CN205918208U - Tubular communication tower - Google Patents

Tubular communication tower Download PDF

Info

Publication number
CN205918208U
CN205918208U CN201620829430.9U CN201620829430U CN205918208U CN 205918208 U CN205918208 U CN 205918208U CN 201620829430 U CN201620829430 U CN 201620829430U CN 205918208 U CN205918208 U CN 205918208U
Authority
CN
China
Prior art keywords
tower
plate
steel
pipe pile
crab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620829430.9U
Other languages
Chinese (zh)
Inventor
李震
范志华
许清秀
陈维健
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Juyi Steel Co ltd
Original Assignee
ZHEJIANG JUJIANG STEEL INDUSTRIAL Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG JUJIANG STEEL INDUSTRIAL Co Ltd filed Critical ZHEJIANG JUJIANG STEEL INDUSTRIAL Co Ltd
Priority to CN201620829430.9U priority Critical patent/CN205918208U/en
Application granted granted Critical
Publication of CN205918208U publication Critical patent/CN205918208U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model relates to a tubular communication tower, including column foot and tower body, the column foot includes the steel -pipe pile, sets up the cushion cap that is used for connecting the connecting portion of communication tower and is used for the counter weight on the steel -pipe pile. The tower body includes through bushing's first tower pole, second tower pole, third tower pole, fourth tower pole and the 5th tower pole from bottom to top, first tower pole lower extreme is equipped with the flange board, be equipped with on the flange board with the flange hole that the crab -bolt is matchd, first tower pole is fixed on the column foot. The utility model discloses the accessible presses the stake machine direct with the steel -pipe pile underground of impressing when buildding the column foot, construction convenience's, construction cycle is short to it strengthens the holistic stability of communication tower to set up the cushion cap.

Description

A kind of tubular communication tower
Technical field
The present invention relates to communication tower field, more particularly, to a kind of tubular communication tower.
Background technology
At present, in fields such as electric power, communication, broadcast, TV signals, widely used communication tower to carry out transmission of wireless signals, When setting up communication tower, need to build pedestal below tower body, communication tower is fixed on pedestal.In prior art, large-scale logical The column foot of letter tower generally passes through concreting, and column foot is needed to meet the requirement of antidumping, therefore needed relatively by column foot Big volume to realize antidumping to have enough counterweights.Need to dig Large Foundation Pit when column foot is built, building of column foot is applied Work is inconvenient, long construction period, and in addition the anti-overturning of column foot is affected by job site soil property.
Content of the invention
In order to solve the above problems, it is an object of the invention to provide a kind of high tubular communication tower of stability.
In order to realize above-mentioned purpose, present invention employs following technical scheme:
A kind of tubular communication tower, including column foot and tower body, column foot includes steel-pipe pile, is arranged on steel-pipe pile upper end and is used for connecting The connecting portion of communication tower and the cushion cap for counterweight;The inner hollow of described steel-pipe pile, in connecting portion, cushion cap and steel-pipe pile three Portion connects;, between 0.9 meter~1.5 meters, the length of steel-pipe pile is between 9 meters~11 meters for the diameter of steel-pipe pile;Cushion cap passes through steel Reinforced concrete is directly cast in steel-pipe pile upper end;Cushion cap be square, its length of side between 250-350cm, wherein in cushion cap Reinforcing bar is in horizontal, longitudinal two-way cross setting;Multiple crab-bolts b are arranged on cushion cap, multiple crab-bolts b are vertically arranged and in the horizontal plane Rounded array distribution;Connecting portion includes upper junction plate, lower connecting plate, side plate and multiple crab-bolt a being arranged on steel-pipe pile upper end; Described upper junction plate and lower connecting plate are horizontally disposed with, and lower connecting plate is provided with the connecting hole with the cooperation of described crab-bolt b, lower connecting plate It is fixed on cushion cap by crab-bolt b and nut screw connection, upper junction plate is arranged on above lower connecting plate, lower connecting plate and upper junction plate Between be connected by side plate, be evenly distributed with multiple reinforcing plates being vertically arranged outside side plate, reinforcing plate connects and connects Plate, lower connecting plate and side plate, the upper and lower ends of crab-bolt a are equipped with nut, and crab-bolt a coordinates described nut to be fixed on upper junction plate On, multiple crab-bolts a are vertically arranged and rounded array distribution in the horizontal plane;Described tower body is included by sleeve pipe even from bottom to top The first tower bar, the second tower bar, the 3rd tower bar, the 4th tower bar and the 5th tower bar connecing;First tower bar lower end is provided with flanged plate, described Flanged plate is provided with the flange hole mating with described crab-bolt, and the first tower bar is fixed on the upper junction plate (111) of column foot;Described method It is provided with gripper shoe between blue plate and the first tower bar, described 5th tower bar is provided with pair pole for communication, pay a pole and divide two-layer Setting up and down, and offer, on the 5th tower bar, the feeder hole connecting with the through wires hole on column foot;The top of the 5th tower bar is provided with Discharging rod.
The pass tubular letter tower of said structure, is to only need to dig small-scale pit building column foot, then passes through pile press machine Directly steel-pipe pile is pressed into underground, easy construction, short construction period.Anti-overturning due to column foot is subject to job site soil property Impact, directly adopts steel-pipe pile it is possible that tilting in the case that soil property situation is poor, and it is right that setting cushion cap one side is used for Steel-pipe pile counterweight, is on the other hand used for increasing the contact area between column foot and foundation ditch, makes steel-pipe pile under the poor environment of soil property Still there is stronger stability.And, pass through anchor bolts between cushion cap and connecting portion, connect reliable.Logical between each section of tower body Cross telescopic joint, sound construction, the shake of tower body upper end is little.
Preferably, described side plate is provided with multiple through wires holes, two adjacent through wires holes are separated by reinforcing plate.Even Socket part arranges through wires hole, and the holding wire for being arranged on the communication tower on connecting portion is passed and is connected with rack, arranges through wires hole Separated by reinforcing plate, each holding wire passing from through wires hole can be made in good order.
Preferably, described tower body is less than 35m, the described tower bar constituting described tower body is caliber 40-80cm's Pipe, described the first tower bar, the second tower bar, the length ratio of the 3rd tower bar, the 4th tower bar and the 5th tower bar are 7:8:8:8: 7.Steadiness by the tower body of said structure setting is strong.
The tubular communication tower of said structure, only needs to dig small-scale pit when building column foot, then passes through pile press machine Directly steel-pipe pile is pressed into underground, easy construction, short construction period;Setting cushion cap one side is used for steel-pipe pile counterweight, separately On the one hand it is used for increasing the contact area between column foot and foundation ditch, so that steel-pipe pile is still had under the poor environment of soil property stronger steady Qualitative;Pass through anchor bolts between cushion cap and connecting portion, connect reliable;Each section of tower body will be by telescopic joint, sound construction.
Brief description
Fig. 1 is the cross-sectional view of column foot in this utility model.
Fig. 2 is the connecting portion structural representation in this utility model.
Fig. 3 is for the a-a in Fig. 2 to generalized section.
Fig. 4 is for the b-b in Fig. 2 to generalized section
Fig. 5 is the generalized section of the cushion cap in this utility model.
Fig. 6 is the generalized section of another angle of cushion cap in this utility model.
Fig. 7 is housing structure schematic diagram in this utility model.
Fig. 8 build for this utility model after the completion of tower body and pedestal junction generalized section.
Specific embodiment
Below in conjunction with the accompanying drawings the preferred embodiment of this patent is described in further detail.
A kind of tubular communication tower as shown in figures 1-8, including column foot 1 and tower body 2.Column foot includes steel-pipe pile 12, is arranged on Steel-pipe pile 12 upper end is used for connecting portion 11 and the cushion cap 13 of connection communication tower.
As shown in figure 1, the inner hollow of described steel-pipe pile 12, connect inside connecting portion 11, cushion cap 13 and steel-pipe pile 12 three Logical., between 0.9 meter~1.5 meters, the length of steel-pipe pile 12 is between 9 meters~11 meters for the diameter of steel-pipe pile 12.
As shown in Fig. 1, Fig. 5 and Fig. 6, cushion cap 13 is directly cast in steel-pipe pile 12 upper end by armored concrete.Cushion cap 13 On the one hand it is used for, to steel-pipe pile 12 counterweight, being on the other hand used for increasing the contact area between column foot and foundation ditch, so that steel-pipe pile 12 is existed Under the poor environment of soil property, still there is stronger resistance to capsizing.Cushion cap 13 be square, its length of side between 250-350cm, Reinforcing bar 131 wherein in cushion cap 13 is in horizontal, longitudinal two-way cross setting, makes cushion cap 13 have enough intensity.On cushion cap 13 Multiple crab-bolts b132 are set, and multiple crab-bolts b132 are vertically arranged and rounded array distribution in the horizontal plane, crab-bolt b132 is direct Fix when cushion cap 13 pours.
As Figure 1-4, connecting portion 11 include being arranged on the upper junction plate 111 of steel-pipe pile 12 upper end, lower connecting plate 112, Side plate 113 and multiple crab-bolt a114.Described upper junction plate 111 and lower connecting plate 112 are horizontally disposed with, and lower connecting plate 112 is provided with With the connecting hole of described crab-bolt b132 cooperation, lower connecting plate 112 passes through crab-bolt b132 and nut 4 cooperation is fixed on cushion cap 13. Upper junction plate 111 is arranged on above lower connecting plate 112, is connected by side plate 113 between lower connecting plate 112 and upper junction plate 111 Fixing.The upper and lower ends of crab-bolt a114 are equipped with nut 4, and crab-bolt a114 coordinates described nut 4 to be fixed on upper junction plate 111, Multiple crab-bolts a114 are vertically arranged and rounded array distribution in the horizontal plane.Side plate 113 be provided with multiple for communication tower 2 The through wires hole 1131 that holding wire passes, is evenly distributed with multiple reinforcing plates 116 being vertically arranged, reinforcing plate 116 outside side plate 113 Connect upper junction plate 111, lower connecting plate 112 and side plate 113, two adjacent through wires holes 1131 are separated by reinforcing plate 116.
As shown in Figure 7 and Figure 8, the of length no more than 35m of tower body 2, tower body 2 is included from bottom to top by telescopic joint first Tower bar 21, the second tower bar 22, the 3rd tower bar 23, the 4th tower bar 24 and the 5th tower bar 25.The described tower bar constituting described tower body 2 is equal For caliber 40-80cm pipe, described the first tower bar 21, the second tower bar 22, the 3rd tower bar 23, the 4th tower bar 24 and the 5th The length ratio of tower bar 25 is 7:8:8:8:7;First tower bar 21 lower end is provided with flanged plate 6, described flanged plate 6 be provided with described The flange hole of crab-bolt a114 coupling, the first tower bar 21 is fixed on the connecting portion 11 of column foot 1;Described flanged plate 6 and the first tower bar It is provided with gripper shoe 7 between 21.5th tower bar 25 is provided with pair pole 9 for communication, and pair 9 points of two-layers of pole are setting up and down, and The feeder hole 251 being connected with the through wires hole 1131 on column foot is offered on the 5th tower bar 25.The top of the 5th tower bar 25 is provided with Discharging rod 10.
As shown in figure 8, this utility model construction when it is only necessary to dig shallow foundation to cheat connecting portion 11 He for column foot upper end Cushion cap 13 is imbedded, and because the radial dimension of steel-pipe pile 12 is less, the steel-pipe pile 12 of bottom directly can be pressed into underground by pile press machine, Steel-pipe pile 12 cooperation cushion cap 13 ensures that column foot has enough anti-overturnings.Fill out toward steel-pipe pile 12 inner canister yellow sand after the completion of piling Real, strengthen the resistance to capsizing of column foot 1.Tower body 2 is fixed on the connecting portion of column foot, after the completion of tower body 2 is fixing, toward in foundation ditch 4 Fill concrete 5, and the junction of tower body 2 bottom and column foot is encapsulated using concrete 5.
Above-mentioned tubular communication tower, column foot 1 is easy for installation directly to be used it is not necessary to dig Large Foundation Pit it is only necessary to dig after shallow foundation is cheated Steel-pipe pile 12 is pressed into by pile press machine.In addition, it is ensured that column foot remains to keep in the poor place of soil property after setting cushion cap 13 Preferably stability.The steadiness of tower body 2 is strong, and the shake of tower body upper end is less.

Claims (3)

1. it is characterised in that including column foot (1) and tower body (2), column foot (1) includes steel-pipe pile (12), sets a kind of tubular communication tower Put connecting portion (11) and the cushion cap (13) for counterweight being used for connection communication tower in steel-pipe pile (12) upper end;Described steel-pipe pile (12) connect inside inner hollow, connecting portion (11), cushion cap (13) and steel-pipe pile (12) three;The diameter of steel-pipe pile (12) exists Between 0.9 meter~1.5 meters, the length of steel-pipe pile (12) is between 9 meters~11 meters;Cushion cap (13) is directly poured by armored concrete Build in steel-pipe pile (12) upper end;Cushion cap (13) is square, steel between 250-350cm, wherein in cushion cap (13) for its length of side Muscle (131) is in horizontal, longitudinal two-way cross setting;Cushion cap (13) is upper to arrange multiple crab-bolts b (132), and multiple crab-bolts b (132) are erected Straight setting and in the horizontal plane rounded array distribution;Connecting portion (11) includes being arranged on the upper junction plate of steel-pipe pile (12) upper end (111), lower connecting plate (112), side plate (113) and multiple crab-bolt a (114);Described upper junction plate (111) and lower connecting plate (112) it is horizontally disposed with, lower connecting plate (112) is provided with the connecting hole coordinating with described crab-bolt b (132), lower connecting plate (112) leads to Cross crab-bolt b (132) and nut (4) cooperation is fixed on cushion cap (13), upper junction plate (111) is arranged on lower connecting plate (112) Side, is connected by side plate (113) between lower connecting plate (112) and upper junction plate (111), side plate uniformly divides outside (113) It is furnished with multiple reinforcing plates (116) being vertically arranged, reinforcing plate (116) connects upper junction plate (111), lower connecting plate (112) and side Plate (113), the upper and lower ends of crab-bolt a (114) are equipped with nut (4), and crab-bolt a (114) coordinates described nut (4) company of being fixed on On fishplate bar (111), multiple crab-bolts a (114) are vertically arranged and rounded array distribution in the horizontal plane;Described tower body (2) under And on include by the first telescopic joint tower bar (21), the second tower bar (22), the 3rd tower bar (23), the 4th tower bar (24) and Five tower bars (25);First tower bar (21) lower end is provided with flanged plate (6), and described flanged plate (6) is provided with and described crab-bolt a (114) The flange hole of coupling, the first tower bar (21) is fixed on the upper junction plate (111) of column foot (1);Described flanged plate (6) and the first tower It is provided with gripper shoe (7), described 5th tower bar (25) is provided with pair pole (9) for communication, pays pole (9) between bar (21) Divide two-layer setting up and down, and the feeder hole being connected with the through wires hole (1131) on column foot (1) is offered on the 5th tower bar (25) (251);The top of the 5th tower bar (25) is provided with discharging rod (10).
2. a kind of tubular communication tower according to claim 1 is it is characterised in that described side plate (113) is provided with multiple wearing String holes (1131), two adjacent through wires holes (1131) are separated by reinforcing plate (116).
3. a kind of tubular communication tower according to claim 1, it is characterised in that described tower body (2) is less than 35m, is constituted The described tower bar of described tower body (2) is the pipe in 40-80cm for the caliber, described the first tower bar (21), the second tower bar (22), The length ratio of the 3rd tower bar (23), the 4th tower bar (24) and the 5th tower bar (25) is 7:8:8:8:7.
CN201620829430.9U 2016-08-01 2016-08-01 Tubular communication tower Expired - Fee Related CN205918208U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620829430.9U CN205918208U (en) 2016-08-01 2016-08-01 Tubular communication tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620829430.9U CN205918208U (en) 2016-08-01 2016-08-01 Tubular communication tower

Publications (1)

Publication Number Publication Date
CN205918208U true CN205918208U (en) 2017-02-01

Family

ID=57871408

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620829430.9U Expired - Fee Related CN205918208U (en) 2016-08-01 2016-08-01 Tubular communication tower

Country Status (1)

Country Link
CN (1) CN205918208U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108060818A (en) * 2017-11-24 2018-05-22 安徽电通通信工程有限公司 A kind of catamaran type communication tower

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108060818A (en) * 2017-11-24 2018-05-22 安徽电通通信工程有限公司 A kind of catamaran type communication tower
CN108060818B (en) * 2017-11-24 2019-10-22 安徽电通通信工程有限公司 A kind of catamaran type communication tower

Similar Documents

Publication Publication Date Title
CN106836489B (en) A kind of assembled round steel pipe casing fiber concrete column connected node and installation method
CN104712143B (en) A kind of circular steel reinforced concrete chimney wall reverse mould construction method
CN107675809A (en) Intelligent passive type building module
CN203200771U (en) Connection structure for pile extension top and bearing platform
CN104897143B (en) A kind of cylinder forced centering observation pier and its method for embedding
CN108824475A (en) A kind of transmission line of electricity equilateral triangle cushion cap stake assembling type base
CN205918208U (en) Tubular communication tower
CN206174594U (en) Roofing concatenation formula pole setting connection structure
CN104196023A (en) Precast concrete tubular pile tip with mechanical connection device and using method of precast concrete tubular pile tip
CN205917725U (en) Communication tower
CN207863305U (en) A kind of building iron concrete structure column contracture device
CN205976692U (en) Base of communication tower
CN103195079B (en) Installing type template, installing type template group and complete installing type plate device
CN206408758U (en) A kind of concrete-filled circular steel tube column connecting node construction
CN212104034U (en) Prefabricated combined underground continuous wall
CN212104156U (en) Building foundation pile
CN201746830U (en) Long screw bored concrete pile post-inserted cage tool
CN208965578U (en) A kind of steel tower concrete pedestal
CN206902702U (en) Mixed mud built pile
CN207714552U (en) Prefabricated sleeper and prefabricated panel component
CN211081218U (en) Combined type cement telegraph pole
CN205976688U (en) Single -pipe tower
CN209799529U (en) communication tower prefabricated base convenient for wiring
CN207436091U (en) A kind of annular foundation bolt fast-positioning device of Equipment Foundations
CN207047868U (en) A kind of pattern foundation pit supporting structure barricade

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 314515 Gaoqiao Street Industrial Zone, Tongxiang City, Jiaxing City, Zhejiang Province

Patentee after: Zhejiang Juyi Steel Co.,Ltd.

Address before: Takahashi Tongxiang City Industrial Zone Jiaxing city Zhejiang province 314515 Zhejiang masters of Steel Industry Co. Ltd.

Patentee before: Zhejiang Jujiang Steel Industrial Co.,Ltd.

CP03 Change of name, title or address
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170201

Termination date: 20210801

CF01 Termination of patent right due to non-payment of annual fee