CN205843498U CN201620171969.XU CN201620171969U CN205843498U CN 205843498 U CN205843498 U CN 205843498U CN 201620171969 U CN201620171969 U CN 201620171969U CN 205843498 U CN205843498 U CN 205843498U
Authority
CN
China
Prior art keywords
dyke
explosion
loading
powder charge
buried
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620171969.XU
Other languages
Chinese (zh)
Inventor
张风德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Heilongjiang Sanjiang Engineering Construction Authority
Original Assignee
Heilongjiang Sanjiang Engineering Construction Authority
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Heilongjiang Sanjiang Engineering Construction Authority filed Critical Heilongjiang Sanjiang Engineering Construction Authority
Priority to CN201620171969.XU priority Critical patent/CN205843498U/en
Application granted granted Critical
Publication of CN205843498U publication Critical patent/CN205843498U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

This utility model provide a kind of can explosion dyke for take off mouthful flood diversion, including dyke explosion section (4), dyke explosion section (4) is provided with multiple boring being arranged in rows, being provided with pre-buried means for loading (5) in each boring, each pre-buried means for loading (5) includes for the powder charge pipeline (1) of explosive and is located at the openable duct sealing lid (2) at powder charge pipeline (1) two ends;It is provided with carn (3) at the embedment of each pre-buried means for loading (5).The pre-buried means for loading of this utility model is embedded in dyke in advance when dyke is properly functioning, breaks when mouthful flood diversion task taken off by dike use as explosive coyote hole undertaking explosion.This utility model dyke, compared with conventional concentrated charge blasting procedure, has the most pre-buried, and detonate rapid, small volume, the advantage not reducing dyke intensity.

Description

A kind of can explosion dyke for take off mouthful flood diversion
Technical field
This utility model belongs to the explosion flood diversion technical field of engineering explosion, a kind of for taking off mouthful flood diversion Can explosion dyke.
Background technology
As the important component part of rivers and lakes Flood Control System, dyke building controlling flood, irrigate, supply water, shipping, water are protected Etc. aspect bring huge society, economy and environmental benefit, the development of the national economy and social safety play huge work With.In the high flood unusual time, can retrain, when upland water exceedes this section dyke, the discharge passed through, for avoid being likely to occur Unfavorable situation, need to carry out in a planned way flood diversion crevasse to exceeding the section safety discharge flood that exceeds the quata, i.e. the flood that exceeds the quata be imported Flood storage areas planned in advance.Flood diversion method conventional in engineering is that dike technology is broken in explosion, has construction dike high-efficiency precision quick, broken Accurate feature.
Existing explosion is broken dike arrangement and method for construction and is generally solid explosive concentrated charge explosion, sees Fig. 7, and its operation sequence is for opening Dig coyote hole, powder charge, wiring, detonate, not necessarily detonate after powder charge.Except the flood diversion dyke on the important location of only a few may be reserved Having outside coyote hole, generally, coyote hole is by manually excavating with instruments such as army banjo, Luoyang Spade, ladle temporarily.Owing to broken dike calls time in advance Short, severe operational environment, whether breaking dike and affected by the factor such as weather, magnanimity, it is scarce that interim excavation coyote hole is primarily present two big technology Fall into: one is that excavation operating speed is relatively slow temporarily, and the broken dike of impact is carried out in time;Two is that concentrated charge coyote hole volume is relatively big, easily drops Low dyke intensity.
Summary of the invention
The purpose of this utility model be to provide a kind of for take off mouthful flood diversion can explosion dyke, with solve excavate coyote hole temporarily Operating speed is slow, reduce the defect of dyke intensity.
A kind of can explosion dyke for take off mouthful flood diversion, it is characterised in that:
Including dyke explosion section, dyke explosion section is provided with multiple boring being arranged in rows, and is provided with pre-buried dress in each boring Medicine device, each pre-buried means for loading includes for the powder charge pipeline of explosive and is located at the openable of powder charge pipe ends Duct sealing lid;It is provided with carn at the embedment of each pre-buried means for loading.
The inclination angle of described boring is 10~40 °;Array pitch and the pitch-row of boring are 2~4m, go up most hanging down of row hole drilling and levee crown Straight distance is 1~3m.
The two ends of described dyke explosion section are provided with deep-mixed pile.
Of the present utility model a kind of it be applicable to explosion and break dike and take off the pre-buried means for loading of mouthful flood diversion, including for explosive Powder charge pipeline, described powder charge pipe ends is provided with openable duct sealing lid.
This new device is embedded in dyke in advance by drillhole blasting steel for shot mode, the conduct when needs carry out flood diversion task Coyote hole uses.Primarily serving the purpose of of powder charge pipeline is embedded in dyke formation coyote hole.Duct sealing lid act as close powder charge Pipeline, it is to avoid subsoil water enters closed conduct with impurity when dyke is properly functioning, in order to avoid explosive is subject to when dike powder charge is broken in explosion Tide.
As preferably, described powder charge pipe end and duct sealing lid are provided with the screw thread complemented one another, duct sealing lid In the way of screw thread socket, powder charge pipe ends is closed.
As preferably, described duct sealing lid is flat mouth lid, and powder charge pipe end is the flat mouth supporting with duct sealing lid End, powder charge pipe ends is closed in the way of directly socket by duct sealing lid.
As preferably, described powder charge pipeline is PVC plastic material, its diameter 25~150mm, and they are a length of 10~50m years old;Institute Stating duct sealing lid is plastics or quality of rubber materials, and its diameter is than powder charge pipeline big 1~2cm.
In this utility model, the thickness of powder charge pipeline, hardness are commonly used pvc pipe with engineering and are as the criterion;The length of powder charge pipeline is pressed Explosion design is chosen, generally 10~50m.
The using method of the pre-buried means for loading of this utility model is:
Step 1, at dike construct or normal operating phase, breaks dike explosion design according to flood diversion and requires boring, inclination angle 10~ 40 °, array pitch and pitch-row take 2~4m, first row boring vertical dimension levee crown 1~3m;Step 2, by the pre-buried powder charge of sealing two ends In device embedment boring, pipeline upper end port embedment dyke 20~80cm, at embedment, stack soil stone be marked, convenient broken dike Time find pipeline carry out powder charge, simultaneously protective conduit;Step 3, needs to carry out explosion and breaks dike when taking off mouthful flood diversion task, by step 2 Mark search out pre-buried powder charge plumbing installation, open end closure on it, in pipe, carry out blast with linear charges powder charge, form explosion Networking;Step 4, receives networked detonation after explosion order.
Above-mentioned steps must use dual fail-safe detonate circuit during broken dike, generally by electric initiating circuit as main detonating line Road, primacord or the detonator circuit that detonates detonates circuit as pair, two lines road ignition and detonation simultaneously.
Of the present utility model a kind of for take off mouthful flood diversion can the advantage of explosion dyke be:
1. this utility model dyke is the most pre-buried when dyke is properly functioning, receive explosion break dike order thing can be rapid Powder charge, explosion, efficient quick;
2. powder charge conduit volume is less, less to dyke intensity effect.
Accompanying drawing explanation
Fig. 1 is this utility model pre-buried means for loading axonometric chart;
Fig. 2 is that this utility model pre-buried means for loading screw thread is socketed schematic diagram;
Fig. 3 is that the pre-buried means for loading of this utility model is directly socketed schematic diagram;
Fig. 4 is that the pre-buried means for loading of this utility model arranges drawing in side sectional elevation;
Fig. 5 is this utility model pre-buried means for loading site plan;
Fig. 6 is this utility model pre-buried means for loading powder charge schematic diagram;
Fig. 7 breaks dike schematic diagram for conventional concentrated charge explosion.
In figure: 1-powder charge pipeline;2-duct sealing lid;3-carn;4-dyke explosion section;The pre-buried means for loading of 5-; 6-gutter;7-deep-mixed pile;8-blast with linear charges;9-multiple-row blasting thing;10-goes between;11-concentrated charge burst-chamber.
Detailed description of the invention
Below in conjunction with the accompanying drawings 1~6, the utility model is described in further detail.
Embodiment 1
Break dike take off a mouthful flood diversion to make device be applied to dyke explosion generally, design holding one with conventional explosion Cause, the utility model proposes a kind of preferred version:
A kind of it be applicable to explosion and break dike and take off the pre-buried means for loading of mouthful flood diversion, including the powder charge pipeline 1 for explosive, Powder charge pipeline 1 two ends are provided with openable duct sealing lid 2, as shown in Figure 1.Powder charge pipeline 1 is PVC plastic material, its diameter 90mm;Duct sealing lid 2 is PVC plastic material, its a diameter of 100mm;Powder charge pipeline 1 port is provided with duct sealing lid 2 The screw thread complemented one another, powder charge pipeline 1 two ends are closed, as shown in Figure 2 in the way of screw thread socket by duct sealing lid 2.
The using method of the pre-buried means for loading of this utility model is as shown in Figures 4 to 6.The pre-buried means for loading of this utility model Mounted angle 20 °, array pitch 3m, pitch-row 4m, first row pipeline, away from levee crown vertical dimension 2m, pipeline upper end embedment dyke 50cm, is adopted Use enrockment covering marking.
Pre-buried for this utility model means for loading is normally used at dyke and is embedded in advance in dyke, break dike in needs explosion and take off mouth Carrying out powder charge during flood diversion to detonate, its using method is:
Step 1, holes according to powder charge pipeline 1 diameter, and boring is arranged and carried out according to explosion design;
Step 2, nuzzles in the hole being drilled the most in advance by this device of closed at both ends, and is identified at aperture enrockment;
Step 3, finds this device when receiving explosion order, and the duct sealing lid opening its upper end carries out powder charge;
Step 4, uses electric initiating circuit to detonate circuit as secondary detonating cord as main detonating line road, primacord or detonator Road, two lines road ignition and detonation simultaneously.
Embodiment 2
Certain dyke building length 800 meters, high 8 meters, slope is than for 1:3, and upper a width of 6 meters, bottom width is 54 meters.Require undertaking flood diversion During task, dike is broken in explosion, offers 200m excessive flood breach.Designing two artillery salvo holes, array pitch 3m, pitch-row 4m on request, hangs down in the first artillery salvo hole Straight distance levee crown 1.5m.Big gun hole aperture 90mm, medicine footpath 70mm, 15 ° of inclination angle, first row hole depth 20m, second row 12m.In employing hole MS5 detonator delaying blasting, electric initiating circuit is as main detonating line road, and fuse arming test experiment initiation circuit detonates circuit as pair, two lines Road ignition and detonation simultaneously.For flood diversion entrance width, use deep-mixed pile protection dike head at Kou Men both sides dike head.
This separate explosion breaks dike and takes off the pre-buried means for loading of this utility model that mouthful flood diversion uses, including the dress for explosive Pencil road 1, powder charge pipeline 1 two ends are provided with openable duct sealing lid 2, as shown in Figure 1.Powder charge pipeline 1, duct sealing lid 2 Being PVC plastic material, its diameter is respectively 90,100mm;Duct sealing lid 2 is flat mouth lid, and powder charge pipeline 1 port is and pipe The flat mouth end that road seal closure 2 is supporting, powder charge pipeline 1 two ends are closed in the way of directly socket by duct sealing lid 2, such as figure Shown in 3.
The using method of the pre-buried means for loading of this utility model is as shown in Figures 4 to 6.
The pre-buried means for loading of this utility model is installed according to following steps and is implemented:
Step 1, at dyke normal operating phase, breaks dike explosion design according to flood diversion and requires to use drill bit with well to bore Hole;
Step 2, imbeds this device of sealing two ends in boring, pipeline upper end port embedment dyke 50cm, stacks soil stone It is marked at embedment;
Step 3, needs to carry out explosion and breaks dike when taking off mouthful flood diversion task, search out this device by the mark of step 2, open it The duct sealing lid of upper end, powder charge, networking in pipe;
Step 4, receives ignition and detonation after explosion order.
Specific embodiment described herein is only to this utility model spirit explanation for example.This utility model institute Belong to those skilled in the art described specific embodiment to make various amendment or supplement or use similar Method substitute, but without departing from spirit of the present utility model or surmount scope defined in appended claims.

Claims (3)

1. one kind can explosion dyke for take off mouthful flood diversion, it is characterised in that:
Including dyke explosion section (4), dyke explosion section (4) is provided with multiple boring being arranged in rows, is provided with pre-buried in each boring Means for loading (5), each pre-buried means for loading (5) includes for the powder charge pipeline (1) of explosive and is located at powder charge pipeline (1) The openable duct sealing lid (2) at two ends;It is provided with carn (3) at the embedment of each pre-buried means for loading (5).
The most according to claim 1 a kind of can explosion dyke for take off mouthful flood diversion, it is characterised in that:
The inclination angle of described boring is 10~40 °;Array pitch and the pitch-row of boring are 2~4m, go up most row hole drilling vertical with levee crown away from From for 1~3m.
The most according to claim 1 a kind of can explosion dyke for take off mouthful flood diversion, it is characterised in that:
The two ends of described dyke explosion section (4) are provided with deep-mixed pile (7).
CN201620171969.XU 2016-03-07 2016-03-07 A kind of can explosion dyke for take off mouthful flood diversion Expired - Fee Related CN205843498U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620171969.XU CN205843498U (en) 2016-03-07 2016-03-07 A kind of can explosion dyke for take off mouthful flood diversion

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620171969.XU CN205843498U (en) 2016-03-07 2016-03-07 A kind of can explosion dyke for take off mouthful flood diversion

Publications (1)

Publication Number Publication Date
CN205843498U true CN205843498U (en) 2016-12-28

Family

ID=57627339

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620171969.XU Expired - Fee Related CN205843498U (en) 2016-03-07 2016-03-07 A kind of can explosion dyke for take off mouthful flood diversion

Country Status (1)

Country Link
CN (1) CN205843498U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108731565A (en) * 2018-05-24 2018-11-02 中钢集团武汉安全环保研究院有限公司 A kind of Prefabricated block and method of demolition blasting H profile steel structure
CN110823027A (en) * 2019-10-12 2020-02-21 南昌大学 Flood-control blasting opening structure of dike and setting method thereof
CN114061390A (en) * 2020-07-30 2022-02-18 神华神东煤炭集团有限责任公司 Blasting demolition method for artificial dam body

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108731565A (en) * 2018-05-24 2018-11-02 中钢集团武汉安全环保研究院有限公司 A kind of Prefabricated block and method of demolition blasting H profile steel structure
CN110823027A (en) * 2019-10-12 2020-02-21 南昌大学 Flood-control blasting opening structure of dike and setting method thereof
CN110823027B (en) * 2019-10-12 2022-03-22 南昌大学 Flood-control blasting opening structure of dike and setting method thereof
CN114061390A (en) * 2020-07-30 2022-02-18 神华神东煤炭集团有限责任公司 Blasting demolition method for artificial dam body

Similar Documents

Publication Publication Date Title
CN103195466B (en) A kind of directed hydraulic pressure demolition improves the method for gas permeability of coal seam
CN103615941B (en) The blasting method of modernized railway shallow-buried sector
CN108286920A (en) A kind of implementation of Tunnel Blasting and excavation
CN205843498U (en) A kind of can explosion dyke for take off mouthful flood diversion
CN104748632A (en) Underwater rock plug blasting construction method
CN106839907B (en) Underwater demolition construction method
CN101864961B (en) Method for actively preventing and controlling rock burst
CN102032844A (en) Method for blasting closed rock of shield tunnel in complex strata
CN108194094B (en) The construction technology of Tunnel Passing gas stratomere
CN106638693A (en) Dismantling construction method of immersed tunnel steel-pipe pile concrete wall by drilling and blasting
CN101608885A (en) Underwater drilling and blasting construction method of mountain river
CN108625859B (en) A kind of freeze-wellboring carbon dioxide phase transformation fracturing auxiliary driving method and its device
EA201290820A1 (en) UNDERGROUND DEVELOPMENT OF THE DEPOSIT
CN104806249B (en) A kind of short vertical shaft pilot shaft tunneling construction method
CN102518470A (en) Method for preventing and controlling water by using freezing pipes in annular water intercepting tunnel
CN101793486A (en) High-grade highway rock cutting blasting construction process
CN1560557A (en) Technology method of artificial frozen soil control blasting by deep surface forzen method
CN105401946A (en) Reverse blasting excavation method of shaft and pilot shaft
CN105823387A (en) Rapid construction method for deep hole blasting of vertical shaft frozen bedrock
CN106677786A (en) Ultra-deep large-section vertical shaft one-time blasting forming method based on electronic detonators
CN102661688A (en) Pile foundation control blasting excavation method of integral-plate rocky area
CN105953671A (en) Construction method for excavating siliceous slate stone side slope
CN103868419A (en) Smooth surface blasting construction method used in tunnel excavation process in hydraulic engineering
CN105443133A (en) Underground rock cumulative charge explosion device and method for non-excavation construction
CN103791786B (en) Underground diaphragm wall bed rock grooving pre-splitting blasting method

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Zhang Fengde

Inventor before: Zhang Fengde

CB03 Change of inventor or designer information
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161228

Termination date: 20190307

CF01 Termination of patent right due to non-payment of annual fee