Prior art keywords
channel body
spigot
rubbish
garbage shaft
rise
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620892601.2U
Other languages
Chinese (zh)
Inventor
王旭杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN201620892601.2U priority Critical patent/CN205976365U/en
Application granted granted Critical
Publication of CN205976365U publication Critical patent/CN205976365U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuse Collection And Transfer (AREA)

Abstract

The utility model discloses a high -rise construction garbage shaft of socket joint formula relates to building construction tool technique neck, including the two double -phase passageway bodies that connect of a plurality of head and the tail, passageway body upper portion is equipped with the fixed bolster, the inside buffer that is equipped with of passageway body, simple structure, convenient to use improves rubbish clearance speed, can rise along with the floor to rise, easy dismounting, safe and reliable reduces environmental pollution.

Description

Spigot-and-socket Construction of High-rise garbage shaft
Technical field
This utility model is related to construction technical field of tools.
Background technology
Now city is mostly based on skyscraper, construct in building work progress due to floor higher, rubbish of constructing Cleaning is inconvenient, and commonly use at present is will to construct refuse collection to ground by construction elevator, because construction elevator wing plate is busier Commonplace, rubbish needs to pile up long period concentration cleaning, does not only take up construction site, brings pollution, impact green to construction environment Civilized construction and airborne dust preventing and treating.Existing Construction of High-rise floor rubbish is cleared using construction elevator or discharging platform, and exist lacks Point:Discharging platform cleaning rubbish easily produces high-altitude and drops phenomenon and dangerous, and construction elevator is typically all that main body is arrived in construction Complete half just start install and also construction elevator usage frequency is higher;Taking manpower increases labour force, the little cleaning for quantity of refuse Once inconvenient, not fast, there is the hidden danger of falling object from high altitude.
Utility model content
The technical problems to be solved in the utility model is for above-mentioned the deficiencies in the prior art, provides a kind of spigot-and-socket high-rise Construction garbage shaft, structure is simple, easy to use, improves garbage-cleaning speed, can rise with floor and raise, easy accessibility, Safe and reliable, reduce environmental pollution.
For solving above-mentioned technical problem, technical solution adopted in the utility model is:Connect two-by-two including some head and the tail Channel body;Channel body top is provided with fixed support;It is provided with buffer unit inside channel body.
Preferably, fixed support includes being fixed on the fixed mount of channel body both sides and is arranged between two fixed mounts Link, fixed mount is vertically arranged with channel body, and fixed mount is provided with fixing hole.
Preferably, fixed support is welded for angle steel.
Preferably, buffer unit includes a cambered plate matching with channel body, cambered plate is arranged below circle The connecting rod of hollow, connecting rod be arranged in the middle of cambered plate along top level line be distributed, the relative both sides of channel body be provided with The corresponding screw of connecting rod, threaded rod passes through screw to enter connecting rod, and cambered plate can be overturn centered on threaded rod.
Preferably, channel body bottom is additionally provided with rubbish pour spout on channel body medial surface, outside rubbish pour spout It is provided with sealing door to be opened/closed.
Preferably, rubbish pour spout is arranged on and buffer unit opposite position.
Preferably, sealing door lower end is connected by hinge with rubbish pour spout lower end, sealing door top is provided with lockhole, rubbish Rubbish pour spout Upper passage body is provided with the lock corresponding with lockhole, and lock may be inserted into lockhole.
Have the beneficial effects that using produced by technique scheme:This utility model structure is simple, easy to use, improves Garbage-cleaning speed, socket fitting type structure, socket joint can be risen with floor and raise, easy accessibility, safe and reliable, reduce environment dirty Dye, buffer unit plays cushioning effect to the object speed that eminence drops, reduce further the rubbish that eminence falls down The dust causing, reduces the pollution to environment.
Brief description
Fig. 1 is the structural representation of one embodiment of this utility model;
Fig. 2 is the assembling schematic diagram of buffer unit and channel body in Fig. 1.
In figure:1st, channel body;2nd, fixed support;3rd, buffer unit;4th, sealing door;2.1st, fixed mount;2.2nd, link; 3.1st, cambered plate;3.2nd, connecting rod.
Specific embodiment
With reference to the accompanying drawings and detailed description this utility model is described in further detail.
As shown in Figure 1-2, be a kind of this utility model spigot-and-socket Construction of High-rise garbage shaft an embodiment, if including The channel body 1 that dry head and the tail connect two-by-two, channel body 1 is the rectangular structure of upper and lower opening, and the suitable for reading of channel body 1 is more than The lower mouth of channel body 1, lower mouth may be inserted into suitable for reading interior, this socket fitting type structure convenient use, simultaneously can be according to different buildings Height select connect channel body 1 number, easy accessibility;Channel body 1 top is provided with fixed support 2, fixed support 2 It is arranged on channel body 1 top, by fixed support 2 is fixed on floor and then channel body 1 is fixing;Channel body 1 Inside is provided with buffer unit 3, and in high-building construction, high-rise rubbish is poured channel body 1 into and directly can be dropped to ground from eminence Face, speed is very fast, falls earthward and can raise a huge cloud of dust, and the setting of buffer unit 3 can rise to the rubbish sinking speed in passage To cushioning effect, reduce the speed that rubbish falls earthward, reduce sand and dust, reduce environmental pollution, realize environmental protection construction.
On every floor, this device is all installed in construction, improves garbage-cleaning speed, reduce environmental pollution.
Fixed support 2 includes being fixed on the fixed mount 2.1 of channel body 1 both sides and is arranged between two fixed mounts 2.1 Link 2.2, fixed mount 2.1 is vertically arranged with channel body 1, and fixed mount 2.1 is provided with fixing hole, on fixed support 2 Fixed mount 2.1 is screwed on floor by fixing hole, arranges link 2.2, on the one hand to fixation between fixed mount 2.1 Frame 2.1 is played a supporting role, and makes total more more stable and stronger, and on the other hand, when fixing, link 2.2 can also be put Put on floor, play a supporting role.
Fixed support 2 is welded for angle steel, and angle steel is sturdy and durable, and material easily obtains.
Buffer unit 3 includes a cambered plate matching with channel body 1 3.1, and cambered plate 3.1 is arranged below in circle Empty connecting rod 3.2, connecting rod 3.2 is arranged on and is distributed along top level line in the middle of cambered plate 3.1, channel body 1 relative two Side is provided with the screw corresponding with connecting rod 3.2, and threaded rod passes through screw to enter connecting rod 3.2, and cambered plate 3.1 can be with threaded rod Centered on overturn, threaded rod can dismount, and when channel body 1 is in orlop, loads onto the rubbish that buffer unit 3 falls to top Rubbish carries out speed-buffering, and cambered plate 3.1 can be pulled down by the channel body 1 being in 2 layers even more than 2 layers by threaded rod, this Sample enables rubbish to pass through center-aisle is smooth rapidly, can also be equipped with buffer unit in certainly all of channel body 1 3;During use after exceeding rubbish and fall, the both sides of cambered plate 3.1 can be impacted by rubbish, and cambered plate 3.1 side can downwards, phase To opposite side can be upwards so that rubbish passes through.
Channel body 1 bottom is additionally provided with rubbish pour spout on channel body 1 medial surface, and rubbish pour spout is externally provided with can be opened The sealing door 4 closing, rubbish pour spout facilitates intermediate floor to dump rubbish, when channel body 1 one by one end to end fix after, Can not being dumped rubbish by the suitable for reading of channel body 1 again of intermediate floor, can pass through the rubbish pour spout of channel body 1 bottom Rubbish is poured in channel body 1, when not using, the sealed door of rubbish pour spout 4 blocks, and does not interfere with the rubbish in channel body 1 Rubbish passes through, and prevents rubbish from discharging from garbage shaft mouth, reduces pollution.
Rubbish pour spout is arranged on and buffer unit 3 opposite position, and buffer unit 3 is arranged in rubbish pour spout, energy The position seen and can touch from rubbish pour spout, is on the one hand to facilitate buffer unit 3 to go wrong when blocking or using When the convenient rubbish exclusion overhauled, facilitate residual on buffer unit 3 simultaneously;On the other hand, buffer unit 3 is facilitated to dismount, middle Buffer unit 3 can be not provided with, only setting buffer unit 3 is in bottom channel body 1 in the channel body 1 of floor Can, so more convenient rubbish passes through.
Sealing door 4 lower end is connected by hinge with rubbish pour spout lower end, and sealing door 4 top is provided with lockhole, and rubbish is toppled over Mouth Upper passage body 1 is provided with the lock corresponding with lockhole, and lock may be inserted into lockhole, opens lock, pulls sealing door Upper end, sealing door upper end is downward-sloping, and rubbish pour spout is opened.
Using process:
Channel body is fixed on floor by fixed support, channel body is end to end, the channel body of bottom Interior setting buffer unit, the superiors' rubbish can be toppled over into by the suitable for reading of channel body, and middle and undermost rubbish can To be poured into by the rubbish pour spout of channel body bottom.
After technique scheme, structure is simple, easy to use, raising garbage-cleaning speed, and socket fitting type structure is permissible Rise socket joint with floor to raise, be used in turn, easy accessibility, safe and reliable, reduce environmental pollution, buffer unit drops to eminence Object speed play cushioning effect, reduce further the dust causing of the rubbish that eminence falls down, reduce to environment Pollution;The design of sealing door both can ensure that intermediate floor can be dumped rubbish, simultaneously also can be residual in easy cleaning channel interior Stay rubbish.
The foregoing is only preferred embodiment of the present utility model, not in order to limit this utility model, all this Any modification, equivalent and improvement made within the spirit of utility model and principle etc., should be included in this utility model Protection domain within.

Claims (7)

1. a kind of spigot-and-socket Construction of High-rise garbage shaft it is characterised in that:The channel body connecting two-by-two including some head and the tail (1);Channel body(1)Top is provided with fixed support(2);Described channel body(1)Inside is provided with buffer unit(3).
2. spigot-and-socket Construction of High-rise garbage shaft according to claim 1 is it is characterised in that described fixed support(2)Including It is fixed on channel body(1)The fixed mount of both sides(2.1)Be arranged on two fixed mounts(2.1)Between link(2.2)Gu, Determine frame(2.1)With channel body(1)It is vertically arranged, fixed mount(2.1)It is provided with fixing hole.
3. spigot-and-socket Construction of High-rise garbage shaft according to claim 1 and 2 is it is characterised in that described fixed support(2) It is welded for angle steel.
4. spigot-and-socket Construction of High-rise garbage shaft according to claim 1 is it is characterised in that described buffer unit(3)Including One and channel body(1)The cambered plate matching(3.1), cambered plate(3.1)The connecting rod of circular hollow is arranged below (3.2), connecting rod(3.2)It is arranged on cambered plate(3.1)Centre is along the distribution of top level line, channel body(1)Relative both sides It is provided with and connecting rod(3.2)Corresponding screw, threaded rod passes through screw to enter connecting rod(3.2), cambered plate(3.1)Can be with spiral shell Overturn centered on rasp bar.
5. spigot-and-socket Construction of High-rise garbage shaft according to claim 1 and 2 is it is characterised in that described channel body(1) Bottom is in channel body(1)Rubbish pour spout is additionally provided with medial surface, rubbish pour spout is externally provided with sealing door to be opened/closed(4).
6. spigot-and-socket Construction of High-rise garbage shaft according to claim 5 is it is characterised in that described rubbish pour spout is arranged With buffer unit(3)Opposite position.
7. spigot-and-socket Construction of High-rise garbage shaft according to claim 5 is it is characterised in that described sealing door(4)Lower end with Rubbish pour spout lower end is passed through hinge and is connected, sealing door(4)Top is provided with lockhole, rubbish pour spout Upper passage body(1)On It is provided with the lock corresponding with lockhole, lock may be inserted into lockhole.
CN201620892601.2U 2016-08-17 2016-08-17 High -rise construction garbage shaft of socket joint formula Expired - Fee Related CN205976365U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620892601.2U CN205976365U (en) 2016-08-17 2016-08-17 High -rise construction garbage shaft of socket joint formula

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620892601.2U CN205976365U (en) 2016-08-17 2016-08-17 High -rise construction garbage shaft of socket joint formula

Publications (1)

Publication Number Publication Date
CN205976365U true CN205976365U (en) 2017-02-22

Family

ID=58030905

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620892601.2U Expired - Fee Related CN205976365U (en) 2016-08-17 2016-08-17 High -rise construction garbage shaft of socket joint formula

Country Status (1)

Country Link
CN (1) CN205976365U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109138367A (en) * 2017-06-15 2019-01-04 五冶集团上海有限公司 A kind of floor garbage cleaning device
CN113152843A (en) * 2021-03-09 2021-07-23 中建二局第一建筑工程有限公司 Flue combined type garbage channel and process flow thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109138367A (en) * 2017-06-15 2019-01-04 五冶集团上海有限公司 A kind of floor garbage cleaning device
CN113152843A (en) * 2021-03-09 2021-07-23 中建二局第一建筑工程有限公司 Flue combined type garbage channel and process flow thereof

Similar Documents

Publication Publication Date Title
CN208830666U (en) A kind of skyscraper vertical garbage transportation system
CN205976365U (en) High -rise construction garbage shaft of socket joint formula
CN104234388B (en) Garbage chute for high-building construction
CN109941646A (en) A kind of vertical vertical compression refuse compaction equipment
CN109339400A (en) A kind of skyscraper refuse collection channel
CN105236055B (en) A kind of vertical case apparatus of vertical refuse compression transfer station
CN208165797U (en) A kind of environment-friendly trash can of separation of solid and liquid
CN204826553U (en) High -rise building waste classification handles passageway from buffering formula
CN206752961U (en) Rubbish storage case
CN212053623U (en) Self-closing door system for high-rise building garbage channel
CN209618058U (en) A kind of Construction of High-rise multipurpose body feed tank
CN205617771U (en) Construction operation platform and pipe -line transportation integrated device in high residential building elevartor shaft
CN206873966U (en) Elevator hoistways isolating and protecting structure
CN206766819U (en) A kind of building waste storing unit
CN209509401U (en) A kind of refuse collection structure for skyscraper
CN207812953U (en) A kind of adjustment height construction garbage shaft
CN113211596A (en) Carbon fiber cement-based concrete civil air defense door and processing device thereof
CN208321320U (en) A kind of construction material sieving garbage environment-friendly materials sieve
CN207312377U (en) A kind of big draw box mechanism of novel intelligent movement station
CN206766826U (en) Solid water separate type outdoor large dustbin
CN206456795U (en) A kind of transport of cement case for being easy to discharging
CN206679666U (en) A kind of bulky refuse case
CN208066915U (en) Waste deposit station
CN219175916U (en) Ash receiving device in construction process
CN203113381U (en) Double-layer inspection well cover

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170222

Termination date: 20190817

CF01 Termination of patent right due to non-payment of annual fee