CN205874884U - Slag permeable pavement structure - Google Patents

Slag permeable pavement structure Download PDF

Info

Publication number
CN205874884U
CN205874884U CN201620193921.9U CN201620193921U CN205874884U CN 205874884 U CN205874884 U CN 205874884U CN 201620193921 U CN201620193921 U CN 201620193921U CN 205874884 U CN205874884 U CN 205874884U
Authority
CN
China
Prior art keywords
slag
granularity
adhesive
pavement structure
permeable pavement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620193921.9U
Other languages
Chinese (zh)
Inventor
赵建林
徐社阳
董荣珍
赵凯
赵芳中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Jingchen Ecology Environmental Protection Technology Co Ltd
Original Assignee
Hunan Jingchen Ecology Environmental Protection Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Jingchen Ecology Environmental Protection Technology Co Ltd filed Critical Hunan Jingchen Ecology Environmental Protection Technology Co Ltd
Priority to CN201620193921.9U priority Critical patent/CN205874884U/en
Application granted granted Critical
Publication of CN205874884U publication Critical patent/CN205874884U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a slag permeable pavement structure and construction method, slag permeable pavement structure sets up on the road bed, and this slag permeable pavement structure is included under to by last in proper order: the surface course, is the surface course 0.1 by the granularity 2mm's slag forms through adhesive mixed and cured, the basic unit, is the basic unit 2 by the granularity 15mm's aggregate forms through adhesive mixed and cured, the bed course, is the bed course 2 by the granularity 30mm's aggregate forms through adhesive mixed and cured, siphon hookup layer, is siphon hookup layer 2 by the granularity 15mm's slag and plain soil mix, tamp together to form. Utilize the performance that has the water permeability behind slag and the adhesive curing for the rainwater on road surface can enter into groundwater through osmosis, avoids the rainwater to form runoff and ponding in the road, and especially to the city, can be fine permeate the rainwater to the underground in has alleviateed the burden that municipal drainage pipe said, the appearance of avoiding the waterlogging that can be fine.

Description

A kind of slag permeable pavement structure
Technical field
This utility model relates to road engineering technical field, in particular, relates to a kind of slag permeable pavement structure.
Background technology
In urbanization process, the use of the waterproof construction materials of hard such as a large amount of reinforced concrete buildings and pitch, by former Some natural soils surface breakdowns, and airtight ground surface is closed, make moisture ooze under being difficult to, during precipitation, quickly form ground Table runoff, runoff enters river course or municipal drainage pipeline, easily beyond river course and municipal drainage pipeline in the case of big rainfall Burden, serious in the case of can form waterlogging, phenomenon occurs again and again to cause city " to see sea ".Due to rainwater table impenetrably Penetrate under earth's surface so that subsoil water can not get supplementing timely and effectively, cause level of ground water degradation, applicable water Resource exhaustion, water ecological environment deteriorates.
The waterproof pavement that the closely list structure of urban pavement causes now lacks urban surface temperature, the tune of humidity Joint function, rainwater evaporation is fast, and earth's surface is easily dried, and dust pollution is serious, produces the city " tropical island effect " on meteorology;To city Integrated environment
It addition, close the waterproof pavement that earth's surface is caused, it will make in city raw for regulating the ground flora of miniclimate Long difficulty, some trees are even because root system hydropenia is dead, lodging, thus lose Ecological regulation effect.
Therefore, a kind of slag permeable pavement structure water-permeable and air permeable with increase city with good water penetration of proposition is needed badly Space, reaches the good result regulating urban microclimate, keeping ecological balance.
Utility model content
Technical problem to be solved in the utility model is to provide the slag permeable pavement structure that a kind of permeability is good.
The purpose of this utility model is achieved through the following technical solutions:
A kind of slag permeable pavement structure, described slag permeable pavement structure is arranged on roadbed, the permeable road of this slag Face structure includes the most successively:
Surface layer, described surface layer is formed by adhesive is mixing cured by the slag that granularity is 0.1-2mm;
Basic unit, described basic unit is formed by adhesive is mixing cured by the aggregate that granularity is 2-15mm;
Bed course, described bed course is formed by adhesive is mixing cured by the aggregate that granularity is 2-30mm;
Siphon context layer, described siphon context layer is by the slag that granularity is 2-15mm and element soil mixing, and compacting forms together Slag element soil mixing material.
Preferably, being mixed with pigment in the adhesive of described surface layer, the thickness of described surface layer is 10-60mm.
Preferably, the thickness of described surface layer is 40mm.
Preferably, in described surface layer, also it is mixed with glass fibre;Wherein, glass fibre in the described surface layer of 100 weight portions Mass parts be 0-5, the mass parts of described adhesive is 5-30, and the mass parts of described slag is 95-65.
Preferably, in described basic unit, also it is mixed with glass fibre;Wherein, glass fibre in the described basic unit of 100 weight portions Mass parts be 0-5, the mass parts of described adhesive is 5-20, and the mass parts of described slag is 95-75, the thickness of described basic unit For 100-400mm.
Preferably, the thickness of described basic unit is 200mm.
Preferably, in described bed course, also it is mixed with glass fibre;Wherein, glass fibre in the described bed course of 100 weight portions Mass parts be 0-5, the mass parts of described adhesive is 5-20, and the mass parts of described slag is 95-75, the thickness of described bed course For 100-500mm.
Preferably, the thickness of described bed course is 300mm.
Preferably, the fibrous material of described siphon context layer is glass fibre, a length of 30-of described glass fibre 300mm。
Preferably, in the described siphon context layer of 100 weight portions, the mass parts of glass fibre is 0-5, the matter of described slag Amount part is 95-75, the thickness 10-50mm of described siphon context layer.
A kind of construction method of slag permeable pavement structure as claimed in claim 1, including step:
Surface layer, described surface layer is formed by adhesive is mixing cured by the slag that granularity is 0.1-2mm;
Basic unit, described basic unit is formed by adhesive is mixing cured by the aggregate that granularity is 2-15mm;
Bed course, described bed course is formed by adhesive is mixing cured by the aggregate that granularity is 2-30mm;
Siphon context layer, described siphon context layer is by the slag that granularity is 2-15mm and element soil mixing, and compacting forms together.
Preferably, in described step S1, it is additionally included in adhesive the step mixing pigment.
Preferably, in described step S1, step S2 and step S3, described slag and described aggregate are mixed by adhesive The process closing solidification also includes mixing the step of glass fibre.
The benefit that this utility model brings is: utilize slag to have the performance of water penetration with adhesive after solidifying so that road The rainwater in face can enter in subsoil water by osmosis, it is to avoid rainwater forms runoff and hydrops in the road, particularly For city, can well rainwater be penetrated in underground, alleviate the burden of municipal drainage pipeline, can well Avoid the appearance of waterlogging.It addition, infiltration makes subsoil water to be supplemented timely so that the utilization of water resource is protected Barrier.Slag permeable pavement structure uses the structure of many levels, and slag or the aggregate size of every Rotating fields are differently formed Different Rotating fields, surface layer and basic unit use less Granularity Structure, it is ensured that its wear-resisting and firm performance, and bed course and rainbow Inhale context layer and use bigger slag Granularity Structure, serve good moistening effect, osmosis can be played, can play again Keeping the effect of moisture content, siphon context layer uses and mixes with element soil, can produce more hole, when rainy, accelerates rainwater Penetrate into effect, and siphon effect (capillarity) can be produced when dry, moisture content is upwards attracted, keep pavement humidity.Additionally, The slag permeable pavement structure that this utility model uses also is the process of a kind of filtration due to its process of osmosis, it is possible to have rainwater Unique purification function.
Accompanying drawing explanation
Fig. 1 is the slag permeable pavement structure structural representation of this utility model embodiment.
Detailed description of the invention
Describing preferred implementation of the present utility model below, those of ordinary skill in the art can be according to hereinafter described Realized by the correlation technique of this area, and innovation of the present utility model and the benefit brought can be will be apparent from.
" national novel urbanization planning (2014-2020) " clearly proposes: construction is had nature and accumulates, naturally ooze Thoroughly, the sponge city of self-purification function, as the target of urban construction of promoting a conservation culture.Low impact in sponge urban construction The core of exploitation storm-water system is that before and after maintaining Site development, hydrological characteristics is constant.From hydrologic cycle angle, after exploitation will be realized The outer row of a certain amount of run-off, is necessary for utilizing source, place adequate space, the mode such as take that infiltration is backflowed, and comes eliminate-incorporate-land Runoff increment after ground exploitation.After realizing exploitation, hydrological characteristics is close to the target before exploitation.
Based on this, the utility model proposes a kind of new slag permeable pavement structure with good water permeability.
Embodiment one
The slag permeable pavement structure of the present embodiment uses slag to make as aggregate, wherein, and the steel selected in this example Slag physical property is following but is not limited to this:
Sequence number Index name Index
1 Crush index (%) < 15
2 Flat-elongated particles content (%) < 15
3 Clay content (%) < 0.5
4 Apparent density (kg/m3) > 2500
5 Tightly fill bulk density (kg/m3) 1350
6 Voidage (%) < 47
Illustrating slag permeable pavement structure below in conjunction with Fig. 1, described slag permeable pavement structure is arranged at roadbed On, this slag permeable pavement structure includes the most successively: surface layer 1, basic unit 2, bed course 3 and siphon context layer 4, described Surface layer 1, basic unit 2, bed course 3 and siphon context layer 4 are formed as aggregate is mixing cured by slag.Wherein, described surface layer 1 by Granularity is that the slag of 0.1-2mm forms by adhesive is mixing cured;, described basic unit 2 is passed through by the slag that granularity is 2-15mm Adhesive is mixing cured to be formed;Described bed course 3 is formed by adhesive is mixing cured by the slag that granularity is 2-30mm;Described rainbow Inhale context layer 4 by the slag that granularity is 2-15mm and element soil mixing, the slag element soil mixing material tamped together.Slag is saturating Water pavement structure uses the structure of many levels, and the slag granularity of every Rotating fields has been differently formed different Rotating fields, face Layer 1 and basic unit 2 use less Granularity Structure, it is ensured that its wear-resisting and firm performance, and bed course 3 and siphon context layer 4 are adopted With bigger slag Granularity Structure, serve good moistening effect, osmosis can be played, can play again and keep moisture content Effect, siphon context layer 4 mixes fibrous material, the capillary structure of available fibrous material, forms good siphon effect, to water Infiltration and holding serve good regulation effect.Additionally, the slag permeable pavement structure that this utility model uses is due to it Process of osmosis is also the process of a kind of filtration, it is possible to have the purification function of uniqueness to rainwater.After utilizing slag to solidify with adhesive There is the performance of water penetration so that the rainwater on road surface can enter in subsoil water by osmosis, it is to avoid rainwater is at road Middle formation runoff and hydrops, for city, can well penetrate in underground by rainwater, alleviates municipal administration row The burden of waterpipe, can well avoid the appearance of waterlogging.
It addition, the adhesive of described surface layer also can mix pigment, so, after forming slag permeable pavement structure, meeting Directly show the color of pigment, be no longer traditional black or Lycoperdon polymorphum Vitt road surface, different colors can be dyed as desired. Further, owing to pigment is incorporated in adhesive, it not to be coated on road surface, thus without because the traveling of automobile rolls Causing comes off fades.
In the present embodiment, described surface layer is also mixed with glass fibre 5;Wherein, glass in the described surface layer of 100 weight portions The mass parts of glass fiber is 0-5, and the mass parts of described adhesive is 5-30, and the mass parts of described slag is 95-65, described surface layer Thickness be 10-60mm, when the thickness of surface layer is 40mm, its anti-wear performance and water permeability are more preferably.Under this proportioning, surface layer There is good anti-wear performance.Certainly, glass fibre 5 can use other fibrous material to replace such as the materials such as resin fibre, Glass fibre can well make road surface keep good permeability performance as capillary channel structure.
In the present embodiment, described basic unit is the most also mixed with glass fibre 5;Wherein, glass in the described basic unit of 100 weight portions The mass parts of glass fiber is 0-5, and the mass parts of described adhesive is 5-20, and the mass parts of described slag is 95-75, described basic unit Thickness be 100-400mm, when the thickness of basic unit is in 200mm, its strength character and penetrate into better.In this proportioning Under, basic unit has good strength character.Certainly, glass fibre can use other fibrous material to replace such as resin fibre etc. Material, glass fibre can well make road surface keep good permeability performance as capillary channel structure.Wherein, in basic unit The slag that used of aggregate, can be the average slag of granularity, it is also possible to be the grating using the mode of grating to be formed Slag.
In the present embodiment, described bed course is also mixed with glass fibre 5;Wherein, glass in the described bed course of 100 weight portions The mass parts of glass fiber is 0-5, and the mass parts of described adhesive is 5-20, and the mass parts of described slag is 95-75, described bed course Thickness be 100-500mm, when the thickness of bed course is in 300mm, its structural strength and penetrate into better.In this proportioning Under, bed course has good strength character.Certainly, glass fibre can use other fibrous material to replace such as resin fibre etc. Material, glass fibre can well make road surface keep good permeability performance as capillary channel structure.Wherein, in bed course The slag that used of aggregate, can be the average slag of granularity, it is also possible to be the grating using the mode of grating to be formed Slag.
In the present embodiment, described siphon context layer is also mixed with glass fibre 5, described glass fibre a length of 30-300mm, glass fibre first passes around surface activation process, processing mode be invade on the surface of glass fibre profit one layer hydrophilic Base organic compound.Siphon context layer uses the glass fibre of a length of 30-300mm, can well be at siphon context layer Middle formation capillary channel, when rainy, it is possible to increase the effect of rain penetration, when dry, it is possible to by siphonage (capillary Phenomenon) subsoil water is upwards attracted, keep the humidity on road surface.Further, glass fibre can also strengthen the intensity of structure.Through surface The guiding at the glass fibre interface processed, under the effect of ground level heat air-flow, quickening subsoil water reverse osmosis is to road surface, and is evaporated to In air, to a certain degree alleviate " tropical island effect " in city.
In the present embodiment, in the described siphon context layer of 100 weight portions, the mass parts of glass fibre is 0-5, described steel The mass parts of slag is 95-75, the thickness 10-50mm of described siphon context layer.Under this proportioning, siphon context layer has good Moisturizing and osmosis, can play the supporting role of good road surface simultaneously.
Embodiment two
Present embodiments provide the construction method of slag permeable pavement structure described in a kind of embodiment one, including step:
S1, will form siphon context layer on roadbed, described siphon context layer granularity be the slag of 2-15mm and element soil mixed Closing, compacting forms together;
S2, forms bed course on described siphon context layer, and described surface layer is passed through gluing by the slag that granularity is 2-30mm Agent is mixing cured to be formed;
S3, forms basic unit on described bed course, and described basic unit is mixed by adhesive by the slag that granularity is 2-15mm Solidification forms;
S4, forms surface layer on described basic unit, and described surface layer is mixed by adhesive by the slag that granularity is 0.1-2mm Solidification forms.
Wherein, in described step S1, it is additionally included in adhesive the step mixing pigment.
Wherein, in described step S1, step S2 and step S3, slag is also wrapped by the process that adhesive is mixing cured Include the step mixing glass fibre.
In the present embodiment, the main chemical compositions of described slag is CaO、SiO2、Al2O3、FeO、Fe2O3、MgO、MnO、 P2O5, have possibly together with V2O5And TiO2.Slag is a kind of aggregation being made up of multi mineral and glass state material, owing to shaping Special environment condition, make slag quality hard, close hole is less, and specific surface area is little, and slag sticks together and fine and closely woven, the boundary of skull crystallization is divided Bright, fracture is neat.Further, since slag compactness is high, the most wear-resisting.
In the present embodiment, in described surface layer 1, basic unit 2, bed course 3 and siphon layer 4, wherein, with the process of surface layer it is Example, its step is as follows:
Step T1: slag is carried out particle filter, selects the slag of the particle size diameter met;
Step T2: the slag after screening is carried out polymer covering layer processing;
Step T3: the slag with polymer covering layer is carried out mix and blend with adhesive, glass fibre;
Step T4: be routed in basic unit and pressurize treat that it solidifies by the slag mix and blend thing in step T3;
Described polymer covering layer is in epoxyn, acrylic resin adhesive and polyurethane adhesive One or more;Described adhesive is in epoxyn, acrylic resin adhesive and polyurethane adhesive Plant or multiple.
Certainly, in the present embodiment, described adhesive is chosen as epoxyn, according to preparation of the present utility model The slag with polymer covering layer is the most first mixed homogeneously by method with epoxy resin, is subsequently adding epoxy curing agent, Mix homogeneously, then by said mixture molding, and solidifies.
In another embodiment, described adhesive is polyurethane adhesive, and described polyurethane adhesive contains guarantor Protect or unprotected isocyanates and polyester or polyether polyol, according to preparation method of the present utility model the most first by polyester or Polyether polyol is mixed homogeneously with the slag with polymer covering layer, is subsequently adding protection or unprotected isocyanates, connects And be shaped and solidify.
In another embodiment, described adhesive is acrylic resin adhesive, according to system of the present utility model Described acrylic resin adhesive is preferably mixed homogeneously by Preparation Method with the slag with polymer covering layer, and carries out solid Change.
This utility model is also not particularly limited for the condition of described solidification, as long as the condition of described solidification be enough to make institute State adhesive to solidify.In this utility model, described solidification refers to that adhesive is transformed into solid-state also by liquid or semisolid There is certain intensity.
Usually, the condition of described solidification includes: temperature is 25-180 DEG C, and the time is 2-108 hour.Preferably, described The condition of solidification includes: temperature is 45-150 DEG C, and the time is 3-48 hour.
Certainly, in the present embodiment, the processing that slag does not carry out in described basic unit and bed course polymer covering layer is also Permissible, directly by slag is mixed with adhesive.
For basic unit, bed course and the making of siphon context layer, then it is to have employed different mixing materials and slag granularity Diameter, the making of its basic step heel layer is identical.
As a kind of alternate embodiment, adhesive described in basic unit and bed course can also select silicate cementing material.Separately In one alternate embodiment, the aggregate in described basic unit and bed course can also use rubble as an alternative, and now, used is gluing Agent can be selected for portland cement.Rubble is as basic unit and the aggregate of bed course, it is also possible to reach well to seep water effect.
Above content is to combine concrete preferred implementation further detailed description of the utility model, it is impossible to Assert that of the present utility model being embodied as is confined to these explanations.Ordinary skill for this utility model art For personnel, without departing from the concept of the premise utility, it is also possible to making some simple deduction or replace, these are all answered When being considered as belonging to protection domain of the present utility model.

Claims (4)

1. a slag permeable pavement structure, described slag permeable pavement structure is arranged on roadbed, it is characterised in that this steel Slag permeable pavement structure includes the most successively:
Surface layer, described surface layer is formed by adhesive is mixing cured by the slag that granularity is 0.10-2mm;
Basic unit, described basic unit is formed by adhesive is mixing cured by the aggregate that granularity is 2-15mm;
Bed course, described bed course is formed by adhesive is mixing cured by the aggregate that granularity is 2-30mm;
Siphon context layer, described siphon context layer is by the slag that granularity is 2-15mm and element soil mixing, the steel tamped together Slag element soil mixing material.
2. slag permeable pavement structure as claimed in claim 1, it is characterised in that the thickness of described surface layer is 40mm.
3. slag permeable pavement structure as claimed in claim 1, it is characterised in that the thickness of described basic unit is 200mm.
4. slag permeable pavement structure as claimed in claim 1, it is characterised in that the thickness of described bed course is 300mm.
CN201620193921.9U 2016-03-14 2016-03-14 Slag permeable pavement structure Active CN205874884U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620193921.9U CN205874884U (en) 2016-03-14 2016-03-14 Slag permeable pavement structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620193921.9U CN205874884U (en) 2016-03-14 2016-03-14 Slag permeable pavement structure

Publications (1)

Publication Number Publication Date
CN205874884U true CN205874884U (en) 2017-01-11

Family

ID=57687001

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620193921.9U Active CN205874884U (en) 2016-03-14 2016-03-14 Slag permeable pavement structure

Country Status (1)

Country Link
CN (1) CN205874884U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105625137A (en) * 2016-03-14 2016-06-01 赵建林 Steel slag water-permeable pavement structure and construction method thereof
CN106915926A (en) * 2017-03-30 2017-07-04 中交四公局第三工程有限公司 Low temperature road surface cement treated material compound
CN107587405A (en) * 2017-09-22 2018-01-16 南京林业大学 A kind of construction method of microorganism solidification cinder from refuse incineration porous pavement
CN108118573A (en) * 2017-12-22 2018-06-05 上海市政工程设计研究总院(集团)有限公司 A kind of resource regeneration full-transparency type asphalt pavement structure
CN115490460A (en) * 2022-10-14 2022-12-20 南京赛仕瑞道路工程技术有限公司 Fluorescence permeable pavement surface course, fluorescence permeable pavement and brick that permeates water

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105625137A (en) * 2016-03-14 2016-06-01 赵建林 Steel slag water-permeable pavement structure and construction method thereof
CN106915926A (en) * 2017-03-30 2017-07-04 中交四公局第三工程有限公司 Low temperature road surface cement treated material compound
CN107587405A (en) * 2017-09-22 2018-01-16 南京林业大学 A kind of construction method of microorganism solidification cinder from refuse incineration porous pavement
CN107587405B (en) * 2017-09-22 2021-11-30 南京林业大学 Construction method for microorganism-cured garbage incineration ash permeable pavement
CN108118573A (en) * 2017-12-22 2018-06-05 上海市政工程设计研究总院(集团)有限公司 A kind of resource regeneration full-transparency type asphalt pavement structure
CN115490460A (en) * 2022-10-14 2022-12-20 南京赛仕瑞道路工程技术有限公司 Fluorescence permeable pavement surface course, fluorescence permeable pavement and brick that permeates water
CN115490460B (en) * 2022-10-14 2023-09-08 南京赛仕瑞道路工程技术有限公司 Fluorescent permeable pavement surface layer, fluorescent permeable pavement and permeable brick

Similar Documents

Publication Publication Date Title
CN105625137B (en) A kind of slag permeable pavement structure and its construction method
CN205874884U (en) Slag permeable pavement structure
CN104264692B (en) A kind of side slope ecological renovation method
AU2011362016B2 (en) Water-permeable and water-absorbable ecological paving
CN103124585B (en) For building method and the mixture of motor area
CN207793788U (en) A kind of porous pavement rain infiltration structure
CN102010155A (en) High-strength plant growing type porous concrete and preparation method thereof
CN110698222B (en) Composite vegetation concrete for ecological protection of stone slope and preparation method thereof
CN101182172A (en) High-strength highly-permeable concrete and method for making the same
KR101311748B1 (en) The binder for water permeable concrete and paving method using the same
CN201232150Y (en) Moisture-keeping ecological brick
KR100621963B1 (en) Soil paving composition using water-quenched blast furnace slag and method for paving ground using the same
KR101726392B1 (en) Construction method of rain water management and recycle system of playground and rain water management and recycle system of playground
CN107651898A (en) A kind of novel gradient water-permeable brick and preparation method thereof
CN105967729A (en) Novel pavement water-permeable composite material and preparation method thereof
CN205999746U (en) A kind of permeable plastic cement race track
KR100698488B1 (en) Construction work method of playground or stadium
CN207749380U (en) Vegetation type eco-concrete
JP2009270302A (en) Pavement structure
CN207793792U (en) A kind of road surface permeable pavement structure
CN109577130A (en) A kind of porous pavement of quaternity and preparation method thereof
JPS59206502A (en) Production of water pervious cement concrete construction
KR100874496B1 (en) Road paving material formation having steel making slag and method for paving of road using that
JP4555460B2 (en) Permeable block pavement and construction method of permeable block pavement
CN104045282B (en) Nonporous closed water-permeable drainage ditch cover plate and manufacturing method thereof

Legal Events

Date Code Title Description
GR01 Patent grant