CN205976692U - Base of communication tower - Google Patents

Base of communication tower Download PDF

Info

Publication number
CN205976692U
CN205976692U CN201620829932.1U CN201620829932U CN205976692U CN 205976692 U CN205976692 U CN 205976692U CN 201620829932 U CN201620829932 U CN 201620829932U CN 205976692 U CN205976692 U CN 205976692U
Authority
CN
China
Prior art keywords
plate
crab
steel
pipe pile
cushion cap
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620829932.1U
Other languages
Chinese (zh)
Inventor
李震
范志华
许清秀
陈维健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Juyi Steel Co ltd
Original Assignee
ZHEJIANG JUJIANG STEEL INDUSTRIAL Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG JUJIANG STEEL INDUSTRIAL Co Ltd filed Critical ZHEJIANG JUJIANG STEEL INDUSTRIAL Co Ltd
Priority to CN201620829932.1U priority Critical patent/CN205976692U/en
Application granted granted Critical
Publication of CN205976692U publication Critical patent/CN205976692U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to a base of communication tower, including steel -pipe pile, connecting portion and cushion cap, steel -pipe pile, connecting portion and cushion cap three intercommunication, the diameter of steel -pipe pile is between 0.9 meter~1.5 meters, and the length of steel -pipe pile is between 9 meters~11 meters, the cushion cap is directly pour in the steel -pipe pile upper end through reinforced concrete, the cushion cap is the square, is its length of side 250 between the 350cm, set up a plurality of crab -bolt B on the cushion cap, the vertical setting of a plurality of crab -bolt B just is circular array distributed on the horizontal plane, connecting portion include upper junction plate, lower connecting plate, curb plate and a plurality of crab -bolt A, and lower connecting plate is fixed on the cushion cap, the cooperation of crab -bolt A the nut is fixed on the upper junction plate, and the vertical setting of a plurality of crab -bolt A just is circular array distributed on the horizontal plane. The utility model discloses have construction convenience, construction cycle is short, and uses the beneficial effect who still has stronger stability in the relatively poor environment of soil property.

Description

The pedestal of communication tower
Technical field
The present invention relates to communication tower field, more particularly, to a kind of pedestal of communication tower.
Background technology
At present, in fields such as electric power, communication, broadcast, TV signals, widely used communication tower to carry out transmission of wireless signals, When setting up communication tower, need to build pedestal below tower body, communication tower is fixed on pedestal.In prior art, large-scale logical The column foot of letter tower generally passes through concreting, and column foot is needed to meet the requirement of antidumping, therefore needed relatively by column foot Big volume to realize antidumping to have enough counterweights.Need to dig Large Foundation Pit when column foot is built, building of column foot is applied Work is inconvenient, long construction period, and in addition the anti-overturning of column foot is affected by job site soil property.
Content of the invention
In order to solve the above problems, it is an object of the invention to provide a kind of job site bad for soil property situation The pedestal of the high communication tower of steadiness.
In order to realize above-mentioned purpose, present invention employs following technical scheme:
A kind of pedestal of communication tower, including steel-pipe pile, be arranged on steel-pipe pile upper end for connection communication tower connecting portion and Cushion cap for counterweight;Connect inside the inner hollow of described steel-pipe pile, connecting portion, cushion cap and steel-pipe pile three;Steel-pipe pile , between 0.9 meter~1.5 meters, the length of steel-pipe pile is between 9 meters~11 meters for diameter;Cushion cap is directly poured by armored concrete In steel-pipe pile upper end;Cushion cap is square, and between 250-350cm, the reinforcing bar wherein in cushion cap is in horizontal, longitudinally double to its length of side To being crisscross arranged;Multiple crab-bolts B are arranged on cushion cap, multiple crab-bolts B are vertically arranged and rounded array distribution in the horizontal plane;Even Socket part includes upper junction plate, lower connecting plate, side plate and multiple crab-bolt A being arranged on steel-pipe pile upper end;Described upper junction plate and under Connecting plate is horizontally disposed with, and lower connecting plate is provided with the connecting hole with the cooperation of described crab-bolt B, and lower connecting plate passes through crab-bolt B and nut Cooperation is fixed on cushion cap, and upper junction plate is arranged on above lower connecting plate, between lower connecting plate and upper junction plate by side plate even Connect fixation, outside side plate, be evenly distributed with multiple reinforcing plates being vertically arranged, reinforcing plate connects upper junction plate, lower connecting plate and side Plate, the upper and lower ends of crab-bolt A are equipped with nut, and crab-bolt A coordinates described nut to be fixed on upper junction plate, and multiple crab-bolts A are vertical Setting and in the horizontal plane rounded array distribution.
The steel-pipe pile of said structure, is to only need to dig small-scale pit building column foot, then passes through pile press machine direct Steel-pipe pile is pressed into underground, easy construction, short construction period.Anti-overturning due to column foot is subject to the shadow of job site soil property Ring, in the case that soil property situation is poor, directly adopts steel-pipe pile it is possible that tilting, setting cushion cap one side is used for steel Pile tube counterweight, is on the other hand used for increasing contact area between column foot and foundation ditch, make steel-pipe pile under the poor environment of soil property still There is stronger stability.And, pass through anchor bolts between cushion cap and connecting portion, connect reliable.
Preferably, being detachably provided with stake top protection component above upper junction plate, stake top protection component includes base plate, Base plate covers above upper junction plate, and base plate is provided with the connecting hole with the cooperation of described crab-bolt A, stake top protection component and upper connection Plate is fixed by connecting hole and crab-bolt A and nut screw connection, and base plate is provided with riser, and riser is provided with hole for hoist, and riser is along base plate Center line setting, the both sides of riser are provided with the gripper shoe for supporting riser.Setting stake top protection component avoids pile press machine direct The direct force to upper junction plate, and, mainboard is set for coordinating the hold assembly of pile press machine to use, facilitate pile press machine to steel pipe Stake pressurization.
Preferably, the size of base plate and upper junction plate is equivalently-sized, base plate arranges four gripper shoes, riser two altogether The gripper shoe of side is symmetrical arranged.The size of setting base plate is equivalently-sized with upper junction plate, enables bookbinding to protect component to cover completely Cover connecting plate, and be symmetrical arranged the intensity that four gripper shoes ensure riser.
Preferably, described side plate is provided with multiple through wires holes, two adjacent through wires holes are separated by reinforcing plate.Even Socket part arranges through wires hole, and the holding wire for being arranged on the communication tower on connecting portion is passed and is connected with rack, arranges through wires hole Separated by reinforcing plate, each holding wire passing from through wires hole can be made in good order.
The pedestal of the communication tower of said structure, only needs to dig small-scale pit when building column foot, then passes through piling Steel-pipe pile is directly pressed into underground by machine, easy construction, short construction period;Setting cushion cap one side is used for steel-pipe pile counterweight, On the other hand it is used for increasing the contact area between column foot and foundation ditch, so that steel-pipe pile is still had under the poor environment of soil property stronger Stability;Pass through anchor bolts between cushion cap and connecting portion, connect reliable.
Brief description
Fig. 1 is cross-sectional view of the present utility model.
Fig. 2 is the connecting portion structural representation in this utility model.
Fig. 3 is for the A-A in Fig. 2 to generalized section.
Fig. 4 is the B-B direction generalized section in Fig. 2
Fig. 5 is the generalized section of the cushion cap in this utility model.
Fig. 6 is the generalized section of another angle of cushion cap in this utility model.
Fig. 7 protects the top view of component for stake top.
Fig. 8 protects the side view of component for stake top.
Specific embodiment
Below in conjunction with the accompanying drawings the preferred embodiment of this patent is described in further detail.
A kind of pedestal of communication tower as shown in figures 1 to 6, including steel-pipe pile 12, is arranged on steel-pipe pile 12 upper end and is used for connecting The connecting portion 11 of communication tower and cushion cap 13.
As shown in figure 1, the inner hollow of described steel-pipe pile 12, connect inside connecting portion 11, cushion cap 13 and steel-pipe pile 12 three Logical., between 0.9 meter~1.5 meters, the length of steel-pipe pile 12 is between 9 meters~11 meters for the diameter of steel-pipe pile 12.
As shown in Fig. 1, Fig. 5 and Fig. 6, cushion cap 13 is directly cast in steel-pipe pile 12 upper end by armored concrete.Cushion cap 13 On the one hand it is used for, to steel-pipe pile 12 counterweight, being on the other hand used for increasing the contact area between column foot and foundation ditch, so that steel-pipe pile 12 is existed Under the poor environment of soil property, still there is stronger resistance to capsizing.Cushion cap 13 be square, its length of side between 250-350cm, Reinforcing bar 131 wherein in cushion cap 13 is in horizontal, longitudinal two-way cross setting, makes cushion cap 13 have enough intensity.On cushion cap 13 Multiple crab-bolts B132 are set, and multiple crab-bolts B132 are vertically arranged and rounded array distribution in the horizontal plane, crab-bolt B132 is direct Fix when cushion cap 13 pours.
As Figure 1-4, connecting portion 11 include being arranged on the upper junction plate 111 of steel-pipe pile 12 upper end, lower connecting plate 112, Side plate 113 and multiple crab-bolt A114.Described upper junction plate 111 and lower connecting plate 112 are horizontally disposed with, and lower connecting plate 112 is provided with With the connecting hole of described crab-bolt B132 cooperation, lower connecting plate 112 passes through crab-bolt B132 and nut 4 cooperation is fixed on cushion cap 13. Upper junction plate 111 is arranged on above lower connecting plate 112, is connected by side plate 113 between lower connecting plate 112 and upper junction plate 111 Fixing.The upper and lower ends of crab-bolt A114 are equipped with nut 4, and crab-bolt A114 coordinates described nut 4 to be fixed on upper junction plate 111, Multiple crab-bolts A114 are vertically arranged and rounded array distribution in the horizontal plane.Side plate 113 be provided with multiple for communication tower 2 The through wires hole 1131 that holding wire passes, is evenly distributed with multiple reinforcing plates 116 being vertically arranged, reinforcing plate 116 outside side plate 113 Connect upper junction plate 111, lower connecting plate 112 and side plate 113, two adjacent through wires holes 1131 are separated by reinforcing plate 116.
As shown in Figure 7 and Figure 8, stake top protection component 3 is detachably installed above upper junction plate 111.Stake top protects structure Part 3 includes base plate 31, and the size of base plate 31 is equivalently-sized with upper junction plate 111, and base plate 31 covers on upper junction plate 111 Side, base plate 31 is provided with the connecting hole 311 with the cooperation of described crab-bolt A114, and stake top protection component 3 and upper junction plate 111 pass through even Connect hole 311 and crab-bolt A114 and nut 4 cooperation is fixed.Base plate 31 is provided with riser 32, and riser 32 is arranged along the center line of base plate 31, Riser 32 is provided with hole for hoist 321, and for stake top is protected with the lifting of component 3, the both sides of riser 32 are provided with for supporting riser 32 gripper shoe 33, arranges four gripper shoes 33 altogether, and every side arranges two, and the gripper shoe 33 of both sides is symmetrical arranged.
This utility model is imbedded for the connecting portion 11 of column foot upper end and cushion cap 13 it is only necessary to digging shallow foundation and cheating in construction, Because the radial dimension of steel-pipe pile 12 is less, the steel-pipe pile 12 of bottom directly can be pressed into underground by pile press machine, and steel-pipe pile 12 is joined Close cushion cap 13 and ensure that column foot has enough anti-overturnings.During construction, by the gripper mechanism grips of pile press machine on riser 32 after Apply pressure, it is to avoid the directly contact to stake top, steel-pipe pile 12 top can be protected.Stake top protection structure 3 is removed after the completion of piling And tamp toward steel-pipe pile 12 inner canister yellow sand.After communication tower 2 installation, the fill concrete toward in foundation ditch, and to communication tower 2 bottom Encapsulated using concrete 5 with the junction of column foot 2.
The pedestal of above-mentioned communication tower, easy for installation it is not necessary to dig Large Foundation Pit it is only necessary to dig shallow foundation hole after directly use piling Steel-pipe pile 12 is pressed into by machine.In addition, it is ensured that column foot remains to keep preferably in the poor place of soil property after setting cushion cap 13 Stability.

Claims (4)

1. a kind of pedestal of communication tower is it is characterised in that including steel-pipe pile (12), being arranged on steel-pipe pile (12) upper end and be used for connecting The connecting portion (11) of communication tower and the cushion cap (13) for counterweight;The inner hollow of described steel-pipe pile (12), connecting portion (11), holds Platform (13) connects with inside steel-pipe pile (12) three;The diameter of steel-pipe pile (12) between 0.9 meter~1.5 meters, steel-pipe pile (12) Length between 9 meters~11 meters;Cushion cap (13) is directly cast in steel-pipe pile (12) upper end by armored concrete;Cushion cap (13) For square, between 250-350cm, the reinforcing bar (131) wherein in cushion cap (13) sets its length of side in horizontal, longitudinal two-way cross Put;Cushion cap (13) is upper to arrange multiple crab-bolts B (132), and multiple crab-bolts B (132) are vertically arranged and rounded array in the horizontal plane Distribution;Connecting portion (11) includes being arranged on the upper junction plate (111) of steel-pipe pile (12) upper end, lower connecting plate (112), side plate And multiple crab-bolt A (114) (113);Described upper junction plate (111) and lower connecting plate (112) are horizontally disposed with, lower connecting plate (112) It is provided with the connecting hole coordinating with described crab-bolt B (132), lower connecting plate (112) passes through crab-bolt B (132) and nut (4) cooperation is solid It is scheduled on cushion cap (13), upper junction plate (111) is arranged on above lower connecting plate (112), lower connecting plate (112) and upper junction plate (111) it is connected by side plate (113) between, outside side plate (113), be evenly distributed with multiple reinforcing plates being vertically arranged (116), reinforcing plate (116) connects upper junction plate (111), lower connecting plate (112) and side plate (113), crab-bolt A (114) upper and lower Two ends are equipped with nut (4), and crab-bolt A (114) coordinates described nut (4) to be fixed on upper junction plate (111), multiple crab-bolts A (114) it is vertically arranged and rounded array distribution in the horizontal plane.
2. a kind of pedestal of communication tower according to claim 1 is it is characterised in that removable above upper junction plate (111) Unload and stake top protection component (3) is installed, stake top protection component (3) includes base plate (31), and base plate (31) covers in upper junction plate (111) above, base plate (31) is provided with the connecting hole (311) coordinating with described crab-bolt A (114), stake top protection component (3) and upper Connecting plate (111) passes through connecting hole (311) and crab-bolt A (114) and nut (4) cooperation is fixed, and base plate (31) is provided with riser (32), riser (32) is provided with hole for hoist (321), and along the center line setting of base plate (31), the both sides of riser (32) set riser (32) There is the gripper shoe (33) for supporting riser (32).
3. a kind of pedestal of communication tower according to claim 1 is it is characterised in that the size of base plate (31) and upper junction plate (111) equivalently-sized, base plate (31) arranges four gripper shoes (33) altogether, the gripper shoe (33) of riser (32) both sides symmetrically sets Put.
4. a kind of communication tower according to claim 1 pedestal it is characterised in that described side plate (113) be provided with multiple Through wires hole (1131), two adjacent through wires holes (1131) are separated by reinforcing plate (116).
CN201620829932.1U 2016-08-01 2016-08-01 Base of communication tower Expired - Fee Related CN205976692U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620829932.1U CN205976692U (en) 2016-08-01 2016-08-01 Base of communication tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620829932.1U CN205976692U (en) 2016-08-01 2016-08-01 Base of communication tower

Publications (1)

Publication Number Publication Date
CN205976692U true CN205976692U (en) 2017-02-22

Family

ID=58029045

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620829932.1U Expired - Fee Related CN205976692U (en) 2016-08-01 2016-08-01 Base of communication tower

Country Status (1)

Country Link
CN (1) CN205976692U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112392062A (en) * 2019-08-19 2021-02-23 成都华网电力工程咨询有限公司 Electric power iron tower base reinforced structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112392062A (en) * 2019-08-19 2021-02-23 成都华网电力工程咨询有限公司 Electric power iron tower base reinforced structure

Similar Documents

Publication Publication Date Title
CN106245670B (en) Exposed steel column base construction method
CN106836463A (en) The constructing device and construction method of cushion cap and ground girder construction
CN112376552B (en) Energy-saving pile foundation and construction method thereof
CN205976692U (en) Base of communication tower
CN110541429B (en) Energy-consuming bolt type connecting method for connecting concrete prefabricated column and foundation
CN205918208U (en) Tubular communication tower
CN205917725U (en) Communication tower
CN205918216U (en) Base of communication tower
CN103195079B (en) Installing type template, installing type template group and complete installing type plate device
CN206529881U (en) The constructing device of cushion cap and ground girder construction
CN202500146U (en) Steel-structure assembly type bearing platform tubular pile foundation
CN212835477U (en) Collapsible loess foundation structure
CN211849277U (en) Hydraulic engineering side slope reinforcement system
CN208965578U (en) A kind of steel tower concrete pedestal
CN211816376U (en) Tower crane foundation
CN211689865U (en) Reinforced pier
CN207794761U (en) A kind of large bending moment electrical pole
CN210122761U (en) Super high-rise steel pipe concrete column base
CN207047868U (en) A kind of pattern foundation pit supporting structure barricade
CN206752699U (en) A kind of concrete filled steel tube column connected node
CN102134856A (en) Tower crane foundation
CN206706817U (en) A kind of hollow round table gravity type flexibility blower foundation
CN202164622U (en) Tandem tower crane foundation
IT202000011074A1 (en) PREFABRICATED PLINTH, RADIO BASE STATION INCLUDING SUCH PLINTH AND METHOD OF ASSEMBLING A PLINTH
CN210620069U (en) Tower crane foundation for large-span bridge construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 314515 Gaoqiao Street Industrial Zone, Tongxiang City, Jiaxing City, Zhejiang Province

Patentee after: Zhejiang Juyi Steel Co.,Ltd.

Address before: Takahashi Tongxiang City Industrial Zone Jiaxing city Zhejiang province 314515 Zhejiang masters of Steel Industry Co. Ltd.

Patentee before: Zhejiang Jujiang Steel Industrial Co.,Ltd.

CP03 Change of name, title or address
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170222

Termination date: 20210801

CF01 Termination of patent right due to non-payment of annual fee