CN205822451U - A kind of prefabricated assembled concrete composite beam docking connecting structure - Google Patents

A kind of prefabricated assembled concrete composite beam docking connecting structure Download PDF

Info

Publication number
CN205822451U
CN205822451U CN201620788610.7U CN201620788610U CN205822451U CN 205822451 U CN205822451 U CN 205822451U CN 201620788610 U CN201620788610 U CN 201620788610U CN 205822451 U CN205822451 U CN 205822451U
Authority
CN
China
Prior art keywords
composite beam
prefabricated assembled
docking
erection
assembled concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620788610.7U
Other languages
Chinese (zh)
Inventor
姚大鹏
吕臻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenyang Architecture University Design Group Co ltd
Original Assignee
ARCHITECTURAL DESIGNING INSTITUTE OF SHENYANG JIANZHU UNIVERSITY
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ARCHITECTURAL DESIGNING INSTITUTE OF SHENYANG JIANZHU UNIVERSITY filed Critical ARCHITECTURAL DESIGNING INSTITUTE OF SHENYANG JIANZHU UNIVERSITY
Priority to CN201620788610.7U priority Critical patent/CN205822451U/en
Application granted granted Critical
Publication of CN205822451U publication Critical patent/CN205822451U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

This utility model relates to a kind of prefabricated assembled concrete composite beam docking connecting structure, belongs to construction engineering technical field.The longitudinal reinforcement of described composite beam pre-erection stretches out in termination and in end with 180 ° of crotches, in the upside of composite beam pre-erection, overlapping layers is set, back in overlapping layers is indulged muscle termination and is also set 180 ° of crotches, the connection reinforcing bar of 180 ° of crotches of two ends band respectively with indulge muscle at the bottom of beam, back indulge muscle parallel be close to place, form force transmission ring, being inserted into 4 joint bars at each force transmission ring, overlapping layers is fixed-type for composite beam with casting concrete in the join domain of adjacent composite beam pre-erection.This utility model make full use of hooked bar mutually overlap formed force transmission ring complete prefabricated assembled concrete composite beam docking connect, its construction material, construction method are conventional material and method, simple, simplify construction, reduce cost, highly versatile, can directly apply in the engineering practice of prefabricated assembled concrete structure.

Description

A kind of prefabricated assembled concrete composite beam docking connecting structure
Technical field
This utility model belongs to construction engineering technical field, is specifically related to a kind of prefabricated assembled concrete composite beam docking Connecting structure.
Background technology
Prefabricated assembled concrete frame construction is a kind of industrialized architecture production mode, for prefabricated construction System, the beam of agent structure, plate, post all can be in factory process, it is achieved industrialized great production;The processing of batch production simultaneously, can To utilize state-of-the-art modern technologies, in the quality that objectively can ensure that structural elements.Arrive the scene of capital construction, as long as The each several part of precast construction is stitched together, prefabricated assembled concrete frame construction effect fast with its speed of application, economic The advantages such as benefit is good with environmental benefit are increasingly paid close attention to by owner and designer.Prefabricated assembled concrete framework at present In structure, the docking of Vierendeel girder or secondary beam connects and general uses sleeves grouting to connect more, this connected mode to prefabricated components and Site operation installation accuracy all has higher requirements, and requires the highest to the technology of sleeve mortar depositing construction personnel, holds in connection procedure The quality problems that sleeve both sides reinforcing bar cannot be the most in place easily occur.Therefore, on the premise of meeting strength performance, the simplest Changing the connecting structure of site operation interior joint, so that the concatenation construction program at scene is simplified, quality is ensured, this is just It it is the problem researched and solved of the present invention.
Summary of the invention
Setting a roof beam in place for current prefabricated assembled frame structure engineering center or the docking of secondary beam connects, the present invention combines prefabricated The feature of fabricated construction, it is provided that a kind of prefabricated assembled concrete composite beam docking connecting structure, it has, and design is simple, effect The features such as the best, practical, convenient construction.
The technical scheme that this utility model is given is:
Including composite beam pre-erection, connecting reinforcing bar, joint bar, delay-pour joint region and overlapping layers, described composite beam is prefabricated Indulge muscle at the bottom of the beam of part to stretch out in termination and in end with 180 ° of crotches, overlapping is set in the upside of composite beam pre-erection Layer, the back in overlapping layers indulges muscle termination and also sets 180 ° of crotches, the connection reinforcing bar of 180 ° of crotches of two ends band respectively with beam at the bottom of indulge muscle, Back is indulged muscle parallel being close to and is placed, and forms force transmission ring, is inserted into 4 joint bars, overlapping layers and adjacent composite beam at each force transmission ring In the join domain of pre-erection, casting concrete is fixed-type for composite beam.
The longitudinal reinforcement end that described composite beam pre-erection stretches out with 180 ° of crotches set up, it is straight segment length It is longitudinal reinforcement diameter that degree is no less than 10d1, d1.
Back reinforcing bar in described rear pouring concrete overlapping layers with 180 ° of crotches down-set, its flat segments length is not Should be less than 10d2, d2 is back bar diameter.
The connection steel bar end crotch in delay-pour joint region between the adjacent two composite beam pre-erections of described composite beam Direction is identical with connected longitudinal reinforcement crotch direction, and its flat segments length is no less than 10d3, d3 for connecting bar diameter.
The joint bar a length of composite beam width that described force transmission ring is inserted into deducts both sides protective layer thickness.
Described both sides power transmission interannular clear distance is preferably 100mm~400mm.
Described composite beam pre-erection end face, side arrange the concavo-convex degree of depth concrete matsurface not less than 6mm.
Described delay-pour joint region is provided with interior stirrup.
The beneficial effects of the utility model are:
Composite beam the most of the present invention docking connecting structure, is reserved 180 ° of hooked bars of end band, two ends band by beam-ends 180 ° of crotches connect joint bar composition in reinforcing bar and force transmission ring;The present invention is in work progress, to structure manufacture and in-site installation essence Spending less demanding, it is to avoid use the grouting process that difficulty is bigger, can construct by common cast-in-place concrete structure in delay-pour joint region, Speed of application greatly speeds up, and construction quality is easier to ensure that, applied range.
Composite beam the most of the present invention docking connecting structure, can make the reserved steel bar length that prefabricated components end is stretched out greatly Reduce, transport to prefabricated components, lift, in place etc. bringing convenience is installed.
Construction material the most of the present invention, construction method are conventional material and method, simple, can shorten construction period, Good in economic efficiency, highly versatile, it is adaptable to prefabricated assembling type reinforced concrete frame structure, the beam docking in other versions Connect and also refer to.
Accompanying drawing explanation
Fig. 1 is the floor map of the present invention.
Fig. 2 is the A-A generalized section of the present invention.
In figure: 1. composite beam pre-erection;2. overlapping layers;3. concrete matsurface;4. connect reinforcing bar;5. indulge muscle at the bottom of beam; 6. back indulges muscle;7. stirrup in;8. joint bar;9. force transmission ring;10. delay-pour joint region.
Detailed description of the invention
The present invention is described in detail below in conjunction with the accompanying drawings with embodiment.
Embodiment 1: as shown in Figure 1 and Figure 2, the present invention include composite beam pre-erection 1, connect reinforcing bar 4, joint bar 8, after water Join domain 10 and overlapping layers 2, the end of composite beam pre-erection 1 is stretched out and is indulged muscle 5 at the bottom of 180 ° of crotch beams of band, prefabricated at composite beam The upside of part 1 arranges overlapping layers 2, after water overlapping layers 2 in set the back with 180 ° of crotches and indulge muscle 6,180 ° of crotches of two ends band Connect reinforcing bar 4 respectively with indulge muscle 5 at the bottom of beam, back indulge muscle 6 parallel be close to place, formed force transmission ring 9, in each force transmission ring 9 interpolation Entering 4 joint bars 8, overlapping layers 2 is fixed-type with casting concrete in the join domain 10 of adjacent composite beam pre-erection 1 for overlapping Beam.
Indulge at the bottom of the beam that described composite beam pre-erection 1 stretches out muscle 5 end with 180 ° of crotches set up, its flat segments It is the diameter indulging muscle 5 at the bottom of beam that length is no less than 10d1, d1.Back in described overlapping layers 2 indulge muscle 6 with 180 ° of crotches to Lower setting, it is the diameter that back indulges muscle 6 that its flat segments length is no less than 10d2, d2.Adjacent two composite beams of described composite beam Muscle 5 and back are indulged at the bottom of connected beam in the crotch direction, reinforcing bar 4 termination that connects in delay-pour joint region 10 between pre-erection 1 Vertical muscle 6 is identical, and it is the diameter connecting reinforcing bar 4 that its flat segments length is no less than 10d3, d3.Wherein connect reinforcing bar 4 diameter with Indulged muscle 5 at the bottom of coupling beam or back to indulge muscle 6 identical.
The joint bar 8 a length of composite beam width that described force transmission ring 9 is inserted into deducts both sides protective layer thickness.Described both sides pass 9 clear distances of power ring are preferably 100mm~400mm, and this example selects 100mm.Described composite beam pre-erection 1 end face, side arrange recessed The convex degree of depth concrete matsurface not less than 6mm.Described join domain is additionally provided with interior stirrup 7.
During site operation, its order is used as following: install in place by the precast beam lifting preparing to connect;Reinforcing bar 4 will be connected Crotch upwards reserve parallel and near to both sides and indulge muscle 5 at the bottom of beam and place, adjust and connect reinforcing bar 4 position and makes both sides force transmission ring 9 the most right Claim, insert joint bar 8;Lay back and indulge muscle 6, the back that the crotch connecting reinforcing bar 4 lays parallel and near to both sides downwards is indulged muscle 6 Place, adjust connection reinforcement location and make both sides force transmission ring 9 symmetrically, insert joint bar 8;Interior in colligation delay-pour joint region 10 Stirrup 7, finally cast join domain 10 and the concrete of rear pouring concrete overlapping layers 2, complete composite beam docking and connect.
Composite beam docking described in this example connects node, should arrange concrete along composite beam pre-erection 1 end face and side thick Matte 3, its concavo-convex degree of depth is no less than 6mm, to increase shearing strength at concrete joint surface, improves globality.
Embodiment 2: this example as different from Example 1: force transmission ring 9 clear distances in described both sides are 400mm.
Embodiment 3: this example as different from Example 1: force transmission ring 9 clear distances in described both sides are 200mm.
Embodiment 4: this example as different from Example 1: force transmission ring 9 clear distances in described both sides are 300mm.

Claims (8)

1. the docking of a prefabricated assembled concrete composite beam connects joint structure, it is characterised in that: include that composite beam is prefabricated Partly, connect reinforcing bar, joint bar, delay-pour joint region and overlapping layers, indulge muscle at the bottom of the beam of described composite beam pre-erection and stretch in termination Going out and in end with 180 ° of crotches, arrange overlapping layers in the upside of composite beam pre-erection, the back in overlapping layers indulges muscle end Head also set 180 ° of crotches, the connection reinforcing bar of 180 ° of crotches of two ends band respectively with indulge muscle at the bottom of beam, back indulge muscle parallel be close to place, shape Becoming force transmission ring, be inserted into 4 joint bars at each force transmission ring, overlapping layers pours in the join domain of adjacent composite beam pre-erection Concrete is fixed-type for composite beam.
The most according to claim 1, the docking of prefabricated assembled concrete composite beam connects joint structure, it is characterised in that: institute State longitudinal reinforcement end that composite beam pre-erection stretches out with 180 ° of crotches set up, its flat segments length is no less than 10d1, d1 are longitudinal reinforcement diameter.
The most according to claim 1, the docking of prefabricated assembled concrete composite beam connects joint structure, it is characterised in that: institute State back reinforcing bar in rear pouring concrete overlapping layers with 180 ° of crotches down-set, its flat segments length is no less than 10d2, d2 are back bar diameter.
The most according to claim 1, the docking of prefabricated assembled concrete composite beam connects joint structure, it is characterised in that: institute State the connection steel bar end crotch direction in the delay-pour joint region between the adjacent two composite beam pre-erections of composite beam and connected The longitudinal reinforcement crotch direction connect is identical, and its flat segments length is no less than 10d3, d3 for connecting bar diameter.
The most according to claim 1, the docking of prefabricated assembled concrete composite beam connects joint structure, it is characterised in that: institute State the joint bar a length of composite beam width that force transmission ring is inserted into and deduct both sides protective layer thickness.
The most according to claim 1, the docking of prefabricated assembled concrete composite beam connects joint structure, it is characterised in that: institute State both sides power transmission interannular clear distance and be preferably 100mm~400mm.
The most according to claim 1, the docking of prefabricated assembled concrete composite beam connects joint structure, it is characterised in that: institute State composite beam pre-erection end face, side arranges the concavo-convex degree of depth concrete matsurface not less than 6mm.
The most according to claim 1, the docking of prefabricated assembled concrete composite beam connects joint structure, it is characterised in that: institute State delay-pour joint region and be provided with interior stirrup.
CN201620788610.7U 2016-07-26 2016-07-26 A kind of prefabricated assembled concrete composite beam docking connecting structure Active CN205822451U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620788610.7U CN205822451U (en) 2016-07-26 2016-07-26 A kind of prefabricated assembled concrete composite beam docking connecting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620788610.7U CN205822451U (en) 2016-07-26 2016-07-26 A kind of prefabricated assembled concrete composite beam docking connecting structure

Publications (1)

Publication Number Publication Date
CN205822451U true CN205822451U (en) 2016-12-21

Family

ID=57560119

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620788610.7U Active CN205822451U (en) 2016-07-26 2016-07-26 A kind of prefabricated assembled concrete composite beam docking connecting structure

Country Status (1)

Country Link
CN (1) CN205822451U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049675A (en) * 2016-07-26 2016-10-26 沈阳建筑大学建筑设计研究院 Docking connection construction of prefabricated assembly concrete superposed beams
CN109024875A (en) * 2018-07-24 2018-12-18 山东建筑大学 A kind of assembled integral concrete component and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049675A (en) * 2016-07-26 2016-10-26 沈阳建筑大学建筑设计研究院 Docking connection construction of prefabricated assembly concrete superposed beams
CN109024875A (en) * 2018-07-24 2018-12-18 山东建筑大学 A kind of assembled integral concrete component and construction method

Similar Documents

Publication Publication Date Title
CN106049675A (en) Docking connection construction of prefabricated assembly concrete superposed beams
CN103031917B (en) A kind of reinforced concrete prefabricated superimposed sheet with truss rib
CN105625572B (en) Distinctiveness uses the precast prestressed concrete frame bean column node of high performance material
CN104947831A (en) Prefabricated assembly type profile steel concrete shear wall and construction method thereof
CN203452228U (en) Frame-shear wall architectural structure
CN208486404U (en) A kind of concrete shear force wall of steel bar template integrative installation technology
CN108678220A (en) A kind of concrete shear force wall of steel bar template integrative installation technology
CN205822451U (en) A kind of prefabricated assembled concrete composite beam docking connecting structure
CN104805960B (en) One kind exempts from form removal beams of concrete and its construction method
CN108035241A (en) A kind of assembled steel-mixed combined bridge and its construction technology
CN109184029A (en) A kind of fabricated shear wall Type Composite Structure System and installation method being easily installed
CN206859478U (en) A kind of overlapping reinforced concrete slab structure for bearing heavy duty
CN206521768U (en) A kind of shear connector in the double-deck box hat concrete combined structure of immersed tube tunnel
CN105696453B (en) A kind of steel-concrete combination beam
CN209556195U (en) Fabricated Beam-Slab connection structure
CN107246094A (en) A kind of overlapping reinforced concrete slab structure and preparation method for bearing heavy duty
CN208472958U (en) A kind of partial precast assembled steel reinforced concrete giant frame structure
CN207672745U (en) A kind of node structure of precast prestressed assembled composite beam-prefabricated post
CN205421710U (en) Permanent beam mold board, concrete structure component are connected to arrangement of reinforcement formula buckle
CN105951986B (en) A kind of the mid-side node connection structure and its method of prefabricated integral frame column beam
CN106088470B (en) Assembly concrete complex case shape beam and its construction method
CN203795708U (en) Prefabricated reinforced concrete element
CN209723341U (en) A kind of bidirectional laminated slab bottom plate of close piece connection
CN209369054U (en) A kind of connecting node of concrete filled steel tube combined special-shaped column and reinforced beam
CN208219409U (en) A kind of ultra-thin prefabricated board seam connection structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 110000 No.9-10 Jianyuan Street, Shenhe District, Shenyang City, Liaoning Province

Patentee after: Institute of Planning and Architectural Design, Shenyang Architectural University

Address before: 110015 Jianyuan Street, Shenyang City, Liaoning Province, 9-10 A

Patentee before: SHENYANG JIANZHU University ARCHITECTURE DESIGNING INSTITUTE

CP03 Change of name, title or address
CP01 Change in the name or title of a patent holder

Address after: 110000 a, No. 9-10, Jianyuan street, Shenhe District, Shenyang City, Liaoning Province

Patentee after: Shenyang Architecture University Design Group Co.,Ltd.

Address before: 110000 a, No. 9-10, Jianyuan street, Shenhe District, Shenyang City, Liaoning Province

Patentee before: Institute of Planning and Architectural Design, Shenyang Architectural University

CP01 Change in the name or title of a patent holder