CN205773101U - Underground based on hydraulic jack and the pulley mechanism aboveground lid arrangement of work - Google Patents

Underground based on hydraulic jack and the pulley mechanism aboveground lid arrangement of work Download PDF

Info

Publication number
CN205773101U
CN205773101U CN201620520848.1U CN201620520848U CN205773101U CN 205773101 U CN205773101 U CN 205773101U CN 201620520848 U CN201620520848 U CN 201620520848U CN 205773101 U CN205773101 U CN 205773101U
Authority
CN
China
Prior art keywords
cover plate
hydraulic jack
concrete tunnel
length
pulley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201620520848.1U
Other languages
Chinese (zh)
Inventor
杨杰
文东辉
蔡东海
金明生
王扬渝
程金强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Co Ltd Of Yiwu Scientific And Technical Research Institute Of Zhejiang Polytechnical University
Yiwu Science and Technology Research Institute of ZJUT
Original Assignee
Co Ltd Of Yiwu Scientific And Technical Research Institute Of Zhejiang Polytechnical University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Co Ltd Of Yiwu Scientific And Technical Research Institute Of Zhejiang Polytechnical University filed Critical Co Ltd Of Yiwu Scientific And Technical Research Institute Of Zhejiang Polytechnical University
Priority to CN201620520848.1U priority Critical patent/CN205773101U/en
Application granted granted Critical
Publication of CN205773101U publication Critical patent/CN205773101U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

A kind of underground based on hydraulic jack and pulley mechanism aboveground lid arrangement of work, including the concrete tunnel being cast on earth hole, described concrete tunnel is provided with cover plate, described capping device also includes the hydraulic jack in order to cover plate lifting and in order to the pulley mechanism drive mechanism slided about cover plate, and described concrete tunnel is all installed with described hydraulic jack on two inwalls of length direction;Described pulley mechanism includes track and pulley assembly, described concrete tunnel is mounted on described track on two inwalls of length direction, on the inwall of the same side, concrete tunnel, described track is between the inwall in described hydraulic jack and described concrete tunnel.This utility model provides a kind of underground based on hydraulic jack and pulley mechanism aboveground lid arrangement of work be easy to and dismount, maintenance cost is relatively low.

Description

Underground based on hydraulic jack and the pulley mechanism aboveground lid arrangement of work
Technical field
This utility model relates to a kind of underground based on hydraulic jack and pulley mechanism aboveground lid arrangement of work.
Background technology
Along with the quickening of Urbanization in China, increasing building is rised sheer from level ground, and mansion is intensive, city Road extends in all direction, but simultaneously, land used is nervous, vivosphere is crowded, traffic jam, ecology are lost The problems such as weighing apparatus are also comed one after another, and live to people and bring the biggest impact, also govern economy and society Development further.Devoting Major Efforts To Developing utilizes underground Gong Jing, for solving land used anxiety, congested in traffic, environment evil Many difficult problems in the urbanization process such as change, it is achieved sustainable development is significant.
For solving place anxiety, environmental pollution and qualitative problems of construction, commonly use now batch production batch system The concrete mould module component made, build pipeline facility underground job well, as drainer well, communication work well, Power cable work well, ring main unit basis well, switch cubicle basis well, various case become basis well, cable branch box Basis well etc..But, if underground Gong Jing needs repairing, upkeep operation time, need to open work manhole cover plate, To facilitate entrance and to implement lifting operation.But, owing to underground work well surrounding enviroment are complicated, typically no foot On-site hoisting operation is implemented in enough places, and it is dynamic typically not possess electric power, hydraulic oil source, compressed air source etc. Power is originated, and generally by workman's manual work, labor intensity is big, how to design the aboveground lid of work and the fastest Speed opens the aboveground lid of work easily becomes a problem demanding prompt solution.
Summary of the invention
In order to overcome existing work manhole cover plate to open the deficiency that technology exists, this utility model provides one and is easy to Dismounting, relatively low underground based on hydraulic jack and the pulley mechanism aboveground lid arrangement of work of maintenance cost.
This utility model solves the technical scheme that its technical problem used:
A kind of underground based on hydraulic jack and pulley mechanism aboveground lid arrangement of work, including being cast in earth hole On concrete tunnel, described concrete tunnel is provided with cover plate, and described capping device also includes in order to cover plate Lifting hydraulic jack and in order to the pulley mechanism slided about cover plate, described concrete tunnel is in length side To two inwalls on be all installed with described hydraulic jack;
Described cover plate includes that cover plate block, described cover plate block include end cover plate and middle cover plate, described end Portion's cover plate block includes the left end cap plate being positioned at concrete tunnel length direction and is positioned at concrete tunnel length side To right end cap plate, described middle cover plate is provided with two or more, and the lower section of each middle cover plate is equal It is provided with two hydraulic jack;Increase successively from the length of the cover plate block of two ends end cover plate to middle cover plate Long;
Described pulley mechanism includes track and pulley assembly, and described concrete tunnel is in two of length direction Being mounted on described track on wall, on the inwall of the same side, concrete tunnel, described track is positioned at described liquid Between pressure jack and the inwall in described concrete tunnel, described pulley assembly includes wheel support and pulley, The bottom at the two ends of described middle cover plate is respectively equipped with described wheel support, the upper end of described wheel support with The described collapsible connection of middle cover plate, the lower end of described wheel support is provided with described pulley, described pulley with Described track forms the length in sliding pair, the left and right line of travel of described middle cover plate and described concrete tunnel Degree direction is identical;
On two ends end cover plate to middle cover plate, the length of wheel support increases successively, described pulley with Track one_to_one corresponding, be arranged in parallel between adjacent orbit.
Further, the bottom at the two ends of each middle cover plate is respectively equipped with two pulley assemblies, with one end The pulley of two pulley assemblies forms sliding pair with same track.
Further, described concrete tunnel is respectively equipped with erecting bed on two inwalls of length direction, institute State hydraulic jack and be fixed on described erecting bed on the side away from concrete tunnel inwall;Described track is pacified It is contained in described erecting bed on the side near concrete tunnel inwall.
Further, each cover plate block be respectively arranged at two ends with head lawn, long before and after described head lawn Degree is sequentially reduced to middle cover plate from two ends end cover plate, and before and after each cover plate block, length is plus corresponding Before and after head lawn, the total length of length is identical.
Further, the number of described cover plate block is 2n, and n is the natural number more than or equal to 1, described in Between cover plate block include left cap plate, LC cover plate block, right central cover block and right cap plate, from left End cap plate sets to the two ends of right cap plate respectively to the two ends of left cap plate and from right end cap plate Having described head lawn, described LC cover plate block is arranged side by side with right central cover block and anterior-posterior length is identical, Before and after left end cap plate to left cap plate, length is plus length, the certainly right side before and after corresponding head lawn End cap plate to length before and after right cap plate plus length before and after corresponding head lawn all with a described left side Before and after central lid plate, right central cover block, length is identical.
Further, the number of described cover plate block is 12, wherein, and described left end cap plate and right end cap Plate is one, and the number of described middle cover plate is ten, on the inwall of the same side, concrete tunnel The number of track is five.
What this utility model mainly showed has the beneficial effect that this utility model can on the cover board plant vegetation, When needing to be serviced, use hydraulic jack and pulley mechanism to open cover plate, alleviate operator's Labor intensity;And the cover plate Symmetrical vertical after opening up is stacked on Gong Jing both sides, for carrying out safeguarding, The operant activities such as maintenance, lifting operation provide the biggest space;Environmental protection simultaneously, Economization on land and have relatively High safety.
Accompanying drawing explanation
Fig. 1 is the length scattergram of the wheel support on cover plate block of the present utility model.
Fig. 2 is the structural representation of cover plate block of the present utility model.
Fig. 3 is the state diagram that cover plate block of the present utility model is fully open.
Fig. 4 is the structural representation of hydraulic jack.
Detailed description of the invention
Below in conjunction with the accompanying drawings this utility model is further described.
With reference to Fig. 1~Fig. 4, a kind of underground based on hydraulic jack and pulley mechanism aboveground lid arrangement of work, bag Including the concrete tunnel 8 being cast on earth hole, described concrete tunnel 8 is provided with cover plate, and described upper cover fills Put and also include the hydraulic jack 11 in order to cover plate lifting and in order to the pulley mechanism slided about cover plate, described Concrete tunnel is all installed with described hydraulic jack 11 on two inwalls of length direction;
Described cover plate includes that cover plate block, described cover plate block include end cover plate and middle cover plate, described end Portion's cover plate block includes the left end cap plate being positioned at the left end of concrete tunnel 8 length direction and is positioned at coagulation heatable adobe sleeping platform The right end cap plate of the right-hand member of road 8 length direction, described middle cover plate is provided with two or more, Mei Gezhong Between the lower section of cover plate block be equipped with two hydraulic jack;Lid from two ends end cover plate to middle cover plate The length of plate increases successively;
Described pulley mechanism includes track and pulley assembly, and described concrete tunnel is in two of length direction Being mounted on described track on wall, on the inwall of the same side, concrete tunnel, described track is positioned at described liquid Between pressure jack and the inwall in described concrete tunnel, described pulley assembly includes wheel support 10 and pulley, The bottom at the two ends of described middle cover plate is respectively equipped with described wheel support 10, described wheel support 10 upper Holding be connected collapsible with described middle cover plate, the lower end of described wheel support 10 is provided with described pulley, described Pulley and described track form sliding pair, the left and right line of travel of described middle cover plate and described coagulation heatable adobe sleeping platform The length direction in road is identical;
On two ends end cover plate to middle cover plate, the length of wheel support increases successively, described pulley with Track one_to_one corresponding, be arranged in parallel between adjacent orbit.
Further, the bottom at the two ends of each middle cover plate is respectively equipped with two pulley assemblies, with one end The pulley of two pulley assemblies forms sliding pair with same track.
Further, described concrete tunnel 8 is respectively equipped with erecting bed on two inwalls of length direction, Described hydraulic jack is fixed on described erecting bed on the side away from concrete tunnel inwall;Described track It is arranged on described erecting bed on the side near concrete tunnel inwall.
Further, each cover plate block be respectively arranged at two ends with head lawn 9, before and after described head lawn 9 Length is sequentially reduced to middle cover plate from two ends end cover plate, and before and after each cover plate block, length adds phase Answer the total length of length before and after head lawn identical.
Further, the number of described cover plate block is 2n, and n is the natural number more than or equal to 1, described in Between cover plate block include left cap plate, LC cover plate block, right central cover block and right cap plate, from left End cap plate sets to the two ends of right cap plate respectively to the two ends of left cap plate and from right end cap plate Described head lawn 9, described LC cover plate block is had to be arranged side by side and anterior-posterior length phase with right central cover block With, before and after left end cap plate to left cap plate length plus length before and after corresponding head lawn, Before and after right end cap plate to right cap plate, length is plus length before and after corresponding head lawn all and institute Before and after stating LC cover plate block, right central cover block, length is identical.
Further, the number of described cover plate block is 12, wherein, and described left end cap plate and right end cap Plate is one, and the number of described middle cover plate is ten, on the inwall of the same side, concrete tunnel The number of track is five.
In the present embodiment, being equipped with various pipeline in concrete tunnel 8, planting above cover plate has vegetation or block to have drip Green grass or young crops, when cover plate tiles, wheel support 10 is folded in the bottom of cover plate block;Head lawn 1 is placed on each lid The two ends of plate, its bottom surface contacts with track 7;Inwall in the same side, concrete tunnel 8 gets on the right track Number is the half of the number of inter panel, because the number of inter panel is even number left and right mean allocation.
As it is shown on figure 3, described track 7 is arranged on concrete tunnel 8 on two inwalls of length direction, Orbital Symmetry on two inwalls in concrete tunnel 8 is arranged, the two ends of described middle cover plate lay respectively at In corresponding hydraulic jack 11, the corresponding corresponding track of the pulley at each middle cover plate two ends;Described hydraulic pressure Jack 11 is adjacent with track 7;When inter panel block is even number and also be to divide the left and right sides equally to move, described The number of track is identical with the number of middle cover plate, divides equally carry out to from left to right because inter panel is left and right Slide, so the track number on the concrete tunnel of the same side should be the half of the number of inter panel.
As shown in Figure 4, hydraulic jack 11 is additionally provided with handle 13 and rocking bar 12, during external drive is passed through Between the installing hole of cover plate and docking mechanism docking, inter panel is risen a segment distance, then lateral symmetry ground Hydraulic jack is risen, and concrete operations are that pressing handle 13 carries out pressurizeing and steadily risen by inter panel, when Wheel support 10 opens rear pressure-bearing, and hydraulic jack 11 being lowered is to carry out pressure release by rocking bar 12.
Work process of the present utility model is: the initial condition of whole device is inter panel and head lawn 9 Being laid on concrete tunnel 7, when needs overhaul, the head lawn of both sides is motionless, then passes through outside Drive docking mechanism that the middle cover plate 2 of side first rises a segment distance, the most monosymmetric be fixed on Middle cover plate 2 is the most steadily risen by the hydraulic jack 11 on concrete tunnel 8 simultaneously, by pressing Handle 13 supercharging is raised to certain altitude, then the four wheels being connected between bottom cover plate block is supported 10 Open, the pulley alignment rail 7 of described wheel support 10 lower end, then turn oil return valve decompression by rocking bar 12, Hydraulic jack 11 slowly declines middle cover plate 2 and declines hydraulic pressure thousand to its pulley contact to track 7, continuation Jin top 11 is until no longer contacting middle cover plate 2, and now four wheels support 10 starts to support middle cover plate The weight of 2, is manually pushed into the one end in concrete tunnel 8 by middle cover plate 2 along with wheel support 10 together, So inter panel 2 just vertical above the end cover plate 1 being stacked on avris, because of middle Wheel support length shortens successively toward direction of both ends, and each middle cover plate all has single track, depends on Secondary repetition aforesaid way stacks remaining middle cover plate, and the middle cover plate of opposite side is also to repeat above-mentioned side Formula is stacked five cover plate blocks vertically upward, the end cover plate at the two ends, left and right in concrete tunnel 8 during beginning It is fixed;So far the cover plate of underground work well opens, symmetrical vertical distribution both sides on the ground, Middle cover plate 2 pushes both sides to by pulley assembly and track 7, so result is the stacking realizing both sides, Advantage is to use hydraulic jack 11 and track 7 to alleviate labour force, and cover plate block is in both sides vertical direction Symmetrical stack also saves space, and the cover plate gate also making underground work well is broader, carries out for underground Operant activity provides the biggest space;After maintenance, both sides middle cover plate is shifted onto when tiling On home position, make hydraulic jack 11 rise, then wheel support 6 is folded into the end of middle cover plate Portion, carries out pressure release by rocking bar 12 and hydraulic jack 11 is lowered.
This utility model, primarily to save space and ensure safety of surrounding environment, is generally used for underground electricity Laying of cable.
It should be appreciated that above-mentioned detailed description of the invention of the present utility model is used only for exemplary illustration or solution Release principle of the present utility model, and do not constitute restriction of the present utility model.Therefore, without departing from this practicality Any modification, equivalent substitution and improvement etc. done in the case of novel spirit and scope, should be included in Within protection domain of the present utility model.Additionally, this utility model claims are intended to fall into institute Whole in the equivalents on attached right and border or this scope and border change and modifications Example.

Claims (6)

1. underground based on hydraulic jack and the pulley mechanism aboveground lid arrangement of work, including being cast in earth hole On concrete tunnel, described concrete tunnel is provided with cover plate, it is characterised in that: described capping device is also Including the hydraulic jack lifted in order to cover plate with in order to the pulley mechanism slided about cover plate, described concrete Tunnel is all installed with described hydraulic jack on two inwalls of length direction;
Described cover plate includes that cover plate block, described cover plate block include end cover plate and middle cover plate, described end Portion's cover plate block includes the left end cap plate being positioned at the left end of concrete tunnel length direction and is positioned at concrete tunnel The right end cap plate of the right-hand member of length direction, described middle cover plate is provided with two or more, each middle cover The lower section of plate is equipped with two hydraulic jack;Cover plate block from two ends end cover plate to middle cover plate Length increase successively;
Described pulley mechanism includes track and pulley assembly, and described concrete tunnel is in two of length direction Being mounted on described track on wall, on the inwall of the same side, concrete tunnel, described track is positioned at described liquid Between pressure jack and the inwall in described concrete tunnel, described pulley assembly includes wheel support and pulley, The bottom at the two ends of described middle cover plate is respectively equipped with described wheel support, the upper end of described wheel support with The described collapsible connection of middle cover plate, the lower end of described wheel support is provided with described pulley, described pulley with Described track forms the length in sliding pair, the left and right line of travel of described middle cover plate and described concrete tunnel Degree direction is identical;
On two ends end cover plate to middle cover plate, the length of wheel support increases successively, described pulley with Track one_to_one corresponding, be arranged in parallel between adjacent orbit.
2. underground based on hydraulic jack and the pulley mechanism as claimed in claim 1 aboveground lid arrangement of work, it is special Levy and be: the bottom at the two ends of each middle cover plate is respectively equipped with two pulley assemblies, with two of one end The pulley of pulley assembly forms sliding pair with same track.
3. underground based on hydraulic jack and the pulley mechanism as claimed in claim 1 or 2 aboveground lid arrangement of work, It is characterized in that: described concrete tunnel is respectively equipped with erecting bed on two inwalls of length direction, described Hydraulic jack is fixed on described erecting bed on the side away from concrete tunnel inwall;Described track installation At described erecting bed on the side near concrete tunnel inwall.
4. underground based on hydraulic jack and pulley mechanism as claimed in claim 1 or 2 work aboveground lid dress Put, it is characterised in that: each cover plate block be respectively arranged at two ends with head lawn, before and after described head lawn Length is sequentially reduced to middle cover plate from two ends end cover plate, and before and after each cover plate block, length adds phase Answer the total length of length before and after head lawn identical.
5. underground based on hydraulic jack and the pulley mechanism as claimed in claim 4 aboveground lid arrangement of work, its It is characterised by: the number of described cover plate block is 2n, and n is the natural number more than or equal to 1, described middle cover Plate includes left cap plate, LC cover plate block, right central cover block and right cap plate, from left end cap Plate is to the two ends of left cap plate and is provided with institute respectively to the two ends of right cap plate from right end cap plate Stating head lawn, described LC cover plate block is arranged side by side with right central cover block and anterior-posterior length is identical, from Left end cap plate to length before and after left cap plate plus length before and after corresponding head lawn, from right-hand member Cover plate block is all left with described plus length before and after corresponding head lawn to length before and after right cap plate Before and after heart cover plate block, right central cover block, length is identical.
6. underground based on hydraulic jack and the pulley mechanism as claimed in claim 5 aboveground lid arrangement of work, its It is characterised by: the number of described cover plate block is 12, wherein, described left end cap plate and right end cap plate Being one, the number of described middle cover plate is ten, and the inwall in the same side, concrete tunnel gets on the right track Number be five.
CN201620520848.1U 2016-06-01 2016-06-01 Underground based on hydraulic jack and the pulley mechanism aboveground lid arrangement of work Withdrawn - After Issue CN205773101U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620520848.1U CN205773101U (en) 2016-06-01 2016-06-01 Underground based on hydraulic jack and the pulley mechanism aboveground lid arrangement of work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620520848.1U CN205773101U (en) 2016-06-01 2016-06-01 Underground based on hydraulic jack and the pulley mechanism aboveground lid arrangement of work

Publications (1)

Publication Number Publication Date
CN205773101U true CN205773101U (en) 2016-12-07

Family

ID=58135520

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620520848.1U Withdrawn - After Issue CN205773101U (en) 2016-06-01 2016-06-01 Underground based on hydraulic jack and the pulley mechanism aboveground lid arrangement of work

Country Status (1)

Country Link
CN (1) CN205773101U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105858540A (en) * 2016-06-01 2016-08-17 浙江工业大学义乌科学技术研究院有限公司 Underground well covering device based on hydraulic jack and pulley mechanism
CN108824481A (en) * 2018-06-20 2018-11-16 上海市政工程设计研究总院(集团)有限公司 A kind of piping lane system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105858540A (en) * 2016-06-01 2016-08-17 浙江工业大学义乌科学技术研究院有限公司 Underground well covering device based on hydraulic jack and pulley mechanism
CN108824481A (en) * 2018-06-20 2018-11-16 上海市政工程设计研究总院(集团)有限公司 A kind of piping lane system

Similar Documents

Publication Publication Date Title
CN104453231B (en) Gantry type building construction lifting device as well as manufacturing method and construction method thereof
CN102704723A (en) Independent household hydraulic miniature double-parking space stereo garage and using method thereof
CN105129627A (en) Folding type suspension arm device supported by electric pole
CN201268937Y (en) Double-layer hanging cradle for working aloft
CN203412273U (en) Full-circular orbit type lifting work platform of storage tank
CN205894099U (en) Be applied to underground pipe gallery's portable sliding template device
CN205773101U (en) Underground based on hydraulic jack and the pulley mechanism aboveground lid arrangement of work
CN105858540A (en) Underground well covering device based on hydraulic jack and pulley mechanism
CN103806654A (en) Hydraulic support system for elevator shaft mold and operating method thereof
CN104453951B (en) Combined type subway station lining template trolley for baffle
CN206955590U (en) A kind of Portable lifting workbench
CN102852357A (en) Structural mode of independently-arranged household hydraulic miniature double parking place three-dimensional garage
CN210858185U (en) Transformer oil pool overhauling operation platform for high-speed railway traction substation pavilion
CN206625845U (en) A kind of inverted arch trestle
CN203147030U (en) Mobile under-hanging operating platform for construction of laying gas pipeline along bridge
CN206942295U (en) A kind of assembled urban road upper strata space intelligent stereo-parking system
CN105887933B (en) A kind of underground work manhole cover plate quickly opening and closing mechanism
CN205474847U (en) Bridge water -drain mast installation platform truck
CN204982776U (en) A plurality of large -scale concrete buttress synchronous construction slipform systems
CN212771963U (en) Movable suspension operation platform
CN210795641U (en) Lifting platform for waterproof, anti-corrosion and heat-preservation engineering
CN204097020U (en) Fluid pressure type boiler assembling jacking system
CN204022222U (en) The integrated driving device of a kind of building hoist
CN208022659U (en) A kind of civil engineering elevator
CN202370422U (en) Automatic extension ladder device of working platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20161207

Effective date of abandoning: 20180109

AV01 Patent right actively abandoned