CN205844539U CN201620522552.3U CN201620522552U CN205844539U CN 205844539 U CN205844539 U CN 205844539U CN 201620522552 U CN201620522552 U CN 201620522552U CN 205844539 U CN205844539 U CN 205844539U
Authority
CN
China
Prior art keywords
bus
line
detonator
detonates
single line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620522552.3U
Other languages
Chinese (zh)
Inventor
荣耀
饶和根
侯俊敏
余斯冬
习小华
刘志辉
江炜
房丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Province Expressway Investment Group Co Ltd
JIANGSU TRAFFIC RESEARCH INSTITUTE
Original Assignee
Jiangxi Province Expressway Investment Group Co Ltd
JIANGSU TRAFFIC RESEARCH INSTITUTE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Province Expressway Investment Group Co Ltd, JIANGSU TRAFFIC RESEARCH INSTITUTE filed Critical Jiangxi Province Expressway Investment Group Co Ltd
Priority to CN201620522552.3U priority Critical patent/CN205844539U/en
Application granted granted Critical
Publication of CN205844539U publication Critical patent/CN205844539U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Air Bags (AREA)

Abstract

This utility model provides a kind of tunnel geological forecast electric detonator initiation and controls device, triggers bus including signal and detonator excites bus.In signal triggers bus, trigger bus and be sequentially connected with TGP geologic prediction instrument by described firing line switching switch and trigger bus single line;Trigger bus to be connected to trigger bus single line by firing line;Detonator it is bundled with in firing line.In detonator excites bus, the bus that detonates is sequentially connected with initiator and the bus single line that detonates by detonating cord switching switch.Connect on detonator line and have detonator;The bus that detonates is connected to, by detonator line, the bus single line that detonates.Before this utility model gathers seismic data, all circuits have connected, so need not artificial wiring again in data acquisition.And gathering in data procedures, circuit switching can be by being manually switched fast.Both reach quick, the purpose of safety operation, take into account again the quality of data, reliability and the instrument suitability.

Description

A kind of tunnel geological forecast electric detonator initiation controls device
Technical field
This utility model belongs to geologic prediction signal to be triggered and detonator excitation technique field, is specifically related to a kind of tunnel advanced Geologic prediction electric detonator initiation controls device.
Background technology
Grasp tunnel front geological condition, have highly important effect for tunnel construction.By advanced prediction, in time Unusual circumstance, the integrity of the forecast position of front of tunnel heading unfavorable geologic body, occurrence and surrounding rock structure thereof is with aqueous Probability, for correctly selecting excavated section, support parameters and Optimizing Construction Scheme to provide foundation, and gushes for prevention tunnel The disastrous accident that water, prominent mud, prominent gas etc. are likely to be formed provides information in time, makes engineering unit carry out preparation of construction in advance, protects Card construction safety, the most also can save substantial contribution.
TGP tunnel geological forecast seismic wave method is outside in arrange on the same level line of tunnel one side wall One receptor (another receptor is laid in the position that the same side is identical) and 24 big gun holes, exciting detonator detonating charge While trigger TGP geologic prediction instrument, the seismic wave excited in utilizing big gun hole to three dimensions propagate during, run into sound Impedance interface, both interface, structurally fractured zone, karst and the karst growth zone etc. of geologic lithology change, it may occur that elastic reflection Phenomenon, the detector arrangement that this echo is disposed in tunnel surrounding receives, be input in instrument to carry out signal amplification, Digital collection and process, it is achieved the reflected wave information in pickup front of tunnel heading rock mass, reach the purpose of forecast.
At present, TGP tunnel geological forecast signal triggers and excites respectively by triggering bus and exciting bus even with detonator Connect control, before each track data collection, all need workman to connect firing line the most respectively, trigger bus and excitation line, detonator line, this One method has time-consuming long, unsafe shortcoming.The method that the Cui Yi peace opponent of Central South University is dynamically connected is improved, permissible After once connecting porous focus, the most automatically excite the focus that detonates, though the collection data that this method can be efficient, safe, but nothing Waveform is diagnosed in gatherer process and takes corrective measure by method;Secondly, this device only excites bus, and does not trigger Bus, is only applicable to TSP advance geologic prediction instrument;Again, it is integrated that the environment that newly built tunnels is moist, shake the most seriously constrains band The application of this device of circuit board.To sum up stating, manual method of attachment poor efficiency, dangerous, automatic connection method is owed flexibly, no Stablize and be not suitable for TGP geologic prediction instrument.
Summary of the invention
This utility model purpose is to provide a kind of tunnel geological forecast electric detonator initiation to control device, overcomes manually Method of attachment poor efficiency, dangerous, automatic connection method owes the shortcoming of flexible, unstable and inapplicable TGP geologic prediction instrument, this dress Put and do not use any circuit board and welding procedure, adapt to moist in newly built tunnels, the environment of vibrations and to be applicable to TGP geology pre- Report instrument.
A kind of tunnel geological forecast electric detonator initiation that this utility model provides controls device, triggers mother including signal Line and detonator excite bus;
Described signal triggers bus and includes: triggers bus, firing line switching switch, TGP geologic prediction instrument, trigger bus list Line and firing line;Described triggering bus is sequentially connected with described TGP geologic prediction instrument and triggering by described firing line switching switch Bus single line;Every described triggering bus is all connected to same described triggering bus single line by a described firing line;Often Detonator all it is bundled with in firing line described in root;
Described detonator excites bus to include: the bus that detonates, detonating cord switch switch, initiator, detonate bus single line and thunder Pipeline;The described bus that detonates is sequentially connected with described initiator and the bus single line that detonates by described detonating cord switching switch;Every Connect on described detonator line and have detonator;The bus that detonates described in every all is connected to described in same rise by a described detonator line Quick-fried bus single line.
Further, described firing line and described triggering bus and the firing line binding post of triggering bus single line, and Described detonator line and the described excitation line binding post detonating bus and the bus single line that detonates are exempts from solder terminal.
Further, described triggering bus is respectively 24 with the bus that detonates.
Further, described firing line switching switch and detonating cord switching switch carry out synchronism switching.
The beneficial effects of the utility model are, can connect detonator and explosive before TGP geologic prediction instrument is started shooting Volume all joints of end, operator only need in instrument end manual switching two lines road corresponding circuit, if finding, certain track data has Interference, can suspend data collection task, after ELIMINATION OF ITS INTERFERENCE, and the next loop of switching.Both quick, safety operation had been reached Purpose, taken into account again the quality of data, reliability and the instrument suitability.
Accompanying drawing explanation
Fig. 1 show this utility model one tunnel geological forecast electric detonator initiation and controls device schematic diagram.
Detailed description of the invention
This utility model is described in detail below in conjunction with specific embodiment.It should be noted that, described in following embodiment Technical characteristic or the combination of technical characteristic be not construed as isolating, they can be mutually combined thus be reached more Good technique effect.
As it is shown in figure 1, this utility model provides a kind of tunnel geological forecast electric detonator initiation controls device, including Signal triggers bus and detonator excites bus;
Signal triggers bus and includes: triggers bus 1, firing line switching switch 2, TGP geologic prediction instrument 3, trigger bus list Line 4 and firing line 5;Trigger bus 1 be sequentially connected with TGP geologic prediction instrument 3 by firing line switching switch 2 and trigger bus single line 4;Every is triggered bus 1 and is all connected to same triggering bus single line 4 by a firing line 5;It is bundled with in every firing line 5 Detonator 13.The effect triggering bus 4 is the relay of TGP geologic prediction instrument 3 and the firing line 5 being bound on explosive to have been connected Come.
Detonator excites bus to include: the bus 6 that detonates, detonating cord switch switch 7, initiator 8, detonate bus single line 9 and thunder Pipeline 10;The bus 6 that detonates is sequentially connected with initiator 8 and the bus single line 9 that detonates by detonating cord switching switch 7;Every detonator line Connect on 10 and have detonator 13;The every bus 6 that detonates all is connected to the same bus single line 9 that detonates by a detonator line 10.Thunder Pipe excites the effect of bus to be initiator 8 and detonator line 10 to be together in series.
Firing line 5 switching switch 2 and detonating cord switching switch 7 carry out synchronism switching.
Firing line 5 with trigger bus 1 and trigger the firing line binding post 11 of bus single line 4, and detonator line 10 with rise The excitation line binding post 12 of quick-fried bus 6 and the bus single line 9 that detonates all uses exempts from solder terminal, with damp in adapting to newly built tunnels Wet, the environment of vibrations.
Trigger bus 1 and the bus 6 that detonates is respectively 24.First firing line 5 and detonator 13 are bundled, fill in Tunnel Wall excite in hole, lay detonator along tunnel axis direction and excite bus and signal to trigger bus, by detonator line 10 and excitation line Binding post 12 connects one by one, firing line 5 is connected one by one with firing line binding post 11, after opening TGP geologic prediction instrument 3, Utilize detonating cord switching switch 7 and firing line 5 switching switch 2 synchronism switching, after detonating and receiving seismic data more subsynchronous Switching detonating cord switching switch 7 and firing line 5 switch switch 2, until 24 track datas are fully completed.Before gathering seismic data, All circuits have connected, so need not artificial wiring again in data acquisition.And gathering in data procedures, circuit is cut Changing can be by being manually switched fast.
This utility model can connect detonator and all joints of explosive cartridge end before TGP geologic prediction instrument is started shooting, behaviour Make personnel only need in instrument end manual switching two lines road corresponding circuit, if finding, certain track data has interference, can suspend data Collecting work, after ELIMINATION OF ITS INTERFERENCE, the next loop of switching.Both reached quick, the purpose of safety operation, taken into account again The quality of data, reliability and the instrument suitability.
Although this utility model has been presented for embodiment, it will be appreciated by those of skill in the art that without departing from In the case of this utility model spirit, the embodiments herein can be changed.Above-described embodiment is exemplary, should not Using the embodiments herein as the restriction of this utility model interest field.

Claims (4)

1. a tunnel geological forecast electric detonator initiation controls device, it is characterised in that: include that signal triggers bus and thunder Pipe excites bus;
Described signal trigger bus include: trigger bus, firing line switching switch, TGP geologic prediction instrument, triggering bus single line and Firing line;Described triggering bus is sequentially connected with described TGP geologic prediction instrument by described firing line switching switch and is triggered bus Single line;Every described triggering bus is all connected to same described triggering bus single line by a described firing line;Every institute State and in firing line, be all bundled with detonator;
Described detonator excites bus to include: the bus that detonates, detonating cord switch switch, initiator, detonate bus single line and detonator line; The described bus that detonates is sequentially connected with described initiator and the bus single line that detonates by described detonating cord switching switch;Every described thunder Connect on pipeline and have detonator;The bus that detonates described in every is all connected to described in same detonate bus by a described detonator line Single line.
2. a kind of tunnel geological forecast electric detonator initiation as claimed in claim 1 controls device, it is characterised in that: described Firing line and described triggering bus and trigger the firing line binding post of bus single line, and described detonator line and described mother of detonating The excitation line binding post of line and the bus single line that detonates is exempts from solder terminal.
3. a kind of tunnel geological forecast electric detonator initiation as claimed in claim 1 controls device, it is characterised in that: described Trigger bus and be respectively 24 with the bus that detonates.
4. a kind of tunnel geological forecast electric detonator initiation as claimed in claim 1 controls device, it is characterised in that: described Firing line switching switch and detonating cord switching switch carry out synchronism switching.
CN201620522552.3U 2016-06-01 2016-06-01 A kind of tunnel geological forecast electric detonator initiation controls device Expired - Fee Related CN205844539U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620522552.3U CN205844539U (en) 2016-06-01 2016-06-01 A kind of tunnel geological forecast electric detonator initiation controls device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620522552.3U CN205844539U (en) 2016-06-01 2016-06-01 A kind of tunnel geological forecast electric detonator initiation controls device

Publications (1)

Publication Number Publication Date
CN205844539U true CN205844539U (en) 2016-12-28

Family

ID=57622381

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620522552.3U Expired - Fee Related CN205844539U (en) 2016-06-01 2016-06-01 A kind of tunnel geological forecast electric detonator initiation controls device

Country Status (1)

Country Link
CN (1) CN205844539U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108732615A (en) * 2018-03-29 2018-11-02 中铁第六勘察设计院集团有限公司 Seismic reflection method advanced geology prediction system blasting cap initiation alarming device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108732615A (en) * 2018-03-29 2018-11-02 中铁第六勘察设计院集团有限公司 Seismic reflection method advanced geology prediction system blasting cap initiation alarming device
CN108732615B (en) * 2018-03-29 2023-06-09 中铁第六勘察设计院集团有限公司 Detonator detonation warning device of advanced geological prediction system by seismic wave reflection method

Similar Documents

Publication Publication Date Title
CN109115061B (en) Detonation control method for reducing blasting vibration
CN103398637A (en) Mean-peak micro-quake fine control blasting construction method using high-precision digital electronic detonators
CN205844539U (en) A kind of tunnel geological forecast electric detonator initiation controls device
AU2015101608A4 (en) Rock acoustic wave detection transducer
CN109506536A (en) A kind of method of the quick-fried heap width of optimal control surface mine bench blasting
CN107289826B (en) Explosion bulge test device and blasting method
AU2016260872B2 (en) Detonator information system
CN114111478B (en) Detonating circuit combining electronic detonator and detonating cord and construction method thereof
JP6342749B2 (en) Blasting method
CN101858715A (en) Method for recognizing and positioning misfired blasting cartridges in blasting
CN103776320A (en) Steel pipe leading-in blasting method for unblocking ore-pass
CN116696342A (en) Front cabin type secondary explosion composite perforation method for coal-bed gas well
CN203066956U (en) Oil and gas well perforating ground monitoring device
CN207197379U (en) A kind of tunnel surrounding blasting system
CN102426385B (en) Improved triggering and receiving system of TSP advanced geological forecast signal and method thereof
CN202217063U (en) Composite signal trigger wiring structure of total suspended particulate (TSP) advanced geological forecast
CN102434207A (en) Multi-channel trigger device and multi-channel trigger method for tunnel TSP (Tunnel Seism Prediction) advanced geological prediction signal
CN103398683B (en) Detection device for underground coal mine drill rod length and fault and using method thereof
CN107401958A (en) A kind of method for identifying blind big gun using the vibration wave analysis of electronic chip detonator blasting
CN203629462U (en) Underground detonating device for magnetoelectric detonator
Battison et al. Reducing crest loss at Barrick Cowal gold mine
CN201352095Y (en) Inverse VSP remote explosion exciting system of deep well
CN114046700B (en) Intelligent detonation network system during hole extension and detonation method thereof
CN207332857U (en) A kind of oil/gas well partition delay explosion fracturing device
CN109238049A (en) Device is arranged in the method for measurement on-site mixed explosive explosion velocity and its signal in blast hole

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161228

Termination date: 20170601