CN205804687U - High strength easy dismounting construction wall - Google Patents
High strength easy dismounting construction wall Download PDFInfo
- Publication number
- CN205804687U CN205804687U CN201620697000.6U CN201620697000U CN205804687U CN 205804687 U CN205804687 U CN 205804687U CN 201620697000 U CN201620697000 U CN 201620697000U CN 205804687 U CN205804687 U CN 205804687U
- Authority
- CN
- China
- Prior art keywords
- connecting pin
- lapping plate
- plate
- cap bag
- muscle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Packaging Of Annular Or Rod-Shaped Articles, Wearing Apparel, Cassettes, Or The Like (AREA)
Abstract
This utility model provides a kind of high strength easy dismounting construction wall, belongs to body of wall field;Which solve the highest problem of existing strength of wall body.This utility model includes some building blocks and T-shaped skeleton, skeleton includes two side plates, side plate is located between adjacent two building blocks, two side end overlap and form clinch, two side end that clinch is corresponding are respectively lapping plate one and lapping plate two, clinch is provided with disassembly mechanism, disassembly mechanism includes connecting pin, cap bag one and cap bag two, and it is located at the connecting hole on lapping plate one and lapping plate two, cap bag one one end is provided with shrouding, connecting pin passes connecting hole, it is connected between connecting pin head end and shrouding and has spring, cap bag two is provided with perforation, also include that be connected with wall body vertical breaks muscle, break muscle outer end and be positioned at wall outer side face, inner through perforation, and be connected with connecting pin tail end, connecting pin is provided with the annular snap slot near lapping plate two.This utility model intensity is higher, also allows for demolishing walls.
Description
Technical field
This utility model belongs to wall technology field, relates to a kind of high strength easy dismounting construction wall.
Background technology
Construction wall is generally concrete block masonry and is formed, and owing to building block exists gap, therefore the heat insulating ability at gap is poor,
Between building block, bonding strength is the highest simultaneously, makes strength of wall body poor, if but be internally formed ruggedized construction at body of wall, then can be to body of wall
Dismounting causes trouble, it is therefore necessary to improve.
Summary of the invention
The purpose of this utility model is for the above-mentioned problems in the prior art, it is provided that a kind of bulk strength is more
Height, and easy-to-dismount high strength easy dismounting construction wall.
The purpose of this utility model can be realized by following technical proposal: a kind of high strength easy dismounting construction wall, bag
Including some square building blocks mutually built by laying bricks or stones, laterally adjacent building block linking is built by laying bricks or stones, and longitudinally adjacent building block dislocation is built by laying bricks or stones, and its feature exists
In: also including some T-shaped skeletons, skeleton includes that orthogonal two side plates, a side plate are located at laterally adjacent two building blocks
Between, another side plate is located between longitudinally adjacent two building blocks, and each building block surrounding is provided with six described skeletons, phase altogether
Two adjacent side end overlap and are formed clinch, and two side end that clinch is corresponding are respectively lapping plate one and overlap joint
Plate two, clinch is provided with disassembly mechanism, and disassembly mechanism includes connecting pin, cap bag one and cap bag two, and is respectively provided at overlap joint
The side that connecting hole on plate one and lapping plate two, cap bag one and cap bag two are contrary with lapping plate one and lapping plate two respectively connects
Connecing, cap bag one is provided with shrouding away from one end of lapping plate one, and connecting pin passes lapping plate one and the connecting hole of lapping plate two, connects
Being connected between plunger end and shrouding and have spring, cap bag two is provided with perforation, also includes that be connected with wall body vertical breaks muscle, breaks
Muscle outer end is positioned at wall outer side face, inner through perforation, and is connected with connecting pin tail end, and connecting pin is provided with near lapping plate two
Annular snap slot, snap slot is positioned at the side of the reverse lapping plate one of lapping plate two, and can pull connecting pin by breaking muscle, makes
Connecting pin fractures at snap slot, and makes spring pull connecting pin to be placed in cap bag one, and now connecting pin separates with connecting hole.
Owing to the side plate of skeleton is connected in the gap of building block, therefore certain guarantor is played in the gap between building block
Temperature effect, is sequentially connected with side plate by connecting pin simultaneously, makes some skeletons connect as one so that bulk strength is higher, when needing
Time to be demolished walls, it is only necessary to utilize instrument, break outward muscle, make to break muscle and pull connecting pin, make connecting pin fracture at snap slot,
And make spring pull connecting pin to be placed in cap bag one, now connecting pin separates with connecting hole, and some skeletons can be made to be separated from each other,
Can conveniently demolish walls.
As preferably, described muscle outer end connection of breaking has the baffle plate being against on wall outer side face.
Therefore can make to break muscle stable connection.
As preferably, described muscle outer end of breaking passes baffle plate, and is provided with draw ring.
Therefore it is easy to pull-out and breaks muscle.
As preferably, described side plate is steel plate, and breaking muscle is reinforcing bar.
Compared with prior art, this utility model has the advantage that
Owing to the side plate of skeleton is connected in the gap of building block, therefore certain guarantor is played in the gap between building block
Temperature effect, is sequentially connected with side plate by connecting pin simultaneously, makes some skeletons connect as one so that bulk strength is higher, when needing
Time to be demolished walls, it is only necessary to utilize instrument, break outward muscle, make to break muscle and pull connecting pin, make connecting pin fracture at snap slot,
And make spring pull connecting pin to be placed in cap bag one, now connecting pin separates with connecting hole, and some skeletons can be made to be separated from each other,
Can conveniently demolish walls.
Accompanying drawing explanation
Fig. 1 is main TV structure schematic diagram of the present utility model;
Fig. 2 is the partial enlarged drawing in Fig. 1;
Fig. 3 is partial side structural representation of the present utility model.
Coding in figure is respectively as follows:
1, building block;2, skeleton;21, side plate;3, lapping plate one;31, connecting hole;32, cap bag one;33, shrouding;34, spring;
4, lapping plate two;41, cap bag two;42, perforation;5, connecting pin;51, snap slot;6, muscle is broken;61, baffle plate;62, draw ring.
Detailed description of the invention
The following is specific embodiment of the utility model and combine accompanying drawing, the technical solution of the utility model is made further
Description, but this utility model is not limited to these embodiments.
As shown in Figure 1, Figure 2 and Figure 3, this high strength easy dismounting construction wall, including some square building blocks mutually built by laying bricks or stones
1, laterally adjacent building block 1 linking is built by laying bricks or stones, and longitudinally adjacent building block 1 dislocation is built by laying bricks or stones, also includes some T-shaped skeletons 2, and skeleton 2 includes phase
Two the most vertical side plates 21, a side plate 21 is located between laterally adjacent two building blocks 1, and another side plate 21 is located at longitudinal phase
Between adjacent two building blocks 1, and each building block 1 surrounding is provided with six skeletons 2 altogether, and two adjacent side plate 21 lapping ends are also formed
Clinch, two side plate 21 ends that clinch is corresponding are respectively lapping plate 1 and lapping plate 24, and clinch is provided with dismounting
Mechanism, disassembly mechanism includes connecting pin 5, cap bag 1 and cap bag 2 41, and is respectively provided at lapping plate 1 and lapping plate 24
On connecting hole 31, contrary with lapping plate 1 and the lapping plate 24 respectively side of cap bag 1 and cap bag 2 41 connects, cap bag
One 32 are provided with shrouding 33 away from one end of lapping plate 1, connecting pin 5 through lapping plate 1 and the connecting hole 31 of lapping plate 24,
Being connected between connecting pin 5 head end and shrouding 33 and have spring 34, cap bag 2 41 is provided with perforation 42, also includes being connected with wall body vertical
Break muscle 6, break muscle 6 outer end and be positioned at wall outer side face, inner through perforation 42, and be connected with connecting pin 5 tail end, connecting pin
5 are provided with the annular snap slot 51 near lapping plate 24, and snap slot 51 is positioned at the side of the reverse lapping plate 1 of lapping plate 24,
And connecting pin 5 can be pulled by breaking muscle 6, make connecting pin 5 fracture at snap slot 51, and make spring 34 pull connecting pin 5 to put
In cap bag 1, now connecting pin 5 separates with connecting hole 31.
Further, break the connection of muscle 6 outer end and have the baffle plate 61 being against on wall outer side face.Break muscle 6 outer end through gear
Plate 61, and it is provided with draw ring 62.Side plate 21 is steel plate, breaks muscle 6 for reinforcing bar.
Owing to the side plate 21 of skeleton 2 is connected in the gap of building block 1, therefore the gap between building block 1 is played one
Fixed insulation effect, is sequentially connected with side plate 21 by connecting pin 5 simultaneously, makes some skeletons 2 connect as one so that bulk strength
Higher, when needs are demolished walls, it is only necessary to utilize instrument, break outward muscle 6, make to break muscle 6 and pull connecting pin 5, make connecting pin 5 exist
Fractureing at snap slot 51, and make spring 34 pull connecting pin 5 to be placed in cap bag 1, now connecting pin 5 separates with connecting hole 31,
Some skeletons 2 can be made to be separated from each other, can conveniently demolish walls.
Claims (4)
1. a high strength easy dismounting construction wall, including some square building blocks (1) mutually built by laying bricks or stones, laterally adjacent building block (1)
Linking is built by laying bricks or stones, and longitudinally adjacent building block (1) dislocation is built by laying bricks or stones, it is characterised in that: also including some T-shaped skeletons (2), skeleton (2) includes
Orthogonal two side plates (21), a side plate (21) is located between laterally adjacent two building blocks (1), another side plate (21)
It is located between longitudinally adjacent two building blocks (1), and each building block (1) surrounding is provided with six described skeletons (2), adjacent two altogether
Individual side plate (21) lapping ends also forms clinch, and two side plate (21) ends that clinch is corresponding are respectively lapping plate one (3)
With lapping plate two (4), clinch is provided with disassembly mechanism, and disassembly mechanism includes connecting pin (5), cap bag one (32) and cap bag two
, and be respectively provided at the connecting hole (31) on lapping plate one (3) and lapping plate two (4), cap bag one (32) and cap bag two (41)
(41) contrary with lapping plate one (3) and lapping plate two (4) respectively side connects, and cap bag one (32) is away from lapping plate one (3)
One end is provided with shrouding (33), and connecting pin (5) passes lapping plate one (3) and the connecting hole (31) of lapping plate two (4), connecting pin (5)
It is connected between head end with shrouding (33) and has spring (34), cap bag two (41) to be provided with perforation (42), also include with wall body vertical even
Connect breaks muscle (6), breaks muscle (6) outer end and is positioned at wall outer side face, inner through perforation (42), and with connecting pin (5) tail end
Connecting, connecting pin (5) is provided with the annular snap slot (51) near lapping plate two (4), and snap slot (51) is positioned at lapping plate two (4)
The reversely side of lapping plate one (3), and connecting pin (5) can be pulled by breaking muscle (6), make connecting pin (5) in snap slot (51)
Place fractures, and makes spring (34) pull connecting pin (5) to be placed in cap bag one (32), now connecting pin (5) and connecting hole (31) point
From.
High strength easy the most according to claim 1 dismounting construction wall, it is characterised in that: described breaks muscle (6) outer end
Connect and have the baffle plate (61) being against on wall outer side face.
High strength easy the most according to claim 2 dismounting construction wall, it is characterised in that: described breaks muscle (6) outer end
Through baffle plate (61), and it is provided with draw ring (62).
High strength easy the most according to claim 3 dismounting construction wall, it is characterised in that: described side plate (21) is steel
Plate, breaking muscle (6) is reinforcing bar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620697000.6U CN205804687U (en) | 2016-07-04 | 2016-07-04 | High strength easy dismounting construction wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620697000.6U CN205804687U (en) | 2016-07-04 | 2016-07-04 | High strength easy dismounting construction wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205804687U true CN205804687U (en) | 2016-12-14 |
Family
ID=58139893
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620697000.6U Expired - Fee Related CN205804687U (en) | 2016-07-04 | 2016-07-04 | High strength easy dismounting construction wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205804687U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
PL126873U1 (en) * | 2017-12-13 | 2019-06-17 | Mbm-Bud Spółka Z Ograniczoną Odpowiedzialnością | Vertical connector for precast walls |
-
2016
- 2016-07-04 CN CN201620697000.6U patent/CN205804687U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
PL126873U1 (en) * | 2017-12-13 | 2019-06-17 | Mbm-Bud Spółka Z Ograniczoną Odpowiedzialnością | Vertical connector for precast walls |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205804687U (en) | High strength easy dismounting construction wall | |
CN105569211A (en) | Fabricated wall, wall board and construction method | |
CN205804686U (en) | Novel construction wall | |
CN204059953U (en) | Hang mould prefab form | |
CN204152527U (en) | The combined type preliminary bracing system of wall multiple-arch tunnel in implicit expression | |
CN205314289U (en) | Assembled wall body, assembled wallboard and assembled wall body subassembly | |
CN104074126B (en) | A kind of steel reinforced concrete composite beam plate structure of small-sized bridges and culverts | |
CN204531072U (en) | A kind of light thermal-insulation partition board connected without slurry | |
CN207194220U (en) | A kind of construction steel structure wall | |
CN202144630U (en) | Tie bar structure for building with masonry structure | |
CN101492964A (en) | Mass concrete construction method | |
CN204975309U (en) | Heat preservation zirconium english brick | |
CN205713154U (en) | A kind of interior wall transverse squeezing device | |
CN204139602U (en) | For drawing device in construction formwork | |
CN205804769U (en) | Construction wall | |
CN205472108U (en) | Villa ladder car stand | |
CN103225358B (en) | Partition plate connecting structure for compound partition | |
CN204139604U (en) | Construction formwork is to drawing device | |
CN204456876U (en) | A kind of two-part split bolt | |
CN217419984U (en) | Quick construction device and system | |
CN206070800U (en) | High-strength building body of wall | |
CN207794378U (en) | A kind of modified steel construction wall | |
CN202831306U (en) | Building wallboard | |
CN203145320U (en) | Anti-cracking lightweight partition plate | |
CN107882189A (en) | A kind of building combined wall board with high integrated connection intensity |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20170728 Address after: 225000, No. 330 Hanjiang Road, Yangzhou (constellation International Business Center), -701, 702, 703, 705, 706, and Patentee after: JIANGSU MANTANGHONG BUILDING DECORATION ENGINEERING CO.,LTD. Address before: 362804 Fujian city of Quanzhou province Nan Pu Zhen Liu CuO Cun Liu Cuo, Quangang District No. 128 Patentee before: Liu Yilong |
|
TR01 | Transfer of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20161214 |
|
CF01 | Termination of patent right due to non-payment of annual fee |