CN205844539U - A kind of tunnel geological forecast electric detonator initiation controls device - Google Patents
A kind of tunnel geological forecast electric detonator initiation controls device Download PDFInfo
- Publication number
- CN205844539U CN205844539U CN201620522552.3U CN201620522552U CN205844539U CN 205844539 U CN205844539 U CN 205844539U CN 201620522552 U CN201620522552 U CN 201620522552U CN 205844539 U CN205844539 U CN 205844539U
- Authority
- CN
- China
- Prior art keywords
- bus
- line
- detonator
- detonates
- single line
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Air Bags (AREA)
Abstract
This utility model provides a kind of tunnel geological forecast electric detonator initiation and controls device, triggers bus including signal and detonator excites bus.In signal triggers bus, trigger bus and be sequentially connected with TGP geologic prediction instrument by described firing line switching switch and trigger bus single line;Trigger bus to be connected to trigger bus single line by firing line;Detonator it is bundled with in firing line.In detonator excites bus, the bus that detonates is sequentially connected with initiator and the bus single line that detonates by detonating cord switching switch.Connect on detonator line and have detonator;The bus that detonates is connected to, by detonator line, the bus single line that detonates.Before this utility model gathers seismic data, all circuits have connected, so need not artificial wiring again in data acquisition.And gathering in data procedures, circuit switching can be by being manually switched fast.Both reach quick, the purpose of safety operation, take into account again the quality of data, reliability and the instrument suitability.
Description
Technical field
This utility model belongs to geologic prediction signal to be triggered and detonator excitation technique field, is specifically related to a kind of tunnel advanced
Geologic prediction electric detonator initiation controls device.
Background technology
Grasp tunnel front geological condition, have highly important effect for tunnel construction.By advanced prediction, in time
Unusual circumstance, the integrity of the forecast position of front of tunnel heading unfavorable geologic body, occurrence and surrounding rock structure thereof is with aqueous
Probability, for correctly selecting excavated section, support parameters and Optimizing Construction Scheme to provide foundation, and gushes for prevention tunnel
The disastrous accident that water, prominent mud, prominent gas etc. are likely to be formed provides information in time, makes engineering unit carry out preparation of construction in advance, protects
Card construction safety, the most also can save substantial contribution.
TGP tunnel geological forecast seismic wave method is outside in arrange on the same level line of tunnel one side wall
One receptor (another receptor is laid in the position that the same side is identical) and 24 big gun holes, exciting detonator detonating charge
While trigger TGP geologic prediction instrument, the seismic wave excited in utilizing big gun hole to three dimensions propagate during, run into sound
Impedance interface, both interface, structurally fractured zone, karst and the karst growth zone etc. of geologic lithology change, it may occur that elastic reflection
Phenomenon, the detector arrangement that this echo is disposed in tunnel surrounding receives, be input in instrument to carry out signal amplification,
Digital collection and process, it is achieved the reflected wave information in pickup front of tunnel heading rock mass, reach the purpose of forecast.
At present, TGP tunnel geological forecast signal triggers and excites respectively by triggering bus and exciting bus even with detonator
Connect control, before each track data collection, all need workman to connect firing line the most respectively, trigger bus and excitation line, detonator line, this
One method has time-consuming long, unsafe shortcoming.The method that the Cui Yi peace opponent of Central South University is dynamically connected is improved, permissible
After once connecting porous focus, the most automatically excite the focus that detonates, though the collection data that this method can be efficient, safe, but nothing
Waveform is diagnosed in gatherer process and takes corrective measure by method;Secondly, this device only excites bus, and does not trigger
Bus, is only applicable to TSP advance geologic prediction instrument;Again, it is integrated that the environment that newly built tunnels is moist, shake the most seriously constrains band
The application of this device of circuit board.To sum up stating, manual method of attachment poor efficiency, dangerous, automatic connection method is owed flexibly, no
Stablize and be not suitable for TGP geologic prediction instrument.
Summary of the invention
This utility model purpose is to provide a kind of tunnel geological forecast electric detonator initiation to control device, overcomes manually
Method of attachment poor efficiency, dangerous, automatic connection method owes the shortcoming of flexible, unstable and inapplicable TGP geologic prediction instrument, this dress
Put and do not use any circuit board and welding procedure, adapt to moist in newly built tunnels, the environment of vibrations and to be applicable to TGP geology pre-
Report instrument.
A kind of tunnel geological forecast electric detonator initiation that this utility model provides controls device, triggers mother including signal
Line and detonator excite bus;
Described signal triggers bus and includes: triggers bus, firing line switching switch, TGP geologic prediction instrument, trigger bus list
Line and firing line;Described triggering bus is sequentially connected with described TGP geologic prediction instrument and triggering by described firing line switching switch
Bus single line;Every described triggering bus is all connected to same described triggering bus single line by a described firing line;Often
Detonator all it is bundled with in firing line described in root;
Described detonator excites bus to include: the bus that detonates, detonating cord switch switch, initiator, detonate bus single line and thunder
Pipeline;The described bus that detonates is sequentially connected with described initiator and the bus single line that detonates by described detonating cord switching switch;Every
Connect on described detonator line and have detonator;The bus that detonates described in every all is connected to described in same rise by a described detonator line
Quick-fried bus single line.
Further, described firing line and described triggering bus and the firing line binding post of triggering bus single line, and
Described detonator line and the described excitation line binding post detonating bus and the bus single line that detonates are exempts from solder terminal.
Further, described triggering bus is respectively 24 with the bus that detonates.
Further, described firing line switching switch and detonating cord switching switch carry out synchronism switching.
The beneficial effects of the utility model are, can connect detonator and explosive before TGP geologic prediction instrument is started shooting
Volume all joints of end, operator only need in instrument end manual switching two lines road corresponding circuit, if finding, certain track data has
Interference, can suspend data collection task, after ELIMINATION OF ITS INTERFERENCE, and the next loop of switching.Both quick, safety operation had been reached
Purpose, taken into account again the quality of data, reliability and the instrument suitability.
Accompanying drawing explanation
Fig. 1 show this utility model one tunnel geological forecast electric detonator initiation and controls device schematic diagram.
Detailed description of the invention
This utility model is described in detail below in conjunction with specific embodiment.It should be noted that, described in following embodiment
Technical characteristic or the combination of technical characteristic be not construed as isolating, they can be mutually combined thus be reached more
Good technique effect.
As it is shown in figure 1, this utility model provides a kind of tunnel geological forecast electric detonator initiation controls device, including
Signal triggers bus and detonator excites bus;
Signal triggers bus and includes: triggers bus 1, firing line switching switch 2, TGP geologic prediction instrument 3, trigger bus list
Line 4 and firing line 5;Trigger bus 1 be sequentially connected with TGP geologic prediction instrument 3 by firing line switching switch 2 and trigger bus single line
4;Every is triggered bus 1 and is all connected to same triggering bus single line 4 by a firing line 5;It is bundled with in every firing line 5
Detonator 13.The effect triggering bus 4 is the relay of TGP geologic prediction instrument 3 and the firing line 5 being bound on explosive to have been connected
Come.
Detonator excites bus to include: the bus 6 that detonates, detonating cord switch switch 7, initiator 8, detonate bus single line 9 and thunder
Pipeline 10;The bus 6 that detonates is sequentially connected with initiator 8 and the bus single line 9 that detonates by detonating cord switching switch 7;Every detonator line
Connect on 10 and have detonator 13;The every bus 6 that detonates all is connected to the same bus single line 9 that detonates by a detonator line 10.Thunder
Pipe excites the effect of bus to be initiator 8 and detonator line 10 to be together in series.
Firing line 5 switching switch 2 and detonating cord switching switch 7 carry out synchronism switching.
Firing line 5 with trigger bus 1 and trigger the firing line binding post 11 of bus single line 4, and detonator line 10 with rise
The excitation line binding post 12 of quick-fried bus 6 and the bus single line 9 that detonates all uses exempts from solder terminal, with damp in adapting to newly built tunnels
Wet, the environment of vibrations.
Trigger bus 1 and the bus 6 that detonates is respectively 24.First firing line 5 and detonator 13 are bundled, fill in Tunnel
Wall excite in hole, lay detonator along tunnel axis direction and excite bus and signal to trigger bus, by detonator line 10 and excitation line
Binding post 12 connects one by one, firing line 5 is connected one by one with firing line binding post 11, after opening TGP geologic prediction instrument 3,
Utilize detonating cord switching switch 7 and firing line 5 switching switch 2 synchronism switching, after detonating and receiving seismic data more subsynchronous
Switching detonating cord switching switch 7 and firing line 5 switch switch 2, until 24 track datas are fully completed.Before gathering seismic data,
All circuits have connected, so need not artificial wiring again in data acquisition.And gathering in data procedures, circuit is cut
Changing can be by being manually switched fast.
This utility model can connect detonator and all joints of explosive cartridge end before TGP geologic prediction instrument is started shooting, behaviour
Make personnel only need in instrument end manual switching two lines road corresponding circuit, if finding, certain track data has interference, can suspend data
Collecting work, after ELIMINATION OF ITS INTERFERENCE, the next loop of switching.Both reached quick, the purpose of safety operation, taken into account again
The quality of data, reliability and the instrument suitability.
Although this utility model has been presented for embodiment, it will be appreciated by those of skill in the art that without departing from
In the case of this utility model spirit, the embodiments herein can be changed.Above-described embodiment is exemplary, should not
Using the embodiments herein as the restriction of this utility model interest field.
Claims (4)
1. a tunnel geological forecast electric detonator initiation controls device, it is characterised in that: include that signal triggers bus and thunder
Pipe excites bus;
Described signal trigger bus include: trigger bus, firing line switching switch, TGP geologic prediction instrument, triggering bus single line and
Firing line;Described triggering bus is sequentially connected with described TGP geologic prediction instrument by described firing line switching switch and is triggered bus
Single line;Every described triggering bus is all connected to same described triggering bus single line by a described firing line;Every institute
State and in firing line, be all bundled with detonator;
Described detonator excites bus to include: the bus that detonates, detonating cord switch switch, initiator, detonate bus single line and detonator line;
The described bus that detonates is sequentially connected with described initiator and the bus single line that detonates by described detonating cord switching switch;Every described thunder
Connect on pipeline and have detonator;The bus that detonates described in every is all connected to described in same detonate bus by a described detonator line
Single line.
2. a kind of tunnel geological forecast electric detonator initiation as claimed in claim 1 controls device, it is characterised in that: described
Firing line and described triggering bus and trigger the firing line binding post of bus single line, and described detonator line and described mother of detonating
The excitation line binding post of line and the bus single line that detonates is exempts from solder terminal.
3. a kind of tunnel geological forecast electric detonator initiation as claimed in claim 1 controls device, it is characterised in that: described
Trigger bus and be respectively 24 with the bus that detonates.
4. a kind of tunnel geological forecast electric detonator initiation as claimed in claim 1 controls device, it is characterised in that: described
Firing line switching switch and detonating cord switching switch carry out synchronism switching.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620522552.3U CN205844539U (en) | 2016-06-01 | 2016-06-01 | A kind of tunnel geological forecast electric detonator initiation controls device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620522552.3U CN205844539U (en) | 2016-06-01 | 2016-06-01 | A kind of tunnel geological forecast electric detonator initiation controls device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205844539U true CN205844539U (en) | 2016-12-28 |
Family
ID=57622381
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620522552.3U Expired - Fee Related CN205844539U (en) | 2016-06-01 | 2016-06-01 | A kind of tunnel geological forecast electric detonator initiation controls device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205844539U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108732615A (en) * | 2018-03-29 | 2018-11-02 | 中铁第六勘察设计院集团有限公司 | Seismic reflection method advanced geology prediction system blasting cap initiation alarming device |
-
2016
- 2016-06-01 CN CN201620522552.3U patent/CN205844539U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108732615A (en) * | 2018-03-29 | 2018-11-02 | 中铁第六勘察设计院集团有限公司 | Seismic reflection method advanced geology prediction system blasting cap initiation alarming device |
CN108732615B (en) * | 2018-03-29 | 2023-06-09 | 中铁第六勘察设计院集团有限公司 | Detonator detonation warning device of advanced geological prediction system by seismic wave reflection method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109115061B (en) | Detonation control method for reducing blasting vibration | |
CN103398637A (en) | Mean-peak micro-quake fine control blasting construction method using high-precision digital electronic detonators | |
CN205844539U (en) | A kind of tunnel geological forecast electric detonator initiation controls device | |
AU2015101608A4 (en) | Rock acoustic wave detection transducer | |
CN109506536A (en) | A kind of method of the quick-fried heap width of optimal control surface mine bench blasting | |
CN107289826B (en) | Explosion bulge test device and blasting method | |
AU2016260872B2 (en) | Detonator information system | |
CN114111478B (en) | Detonating circuit combining electronic detonator and detonating cord and construction method thereof | |
JP6342749B2 (en) | Blasting method | |
CN101858715A (en) | Method for recognizing and positioning misfired blasting cartridges in blasting | |
CN103776320A (en) | Steel pipe leading-in blasting method for unblocking ore-pass | |
CN116696342A (en) | Front cabin type secondary explosion composite perforation method for coal-bed gas well | |
CN203066956U (en) | Oil and gas well perforating ground monitoring device | |
CN207197379U (en) | A kind of tunnel surrounding blasting system | |
CN102426385B (en) | Improved triggering and receiving system of TSP advanced geological forecast signal and method thereof | |
CN202217063U (en) | Composite signal trigger wiring structure of total suspended particulate (TSP) advanced geological forecast | |
CN102434207A (en) | Multi-channel trigger device and multi-channel trigger method for tunnel TSP (Tunnel Seism Prediction) advanced geological prediction signal | |
CN103398683B (en) | Detection device for underground coal mine drill rod length and fault and using method thereof | |
CN107401958A (en) | A kind of method for identifying blind big gun using the vibration wave analysis of electronic chip detonator blasting | |
CN203629462U (en) | Underground detonating device for magnetoelectric detonator | |
Battison et al. | Reducing crest loss at Barrick Cowal gold mine | |
CN201352095Y (en) | Inverse VSP remote explosion exciting system of deep well | |
CN114046700B (en) | Intelligent detonation network system during hole extension and detonation method thereof | |
CN207332857U (en) | A kind of oil/gas well partition delay explosion fracturing device | |
CN109238049A (en) | Device is arranged in the method for measurement on-site mixed explosive explosion velocity and its signal in blast hole |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20161228 Termination date: 20170601 |
|
CF01 | Termination of patent right due to non-payment of annual fee |