steel construction assemblyization house | |
CN107747378A (en) | The body composite board processing method of Fast Installation heat insulation decorative load-bearing one | |
CN204919968U (en) | Ceramsite concrete metal rack light weight wallboard | |
CN206090606U (en) | Integrated basis of low layer steel construction building | |
CN203296209U (en) | Self-insulation mortarless block masonry shear wall system | |
CN207296087U (en) | A kind of Prefabricated outer wall non-load bearing wall standard component | |
CN206016010U (en) | A kind of lap jointing type contignation | |
CN206205139U (en) | A kind of prefabricated composite construction parapet | |
CN109296074A (en) | A kind of assembly concrete column beam connecting node | |
CN204899034U (en) | Prefabricated wall post | |
CN203247750U (en) | Assembled type cement brick | |
CN207032474U (en) | A kind of assembly concrete frame structure beam column rigid connection node | |
CN208294238U (en) | A kind of parapeted prefabricated assembled Assembled surrounding wall of tool | |
CN207079788U (en) | A kind of floor quick structure for assembling | |
CN206408743U (en) | A kind of assembly concrete node | |
CN201778402U (en) | Waterproof node of horizontal seam of outer wall | |
CN206616695U (en) | A kind of concrete panel and girt strip floor dry type connecting node | |
CN204001337U (en) | Close rib building roof is poured into a mould built-in mould | |
CN204876193U (en) | Precast reinforced concrete shear force wall wallboard | |
CN204691047U (en) | The building block of novel block card |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170412 Termination date: 20170831 |