CN205918216U - Base of communication tower - Google Patents

Base of communication tower Download PDF

Info

Publication number
CN205918216U
CN205918216U CN201620829507.2U CN201620829507U CN205918216U CN 205918216 U CN205918216 U CN 205918216U CN 201620829507 U CN201620829507 U CN 201620829507U CN 205918216 U CN205918216 U CN 205918216U
Authority
CN
China
Prior art keywords
plate
steel
pipe pile
upper junction
communication tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620829507.2U
Other languages
Chinese (zh)
Inventor
李震
范志华
许清秀
陈维健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Juyi Steel Co ltd
Original Assignee
ZHEJIANG JUJIANG STEEL INDUSTRIAL Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG JUJIANG STEEL INDUSTRIAL Co Ltd filed Critical ZHEJIANG JUJIANG STEEL INDUSTRIAL Co Ltd
Priority to CN201620829507.2U priority Critical patent/CN205918216U/en
Application granted granted Critical
Publication of CN205918216U publication Critical patent/CN205918216U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to a base of communication tower, including steel -pipe pile and the connecting portion that are used for connecting the communication tower, the diameter of steel -pipe pile is between 0.9 meter~1.5 meters, and the length of steel -pipe pile is between 9 meters~11 meters, and the portion of connecing is including setting up in the upper junction plate of steel -pipe pile upper end, connecting plate, curb plate and a plurality of crab -bolt down, and the upper junction plate sets up with connecting plate level down, lower connecting plate and steel -pipe pile top welded fastening, and the upper junction plate setting is passed through the curb plate connection and is fixed in connecting plate top down between lower connecting plate and the upper junction plate. The utility model discloses a set up the steel -pipe pile and restrict the radial of steel -pipe pile and length and size, can directly bury the underground through pressing a stake machine with the steel -pipe pile part, need not dig the deep basal pit, construction convenience, construction cycle is short.

Description

A kind of pedestal of communication tower
Technical field
The present invention relates to communication tower field, more particularly, to a kind of pedestal of communication tower.
Background technology
At present, in fields such as electric power, communication, broadcast, TV signals, widely used communication tower to carry out transmission of wireless signals, When setting up communication tower, need to build pedestal below tower body, communication tower is fixed on pedestal.In prior art, large-scale logical The column foot of letter tower generally passes through concreting, and column foot is needed to meet the requirement of antidumping, therefore needed relatively by column foot Big volume to realize antidumping to have enough counterweights.Need to dig Large Foundation Pit when column foot is built, building of column foot is applied Work inconvenience, long construction period.
Content of the invention
In order to solve the above problems, it is an object of the invention to provide a kind of pedestal of the communication tower of easy construction.
In order to realize above-mentioned purpose, present invention employs following technical scheme:
A kind of pedestal of communication tower, including steel-pipe pile and be arranged on steel pipe upper end for connection communication tower connecting portion, steel , between 0.9 meter~1.5 meters, the length of steel-pipe pile is between 9 meters~11 meters for the diameter of pile tube;Described connecting portion includes being arranged on The upper junction plate of steel-pipe pile upper end, lower connecting plate, side plate and multiple crab-bolt;Described upper junction plate and lower connecting plate are horizontally disposed with, Lower connecting plate is welded and fixed with steel-pipe pile top, and upper junction plate is arranged on above lower connecting plate, lower connecting plate and upper junction plate it Between be connected by side plate, be evenly distributed with multiple reinforcing plates being vertically arranged outside side plate, reinforcing plate connect upper junction plate, Lower connecting plate and side plate;The upper and lower ends of crab-bolt are equipped with nut, and crab-bolt coordinates described nut to be fixed on upper junction plate, multiple Crab-bolt is vertically arranged and rounded array distribution in the horizontal plane.This utility model, by arranging steel-pipe pile and limiting steel-pipe pile Radial direction and length dimension, can by steel-pipe pile partly directly by pile press machine imbed underground it is not necessary to dig deep basal pit, construction party Just, short construction period.
Preferably, described steel-pipe pile inner hollow, upper junction plate and lower connecting plate are provided with the opening being oppositely arranged, side Plate connects around the edge setting of the opening on upper junction plate and lower connecting plate, described opening with inside steel-pipe pile.Setting steel pipe In stake inner hollow, and connecting portion setting with the opening that connects of steel-pipe pile inside, can be from after so that steel-pipe pile is pressed into the ground Outside inwardly fill implant is it is ensured that its stability.
Preferably, the bore of described opening is more than the caliber of steel-pipe pile.Convenient outside fill.
Preferably, being detachably provided with stake top protection component above upper junction plate, stake top protection component includes base plate, Base plate covers above upper junction plate, and base plate is provided with the connecting hole with the cooperation of described crab-bolt, stake top protection component and upper connection Plate is fixed by connecting hole and crab-bolt and nut screw connection, and base plate is provided with riser, and riser is provided with hole for hoist, and riser is along base plate Center line is arranged, and the both sides of riser are provided with the gripper shoe for supporting riser.Setting stake top protection component avoids pile press machine directly right Upper junction plate directly exerts a force, and, arranges mainboard for coordinating the hold assembly of pile press machine to use, and facilitates pile press machine to steel-pipe pile Pressurization.
Preferably, the size of base plate and upper junction plate is equivalently-sized, base plate arranges four gripper shoes, riser two altogether The gripper shoe of side is symmetrical arranged.The size of setting base plate is equivalently-sized with upper junction plate, enables bookbinding to protect component to cover completely Cover connecting plate, and be symmetrical arranged the intensity that four gripper shoes ensure riser.
Preferably, described side plate is provided with multiple through wires holes, two adjacent through wires holes are separated by reinforcing plate.Even Socket part arranges through wires hole, and the holding wire for being arranged on the communication tower on connecting portion is passed and is connected with rack, arranges through wires hole Separated by reinforcing plate, each holding wire passing from through wires hole can be made in good order.
The pedestal of the communication tower of said structure, by arranging steel-pipe pile and limiting radial direction and the length dimension of steel-pipe pile, can Steel-pipe pile is partly directly imbedded underground it is not necessary to dig deep basal pit by pile press machine, easy construction, short construction period.
Brief description
Fig. 1 is structural representation of the present utility model.
Fig. 2 is for the a-a in Fig. 1 to generalized section.
Fig. 3 protects the top view of component for stake top.
Fig. 4 protects the side view of component for stake top.
Fig. 5 uses schematic diagram for this utility model.
Specific embodiment
Below in conjunction with the accompanying drawings the preferred embodiment of this patent is described in further detail.
A kind of pedestal of communication tower as Figure 1-4, including steel-pipe pile 12 be arranged on steel-pipe pile 12 upper end for even Connect the connecting portion 11 of communication tower, the inner hollow of described steel-pipe pile 12, connecting portion 11 is connected with the inside of steel-pipe pile 12.Steel-pipe pile , between 0.9 meter~1.5 meters, the length of steel-pipe pile 12 is between 9 meters~11 meters for 12 diameter.
As depicted in figs. 1 and 2, connecting portion 11 includes upper junction plate 111, the lower connecting plate being arranged on steel-pipe pile 12 upper end 112nd, side plate 113 and multiple crab-bolt 114.Described upper junction plate 111 and lower connecting plate 112 are horizontally disposed with, lower connecting plate 112 and steel Pile tube 12 top is welded and fixed, and upper junction plate 111 is arranged on above lower connecting plate 112, lower connecting plate 112 and upper junction plate 111 Between be connected by side plate 113.In the present embodiment, upper junction plate 111 and lower connecting plate 112 are provided with opening of being oppositely arranged Mouthful, side plate 113 is around the edge setting of the opening on upper junction plate 111 and lower connecting plate 112.The bore being preferably opening is more than The caliber of steel-pipe pile 12, facilitates and steel-pipe pile 12 is managed during construction in later period with interior filling yellow sand etc..The upper and lower ends of crab-bolt 114 are equal Be provided with nut 115, crab-bolt 114 coordinates described nut 115 to be fixed on upper junction plate 111, multiple crab-bolts 114 be vertically arranged and Rounded array distribution on horizontal plane.Side plate 113 is provided with the through wires hole 1131 that multiple holding wires for communication tower 2 pass, It is evenly distributed with multiple reinforcing plates 116 being vertically arranged, reinforcing plate 116 connects upper junction plate 111, lower connection outside side plate 113 Plate 112 and side plate 113, two adjacent through wires holes 1131 are separated by reinforcing plate 116.
As shown in Figure 3 and Figure 4, stake top protection component 3 is detachably installed above upper junction plate 111.Stake top protects structure Part 3 includes base plate 31, and the size of base plate 31 is equivalently-sized with upper junction plate 111, and base plate 31 covers on upper junction plate 111 Side, base plate 31 is provided with the connecting hole 311 with the cooperation of described crab-bolt 114, and stake top protection component 3 and upper junction plate 111 pass through even Connect hole 311 and crab-bolt 114 and nut 115 cooperation is fixed.Base plate 31 is provided with riser 32, and riser 32 sets along the center line of base plate 31 Put, riser 32 is provided with hole for hoist 321, for stake top is protected with the lifting of component 3, the both sides of riser 32 are provided with perpendicular for supporting The gripper shoe 33 of plate 32, arranges four gripper shoes 33 altogether, and every side arranges two, and the gripper shoe 33 of both sides is symmetrical arranged.
As shown in figure 5, this utility model is imbedded it is only necessary to digging shallow foundation and cheating 4 upper ends being used for communication tower pedestal when using, Because the radial dimension of steel-pipe pile 12 is less, the steel-pipe pile 12 of bottom directly can be pressed into underground by pile press machine, and, steel-pipe pile 12 radical length and the setting of size can ensure that column foot has enough anti-overturnings.During construction, by the clamping machine of pile press machine Structure is clamped in after-applied pressure on riser 32, it is to avoid the directly contact to stake top, can protect steel-pipe pile 12 top.After the completion of piling Remove stake top protection structure 3 and tamp toward steel-pipe pile 12 inner canister yellow sand.After communication tower 2 installation, the filling coagulation toward in foundation ditch 4 Soil 5, and the junction of communication tower 2 bottom and column foot is encapsulated using concrete 5.
The pedestal of above-mentioned communication tower, easy for installation it is not necessary to dig Large Foundation Pit it is only necessary to dig shallow foundation hole after directly use piling Steel-pipe pile is pressed into by machine.
Above example is preferred embodiment of the present utility model.

Claims (6)

1. a kind of pedestal of communication tower is it is characterised in that including steel-pipe pile (12) and being arranged on steel-pipe pile (12) upper end and be used for even Connect the connecting portion (11) of communication tower, between 0.9 meter~1.5 meters, the length of steel-pipe pile (12) is at 9 meters for the diameter of steel-pipe pile (12) Between~11 meters;Described connecting portion (11) includes being arranged on upper junction plate (111), the lower connecting plate of steel-pipe pile (12) upper end (112), side plate (113) and multiple crab-bolt (114);Described upper junction plate (111) and lower connecting plate (112) are horizontally disposed with, lower company Fishplate bar (112) is welded and fixed with steel-pipe pile (12) top, and upper junction plate (111) is arranged on above lower connecting plate (112), lower connection It is connected by side plate (113) between plate (112) and upper junction plate (111), be evenly distributed with multiple perpendicular outside side plate (113) The reinforcing plate (116) of straight setting, reinforcing plate (116) connects upper junction plate (111), lower connecting plate (112) and side plate (113);Anchor The upper and lower ends of bolt (114) are equipped with nut (115), and crab-bolt (114) coordinates described nut (115) to be fixed on upper junction plate (111), on, multiple crab-bolts (114) are vertically arranged and rounded array distribution in the horizontal plane.
2. a kind of pedestal of communication tower according to claim 1 is it is characterised in that described steel-pipe pile (12) inner hollow, Upper junction plate (111) and lower connecting plate (112) are provided with the opening being oppositely arranged, side plate (113) around upper junction plate (111) and under The edge setting of the opening on connecting plate (112), described opening connects with inside steel-pipe pile (12).
3. a kind of pedestal of communication tower according to claim 2 is it is characterised in that the bore of described opening is more than steel-pipe pile (12) caliber.
4. a kind of pedestal of communication tower according to claim 1 is it is characterised in that removable above upper junction plate (111) Unload and stake top protection component (3) is installed, stake top protection component (3) includes base plate (31), and base plate (31) covers in upper junction plate (111) above, base plate (31) is provided with the connecting hole (311) coordinating with described crab-bolt (114), stake top protection component (3) and upper Connecting plate (111) passes through connecting hole (311) and crab-bolt (114) and nut (115) cooperation is fixed, and base plate (31) is provided with riser (32), riser (32) is provided with hole for hoist (321), and along the center line setting of base plate (31), the both sides of riser (32) set riser (32) There is the gripper shoe (33) for supporting riser (32).
5. a kind of pedestal of communication tower according to claim 4 is it is characterised in that the size of base plate (31) and upper junction plate (111) equivalently-sized, base plate (31) arranges four gripper shoes (33) altogether, the gripper shoe (33) of riser (32) both sides symmetrically sets Put.
6. a kind of communication tower according to claim 1 pedestal it is characterised in that described side plate (113) be provided with multiple Through wires hole (1131), two adjacent through wires holes (1131) are separated by reinforcing plate (116).
CN201620829507.2U 2016-08-01 2016-08-01 Base of communication tower Expired - Fee Related CN205918216U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620829507.2U CN205918216U (en) 2016-08-01 2016-08-01 Base of communication tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620829507.2U CN205918216U (en) 2016-08-01 2016-08-01 Base of communication tower

Publications (1)

Publication Number Publication Date
CN205918216U true CN205918216U (en) 2017-02-01

Family

ID=57869965

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620829507.2U Expired - Fee Related CN205918216U (en) 2016-08-01 2016-08-01 Base of communication tower

Country Status (1)

Country Link
CN (1) CN205918216U (en)

Similar Documents

Publication Publication Date Title
CN202124865U (en) Quick plugging device for dewatering wellhead of sand-free cement pipe deep well
CN206034408U (en) A back pitching pile formula jacket structure for marine booster station
CN102570069A (en) Novel shield-type grounding device
CN202840440U (en) Ground prefabricated cable trench
CN205918216U (en) Base of communication tower
CN207159983U (en) A kind of soft clay area building lot structure of cement mixing method combination Pulling-Resistant Anchor Rod
CN205976692U (en) Base of communication tower
CN202454737U (en) Novel shield type grounding device
CN104594317A (en) Working platform, single pile foundation, offshore working platform and installing method of offshore working platform
CN104674839A (en) Foundation structure for wind-driven generator
CN205917725U (en) Communication tower
CN211849277U (en) Hydraulic engineering side slope reinforcement system
CN211713968U (en) Slip casting pipe construction equipment
CN205975610U (en) Insert precast pile anchor clamps
CN212248272U (en) Concrete body supporting system for high-strength precipitation
CN211006686U (en) Deep foundation pit supporting structure
CN105888350A (en) Telegraph pole and mounting and fixing method thereof
CN205918208U (en) Tubular communication tower
CN207295706U (en) A kind of Pile feeder suitable for engineering method pile-type steel
CN209323504U (en) A kind of continuous underground wall structure
CN202347528U (en) Steel tube inserted foundation
CN207846413U (en) A kind of soil pore-forming equipment
CN207794761U (en) A kind of large bending moment electrical pole
CN207419508U (en) Direct burial body of rod basis
CN206693259U (en) Suitable for the rock foundation structure of transmission line construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 314515 Gaoqiao Street Industrial Zone, Tongxiang City, Jiaxing City, Zhejiang Province

Patentee after: Zhejiang Juyi Steel Co.,Ltd.

Address before: Takahashi Tongxiang City Industrial Zone Jiaxing city Zhejiang province 314515 Zhejiang masters of Steel Industry Co. Ltd.

Patentee before: Zhejiang Jujiang Steel Industrial Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170201

Termination date: 20210801