CN206157484U - Moderate -low speed magnetic levitation traffic engineering single line location supporting beam of pile foundation formula support rail girder construction of filling - Google Patents

Moderate -low speed magnetic levitation traffic engineering single line location supporting beam of pile foundation formula support rail girder construction of filling Download PDF

Info

Publication number
CN206157484U
CN206157484U CN201621057171.9U CN201621057171U CN206157484U CN 206157484 U CN206157484 U CN 206157484U CN 201621057171 U CN201621057171 U CN 201621057171U CN 206157484 U CN206157484 U CN 206157484U
Authority
CN
China
Prior art keywords
support rail
rail beam
pile foundation
reinforced concrete
base plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201621057171.9U
Other languages
Chinese (zh)
Inventor
郭建湖
李小和
赵新益
姜鹰
姚洪锡
李巍
王勇刚
杨辉建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201621057171.9U priority Critical patent/CN206157484U/en
Application granted granted Critical
Publication of CN206157484U publication Critical patent/CN206157484U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

The utility model belongs to the technical field of the low circuit of putting of well low -speed maglev traffic engineering to moderate -low speed magnetic levitation traffic engineering single line location supporting beam of pile foundation formula support rail girder construction of filling is disclosed, roadbed filler and support rail roof beam both sides are backfilled and are packed under pile foundation load bearing structure, reinforced concrete joist, reinforced concrete support rail breast board, reinforced concrete beam structure, support rail roof beam, and pile foundation load bearing structure is provided with many, accept at the top of reinforced concrete support rail breast board reinforced concrete beam structure, support rail roof beam both sides are backfilled to pack and are passed through roadbed filler accepts under the support rail roof beam. The utility model discloses can avoid the low defect of putting circuit support rail girder construction of tradition, long term stability is better, and low -speed maglev traffic engineering track structure satisfied the requirement of foundation bed long term stability, durability and construction quality's controllability again to support rail roof beam structural distortion and post -construction settlement's high requirement during it had both satisfied moreover, and just economic nature is better.

Description

Medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction
Technical field
The utility model belongs to that middle low speed magnetic suspension traffic engineering is low to put Line technology field, low more particularly, in Fast magnetic floating traffic engineering single line embankment location support rail girder construction pattern.
Background technology
Middle low speed magnetic suspension track traffic belongs to a kind of novel traffic mode, and achievement in research both domestic and external is less, the whole world The circuit for opening operation is even more minority.The middle low speed magnetic suspension railway business that only in March, 2005 Japan's construction at present is opened is transported The middle low speed magnetic suspension railway business operating line that line-the East Hillside Line and in June, 2014 Korea open.And the middle low speed of China Magnetic suspension traffic only National University of Defense technology's test wire, Green City Mountain test wire, Tangshan experiment line at present, but do not put into effect Formal circuit, and based on elevated structure, the rarely seen relevant low research put in terms of circuit support rail girder construction and applies.
The outstanding traffic civil engineering part of middle low speed magnetic suspension mainly comprising bridge, it is low put circuit, station and rolling stock section, it is low to put circuit It is made up of roadbed under the section of track, support rail beam and support rail beam, the support rail beam of supporting track is arranged on the roadbed being made up of earth structure On, the operation of middle low speed magnetic suspension train includes suspending, be oriented to, drive and braking being required for what is completed on support rail beam.Magnetic Aerotrain is very high to line construction deformation requirements, because the deformation of structure very little may affect comfortableness even prestige by bus Side of body traffic safety, so the design of support rail beam is particularly significant.
Existing support rail girder construction is applied and exist on circuit problems with middle low speed magnetic suspension traffic low putting:
(1) existing low circuit support rail girder construction of putting is arranged on embankment earth structure, embankment earth structure by Filler fills compacting and forms, and compaction quality is wayward, and the later stage is susceptible to deformation, and settlement after construction is difficult to control to.
(2) low circuit support rail girder construction of putting has high demands to the settlement after construction of roadbed and ground, and is routed through the ground in region Matter condition is typically all complicated and changeable, therefore is also needed to while carrying out consolidation process, roadbed filling slope groundwork to ground Area increase is reinforced, cost is high, long in time limit;And basement process belongs to disguised engineering, arranged using conventional reinforced soft soil ground Apply and reinforced, construction quality is wayward.
(3) because the low circuit earth structure of putting that filler fills compacting has vulnerability, and construction quality is difficult Control, relatively easily produces differential settlement, causes bedding vertical and horizontal bad stability under support rail beam, so that support rail beam The resistance to overturning of structure is damaged.
The low circuit support rail beam of putting of magnetic suspension is higher to post-construction settlement of subgrade, bedding long-time stability and life requirement, when When circuit is located at foundation stabilization location, the construction period is long to take traditional support rail girder construction pattern to exist, and construction quality is not easily-controllable System, the defect such as whole structural stability is poor and less economical.
Utility model content
For the disadvantages described above or Improvement requirement of prior art, the utility model provides medium-and low-speed maglev traffic engineering list Line embankment location pile foundation joist type support rail girder construction, can avoid the low defect for putting circuit support rail girder construction of tradition, and construction quality is more Be easily controlled, long-time stability more preferably, and during it both meets low speed magnetic suspension traffic engineering track structure to support rail girder construction Deformation and the high request of settlement after construction, meet the requirement of the controllability of bedding long-time stability, durability and construction quality again, and Economy is more preferably.
For achieving the above object, the utility model provides medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist Formula support rail girder construction, it is characterised in that including pile foundation bearing structure, reinforced concrete supporting beam, armored concrete support rail beam base plate, Roadbed filling and support rail beam both sides backfill filler under reinforced concrete beam type structure, support rail beam, wherein,
The pile foundation bearing structure is provided with many, is vertically arranged per pile foundation bearing structure described in root, and the institute per root Accept the reinforced concrete supporting beam in the top for stating pile foundation bearing structure;
The reinforced concrete supporting beam accepts the armored concrete support rail beam base plate;
Accept the reinforced concrete beam type structure in the top of the armored concrete support rail beam base plate;
The top of the pile foundation bearing structure is embedded in the reinforced concrete supporting beam and just connects with it, the armored concrete support Beam has just connect or has overlapped with the armored concrete support rail beam base plate, the armored concrete support rail beam base plate and the reinforced concrete Native girder structure formed by integrally casting is molded so as to collectively form armored concrete support rail beam;
The reinforced concrete supporting beam both sides are provided with for limiting the armored concrete support rail beam base plate lateral displacement Convex gear platform;
Roadbed filling is arranged between shallow layer reinforcement area and the armored concrete support rail beam base plate under the support rail beam, with It is flat for providing construction for the armored concrete support rail beam base plate, reinforced concrete supporting beam and support rail beam both sides backfill filler Platform, and provide lateral support for the pile foundation bearing structure;Wherein, the shallow layer reinforcement area is arranged on the superficial of soft stratum Layer, and under the shallow layer reinforcement area, the support rail beam roadbed filling and the reinforced concrete beam type structure vertical consistency;
The support rail beam both sides backfill filler is accepted by roadbed filling under the support rail beam, and the support rail beam both sides Backfill filler props up the both sides of the armored concrete support rail beam base plate, to play protection to the armored concrete support rail beam base plate Act on and constrain the transverse shifting of the armored concrete support rail beam base plate, and maintenance passage is provided;
Roadbed filling and support rail beam both sides backfill filler collectively form filler filling body under the support rail beam, described to fill out Material filling body both sides are provided with weathering;
Roadbed filling under the support rail beam, the shallow layer reinforcement area are sequentially passed through per the lower end of pile foundation bearing structure described in root With stretch into after the soft stratum in supporting course, with soft stratum produce sedimentation when, the pile foundation bearing structure can bear negative Frictional resistance, so as to provide stable bearing capacity to armored concrete support rail beam base plate and reinforced concrete beam type structure, to reduce Because of the adverse effect that the sedimentation of filler filling body is produced to the vertical of armored concrete support rail beam, vertical and horizontal rigidity.
Preferably, the pile foundation bearing structure is cast-in-situ bored pile, reinforced concrete supporting beam and support rail beam base plate just connect or Overlap joint, just connects with pile foundation bearing structure.Overlapped using pin in the position of support rail beam internode seam, remaining position adopts and just connects.
Preferably, the support rail beam both sides backfill the height of filler and the height phase of the armored concrete support rail beam base plate Deng.
Preferably, pile foundation bearing structure described in all these is arranged in ranks.
In general, by the contemplated above technical scheme of the utility model compared with prior art, can obtain down Row beneficial effect:
(1) armored concrete support rail beam base plate of the present utility model, reinforced concrete beam type structure adopt reinforced concrete Soil scene one-piece casting, the two composition integral reinforced concrete structure is floated to the magnetic for directly taking on track load and track transmission Train load, then deadweight and upper load are passed to and its rigidly connected pile foundation bearing structure, structural reliability is high.
(2) pile foundation bearing structure of the present utility model is goed deep in supporting course, and when embankment produces certain sedimentation, pile foundation carries knot Structure can still bear negative friction and provide stronger bearing capacity, it is to avoid because filling compaction and foundation stabilization quality it is wayward The differential settlement for causing is vertical to support rail beam, vertical and horizontal rigidity impact, structure vertical cross stiffness and structural reliability It is more excellent.
(3) put circuit soft soil zone low, according to embankment stability need necessity is carried out to the superficial layer of soft stratum Reinforcing, its reinforcement depth by embankment stability control, compared to by settle and tradition when stable Two indices are controlled solely For base reinforcing mode, shallow layer reinforcement area reinforcement depth is little, can effective control roadbed reclamation and roadbed with reference to pile foundation bearing structure Settlement after construction.Non- soft soil zone can more avoid the stiffening basic ground of the wide area produced after embankment slope, and Pile foundation bearing structure construction quality is more easy to control, can effective control construction quality, investment reduction, the reduction of erection time, with obvious Technology and economic advantages.
(4) reinforced concrete supporting beam that pile foundation bearing structure and reinforced concrete floor are arranged, can greatly reduce pile foundation The stress concentration phenomenon of armored concrete support rail beam base plate at bearing structure;Further, since reinforced concrete supporting beam laterally connects Effect is connect, the lateral stiffness of structure and the ability of opposing differential settlement deformation is also increased, the quantity of transverse pile foundation can be reduced, Reduce investment.
Description of the drawings
Fig. 1 is schematic cross-sectional view of the present utility model;
Fig. 2 is schematic longitudinal section of the present utility model;
Fig. 3 is the distribution schematic diagram of the utility model pile foundation bearing structure;
Fig. 4 is that the utility model pile foundation reinforced concrete supporting beam has just connect connection signal with armored concrete support rail beam base plate Figure.
Fig. 5 is that the utility model pile foundation reinforced concrete supporting beam overlaps connection signal with armored concrete support rail beam base plate Figure.
Fig. 6 is the cross-sectional view of pin in the utility model.
Specific embodiment
In order that the purpose of this utility model, technical scheme and advantage become more apparent, below in conjunction with accompanying drawing and enforcement Example, is further elaborated to the utility model.It should be appreciated that specific embodiment described herein is only to explain The utility model, is not used to limit the utility model.Additionally, institute in the utility model disclosed below each embodiment As long as the technical characteristic being related to does not constitute each other conflict and just can be mutually combined.
Reference Fig. 1~Fig. 6, medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction, including Pile foundation bearing structure 3, reinforced concrete supporting beam 90, armored concrete support rail beam base plate 2, reinforced concrete beam type structure 1, support rail Roadbed filling 5 and support rail beam both sides backfill filler 4 under beam, wherein,
The pile foundation bearing structure 3 is provided with many, is vertically arranged per pile foundation bearing structure 3 described in root, and per root Accept the reinforced concrete supporting beam 90 in the top of the pile foundation bearing structure 3;
The reinforced concrete supporting beam 90 accepts the armored concrete support rail beam base plate 2;
Accept the reinforced concrete beam type structure 1 in the top of the armored concrete support rail beam base plate 2;
The top of the pile foundation bearing structure 3 is embedded in the reinforced concrete supporting beam 90 and just connects with it, the reinforced concrete Native joist 90 has just connect or has overlapped with the armored concrete support rail beam base plate 2, the armored concrete support rail beam base plate 2 with it is described Reinforced concrete beam type structure 1 is integrally formed so as to collectively form armored concrete support rail beam 9;
It is provided with the reinforced concrete supporting beam 90 for limiting the lateral displacement of armored concrete support rail beam base plate 2 Convex gear platform 91;
Under the support rail beam roadbed filling 5 be arranged on shallow layer reinforcement area 6 and the armored concrete support rail beam base plate 2 it Between, for be the armored concrete support rail beam base plate 2, reinforced concrete supporting beam 90 and support rail beam both sides backfill filler 4 carry For operation platform, and lateral support is provided for the pile foundation bearing structure 3;Wherein, the shallow layer reinforcement area 6 is arranged on flabbily The superficial layer of layer 7, and roadbed filling 5 and the reinforced concrete beam type structure under the shallow layer reinforcement area 6, the support rail beam 1 vertical consistency;
The support rail beam both sides backfill filler 4 is accepted by roadbed filling 5 under the support rail beam, and the support rail beam two Side backfill filler 4 props up the both sides of the armored concrete support rail beam base plate 2, with to the armored concrete support rail beam base plate 2 The transverse shifting of the armored concrete support rail beam base plate 2 is shielded and constrained, and maintenance passage is provided;
Roadbed filling 5 and support rail beam side backfill filler 4 collectively form filler filling body 10 under the support rail beam, described The both sides of filler filling body 10 are provided with weathering 11;
Roadbed filling 5, the shallow layer reinforcement under the support rail beam are sequentially passed through per the lower end of pile foundation bearing structure 3 described in root Stretch into behind area 6 and the soft stratum 7 in supporting course 8, so that when soft stratum 7 produces sedimentation, the pile foundation bearing structure 3 can Negative friction is born, so as to provide stable carrying to armored concrete support rail beam base plate 2 and reinforced concrete beam type structure 1 Power, is produced not with the sedimentation reduced because backfilling packing section 10 to the vertical of armored concrete support rail beam 9, vertical and horizontal rigidity Profit affects.
Further, the pile foundation bearing structure 3 is cast-in-situ bored pile, reinforced concrete supporting beam and support rail beam base plate just connect or Overlap joint, just connects with pile foundation bearing structure.Pin is adopted in the position reinforced concrete supporting beam of support rail beam internode seam with support rail beam base plate Nail overlap joint, remaining position adopts and just connects.
The pin 10 includes pre-buried connection reinforcing bar 10.1, pitch hemp cut 10.2 and stainless steel sleeve pipe 10.3, described pre-buried Connection reinforcing bar 10.1 is located in the stainless steel sleeve pipe 10.3 and arranges between the two the pitch hemp cut 10.2.
The height of the support rail beam both sides backfill filler 4 and highly equal, the institute of the armored concrete support rail beam base plate 2 These the described pile foundation bearing structures 3 having are arranged in ranks.
The structural shape can in effectively solving the low circuit of putting of low speed magnetic suspension traffic engineering it is tight to post-construction settlement of subgrade requirement Lattice, take that engineering caused by traditional foundation stabilization measure is huge, invest big, long in time limit, and basement process and embankment Construction quality is wayward, the problem of bedding long-time stability and poor durability, so as to improve low circuit support rail girder construction of putting Reliability, reduces the engineering risk of traditional structure pattern.
Armored concrete support rail beam 9 of the present utility model adopts reinforced concrete soil scene one-piece casting, to directly take on rail Road load and the magnetic-levitation train load of track transmission, then deadweight and upper load are passed to and its rigidly connected pile foundation carrying Structure 3, structural reliability is high, can save the large area stiffening basic ground produced after traditional embankment slope.
Pile foundation bearing structure 3 adopts cast-in-situ bored pile, transverse direction and longitudinal direction to fill with many reinforced concrete drillings are arranged with Note stake, vertical and horizontal rigidity is big;And pile foundation bearing structure 3 gos deep into supporting course 8, when soft stratum 7 produces sedimentation, pile foundation is carried Structure 3 can still bear negative friction and provide stronger bearing capacity to armored concrete support rail beam base plate 2.
The reinforced concrete supporting beam 90 that pile foundation bearing structure 3 and reinforced concrete floor 2 are arranged, can greatly reduce pile foundation The stress concentration phenomenon of armored concrete support rail beam base plate 2 at bearing structure 3;Further, since the horizontal stroke of reinforced concrete supporting beam 90 To connection function, the lateral stiffness of structure and the ability of opposing differential settlement deformation are also increased, transverse pile foundation can be reduced Quantity, reduces investment.
It is low put circuit by soft soil zone when, should according to embankment stability need ground superficial layer is carried out it is necessary plus Gu, form shallow layer reinforcement area 6., by embankment stability control, its reinforcement depth should be according to embankment for the reinforcement depth in shallow layer reinforcement area 6 Raising, foundation condition are determined by stability calculation.Compared to traditional single ground when being controlled by sedimentation and stable Two indices For reinforcing mode, the reinforcement depth of shallow layer reinforcement area 6 is little, can effective control roadbed reclamation and roadbed with reference to pile foundation bearing structure 3 Settlement after construction.By contrast, the new structure foundation stabilization quantity is little, invests little, and more conducively construction quality and settlement after construction Control, and save cost and reduction of erection time.
The specific making step of the utility model is as follows:
(1) smooth construction site, according to design requirement necessary shallow layer foundation consolidation process is carried out, and forms shallow layer reinforcement area 6, then placement in layers is required according to embankment and be densified to reinforced concrete floor bottom surface absolute altitude;
(2) irrigate in embankment subgrade cross section, vertical section direction construction drill in reinforced concrete floor bottom surface absolute altitude Stake, i.e. pile foundation bearing structure 3, drilled pile construction should be adopted and disturb little construction technology to railway embankment, if necessary in embankment Steel pile casting is set in the range of filled height or draws hole;After cast-in-situ bored pile reaches desired strength, pile crown is amputated by code requirement, Assembling reinforcement concrete joist and the connection reinforcing bar with stake;
(3) formwork erection of platform 91, one-time-concreting shaping, before pouring are kept off to reinforced concrete supporting beam 90, convex according to design attitude Carry out all kinds of built-in fittings such as pin 10 and the positioning with the connection reinforcing bar of pile foundation and install, concrete reaches and removed after design strength Template;
It is (4) long to armored concrete support rail beam base plate 2 and the merogenesis formwork erection of reinforced concrete beam type structure 1 according to design section, One-time-concreting is molded, and all kinds of built-in fittings such as sleeper pedestal connection reinforcing bar, water conservancy diversion rail bearing built-in fitting, pile foundation connection are carried out before pouring The positioning of reinforcing bar etc. and installation;
(5) each part concrete reaches and distinguish after design strength form removal, then by armored concrete support rail beam base plate 2 Bedding filler backfill in thickness range, backfill face is made outward-dipping weathering and carries out top layer waterproof i.e. by design requirement Can.
As it will be easily appreciated by one skilled in the art that preferred embodiment of the present utility model is the foregoing is only, not To limit the utility model, all any modifications made within spirit of the present utility model and principle, equivalent and change Enter, should be included within protection domain of the present utility model.

Claims (6)

1. medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction, it is characterised in that including pile foundation Bearing structure (3), reinforced concrete supporting beam (90), armored concrete support rail beam base plate (2), reinforced concrete beam type structure (1), Roadbed filling (5) and support rail beam both sides backfill filler (4) under support rail beam, wherein,
The pile foundation bearing structure (3) is provided with many, is vertically arranged per pile foundation bearing structure (3) described in root, and per root Accept the reinforced concrete supporting beam (90) in the top of the pile foundation bearing structure (3);
The reinforced concrete supporting beam (90) accepts the armored concrete support rail beam base plate (2);
Accept the reinforced concrete beam type structure (1) in the top of the armored concrete support rail beam base plate (2);
The top of the pile foundation bearing structure (3) is embedded in the reinforced concrete supporting beam (90) and just connects with it, the reinforced concrete Native joist (90) has just connect or has overlapped with the armored concrete support rail beam base plate (2), the armored concrete support rail beam base plate (2) It is molded so as to collectively form armored concrete support rail beam (9) with reinforced concrete beam type structure (1) formed by integrally casting;
Reinforced concrete supporting beam (90) both sides are provided with for limiting the armored concrete support rail beam base plate (2) laterally position Convex gear platform (91) of shifting;
Under the support rail beam roadbed filling (5) be arranged on shallow layer reinforcement area (6) and the armored concrete support rail beam base plate (2) it Between, for backfilling filler for the armored concrete support rail beam base plate (2), reinforced concrete supporting beam (90) and support rail beam both sides (4) operation platform is provided, and lateral support is provided for the pile foundation bearing structure (3);Wherein, the shallow layer reinforcement area (6) sets Put roadbed filling (5) and the steel under the superficial layer in soft stratum (7), and the shallow layer reinforcement area (6), the support rail beam Reinforced concrete beam type structure (1) vertical consistency;
Support rail beam both sides backfill filler (4) are accepted by roadbed filling (5) under the support rail beam, and the support rail beam two Side backfill filler (4) props up the both sides of the armored concrete support rail beam base plate (2), with to the armored concrete support rail beam Base plate (2) shields and constrains the transverse shifting of the armored concrete support rail beam base plate (2), and provides maintenance and lead to Road;
Roadbed filling (5) and support rail beam both sides backfill filler (4) collectively form filler filling body (10) under the support rail beam, Described filler filling body (10) both sides are provided with weathering (11);
Roadbed filling (5), the shallow layer reinforcement under the support rail beam is sequentially passed through per the lower end of pile foundation bearing structure (3) described in root Stretch into behind area (6) and the soft stratum (7) in supporting course (8), so that when soft stratum (7) produces sedimentation, the pile foundation is held Carrying structure (3) can bear negative friction, so as to for armored concrete support rail beam base plate (2) and reinforced concrete beam type structure (1) Stable bearing capacity is provided, to reduce because the sedimentation of filler filling body (10) is to the vertical, longitudinal of armored concrete support rail beam (9) The adverse effect produced with lateral stiffness.
2. pile foundation joist type support rail girder construction in medium-and low-speed maglev traffic engineering single line embankment location according to claim 1, Characterized in that, the pile foundation bearing structure (3) is cast-in-situ bored pile, reinforced concrete supporting beam has just connect or has taken with support rail beam base plate Connect, just connect with pile foundation bearing structure.
3. pile foundation joist type support rail girder construction in medium-and low-speed maglev traffic engineering single line embankment location according to claim 1, Characterized in that, the position reinforced concrete supporting beam in support rail beam internode seam is overlapped with support rail beam base plate using pin, remaining position Put to adopt and just connect.
4. pile foundation joist type support rail girder construction in medium-and low-speed maglev traffic engineering single line embankment location according to claim 1, Characterized in that, the support rail beam both sides backfill the height of filler (4) and the height of the armored concrete support rail beam base plate (2) It is equal.
5. pile foundation joist type support rail girder construction in medium-and low-speed maglev traffic engineering single line embankment location according to claim 1, Characterized in that, pile foundation bearing structure (3) described in all these is arranged in ranks.
6. pile foundation joist type support rail girder construction in medium-and low-speed maglev traffic engineering single line embankment location according to claim 3, Characterized in that, the pin includes pre-buried connection reinforcing bar, pitch hemp cut and stainless steel sleeve pipe, the pre-buried connection reinforcing bar is located at The pitch hemp cut is set in the stainless steel sleeve pipe and between the two.
CN201621057171.9U 2016-09-15 2016-09-15 Moderate -low speed magnetic levitation traffic engineering single line location supporting beam of pile foundation formula support rail girder construction of filling Withdrawn - After Issue CN206157484U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621057171.9U CN206157484U (en) 2016-09-15 2016-09-15 Moderate -low speed magnetic levitation traffic engineering single line location supporting beam of pile foundation formula support rail girder construction of filling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621057171.9U CN206157484U (en) 2016-09-15 2016-09-15 Moderate -low speed magnetic levitation traffic engineering single line location supporting beam of pile foundation formula support rail girder construction of filling

Publications (1)

Publication Number Publication Date
CN206157484U true CN206157484U (en) 2017-05-10

Family

ID=58650312

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621057171.9U Withdrawn - After Issue CN206157484U (en) 2016-09-15 2016-09-15 Moderate -low speed magnetic levitation traffic engineering single line location supporting beam of pile foundation formula support rail girder construction of filling

Country Status (1)

Country Link
CN (1) CN206157484U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106283955A (en) * 2016-09-15 2017-01-04 中铁第四勘察设计院集团有限公司 Medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction
CN108951335A (en) * 2018-09-06 2018-12-07 四川省交通运输厅公路规划勘察设计研究院 A kind of light-duty escarpment road structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106283955A (en) * 2016-09-15 2017-01-04 中铁第四勘察设计院集团有限公司 Medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction
CN106283955B (en) * 2016-09-15 2017-12-12 中铁第四勘察设计院集团有限公司 Medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction
CN108951335A (en) * 2018-09-06 2018-12-07 四川省交通运输厅公路规划勘察设计研究院 A kind of light-duty escarpment road structure

Similar Documents

Publication Publication Date Title
CN206157496U (en) Moderate -low speed magnetic levitation traffic engineering single line location pile foundation combined type support rail girder construction of filling
CN106283948B (en) Medium-and low-speed maglev traffic engineering two-wire embankment location pile foundation joist type support rail girder construction
CN206157484U (en) Moderate -low speed magnetic levitation traffic engineering single line location supporting beam of pile foundation formula support rail girder construction of filling
CN206157483U (en) Moderate -low speed magnetic levitation traffic engineering double -line location supporting beam of pile foundation formula support rail girder construction of filling
CN206157495U (en) Moderate -low speed magnetic levitation double -line compound framing type support rail girder construction of location pile foundation of filling
CN106283955B (en) Medium-and low-speed maglev traffic engineering single line embankment location pile foundation joist type support rail girder construction
CN106283949B (en) Medium-and low-speed maglev traffic engineering single line embankment location independence pier stud type support rail girder construction
CN206127736U (en) Moderate -low speed magnetic levitation double -line compound framing formula support rail roof beam transition section structure of location pile foundation that fills
CN206157489U (en) Moderate -low speed magnetic levitation double -line excavation location supporting beam of pile foundation framing type support rail girder construction
CN206157485U (en) Moderate -low speed magnetic levitation single line excavation location pile foundation combined type support rail roof beam transition section structure
CN106283952B (en) Medium-and low-speed maglev two-wire excavation location pile foundation joist framing type support rail girder construction
CN106283938B (en) The compound framing type support rail girder construction of medium-and low-speed maglev two-wire excavation location pile foundation
CN206157490U (en) Moderate -low speed magnetic levitation double -line location supporting beam of pile foundation framing type support rail girder construction of filling
CN206127745U (en) Moderate -low speed magnetic levitation traffic engineering single line location detached pier column type support rail girder construction of filling
CN206127742U (en) Moderate -low speed magnetic levitation traffic engineering double -line location detached pier column type support rail girder construction of filling
CN206157477U (en) Moderate -low speed magnetic levitation traffic engineering double -line location pile foundation combined type support rail girder construction of filling
CN206157494U (en) Moderate -low speed magnetic levitation traffic engineering single line excavation location supporting beam of pile foundation formula support rail girder construction
CN106436497B (en) Medium-and low-speed maglev traffic engineering two-wire embankment location independence pier stud type support rail girder construction
CN206219896U (en) Medium-and low-speed maglev traffic engineering two-wire excavation location pile foundation joist type support rail girder construction
CN106283968B (en) Medium-and low-speed maglev two-wire embankment location pile foundation is combined framing type support rail girder construction
CN206157486U (en) Moderate -low speed magnetic levitation traffic engineering single line excavation location pile foundation combined type support rail girder construction
CN206157487U (en) Moderate -low speed magnetic levitation single line location pile foundation combined type support rail roof beam transition section structure that fills
CN206157478U (en) Moderate -low speed magnetic levitation double -line excavation location supporting beam of pile foundation formula support rail roof beam transition section structure
CN106283971B (en) Medium-and low-speed maglev traffic engineering single line excavation location pile foundation joist type support rail girder construction
CN206157480U (en) Moderate -low speed magnetic levitation traffic engineering double -line excavation location pile foundation combined type support rail girder construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20170510

Effective date of abandoning: 20171212