CN205776276U - A kind of large-scale buried friction pile of side slope two-part props up mark structure - Google Patents

A kind of large-scale buried friction pile of side slope two-part props up mark structure Download PDF

Info

Publication number
CN205776276U
CN205776276U CN201620655747.5U CN201620655747U CN205776276U CN 205776276 U CN205776276 U CN 205776276U CN 201620655747 U CN201620655747 U CN 201620655747U CN 205776276 U CN205776276 U CN 205776276U
Authority
CN
China
Prior art keywords
friction pile
side slope
buried
pile
scale
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620655747.5U
Other languages
Chinese (zh)
Inventor
沈志平
孙洪
张建磊
袁江文
付君宜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Zhengye Engineering & Investment Inc Ltd
Original Assignee
Guizhou Zhengye Engineering & Investment Inc Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Zhengye Engineering & Investment Inc Ltd filed Critical Guizhou Zhengye Engineering & Investment Inc Ltd
Priority to CN201620655747.5U priority Critical patent/CN205776276U/en
Application granted granted Critical
Publication of CN205776276U publication Critical patent/CN205776276U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model discloses a kind of large-scale buried friction pile of side slope two-part and prop up mark structure, wherein, buried friction pile (1) build-in is on the complete basement rock of side slope middle, entirely bury friction pile (2) build-in on the complete basement rock in side slope forward position, prestress anchorage cable (3) be arranged at side slope forward position domatic on.This utility model is according to this problem of large-scale slope retaining, by buried friction pile (1) and the collaborative work of entirely burying friction pile (2), reasonably it is assigned with the Thrust of Landslide of whole large-scale side slope, and the prestress anchorage cable on domatic with side slope forward position combines, define a kind of comprehensive processing method for large-scale side slope, solve traditional friction pile multisection type and prop up shelves, relatively independent work between each stake, it is impossible to give full play to the problem that each friction pile props up grade effect.

Description

A kind of large-scale buried friction pile of side slope two-part props up mark structure
Technical field
This utility model relates to a kind of large-scale slope supporting structure, particularly relates to a kind of large-scale side slope segmentation retaining structure.
Background technology
The expansion built along with country's economy of large scale, in the engineering construction such as water conservancy and hydropower, traffic, mine, national defence often The reinforcing problem of large-scale side slope can be run into.Owing to large-scale slope and land slide thrust is very big, if only with a shelves of one-part form, the most right Strength and stiffness in a mark structure require high, are all difficult to when actual design and construction;Prop up according to conventional segmentation Shelves, every section mark structure plays bracing effect only for the side slope in this section so that each shelves section is relatively independent, this shelves Form typically requires multistage and props up shelves, and cost is of a relatively high.How by a kind of with low cost, version is simple, construction A mark structure of process safety, solves a shelves problem of large-scale side slope, is the difficult problem needing in slope treatment problem to solve.
Summary of the invention
Problem to be solved in the utility model is: provide a kind of large-scale buried friction pile of side slope two-part to prop up mark structure, solves A certainly shelves problem of large-scale side slope, guarantees that this ruggedized construction technique is simple simultaneously, with low cost, work progress safety.
Organization plan of the present utility model is: a kind of large-scale buried friction pile of side slope two-part props up mark structure, including buried Friction pile, buries friction pile and prestress anchorage cable entirely, and described buried friction pile build-in is in side slope middle, and buried depth rate is at 35%-54% Between, embed the complete basement rock degree of depth and be not less than 4 meters;The described friction pile build-in that entirely buries, in side slope forward position, embeds the complete basement rock degree of depth It is not less than 4 meters;Described prestress anchorage cable be arranged at side slope forward position domatic on, and be anchored on complete basement rock, anchorage length depends on Determine according to practical engineering calculation.
Described buried friction pile and entirely bury friction pile and be square-section embedded rock pile.
Described buried friction pile and the horizontal layout entirely burying friction pile are interlaced arrangement shape.
Buried friction pile, build-in is on the complete basement rock of side slope middle, and buried depth rate be (the stake top buried depth degree of depth and thickness of sliding body Ratio) between 35%-54%;Entirely burying friction pile, build-in is on the complete basement rock in side slope forward position.When buried friction pile buried depth rate When being 35%, this friction pile by the 80% of pile body Thrust of Landslide behind all, remaining 20% Thrust of Landslide will by build-in in The friction pile that entirely buries in side slope forward position bears, the most entirely bury friction pile will bear after self stake with buried friction pile pile body before whole sliding Remaining 20% Thrust of Landslide after slope thrust and buried friction pile pile body;When buried depth rate is 54%, buried friction pile is by stake The 60% of whole Thrust of Landslide after one's death, remaining 40% Thrust of Landslide will be born by entirely burying friction pile, the most entirely bury friction pile and will hold By after self stake with buried friction pile pile body before whole Thrust of Landslide and buried friction pile pile body after remaining 40% landslide Thrust;When buried depth rate is between 35%-54%, buried friction pile can be obtained by linear interpolation and entirely bury between friction pile The distribution of Thrust of Landslide.Buried friction pile with entirely bury friction pile and be square-section, and embed the complete basement rock degree of depth and be all not less than 4 Rice.Buried friction pile and entirely bury friction pile in horizontal layout, presents interlaced arrangement.Prestress anchorage cable is arranged at side slope forward position On domatic, playing bank protection effect for side slope surface, and be anchored in complete basement rock, anchorage length is true according to practical engineering calculation Fixed.
Large-scale side slope two-part of the present utility model buried friction pile retaining structure includes buried friction pile, entirely buries friction pile With three major parts of prestress anchorage cable, buried friction pile build-in in side slope middle, entirely buries friction pile build-in in side slope forward position, cuts Face is square-section, and build-in is not less than 4 meters in the degree of depth of complete basement rock.Buried friction pile and entirely bury friction pile in the plane Arrange in interlaced arrangement.Arranging prestress anchorage cable on side slope forward position is domatic, and be anchored on complete basement rock, anchorage length is according to real Border engineering calculation determines.
This utility model has the beneficial effect that following aspect:
For large-scale side slope, owing to Thrust of Landslide is relatively big, buried friction pile is solely subjected to a rear section Thrust of Landslide, this part Residue Thrust of Landslide bear by entirely burying friction pile, can come down for side slope entirety by adjusting the buried friction pile buried depth degree of depth Thrust is allocated so that buried friction pile and entirely bury the common co-ordination of friction pile, reaches the effect of corporation governance side slope, solves The multisection type friction pile having determined traditional props up mark structure, relatively independent work between each stake, it is impossible to give full play to each friction pile Prop up shelves effect;Being distributed by rational Thrust of Landslide, it is possible to reduce gear number amount is propped up in the segmentation of friction pile, reduction is constructed into simultaneously This.
Accompanying drawing explanation
Fig. 1 is this utility model structural representation profile;
Fig. 2 is this utility model structural representation plane graph.
Detailed description of the invention
Below in conjunction with specific embodiment, the utility model is described in further detail, but the technical solution of the utility model is not It is limited to following example.
As it is shown in figure 1, a kind of large-scale buried friction pile of side slope two-part props up mark structure, including buried friction pile 1, entirely bury anti- Sliding pile 2, prestress anchorage cable 3.As in figure 2 it is shown, described buried friction pile 1 and the horizontal layout entirely burying friction pile 2 are interlaced arrangement Shape.
Carry out the construction of buried friction pile 1 at the middle part needing slope supported, buried friction pile 1 is the embedding rock in square-section Stake, reinforced concrete structure, build-in Thrust of Landslide after side slope middle is carried on the body with soldier pile, pile body socket length is not less than 4 Rice.After buried friction pile 1 pours, due to buried depth rate, producing space between top, stake top and earth's surface, this space is adopted Pour with low-grade plain concrete and fill and lead up.
After buried friction pile 1 construction and maintenance, entirely bury the construction of friction pile 2 in the forward position of slope supported, entirely bury Friction pile 2 is similarly square-section embedded rock pile, and pile body socket length is not less than 4 meters, reinforced concrete structure.
After entirely burying friction pile 2 construction and maintenance, on side slope forward position is domatic, carry out the construction of prestress anchorage cable 3, anchoring Length determines according to practical engineering calculation.

Claims (3)

1. the one kind large-scale buried friction pile of side slope two-part props up mark structure, it is characterised in that: include buried friction pile (1), entirely bury Friction pile (2) and prestress anchorage cable (3), described buried friction pile (1) build-in in side slope middle, buried depth rate 35%-54% it Between, embed the complete basement rock degree of depth and be not less than 4 meters;Described friction pile (2) build-in that entirely buries, in side slope forward position, embeds the complete basement rock degree of depth It is not less than 4 meters;Described prestress anchorage cable (3) be arranged at side slope forward position domatic on, and be anchored on complete basement rock.
The one the most according to claim 1 large-scale side slope buried friction pile of two-part props up mark structure, it is characterised in that: described Buried friction pile (1) and entirely bury friction pile (2) and be square-section embedded rock pile.
The one the most according to claim 1 large-scale side slope buried friction pile of two-part props up mark structure, it is characterised in that: described Buried friction pile (1) and the horizontal layout entirely burying friction pile (2) are interlaced arrangement shape.
CN201620655747.5U 2016-06-28 2016-06-28 A kind of large-scale buried friction pile of side slope two-part props up mark structure Active CN205776276U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620655747.5U CN205776276U (en) 2016-06-28 2016-06-28 A kind of large-scale buried friction pile of side slope two-part props up mark structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620655747.5U CN205776276U (en) 2016-06-28 2016-06-28 A kind of large-scale buried friction pile of side slope two-part props up mark structure

Publications (1)

Publication Number Publication Date
CN205776276U true CN205776276U (en) 2016-12-07

Family

ID=58128404

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620655747.5U Active CN205776276U (en) 2016-06-28 2016-06-28 A kind of large-scale buried friction pile of side slope two-part props up mark structure

Country Status (1)

Country Link
CN (1) CN205776276U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106988325A (en) * 2017-05-05 2017-07-28 中国地质大学(武汉) A kind of apparatus and method for realizing friction pile piles with different spacing for side slope
CN112989465A (en) * 2021-03-09 2021-06-18 贵州正业工程技术投资有限公司 Design method of slope deep-buried shear pile supporting structure based on plane sliding method
CN112989466A (en) * 2021-03-09 2021-06-18 贵州正业工程技术投资有限公司 Design method of slope deep-buried shear pile supporting structure based on simple layout method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106988325A (en) * 2017-05-05 2017-07-28 中国地质大学(武汉) A kind of apparatus and method for realizing friction pile piles with different spacing for side slope
CN112989465A (en) * 2021-03-09 2021-06-18 贵州正业工程技术投资有限公司 Design method of slope deep-buried shear pile supporting structure based on plane sliding method
CN112989466A (en) * 2021-03-09 2021-06-18 贵州正业工程技术投资有限公司 Design method of slope deep-buried shear pile supporting structure based on simple layout method
CN112989466B (en) * 2021-03-09 2023-03-03 贵州正业工程技术投资有限公司 Design method of slope deep-buried shear pile supporting structure based on simple distribution method

Similar Documents

Publication Publication Date Title
CN102134998B (en) Construction method for wind-blown sand tunnel
CN205776276U (en) A kind of large-scale buried friction pile of side slope two-part props up mark structure
CN209924998U (en) Shallow earthing shield tunnel is worn road reinforcement protection architecture down
CN103244130A (en) Quick excavation and expanding construction method of herringbone tunnel section
CN105298516A (en) Combined supporting structure of steel pipe pile steel-bar-embedded tunnel composite lining used for soft foundation
CN105155548A (en) Cable double-row pile (wall) supporting structure
CN103321234B (en) Constructing method of load-bearing structure built on high slope or geological complex area
CN205225280U (en) A combined supporting structure that is used for steel -pipe pile bar planting tunnel composite lining of soft base
CN102425155A (en) Method for reinforcing overlying shallow rockmass in mined-out area
CN205742299U (en) A kind of an ultra shallow buries the float Structure of shield tunnel
CN108194104A (en) A kind of interval rock pillar reinforcement means of city shallow embedding small-clear-distance tunnel
CN106120804B (en) A kind of super-giant foundation pit double-row pile second level support system and its construction method
CN205062827U (en) Compound seepage prevention structure of large -scale solution cavity in karst area
CN206157496U (en) Moderate -low speed magnetic levitation traffic engineering single line location pile foundation combined type support rail girder construction of filling
CN106283948B (en) Medium-and low-speed maglev traffic engineering two-wire embankment location pile foundation joist type support rail girder construction
CN205188976U (en) Drag -line double row pile supporting construction
CN103966981B (en) Force transferring structure and the construction method thereof of arch dam is built on weathering rock mass
CN204780939U (en) Masts type double row pile struts system
CN105696701A (en) Along-slope shear wall building development platform and construction method thereof
CN206157484U (en) Moderate -low speed magnetic levitation traffic engineering single line location supporting beam of pile foundation formula support rail girder construction of filling
CN206157483U (en) Moderate -low speed magnetic levitation traffic engineering double -line location supporting beam of pile foundation formula support rail girder construction of filling
CN206127736U (en) Moderate -low speed magnetic levitation double -line compound framing formula support rail roof beam transition section structure of location pile foundation that fills
CN201908313U (en) Side slope reinforcement structure
CN104404964B (en) A kind of containing thick mud layer deep big foundation pit four synchronization job excavation supporting construction method
CN104500079A (en) Tunnel excavation method in shallow-buried bias-pressure toppling-deformation bulk solid and strong-unloading rock structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant