CN204780939U - Masts type double row pile struts system - Google Patents

Masts type double row pile struts system Download PDF

Info

Publication number
CN204780939U
CN204780939U CN201520408280.XU CN201520408280U CN204780939U CN 204780939 U CN204780939 U CN 204780939U CN 201520408280 U CN201520408280 U CN 201520408280U CN 204780939 U CN204780939 U CN 204780939U
Authority
CN
China
Prior art keywords
seat
soldier pile
fender pile
pile
row
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520408280.XU
Other languages
Chinese (zh)
Inventor
谢纯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201520408280.XU priority Critical patent/CN204780939U/en
Application granted granted Critical
Publication of CN204780939U publication Critical patent/CN204780939U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model discloses a masts type double row pile struts system, including a front -seat fender pile, a back row fender pile, a front -seat fender pile is through first pressure top beam connected, a back row fender pile passes through the second and presses top beam connected, a front -seat fender pile maintains an equal level with ground, a back row fender pile elevates above the soil, forms suo zhu, suo zhuyu be provided with at least prestressed anchorage cable between the front -seat fender pile, prestressed anchorage cable with suo zhu forms and is lighter than 90 degrees contained angle. The utility model discloses a front -seat fender pile and a back row fender pile are connected to the anchor rope, for front -seat suo zhu provides firm support, have increased cantilever type supporting construction's flexural rigidity, and during the foundation ditch excavation, a front -seat fender pile plays the effect of sharing the soil pressure, and the back row is strutted the stake and is played and keep off and draw anchor dual function. The utility model discloses do not support in not having, the construction is convenient, the work efficiency is high, the quality is controllable, have good economic benefits.

Description

A kind of masts type Double-row Piles Support system
Technical field
The utility model belongs to building foundation pit supporting systems technology field, is specifically related to a kind of masts type Double-row Piles Support system.
Background technology
Along with developing rapidly of the novel urbanization planning construction of country, deep foundation ditch has become important component part that is high-rise and super highrise building, and its support engineering has also become the important subitem of construction engineering.Common building foundation pit supporting pattern has undisturbed soil to put the combination of the supporting types such as slope, plate brad supporting, bolt-spary supports, pile-anchor retaining, joist anchor supporting, the supporting of campshed cantilever, steel sheet pile supporting, diaphragm wall and support supporting and wherein two kinds and two or more supporting type, and the pattern foundation pit supporting structure of current most object of construction production adopts above-mentioned supporting type.
Because city building density is more and more higher, congested in traffic, narrow field, geological conditions washability is poor.In order to make full use of soil, the new building deep big foundation pit supporting type of contiguous existing building is restricted.Obviously traditional slope of putting cannot be adopted to excavate, plate brad supporting and bolt-spary supports method can not be carried out again.Take traditional stake (wall) anchor supporting, because neighbour builds the restriction of underground structure and pipeline, soil body limited width behind slope, so anchor cable angle is comparatively large, supporting effect is not good, the anchor cable and some side slopes cannot be constructed at all.Diaphragm wall adds and supports the method for supporting, as interim soil-baffling structure comparatively other method costly, special geological conditions or construction method improper, easily occur that adjacent wall section can not be alignd and leak water problem, the process of waste mud is cumbersome.
" overhang mill pattern " is not with inner support, anchor pole (rope), the soil pressure that the drag entirely provided by the part embedded in the soil body applies to balance foundation pit side-wall supporting and protection structure.Usually, when foundation depth is little, to can yet be regarded as a kind of supporting and protection structure type preferably from aspect analyses such as cost, construction period, construction technologies.But displacement is remarkable by the impact of insert depth, can not meet the requirement of complicated deep big foundation pit engineering stability and controlling distortion aspect.
Utility model content
Large in order to solve above-mentioned " cantilever supporting structure pattern " displacement at pile top, the problem being not suitable for deep big foundation pit is affected by insert depth, the utility model is in order to improve stress performance and the deformation characteristic of Cantilever Retaining, excavate the potential of supporting pile body, supporting and protection structure form is made more to be tending towards rationally reliable, meet the requirement that complicated deep big foundation pit props up the gear soil body, fully utilize the limited underground space, traditional double-row pile gantry type frame construction pattern is improved, remove linking beam or whole plate, propose a kind of masts type Double-row Piles Support system.
In order to solve the problem, the utility model is achieved by following technical scheme:
Masts type Double-row Piles Support system described in the utility model, comprise front-seat soldier pile, rear row's soldier pile, described front-seat soldier pile is connected by the first capping beam, described rear row's soldier pile is connected by the second capping beam, described front-seat soldier pile and ground maintain an equal level, described rear row's soldier pile elevates above the soil, and forms Suo Zhu; Be provided with at least one prestress anchorage cable between described Suo Zhu and described front-seat soldier pile, described prestress anchorage cable and described Suo Zhu form the angle being less than 90 degree.
Further, in order to provide support power for front-seat soldier pile better, the height of described Suo Zhu is greater than the trestle column of described front-seat soldier pile and rear row's soldier pile.
Further, in order to increase the stability of structure, the degree of depth that described rear row's soldier pile embeds front-seat soldier pile embedding soil described in native depth ratio is dark.
Further, the two ends of described prestress anchorage cable are anchored respectively at described front-seat soldier pile and Suo Zhushang.
Further, the layout of described front-seat soldier pile and described rear row's soldier pile is that rectangular array is arranged or T-shaped formula is arranged, limit is arcuately arranged, quincunx is arranged, two trigonometric expression is arranged.
Compared with prior art, the beneficial effects of the utility model are:
The utility model increases the bending rigidity of cantilever supporting structure, and during excavation of foundation pit, front campshed plays a part to share soil pressure, and then campshed has been held concurrently and propped up gear and draw anchor double action.
Comparatively linking beam cost is low for anchor cable of the present utility model, and effectively improves the stability of Double-row-piles Structure, increases its resistance to capsizing.
The utility model makes full use of pile soil common action, plays the self-bearing capacity of the soil body between two campsheds, changes soil body lateral pressure distribution, strengthens supporting effect.
The utility model is applicable to multiple foundation condition, from weak soil to hard stratum, closely knit sandy gravel stratum, various soft or hard rocks etc. can be applied, ground limited within can making full use of building line and space, play returns of investment.
The utility model is high, quality controllable without inner support, convenient construction, work efficiency, have good economic benefit, and anchor cable can be recycled, cost-saving.
Accompanying drawing explanation
Below in conjunction with accompanying drawing, detailed description of the invention of the present utility model is described in further detail, wherein:
Fig. 1 is the schematic diagram of masts type Double-row Piles Support system described in the utility model;
Fig. 2 is the top view of masts type Double-row Piles Support system described in the utility model.
In figure: the front-seat soldier pile of 1-, 2-first capping beam, 3-anchor cable, 4-Suo Zhu, 5-second capping beam, arranges soldier pile after 6-.
Detailed description of the invention
Below in conjunction with accompanying drawing, preferred embodiment of the present utility model is described, should be appreciated that preferred embodiment described herein is only for instruction and explanation of the utility model, and be not used in restriction the utility model.
As shown in Fig. 1 ~ Fig. 2, novel Retaining Structure with Double-row Piles described in the utility model, comprise front-seat soldier pile 1, rear row's soldier pile 6, for connecting the first capping beam 2 of described front-seat soldier pile 1, for connecting the second capping beam 5 of described rear row's soldier pile 6, described front-seat soldier pile 1 maintains an equal level with ground, described rear row's soldier pile 6 elevates above the soil, form Suo Zhu 4, at least one prestress anchorage cable 3 is provided with between described Suo Zhu 4 and described front-seat soldier pile 1, prestress anchorage cable 3 in the present embodiment is three, but prestress anchorage cable 3 of the present utility model is not limited to three, can according to the needs of the construction of reality, arrange one, article two, article four, the prestress anchorage cable 3 of grade.Described prestress anchorage cable 3 forms with described Suo Zhu 4 angle being less than 90 degree.The two ends of described prestress anchorage cable are separately positioned on the reinforcing cage in described front-seat soldier pile 1 and Suo Zhu 4.Or the two ends of described prestress anchorage cable are anchored the surface at described front-seat soldier pile and Suo Zhu respectively.
The height of described Suo Zhu 4 is greater than the spacing of described front-seat soldier pile 1 and rear row's soldier pile.
In order to provide more reliable support force, the degree of depth that described rear row's soldier pile 6 embeds front-seat soldier pile embedding soil described in native depth ratio is dark.
As shown in Figure 2, the described front-seat soldier pile 1 in the present embodiment is set to apart from shape arranged in arrays with the plane of rear row's soldier pile 6.But this arranges by novel front-seat soldier pile 1 and the plane of rear row's soldier pile 6 and is not limited to rectangular array and arranges, also can according to actual needs, T-shaped formula is arranged, limit is arcuately arranged, quincunx layout or two trigonometric expression layout.
The utility model adopts anchor cable to connect front-seat soldier pile and rear row's soldier pile, for front-seat Suo Zhu provides firm support, increase the bending rigidity of cantilever supporting structure, during excavation of foundation pit, front-seat soldier pile plays a part to share soil pressure, and then campshed has been held concurrently and propped up gear and draw anchor double action.The utility model is high, quality controllable without inner support, convenient construction, work efficiency, have good economic benefit.
Described in the present embodiment, other structure of masts type Double-row Piles Support system is see prior art.
The above, it is only preferred embodiment of the present utility model, not any pro forma restriction is done to the utility model, therefore everyly do not depart from technical solutions of the utility model content, the any amendment done above embodiment according to technical spirit of the present utility model, equivalent variations and modification, all still belong in the scope of technical solutions of the utility model.

Claims (5)

1. a masts type Double-row Piles Support system, comprise front-seat soldier pile, rear row's soldier pile, described front-seat soldier pile is connected by the first capping beam, described rear row's soldier pile is connected by the second capping beam, it is characterized in that: described front-seat soldier pile and ground maintain an equal level, described rear row's soldier pile elevates above the soil, and forms Suo Zhu; Be provided with at least one prestress anchorage cable between described Suo Zhu and described front-seat soldier pile, described prestress anchorage cable and described Suo Zhu form the angle being less than 90 degree.
2. masts type Double-row Piles Support system according to claim 1, is characterized in that: the height of described Suo Zhu is greater than the trestle column of described front-seat soldier pile and rear row's soldier pile.
3. masts type Double-row Piles Support system according to claim 1, is characterized in that: the degree of depth that described rear row's soldier pile embeds soil is not less than the degree of depth that described front-seat soldier pile embeds soil.
4. masts type Double-row Piles Support system according to claim 1, is characterized in that: the two ends of described prestress anchorage cable are anchored respectively at described front-seat soldier pile and Suo Zhushang.
5. masts type Double-row Piles Support system according to any one of Claims 1-4, is characterized in that: the layout of described front-seat soldier pile and described rear row's soldier pile is that rectangular array is arranged or T-shaped formula is arranged, limit is arcuately arranged, quincunx is arranged, two trigonometric expression is arranged.
CN201520408280.XU 2015-06-12 2015-06-12 Masts type double row pile struts system Expired - Fee Related CN204780939U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520408280.XU CN204780939U (en) 2015-06-12 2015-06-12 Masts type double row pile struts system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520408280.XU CN204780939U (en) 2015-06-12 2015-06-12 Masts type double row pile struts system

Publications (1)

Publication Number Publication Date
CN204780939U true CN204780939U (en) 2015-11-18

Family

ID=54521022

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520408280.XU Expired - Fee Related CN204780939U (en) 2015-06-12 2015-06-12 Masts type double row pile struts system

Country Status (1)

Country Link
CN (1) CN204780939U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107190756A (en) * 2017-07-25 2017-09-22 北京航天地基工程有限责任公司 Anchor system and slope retaining system
CN110397042A (en) * 2019-07-13 2019-11-01 济邦建设集团有限公司 A kind of support system of deep basal pit

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107190756A (en) * 2017-07-25 2017-09-22 北京航天地基工程有限责任公司 Anchor system and slope retaining system
CN110397042A (en) * 2019-07-13 2019-11-01 济邦建设集团有限公司 A kind of support system of deep basal pit

Similar Documents

Publication Publication Date Title
CN105155548A (en) Cable double-row pile (wall) supporting structure
CN202989937U (en) Grille-type double-row pile supporting structure
CN204530720U (en) A kind of foundation pit supporting construction
CN104631476A (en) Seaside ultra-deep soft foundation floating type steel sheet pile cofferdam and construction method thereof
CN203768912U (en) Double prestressing force high-strength concrete rectangular pile foundation ditch supporting construction
CN202117068U (en) Micropile plate-type composite foundation
CN102691302B (en) Concrete structure for supporting deep foundation pit
CN103924602A (en) Deep soft soil foundation pit construction method
CN204780938U (en) Novel recoverable anchor formula double row pile supporting construction that draws
CN204590038U (en) A kind of permanent foundation pit supporting construction
CN203594035U (en) Multilevel combined protection structure for shallow hole blasting excavation bridge foundation pit construction
CN104895121B (en) Transverse partition method for reducing ground surface settlement and building structure deformation of underground structure construction
CN104563129B (en) A kind of pile body is provided with the Double-row-piles Structure that adds the stake of core horizontal jet grouting
CN205188976U (en) Drag -line double row pile supporting construction
CN203593968U (en) Steel tube bamboo row frame for shallow hole blasting excavation bridge foundation bit construction
CN204780939U (en) Masts type double row pile struts system
CN204940298U (en) A kind of Composite Enclosure Structure of base pit engineering
CN101691760A (en) Composite foundation combining anchor rods with excavation and construction method thereof
CN205399503U (en) Anti floating botton board anchor slab formula of basement machinery anchor stock that excels in
CN205776276U (en) A kind of large-scale buried friction pile of side slope two-part props up mark structure
CN105040707A (en) Combined densely-arrayed pile deep foundation pit supporting and enclosure structure used as basement external wall
CN204849777U (en) Tilting board double row pile supporting construction that bears down on one
CN201502065U (en) Anchor rod joint excavation compound basis
CN203768911U (en) Formula of sloping double row pile underground structure
CN204645058U (en) A kind ofly be provided with the H type Double-row-piles Structure adding core rotary churning pile

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151118

Termination date: 20180612