CN101691760A - Composite foundation combining anchor rods with excavation and construction method thereof - Google Patents

Composite foundation combining anchor rods with excavation and construction method thereof Download PDF

Info

Publication number
CN101691760A
CN101691760A CN200910093283A CN200910093283A CN101691760A CN 101691760 A CN101691760 A CN 101691760A CN 200910093283 A CN200910093283 A CN 200910093283A CN 200910093283 A CN200910093283 A CN 200910093283A CN 101691760 A CN101691760 A CN 101691760A
Authority
CN
China
Prior art keywords
foundation
anchor pole
excavation
anchor
master muscle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200910093283A
Other languages
Chinese (zh)
Other versions
CN101691760B (en
Inventor
鲁先龙
程永锋
苏荣臻
丁士君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
Original Assignee
China Electric Power Research Institute Co Ltd CEPRI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Electric Power Research Institute Co Ltd CEPRI filed Critical China Electric Power Research Institute Co Ltd CEPRI
Priority to CN2009100932838A priority Critical patent/CN101691760B/en
Publication of CN101691760A publication Critical patent/CN101691760A/en
Application granted granted Critical
Publication of CN101691760B publication Critical patent/CN101691760B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

本发明提供了一种锚杆联合掏挖复合基础及其施工方法,主要应用到输电线路杆塔基础中,该复合基础由联合锚杆基础和掏挖基础联合形成,包括掏挖基础部分和锚杆基础部分,所述锚杆基础部分位于地表的岩层中,包括至少一根圆柱形或多边形的岩石锚杆,所述岩石锚杆具有锚杆主筋和围绕锚杆主筋的混凝土或水泥砂浆,所述锚杆主筋伸入到掏挖基础部分中;所述掏挖基础部分位于地表的土层中,由配筋和混凝土构成;所述掏挖基础部分和锚杆基础部分由伸入到掏挖基础部分中的锚杆主筋连接。并提供了具体施工方法。

Figure 200910093283

The invention provides an anchor-bolt combined excavation composite foundation and a construction method thereof, which are mainly applied to transmission line tower foundations. The composite foundation is jointly formed by a combined anchor foundation and an excavation foundation, including an excavation foundation part and an anchor The foundation part, the bolt foundation part is located in the rock formation on the ground surface, including at least one cylindrical or polygonal rock bolt, the rock bolt has a main reinforcement of the bolt and concrete or cement mortar surrounding the main reinforcement of the bolt, the The main reinforcement of the anchor rod extends into the excavated foundation part; the excavated foundation part is located in the soil layer on the ground surface and is composed of reinforcement and concrete; Anchor main reinforcement connection in section. And provide a specific construction method.

Figure 200910093283

Description

一种锚杆联合掏挖复合基础及其施工方法A composite foundation with bolt joint digging and its construction method

技术领域technical field

本发明涉及输电线路的基础施工技术领域,尤其涉及一种锚杆联合掏挖复合基础及其施工方法。The invention relates to the technical field of foundation construction of power transmission lines, in particular to a bolt-bolt combined excavation composite foundation and a construction method thereof.

背景技术Background technique

在输电线路基础中经常遇到有浅层为土层,而稍深处为岩层的地质条件,在这种地质条件下之前采用的基础形式一般为开挖回填类基础(大板式基础、台阶式基础)或掏挖基础,当线路荷载较大时,基础底面深度需超过岩层顶面,基础的承载力才能满足线路荷载要求,这样由于掏挖基础不能对岩层进行掏挖而无法采用,而采用大板式基础和台阶式基础要对岩层进行爆破等方法以便岩层部分的开挖,这样就给施工带来很大的难度,同时有巨大的土方开挖量,破坏原状土,不利于保护环境。In the foundation of transmission lines, it is often encountered that the shallow layer is the soil layer, and the deeper layer is the rock layer. Under such geological conditions, the foundation form used before is generally excavation and backfill foundation (large slab foundation, stepped foundation) foundation) or excavation foundation, when the line load is large, the depth of the bottom surface of the foundation needs to exceed the top surface of the rock layer, and the bearing capacity of the foundation can meet the load requirements of the line. Large slab foundations and stepped foundations require methods such as blasting of the rock strata to excavate the rock strata, which brings great difficulty to the construction. At the same time, there is a huge amount of earth excavation, which destroys the undisturbed soil and is not conducive to environmental protection.

发明内容Contents of the invention

为了克服现有技术中的缺陷,本发明的目的在于提供了一种无需爆破岩层,便于施工,减少土方开挖量的锚杆联合掏挖复合基础,主要应用到输电线路杆塔基础中。In order to overcome the deficiencies in the prior art, the object of the present invention is to provide a bolt-bolt combined excavation and excavation composite foundation without blasting rock formations, which is convenient for construction and reduces the amount of earthwork excavation. It is mainly applied to the foundation of power transmission line poles and towers.

本发明的另一目的在于提供一种锚杆联合掏挖复合基础的施工方法。Another object of the present invention is to provide a construction method for bolt combined digging and excavation composite foundation.

为此,本发明提出了一种锚杆联合掏挖复合基础,包括掏挖基础和锚杆基础,所述锚杆基础位于地表的岩层中,其包括至少一根圆柱形或多边形的岩石锚杆,所述岩石锚杆具有锚杆主筋和围绕锚杆主筋的混凝土或水泥砂浆,所述锚杆主筋伸入到掏挖基础中;所述掏挖基础位于地表的土层中,其由配筋和混凝土构成;所述掏挖基础和锚杆基础由伸入到掏挖基础中的锚杆主筋连接。For this reason, the present invention proposes a kind of bolt joint digging compound foundation, comprises digging foundation and bolt foundation, and described bolt foundation is positioned at the rock stratum of ground surface, and it comprises at least one cylindrical or polygonal rock bolt , the rock bolt has a main reinforcement of the anchor rod and concrete or cement mortar around the main reinforcement of the anchor rod, and the main reinforcement of the anchor rod extends into the excavated foundation; and concrete; the excavation foundation and the anchor foundation are connected by the main reinforcement of the anchor extending into the excavation foundation.

其中,所述锚杆主筋伸入到掏挖基础的长度大于或等于锚杆主筋直径的40倍。Wherein, the length of the main reinforcement of the anchor rod extending into the digging foundation is greater than or equal to 40 times the diameter of the main reinforcement of the anchor rod.

其中,所述围绕锚杆主筋的混凝土或水泥砂浆的顶面伸入到掏挖基础的高度h大于或等于10厘米。Wherein, the height h of the top surface of the concrete or cement mortar surrounding the main reinforcement of the anchor rod protruding into the digging foundation is greater than or equal to 10 cm.

其中,所述掏挖基础在垂直方向的截面形状呈倒扣的漏斗形或矩形或上底边长于下底边的梯形。Wherein, the cross-sectional shape of the excavation foundation in the vertical direction is an inverted funnel shape or a rectangle or a trapezoid whose upper base is longer than the lower base.

本发明还提供了一种锚杆联合掏挖复合基础的施工方法,施工流程如下:The present invention also provides a construction method for bolt combined excavation and excavation composite foundation, the construction process is as follows:

1)成孔,利用锚杆钻机在地表的土层和岩层中钻出锚杆钻孔;1) Forming a hole, using a bolter to drill a bolt hole in the soil layer and rock layer on the surface;

2)成孔结束后,放入并固定所述锚杆主筋,使所述锚杆主筋伸入到掏挖基础部分的长度大于或等于锚杆主筋直径的40倍,然后灌注所述锚杆部分围绕锚杆主筋的混凝土或水泥砂浆,使所述围绕锚杆主筋的混凝土或水泥砂浆的顶面伸入到掏挖基础部分的高度大于或等于10厘米;2) After the hole is formed, put and fix the main reinforcement of the anchor rod, so that the main reinforcement of the anchor rod extends into the excavation foundation part and the length is greater than or equal to 40 times the diameter of the main reinforcement of the anchor rod, and then pour the anchor rod part Concrete or cement mortar surrounding the main reinforcement of the anchor rod, so that the top surface of the concrete or cement mortar surrounding the main reinforcement of the anchor rod protrudes into the digging foundation part to a height greater than or equal to 10 cm;

3)在地表的土层部分掏挖出掏挖基础部分的基坑;3) Excavate and excavate the foundation pit of excavating the foundation part at the soil layer part of the ground surface;

4)在掏挖基础部分安放并固定所述掏挖基础部分配筋,然后浇筑混凝土。4) Place and fix the reinforcement of the excavated foundation part on the excavated foundation part, and then pour concrete.

本发明的锚杆联合掏挖复合基础可用于浅层为土层、稍深处为岩层的地质条件,主要应用到输电线路杆塔基础中,该复合基础由锚杆基础和掏挖基础联合形成,由于掏挖基础底面置于岩层顶面,因此在受力时,由掏挖基础承担主要下压力,掏挖基础和锚杆基础共同承担上拔力和水平力,这样就能满足输电线路荷载要求。The anchor bolt combined digging and excavation composite foundation of the present invention can be used in geological conditions where the shallow layer is the soil layer and the deeper layer is the rock layer. It is mainly applied to the tower foundation of the transmission line. The composite foundation is jointly formed by the anchor bolt foundation and the excavation foundation. Since the bottom surface of the excavated foundation is placed on the top surface of the rock formation, the excavated foundation bears the main downward pressure when the force is applied, and the excavated foundation and the anchor foundation jointly bear the uplift force and horizontal force, so that the load requirements of the transmission line can be met. .

本发明的有益效果在于:该锚杆联合掏挖复合基础无需爆破岩层,便于施工,减少土方开挖量,利用原状土,利于保护环境。The beneficial effect of the present invention is that: the bolt-bolt combined excavation and excavation composite foundation does not need to blast the rock formation, which is convenient for construction, reduces the amount of earthwork excavation, utilizes undisturbed soil, and is beneficial to protect the environment.

附图说明Description of drawings

图1为现有技术的大板式基础或台阶式基础的结构示意图;Fig. 1 is the structural representation of the large slab foundation or stepped foundation of prior art;

图2为本发明的锚杆联合掏挖复合基础的第一种构造示意图;Fig. 2 is the first kind of structure schematic diagram of the anchor rod joint excavation and excavation composite foundation of the present invention;

图3是本发明的锚杆联合掏挖复合基础及其施工方法的流程示意图;Fig. 3 is the schematic flow sheet of the composite foundation and construction method thereof of the anchor rod joint excavation of the present invention;

图4是图2的具体结构尺寸示意图,其中图4-1为图2的剖视图,图4-2为图2的俯视图;Fig. 4 is a schematic diagram of specific structural dimensions of Fig. 2, wherein Fig. 4-1 is a cross-sectional view of Fig. 2, and Fig. 4-2 is a top view of Fig. 2;

图5是本发明的锚杆联合掏挖复合基础的第二种构造示意图;Fig. 5 is the second kind of structure schematic diagram of the anchor rod joint excavation and excavation composite foundation of the present invention;

图6是本发明的锚杆联合掏挖复合基础的第三种构造示意图;Fig. 6 is the third structure schematic diagram of the anchor rod combined excavation and excavation composite foundation of the present invention;

其中,I-土层,II-岩层,1-掏挖基础,2-锚杆基础,3-岩石锚杆,4-锚杆主筋,5-围绕锚杆主筋的混凝土或水泥砂浆,6-配筋,7-混凝土,8-锚杆钻孔,9-掏挖基础的基坑。Among them, I-soil layer, II-rock layer, 1-excavation foundation, 2-bolt foundation, 3-rock bolt, 4-bolt main reinforcement, 5-concrete or cement mortar around the main reinforcement of the bolt, 6-fitting Reinforcement, 7-concrete, 8-anchor drilling, 9-excavation of the foundation pit of the foundation.

具体实施方式Detailed ways

下面结合附图对本发明的锚杆联合掏挖复合基础作进一步说明。Below in conjunction with accompanying drawing, the composite foundation of bolt combined excavation of the present invention will be further described.

如图2所示,本发明的锚杆联合掏挖复合基础的包括掏挖基础1和锚杆基础2,所述锚杆基础2位于地表的岩层II中,其包括至少一根圆柱形或多边形的岩石锚杆3,该岩石锚杆3具有锚杆主筋4和围绕锚杆主筋的混凝土或水泥砂浆5,锚杆主筋4伸入到掏挖基础1中;所述掏挖基础1位于地表的土层I中,其掏挖基础1的底面置于岩层II顶面,其由配筋6和混凝土7构成;所述掏挖基础1和锚杆基础2由伸入到掏挖基础中的锚杆主筋4连接,掏挖基础1在垂直方向的截面形状呈倒扣的漏斗形。如图5-6所示,掏挖基础1在垂直方向的截面形状也可呈矩形或上边长于下边的梯形。As shown in Fig. 2, the composite foundation of bolt joint digging of the present invention comprises digging foundation 1 and bolt foundation 2, and described bolt foundation 2 is located in the rock formation II of ground surface, and it comprises at least one cylindrical or polygonal A rock bolt 3, the rock bolt 3 has a main reinforcement 4 and concrete or cement mortar 5 around the main reinforcement of the anchor, the main reinforcement 4 of the anchor extends into the excavated foundation 1; the excavated foundation 1 is located on the ground surface In the soil layer I, the bottom surface of the excavated foundation 1 is placed on the top surface of the rock formation II, which is composed of reinforcement 6 and concrete 7; The rod main reinforcement 4 is connected, and the cross-sectional shape of the digging foundation 1 in the vertical direction is an inverted funnel shape. As shown in Figures 5-6, the cross-sectional shape of the digging foundation 1 in the vertical direction can also be a rectangle or a trapezoid whose upper side is longer than the lower side.

如图4所示,本发明的锚杆联合掏挖复合基础的结构尺寸可采用下述参数:土层I为黄土层,土层下面的岩层II为微风化岩层,所述掏挖基础1的上部窄端直径为0.8m,长度为1m;下部扩大端的直径为1.2cm,长度为0.5m。上部掏挖基础1位于1.5m厚的黄土层中。微风化岩层中设置四根按正方形布置的岩石锚杆3,岩石锚杆3间距为40cm、其直径为0.15m,锚杆主筋4采用36mm直径的HRB335II级螺纹钢、其长度为6m,浇灌在锚杆主筋4周围的混凝土或水泥砂浆5采用C20混凝土或者M20的水泥砂浆。锚杆主筋进入掏挖基础的长度为1.44m。该锚杆联合掏挖复合基础能够承受150吨的上拔力。As shown in Figure 4, the structure size of the bolt joint digging composite foundation of the present invention can adopt the following parameters: the soil layer I is a loess layer, and the rock layer II below the soil layer is a slightly weathered rock layer, and the digging foundation 1 The upper narrow end has a diameter of 0.8m and a length of 1m; the lower enlarged end has a diameter of 1.2cm and a length of 0.5m. The upper digging foundation 1 is located in the 1.5m thick loess layer. Set four rock bolts 3 arranged in a square in the micro-weathered rock stratum. The distance between the rock bolts 3 is 40cm, and its diameter is 0.15m. The concrete or cement mortar 5 around the anchor rod main reinforcement 4 adopts C20 concrete or M20 cement mortar. The length of the main reinforcement of the anchor rod entering the excavated foundation is 1.44m. The composite foundation with combined digging and excavation of anchor rods can withstand a pull-up force of 150 tons.

图3示出了本发明的基础的施工示意图。具体施工流程如下:Figure 3 shows a schematic diagram of the construction of the foundation of the present invention. The specific construction process is as follows:

1)成孔,利用锚杆钻机在地表的土层和岩层中钻出锚杆钻孔;1) Forming a hole, using a bolter to drill a bolt hole in the soil layer and rock layer on the surface;

2)成孔结束后,放入并固定所述锚杆主筋,使所述锚杆主筋伸入到掏挖基础的长度大于或等于锚杆主筋直径的40倍,然后灌注所述锚杆部分围绕锚杆主筋的混凝土或水泥砂浆,使所述围绕锚杆主筋的混凝土或水泥砂浆的顶面伸入到掏挖基础的高度大于或等于10厘米;2) After the hole is completed, put and fix the main reinforcement of the anchor rod, so that the main reinforcement of the anchor rod extends into the excavation foundation and the length is greater than or equal to 40 times the diameter of the main reinforcement of the anchor rod, and then pour the part of the anchor rod around The concrete or cement mortar of the main reinforcement of the anchor rod, so that the top surface of the concrete or cement mortar surrounding the main reinforcement of the anchor rod extends into the digging foundation to a height greater than or equal to 10 cm;

3)在地表的土层部分掏挖出掏挖基础的基坑;3) Excavate and excavate the foundation pit of excavating the foundation at the soil layer part of the surface;

4)在掏挖基础安放并固定所述掏挖基础配筋,然后浇筑混凝土。4) Place and fix the excavated foundation reinforcement on the excavated foundation, and then pour concrete.

此外,本发明所述的锚杆基础、台阶式基础、大板式、掏挖基础均为公知基础形式,常用于输电线路基础。In addition, the bolt foundation, stepped foundation, large slab type, and excavated foundation described in the present invention are all known foundation forms, which are often used for power transmission line foundations.

图5是本发明的锚杆联合掏挖复合基础的第二种构造示意图,图6是本发明的锚杆联合掏挖复合基础的第三种构造示意图。其中,所述掏挖基础在垂直方向的截面形状呈倒扣的漏斗形或矩形或上底边长于下底边的梯形。Fig. 5 is a schematic diagram of the second structure of the composite foundation with combined digging of bolts according to the present invention, and Fig. 6 is a schematic diagram of the third configuration of the composite foundation with combined digging of bolts according to the present invention. Wherein, the cross-sectional shape of the excavation foundation in the vertical direction is an inverted funnel shape or a rectangle or a trapezoid whose upper base is longer than the lower base.

此处已经根据特定的示例性实施例对本发明进行了描述。对本领域的技术人员来说在不脱离本发明的范围下进行适当的替换或修改将是显而易见的。示例性的实施例仅仅是例证性的,而不是对本发明的范围的限制,本发明的范围由所附的权利要求定义。The invention has been described herein in terms of specific exemplary embodiments. Appropriate substitutions or modifications will be apparent to those skilled in the art without departing from the scope of the present invention. The exemplary embodiments are illustrative only, and not limiting of the scope of the invention, which is defined by the appended claims.

Claims (5)

1. composite foundation combining anchor rods with excavation, comprise digging foundation (1) and anchor pole basis (2), it is characterized in that: described anchor pole basis (2) is arranged in the rock stratum (II) on the face of land, it comprises at least one cylindrical or polygonal rock bolt (3), described rock bolt (3) has anchor pole master muscle (4) and centers on the concrete or the cement mortar (5) of anchor pole master muscle, and described anchor pole master muscle (4) extend in the digging foundation (1); Described digging foundation (1) is arranged in the soil layer (I) on the face of land, and it is made of arrangement of reinforcement (6) and concrete (7); Described digging foundation (1) is connected by the anchor pole master muscle (4) that extend in the digging foundation with anchor pole basis (2).
2. composite foundation combining anchor rods with excavation as claimed in claim 1 is characterized in that: the length that described anchor pole master muscle (4) extend into digging foundation (1) is more than or equal to 40 times of anchor pole master muscle (4) diameter.
3. composite foundation combining anchor rods with excavation as claimed in claim 1 or 2 is characterized in that: described around anchor pole master muscle concrete or the end face of cement mortar (5) extend into the height h of digging foundation (1) more than or equal to 10 centimetres.
4. as the described composite foundation combining anchor rods with excavation of claim 1-3, it is characterized in that: described digging foundation (1) is the infundibulate of back-off or rectangle or top at the cross sectional shape of vertical direction and is longer than following trapezoidal.
5. job practices as the described composite foundation combining anchor rods with excavation of claim 1-4, construction process is as follows:
1) pore-forming utilizes jumbolter to get out armature boring in the soil layer on the face of land and rock stratum;
2) after pore-forming finishes, put into and fixing described anchor pole master muscle, make described anchor pole master muscle extend into digging foundation length partly 40 times greater than anchor pole master muscle diameter, pour into described anchor pole then partly around the concrete or the cement mortar of anchor pole master muscle, make describedly to extend into the height of digging foundation part greater than 10 centimetres around the concrete of anchor pole master muscle or the end face of cement mortar;
3) partly draw the foundation ditch that digs out the digging foundation part at the soil layer on the face of land;
4) partly lay and fixing described digging foundation part arrangement of reinforcement, concreting then at digging foundation.
CN2009100932838A 2009-09-25 2009-09-25 Composite foundation combining anchor rods with excavation and construction method thereof Active CN101691760B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009100932838A CN101691760B (en) 2009-09-25 2009-09-25 Composite foundation combining anchor rods with excavation and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009100932838A CN101691760B (en) 2009-09-25 2009-09-25 Composite foundation combining anchor rods with excavation and construction method thereof

Publications (2)

Publication Number Publication Date
CN101691760A true CN101691760A (en) 2010-04-07
CN101691760B CN101691760B (en) 2011-07-27

Family

ID=42080470

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009100932838A Active CN101691760B (en) 2009-09-25 2009-09-25 Composite foundation combining anchor rods with excavation and construction method thereof

Country Status (1)

Country Link
CN (1) CN101691760B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103147456A (en) * 2013-03-08 2013-06-12 中节能风力发电股份有限公司 Prestressed combination pile structure and construction method thereof
CN108019086A (en) * 2017-12-06 2018-05-11 浙江飞英电力器材有限公司 A kind of large bending moment electrical pole and its installation method
CN108589759A (en) * 2018-05-15 2018-09-28 中国电力科学研究院有限公司 A kind of shaft tower composite foundation
CN111576469A (en) * 2020-04-02 2020-08-25 国网浙江省电力有限公司湖州供电公司 Novel power transmission line tower foundation and construction method
CN111910671A (en) * 2020-07-20 2020-11-10 国网浙江省电力有限公司丽水供电公司 Prestressed anchor rod combined excavation composite foundation and construction method thereof
CN111910670A (en) * 2020-07-20 2020-11-10 国网浙江省电力有限公司丽水供电公司 Assembly type rock anchor rod composite foundation and construction method thereof
CN113789806A (en) * 2021-08-20 2021-12-14 中国电力工程顾问集团华北电力设计院有限公司 Annular-section rock foundation suitable for mountainous area and construction method thereof

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU3589000A (en) * 1999-02-05 2000-08-25 Northern Technologies, Inc. Support structure for elevating and supporting monopoles and associated equipment
NO311184B1 (en) * 2000-03-10 2001-10-22 Norsk Miljoekraft As Method and apparatus for attaching a foundation to the bedrock
CN201232193Y (en) * 2008-07-16 2009-05-06 钱自力 Wind motor tower foundation anchor pile structure on rock foundation
CN201485863U (en) * 2009-09-04 2010-05-26 中国电力工程顾问集团东北电力设计院 Digging rock bolt compound environment-protection basis
CN201495554U (en) * 2009-09-25 2010-06-02 中国电力科学研究院 An Anchor Combined Excavation and Excavation Composite Foundation

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103147456A (en) * 2013-03-08 2013-06-12 中节能风力发电股份有限公司 Prestressed combination pile structure and construction method thereof
CN108019086A (en) * 2017-12-06 2018-05-11 浙江飞英电力器材有限公司 A kind of large bending moment electrical pole and its installation method
CN108589759A (en) * 2018-05-15 2018-09-28 中国电力科学研究院有限公司 A kind of shaft tower composite foundation
CN111576469A (en) * 2020-04-02 2020-08-25 国网浙江省电力有限公司湖州供电公司 Novel power transmission line tower foundation and construction method
CN111910671A (en) * 2020-07-20 2020-11-10 国网浙江省电力有限公司丽水供电公司 Prestressed anchor rod combined excavation composite foundation and construction method thereof
CN111910670A (en) * 2020-07-20 2020-11-10 国网浙江省电力有限公司丽水供电公司 Assembly type rock anchor rod composite foundation and construction method thereof
CN113789806A (en) * 2021-08-20 2021-12-14 中国电力工程顾问集团华北电力设计院有限公司 Annular-section rock foundation suitable for mountainous area and construction method thereof

Also Published As

Publication number Publication date
CN101691760B (en) 2011-07-27

Similar Documents

Publication Publication Date Title
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
CN103967031B (en) A kind of caisson of consolidated subsoil and stake combination foundation and construction method thereof
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN103321244B (en) Sand foundation existing building sets up the construction method of basement
CN101691760B (en) Composite foundation combining anchor rods with excavation and construction method thereof
CN106013171B (en) A kind of semi-rigid supporting construction semi-flexible and method of deep-foundation side wall
CN205369231U (en) Steel -pipe pile is filled in drilling
CN206034454U (en) Supporting construction
CN107642041A (en) Super large diameter hollow pile group anchorage
CN103114595A (en) Support method and device of support pile preformed core-soil double-buttress inclined inner-strut foundation ditch
CN105604065A (en) Foundation fit support and peat-soil deep-foundation-pit-support high-pressure jet grouting anchoring method
CN106368219A (en) Supporting reinforcing structure of deep foundation pit and construction method
CN103572770B (en) A kind of stake case hydraulic structures and construction method thereof
CN205382942U (en) Multilayer underground space curtain posture subsurface excavated construction's supporting construction under existing facility
CN107642040A (en) Construction method of super large diameter hollow pile group anchorage
CN201502065U (en) A type of composite foundation for bolt combined excavation
CN207484290U (en) The hollow clump of piles anchorage of super-large diameter
CN101691759A (en) Construction method for digging composite environmental protection base of anchorage bar adding rock
CN204125850U (en) A kind of cantilever shed tunnel being provided with steel tube concrete pile and prestress anchorage cable
CN206418517U (en) A kind of prefabricated anchor foundation for frozen soil foundation
CN108330963A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN101565955B (en) A Method of Reinforcing Existing Pile Foundation Using Miniature Stress Isolation Pile
CN201495554U (en) An Anchor Combined Excavation and Excavation Composite Foundation
CN100545357C (en) A cement-soil embedded pile wall for foundation pit support and its construction method
CN204676581U (en) A kind of rock foundation overhead power transmission line line pole tower and bracing wire novel foundation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP.

Effective date: 20130129

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20130129

Address after: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15

Patentee after: China Electric Power Research Institute

Patentee after: State Grid Corporation of China

Address before: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15

Patentee before: China Electric Power Research Institute

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15

Patentee after: China Electric Power Research Institute

Country or region after: China

Patentee after: STATE GRID CORPORATION OF CHINA

Address before: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15

Patentee before: China Electric Power Research Institute

Country or region before: China

Patentee before: State Grid Corporation of China

CP03 Change of name, title or address

Address after: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15

Patentee after: CHINA ELECTRIC POWER RESEARCH INSTITUTE Co.,Ltd.

Country or region after: China

Patentee after: STATE GRID CORPORATION OF CHINA

Address before: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15

Patentee before: China Electric Power Research Institute

Country or region before: China

Patentee before: STATE GRID CORPORATION OF CHINA

CP03 Change of name, title or address