CN205934891U - Dc -to -ac converter case flattens platform - Google Patents
Dc -to -ac converter case flattens platform Download PDFInfo
- Publication number
- CN205934891U CN205934891U CN201620900572.XU CN201620900572U CN205934891U CN 205934891 U CN205934891 U CN 205934891U CN 201620900572 U CN201620900572 U CN 201620900572U CN 205934891 U CN205934891 U CN 205934891U
- Authority
- CN
- China
- Prior art keywords
- platform
- pipe pile
- inverter box
- landing
- prestressed concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Foundations (AREA)
Abstract
The utility model provides a dc -to -ac converter case flattens platform, include that prestressed concrete pipe pile and setting as basis and post are in the platform of prestressed concrete pipe pile upper end, the platform is the reinforced concrete contignation landing girder and landing slab, landing girder fixes prestressed concrete pipe pile's upper end, the landing slab is fixed landing girder is last.
Description
Technical field
This utility model is related to a kind of inverter box and becomes platform, belongs to fishing light complementation photovoltaic power generation project structure technology neck
Domain.
Background technology
Photovoltaic generation is the important component part of national green energy construction, and fishing light complementation photovoltaic plant is then ground light
One of principal mode of overhead utility.
Traditional inverter box becomes platform and adopts subsoil isolated footing or strip footing, is up steel successively from basis
Reinforced concrete column and reinforced concrete platform, platform typically adopts beam and slab type structure.Because of fishing light complementary terms purpose inverter box
Become platform and be generally individually arranged in fish pond adjacent edges, basis is still seated in inside fish pond.There is water all the year round due in fish pond, lead to
Ground topsoil is generally silt soil, thus basic stock size is larger, buried depth relatively deep to ensure that foundation bearing capacity and ground sink
Fall meets requirement simultaneously.Generally require a water during construction all to drain, silt soil is excavated simultaneously, excavate and complete after-pouring
Plain concrete cushion layer, then shuttering, colligation reinforcement foundation, pour base concrete;After the completion of foundation construction colligation column and
Beam reinforced steel bar, finally carries out column and beam slab concreting.Traditional scheme construction technology is relatively cumbersome, difficulty of construction is inclined
Greatly, especially when fish pond, bottom sludge soil is very thick, and when bearing capacity is very poor, difficulty of construction is bigger, and the construction period is longer.
Utility model content
This utility model is in order to solve drawbacks described above present in prior art and deficiency, there is provided a kind of inverter box becomes
Platform, this platform both can meet the supporting of inverter box change, easy construction simultaneously, quick, and simplifies work progress, significantly
Accelerate the duration.
For solving above-mentioned technical problem, this utility model provides a kind of inverter box to become platform, including based on and post
Prestressed concrete pipe pile and the platform being arranged on described prestressed concrete pipe pile upper end, described platform for reinforcing bar mix
Solidifying soil contignation, including landing beam and landing slab, described landing beam is fixed on the upper end of described prestressed concrete pipe pile,
Described landing slab is fixed on described landing beam.
Further, described landing beam includes 2 crossbeams and 2 tie-beams, 2 described crossbeams be arranged on the pre- of same row
The top of prestressed concrete pile tube is connected, and its end is passed through 2 tie-beams and is connected.
Further, it is provided with some secondary beams, described secondary beam and beam vertical and described tie-beam between 2 described crossbeams
Parallel.
Further, it is provided with fence at described platform surrounding edge.
Further, described platform is provided with steel ladder, described steel ladder extends to ground, for the upper lower platform of staff.
Further, described steel ladder is collapsible steel ladder.
The Advantageous Effects that this utility model is reached:A kind of inverter box that this utility model provides becomes platform, adopts
Replace basis and column with prestressed concrete pipe pile, during making, there is no earth moving, do not found foundation formss, colligation basis steel
Muscle, pour the work of base concrete, also found model of the column, colligation column reinforcing bar, pour the work of column concrete.This
Construction work amount is greatly reduced, has shortened the construction period.Meanwhile, basis and column are replaced using prestressed concrete pipe pile,
Concrete amount, amount of reinforcement have all declined.
Brief description
The inverter box of Fig. 1 this utility model becomes the overlooking the structure diagram of platform;
The inverter box of Fig. 2 this utility model becomes the left view structural representation of platform.
Specific embodiment
Below in conjunction with the accompanying drawings this utility model is further described.Following examples are only used for this is clearly described
The technical scheme of utility model, and protection domain of the present utility model can not be limited with this.
As shown in Figure 1-2, this utility model provides a kind of inverter box to become platform, including based on and post prestressing force
Concrete tubular pile 1 and the platform being arranged on described prestressed concrete pipe pile upper end, described platform is reinforced concrete girder slab
Structure, including landing beam and landing slab 3, described landing beam is fixed on the upper end of described prestressed concrete pipe pile 1, described flat
Platen 3 is fixed on described landing beam.
Based on this platform adopts prestressed concrete pipe pile and post, prestressed concrete pipe pile top and platform are even
Connect, platform adopts reinforced concrete beam and plate, inverter, box type transformer are seated on reinforced concrete platform.Using side
After case, inverter box becomes platform and decreases earth excavation and backfilling of earthwork amount, decreases the quantities on basis, including formwork
The techniques such as plate, reinforcing bar binding, casting concrete, simplify the construction technology of column simultaneously, only include piling technique, decrease steel
The techniques such as muscle colligation, casting concrete, the quantities of platform is basically unchanged.Become platform in view of fish pond photovoltaic project inverter box
Be arranged in fish pond side, the work such as the earthwork, construction of foundation formss affected by fishpond water larger, existing using reducing after this programme
Field difficulty of construction.Therefore, the inverter box for fishing light complementation photovoltaic project becomes platform, after this programme, has both saved mixed
Solidifying soil consumption and reinforcing bar binding engineering amount, in turn simplify the difficulty of site operation, decrease the construction period.
Described landing beam includes 2 crossbeams 2 and 5,2 described crossbeams 2 of 2 tie-beams and the prestressing force being arranged on same row
The top of concrete tubular pile 1 is connected, and its end is passed through 2 tie-beams 5 and is connected.It is provided with some secondary beams between 2 described crossbeams 2
6, described secondary beam 6 is vertical with crossbeam 2 and described tie-beam 5 is parallel.It is provided with fence 7 at described platform surrounding edge, increase platform
Security performance.Steel ladder 4 is provided with described platform, described steel ladder 4 extends to ground, for the upper lower platform of staff, institute
Stating steel ladder 4 is collapsible steel ladder.
The above is only preferred implementation of the present utility model it is noted that common skill for the art
For art personnel, on the premise of without departing from this utility model know-why, some improvement can also be made and deform, these change
Enter and deform also to should be regarded as protection domain of the present utility model.
Claims (6)
1. a kind of inverter box become platform it is characterised in that:Including based on and post prestressed concrete pipe pile and setting
In the platform of described prestressed concrete pipe pile upper end, described platform is reinforced concrete beam and plate, include landing beam with
Landing slab, described landing beam is fixed on the upper end of described prestressed concrete pipe pile, and described landing slab is fixed on described platform
Liang Shang.
2. inverter box according to claim 1 become platform it is characterised in that:Described landing beam includes 2 crossbeams and 2
Tie-beam, 2 described crossbeams are connected with the top of the prestressed concrete pipe pile being arranged on same row, and 2 companies are passed through in its end
Connect beam to be connected.
3. inverter box according to claim 2 become platform it is characterised in that:It is provided with some between 2 described crossbeams
Secondary beam, described secondary beam is parallel with described tie-beam with beam vertical.
4. inverter box according to claim 1 become platform it is characterised in that:It is provided with described platform surrounding edge and enclose
Hurdle.
5. inverter box according to claim 1 become platform it is characterised in that:It is provided with steel ladder on described platform, described
Steel ladder extends to ground, for the upper lower platform of staff.
6. inverter box according to claim 5 become platform it is characterised in that:Described steel ladder is collapsible steel ladder.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620900572.XU CN205934891U (en) | 2016-08-17 | 2016-08-17 | Dc -to -ac converter case flattens platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620900572.XU CN205934891U (en) | 2016-08-17 | 2016-08-17 | Dc -to -ac converter case flattens platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205934891U true CN205934891U (en) | 2017-02-08 |
Family
ID=57919407
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620900572.XU Active CN205934891U (en) | 2016-08-17 | 2016-08-17 | Dc -to -ac converter case flattens platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205934891U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106120690A (en) * | 2016-08-17 | 2016-11-16 | 中国能源建设集团江苏省电力设计院有限公司 | A kind of inverter box flattens platform and preparation method thereof |
-
2016
- 2016-08-17 CN CN201620900572.XU patent/CN205934891U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106120690A (en) * | 2016-08-17 | 2016-11-16 | 中国能源建设集团江苏省电力设计院有限公司 | A kind of inverter box flattens platform and preparation method thereof |
CN106120690B (en) * | 2016-08-17 | 2018-02-13 | 中国能源建设集团江苏省电力设计院有限公司 | A kind of inverter box becomes platform and preparation method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102182325B (en) | Storey adding method for existing building basement with frame structure and independent foundation | |
CN108005084A (en) | The supporting of deep basal pit combined type and construction method | |
CN203174619U (en) | Reverse raft concrete terrace | |
CN104863063B (en) | Cofferdam method for rapidly reinforcing is exempted from based on the bridge submerged structure of PVC composite shuttering | |
CN108103939A (en) | Oblique section steel trestle construction composite reinforcement mode and construction technology | |
CN109487812A (en) | A kind of concrete assembled basic and its construction method of diagonal-bracing type | |
CN108277996A (en) | The construction method of multi-storey basement is extended under a kind of protection groups of building | |
CN211340800U (en) | Super dark foundation ditch earthwork excavation platform structure | |
CN113931166A (en) | Barrel-shaped fan foundation of prefabricated sheet pile assembly type connecting structure and construction method thereof | |
CN207567784U (en) | Deep basal pit combined type supporting | |
CN106120690B (en) | A kind of inverter box becomes platform and preparation method thereof | |
CN205934891U (en) | Dc -to -ac converter case flattens platform | |
CN103233537A (en) | Heavy-load superimposed overhead terrace and construction method | |
CN110805049B (en) | Construction method of mountain slope ultra-thickness spray anchor permanent supporting structure | |
CN209339171U (en) | Transmission line assembled sheet pile composite foundation | |
CN113585336B (en) | Quick construction method of sinking type concrete mixing station in soft foundation environment | |
CN218813780U (en) | Slope protection structure for mine geological environment treatment | |
CN216640550U (en) | Prefabricated sheet pile assembled connection structure's section of thick bamboo type fan basis and wind generating set | |
CN108951654A (en) | Different cutting depth basement construction method for supporting | |
CN207919582U (en) | A kind of assembled pile foundation wharfs structure | |
CN206337566U (en) | Foundation ditch vertical prestressing anchor pole supporting construction | |
CN213952237U (en) | Take a four corners supporting beam's underground structure | |
CN209958290U (en) | Take shore protection structure of pile foundation | |
CN109403297A (en) | A kind of inverter box flattens platform and preparation method thereof | |
CN208088873U (en) | The construction stress structure of multi-storey basement is extended under a kind of protection groups of building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |