CN105858540A - Underground well covering device based on hydraulic jack and pulley mechanism - Google Patents

Underground well covering device based on hydraulic jack and pulley mechanism Download PDF

Info

Publication number
CN105858540A
CN105858540A CN201610383842.9A CN201610383842A CN105858540A CN 105858540 A CN105858540 A CN 105858540A CN 201610383842 A CN201610383842 A CN 201610383842A CN 105858540 A CN105858540 A CN 105858540A
Authority
CN
China
Prior art keywords
cover plate
length
pulley
block
hydraulic jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610383842.9A
Other languages
Chinese (zh)
Other versions
CN105858540B (en
Inventor
文东辉
王扬渝
蔡东海
金明生
杨杰
章少杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Co Ltd Of Yiwu Scientific And Technical Research Institute Of Zhejiang Polytechnical University
Original Assignee
Co Ltd Of Yiwu Scientific And Technical Research Institute Of Zhejiang Polytechnical University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Co Ltd Of Yiwu Scientific And Technical Research Institute Of Zhejiang Polytechnical University filed Critical Co Ltd Of Yiwu Scientific And Technical Research Institute Of Zhejiang Polytechnical University
Priority to CN201610383842.9A priority Critical patent/CN105858540B/en
Publication of CN105858540A publication Critical patent/CN105858540A/en
Application granted granted Critical
Publication of CN105858540B publication Critical patent/CN105858540B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66FHOISTING, LIFTING, HAULING OR PUSHING, NOT OTHERWISE PROVIDED FOR, e.g. DEVICES WHICH APPLY A LIFTING OR PUSHING FORCE DIRECTLY TO THE SURFACE OF A LOAD
    • B66F7/00Lifting frames, e.g. for lifting vehicles; Platform lifts
    • B66F7/10Lifting frames, e.g. for lifting vehicles; Platform lifts with platforms supported directly by jacks
    • B66F7/16Lifting frames, e.g. for lifting vehicles; Platform lifts with platforms supported directly by jacks by one or more hydraulic or pneumatic jacks
    • B66F7/20Lifting frames, e.g. for lifting vehicles; Platform lifts with platforms supported directly by jacks by one or more hydraulic or pneumatic jacks by several jacks with means for maintaining the platforms horizontal during movement
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/14Covers for manholes or the like; Frames for covers
    • E02D29/1418Covers for manholes or the like; Frames for covers with implements to assist in lifting, e.g. counterweights, springs

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Geology (AREA)
  • Mechanical Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses an underground well covering device based on hydraulic jacks and a pulley mechanism. The underground well covering device comprises a concrete adit poured on a soil pit, wherein a cover plate is arranged on the concrete adit. The covering device also comprises hydraulic jacks for lifting/lowering the cover plate and a pulley mechanism transmission mechanism sliding left and right along the cover plate, wherein the hydraulic jacks are fixedly mounted on the two inner walls of the concrete adit in the length direction; the pulley mechanism comprises tracks and a pulley component; the tracks are mounted on the two inner walls of the concrete adit in the length direction; and on the inner wall on the same side of the concrete adit, the tracks are positioned between the hydraulic jacks and the inner wall of the concrete adit. The underground well covering device based on hydraulic jacks and a pulley mechanism provided by the invention is convenient to assemble/disassemble while the maintenance cost is relatively low.

Description

Underground based on hydraulic jack and the pulley mechanism aboveground lid arrangement of work
Technical field
The present invention relates to a kind of underground based on hydraulic jack and pulley mechanism aboveground lid arrangement of work.
Background technology
Along with the quickening of Urbanization in China, increasing building is rised sheer from level ground, and mansion is intensive, city Road extends in all direction, but simultaneously, land used is nervous, vivosphere is crowded, traffic jam, ecology are lost The problems such as weighing apparatus are also comed one after another, and live to people and bring the biggest impact, also govern economy and society Development further.Devoting Major Efforts To Developing utilizes underground Gong Jing, for solving land used anxiety, congested in traffic, environment evil Many difficult problems in the urbanization process such as change, it is achieved sustainable development is significant.
For solving place anxiety, environmental pollution and qualitative problems of construction, commonly use now batch production batch system The concrete mould module component made, build pipeline facility underground job well, as drainer well, communication work well, Power cable work well, ring main unit basis well, switch cubicle basis well, various case become basis well, cable branch box Basis well etc..But, if underground Gong Jing needs repairing, upkeep operation time, need to open work manhole cover plate, To facilitate entrance and to implement lifting operation.But, owing to underground work well surrounding enviroment are complicated, typically no foot On-site hoisting operation is implemented in enough places, and it is dynamic typically not possess electric power, hydraulic oil source, compressed air source etc. Power is originated, and generally by workman's manual work, labor intensity is big, how to design the aboveground lid of work and the fastest Speed opens the aboveground lid of work easily becomes a problem demanding prompt solution.
Summary of the invention
In order to overcome existing work manhole cover plate open technology exist deficiency, the invention provides one be easy to dismounting, Underground based on hydraulic jack and the pulley mechanism aboveground lid arrangement of work that maintenance cost is relatively low.
The technical solution adopted for the present invention to solve the technical problems is:
A kind of underground based on hydraulic jack and pulley mechanism aboveground lid arrangement of work, including being cast in earth hole On concrete tunnel, described concrete tunnel is provided with cover plate, and described capping device also includes in order to cover plate Lifting hydraulic jack and in order to the pulley mechanism slided about cover plate, described concrete tunnel is in length side To two inwalls on be all installed with described hydraulic jack;
Described cover plate includes that cover plate block, described cover plate block include end cover plate and middle cover plate, described end Portion's cover plate block includes the left end cap plate being positioned at concrete tunnel length direction and is positioned at concrete tunnel length side To right end cap plate, described middle cover plate is provided with two or more, and the lower section of each middle cover plate is equal It is provided with two hydraulic jack;Increase successively from the length of the cover plate block of two ends end cover plate to middle cover plate Long;
Described pulley mechanism includes track and pulley assembly, and described concrete tunnel is in two of length direction Being mounted on described track on wall, on the inwall of the same side, concrete tunnel, described track is positioned at described liquid Between pressure jack and the inwall in described concrete tunnel, described pulley assembly includes wheel support and pulley, The bottom at the two ends of described middle cover plate is respectively equipped with described wheel support, the upper end of described wheel support with The described collapsible connection of middle cover plate, the lower end of described wheel support is provided with described pulley, described pulley with Described track forms the length in sliding pair, the left and right line of travel of described middle cover plate and described concrete tunnel Degree direction is identical;
On two ends end cover plate to middle cover plate, the length of wheel support increases successively, described pulley with Track one_to_one corresponding, be arranged in parallel between adjacent orbit.
Further, the bottom at the two ends of each middle cover plate is respectively equipped with two pulley assemblies, with one end The pulley of two pulley assemblies forms sliding pair with same track.
Further, described concrete tunnel is respectively equipped with erecting bed on two inwalls of length direction, institute State hydraulic jack and be fixed on described erecting bed on the side away from concrete tunnel inwall;Described track is pacified It is contained in described erecting bed on the side near concrete tunnel inwall.
Further, each cover plate block be respectively arranged at two ends with head lawn, long before and after described head lawn Degree is sequentially reduced to middle cover plate from two ends end cover plate, and before and after each cover plate block, length is plus corresponding Before and after head lawn, the total length of length is identical.
Further, the number of described cover plate block is 2n, and n is the natural number more than or equal to 1, described in Between cover plate block include left cap plate, LC cover plate block, right central cover block and right cap plate, from left End cap plate sets to the two ends of right cap plate respectively to the two ends of left cap plate and from right end cap plate Having described head lawn, described LC cover plate block is arranged side by side with right central cover block and anterior-posterior length is identical, Before and after left end cap plate to left cap plate, length is plus length, the certainly right side before and after corresponding head lawn End cap plate to length before and after right cap plate plus length before and after corresponding head lawn all with a described left side Before and after central lid plate, right central cover block, length is identical.
Further, the number of described cover plate block is 12, wherein, and described left end cap plate and right end cap Plate is one, and the number of described middle cover plate is ten, on the inwall of the same side, concrete tunnel The number of track is five.
What the present invention mainly showed has the beneficial effect that the present invention can on the cover board plant vegetation, when needs enter When row is safeguarded, use hydraulic jack and pulley mechanism to open cover plate, alleviate the labor intensity of operator; And the cover plate Symmetrical vertical after opening up is stacked on Gong Jing both sides, for carrying out maintenance, repair, lifting The operant activities such as operation provide the biggest space;Environmental protection simultaneously, Economization on land and there is higher safety.
Accompanying drawing explanation
Fig. 1 is the length scattergram of the wheel support on the cover plate block of the present invention.
Fig. 2 is the structural representation of the cover plate block of the present invention.
Fig. 3 is the state diagram that the cover plate block of the present invention is fully open.
Fig. 4 is the structural representation of hydraulic jack.
Detailed description of the invention
The invention will be further described below in conjunction with the accompanying drawings.
With reference to Fig. 1~Fig. 4, a kind of underground based on hydraulic jack and pulley mechanism aboveground lid arrangement of work, bag Including the concrete tunnel 8 being cast on earth hole, described concrete tunnel 8 is provided with cover plate, and described upper cover fills Put and also include the hydraulic jack 11 in order to cover plate lifting and in order to the pulley mechanism slided about cover plate, described Concrete tunnel is all installed with described hydraulic jack 11 on two inwalls of length direction;
Described cover plate includes that cover plate block, described cover plate block include end cover plate and middle cover plate, described end Portion's cover plate block includes the left end cap plate being positioned at the left end of concrete tunnel 8 length direction and is positioned at coagulation heatable adobe sleeping platform The right end cap plate of the right-hand member of road 8 length direction, described middle cover plate is provided with two or more, Mei Gezhong Between the lower section of cover plate block be equipped with two hydraulic jack;Lid from two ends end cover plate to middle cover plate The length of plate increases successively;
Described pulley mechanism includes track and pulley assembly, and described concrete tunnel is in two of length direction Being mounted on described track on wall, on the inwall of the same side, concrete tunnel, described track is positioned at described liquid Between pressure jack and the inwall in described concrete tunnel, described pulley assembly includes wheel support 10 and pulley, The bottom at the two ends of described middle cover plate is respectively equipped with described wheel support 10, described wheel support 10 upper Holding be connected collapsible with described middle cover plate, the lower end of described wheel support 10 is provided with described pulley, described Pulley and described track form sliding pair, the left and right line of travel of described middle cover plate and described coagulation heatable adobe sleeping platform The length direction in road is identical;
On two ends end cover plate to middle cover plate, the length of wheel support increases successively, described pulley with Track one_to_one corresponding, be arranged in parallel between adjacent orbit.
Further, the bottom at the two ends of each middle cover plate is respectively equipped with two pulley assemblies, with one end The pulley of two pulley assemblies forms sliding pair with same track.
Further, described concrete tunnel 8 is respectively equipped with erecting bed on two inwalls of length direction, Described hydraulic jack is fixed on described erecting bed on the side away from concrete tunnel inwall;Described track It is arranged on described erecting bed on the side near concrete tunnel inwall.
Further, each cover plate block be respectively arranged at two ends with head lawn 9, before and after described head lawn 9 Length is sequentially reduced to middle cover plate from two ends end cover plate, and before and after each cover plate block, length adds phase Answer the total length of length before and after head lawn identical.
Further, the number of described cover plate block is 2n, and n is the natural number more than or equal to 1, described in Between cover plate block include left cap plate, LC cover plate block, right central cover block and right cap plate, from left End cap plate sets to the two ends of right cap plate respectively to the two ends of left cap plate and from right end cap plate Described head lawn 9, described LC cover plate block is had to be arranged side by side and anterior-posterior length phase with right central cover block With, before and after left end cap plate to left cap plate length plus length before and after corresponding head lawn, Before and after right end cap plate to right cap plate, length is plus length before and after corresponding head lawn all and institute Before and after stating LC cover plate block, right central cover block, length is identical.
Further, the number of described cover plate block is 12, wherein, and described left end cap plate and right end cap Plate is one, and the number of described middle cover plate is ten, on the inwall of the same side, concrete tunnel The number of track is five.
In the present embodiment, being equipped with various pipeline in concrete tunnel 8, planting above cover plate has vegetation or block to have drip Green grass or young crops, when cover plate tiles, wheel support 10 is folded in the bottom of cover plate block;Head lawn 1 is placed on each lid The two ends of plate, its bottom surface contacts with track 7;Inwall in the same side, concrete tunnel 8 gets on the right track Number is the half of the number of inter panel, because the number of inter panel is even number left and right mean allocation.
As it is shown on figure 3, described track 7 is arranged on concrete tunnel 8 on two inwalls of length direction, Orbital Symmetry on two inwalls in concrete tunnel 8 is arranged, the two ends of described middle cover plate lay respectively at In corresponding hydraulic jack 11, the corresponding corresponding track of the pulley at each middle cover plate two ends;Described hydraulic pressure Jack 11 is adjacent with track 7;When inter panel block is even number and also be to divide the left and right sides equally to move, described The number of track is identical with the number of middle cover plate, divides equally carry out to from left to right because inter panel is left and right Slide, so the track number on the concrete tunnel of the same side should be the half of the number of inter panel.
As shown in Figure 4, hydraulic jack 11 is additionally provided with handle 13 and rocking bar 12, during external drive is passed through Between the installing hole of cover plate and docking mechanism docking, inter panel is risen a segment distance, then lateral symmetry ground Hydraulic jack is risen, and concrete operations are that pressing handle 13 carries out pressurizeing and steadily risen by inter panel, when Wheel support 10 opens rear pressure-bearing, and hydraulic jack 11 being lowered is to carry out pressure release by rocking bar 12.
The work process of the present invention is: the initial condition of whole device is inter panel and tiles in head lawn 9 On concrete tunnel 7, when needs overhaul, the head lawn of both sides is motionless, then passes through external drive The middle cover plate 2 of side is first risen a segment distance by docking mechanism, the most monosymmetric is fixed on coagulation Middle cover plate 2 is the most steadily risen by the hydraulic jack 11 on heatable adobe sleeping platform road 8 simultaneously, by pressing handle 13 superchargings are raised to certain altitude, then the four wheels being connected between bottom cover plate block are supported 10 and open, The pulley alignment rail 7 of described wheel support 10 lower end, then turn oil return valve decompression, hydraulic pressure by rocking bar 12 Jack 11 slowly declines middle cover plate 2 and declines hydraulic jack to its pulley contact to track 7, continuation 11 until no longer contacting middle cover plate 2, and now four wheels support 10 starts to support middle cover plate 2 Weight, is manually pushed into the one end in concrete tunnel 8 by middle cover plate 2 along with wheel support 10 together, this Sample inter panel 2 just vertical above the end cover plate 1 being stacked on avris, because of middle wheel Sub-bearing length shortens successively toward direction of both ends, and each middle cover plate all has single track, successively Repeating aforesaid way and stack remaining middle cover plate, the middle cover plate of opposite side is also to repeat aforesaid way Being stacked five cover plate blocks vertically upward, during beginning, the end cover plate at the two ends, left and right in concrete tunnel 8 is Fixed;So far the cover plate of underground work well opens, symmetrical vertical distribution both sides on the ground, in Between cover plate block 2 push both sides to by pulley assembly and track 7, so result is the stacking realizing both sides, excellent Point is to use hydraulic jack 11 and track 7 to alleviate labour force, and cover plate block is in both sides vertical direction pair Claiming stacking to also save space, the cover plate gate also making underground work well is broader, the behaviour carried out for underground The biggest space is provided as activity;When maintenance after, both sides middle cover plate is shifted onto tiling time former On beginning position, make hydraulic jack 11 rise, then wheel support 6 folded into the bottom of middle cover plate, Carrying out pressure release by rocking bar 12 makes hydraulic jack 11 lower.
The present invention, primarily to save space and ensure safety of surrounding environment, is generally used for buried cable Lay.
It should be appreciated that the above-mentioned detailed description of the invention of the present invention is used only for exemplary illustration or explains this The principle of invention, and be not construed as limiting the invention.Therefore, without departing from the spirit and scope of the present invention In the case of any modification, equivalent substitution and improvement etc. done, should be included in protection scope of the present invention Within.Additionally, claims of the present invention be intended to fall into scope and border or Whole in the equivalents on this scope of person and border change and modifications example.

Claims (6)

1. underground based on hydraulic jack and the pulley mechanism aboveground lid arrangement of work, including being cast in earth hole On concrete tunnel, described concrete tunnel is provided with cover plate, it is characterised in that: described capping device is also Including the hydraulic jack lifted in order to cover plate with in order to the pulley mechanism slided about cover plate, described concrete Tunnel is all installed with described hydraulic jack on two inwalls of length direction;
Described cover plate includes that cover plate block, described cover plate block include end cover plate and middle cover plate, described end Portion's cover plate block includes the left end cap plate being positioned at the left end of concrete tunnel length direction and is positioned at concrete tunnel The right end cap plate of the right-hand member of length direction, described middle cover plate is provided with two or more, each middle cover The lower section of plate is equipped with two hydraulic jack;Cover plate block from two ends end cover plate to middle cover plate Length increase successively;
Described pulley mechanism includes track and pulley assembly, and described concrete tunnel is in two of length direction Being mounted on described track on wall, on the inwall of the same side, concrete tunnel, described track is positioned at described liquid Between pressure jack and the inwall in described concrete tunnel, described pulley assembly includes wheel support and pulley, The bottom at the two ends of described middle cover plate is respectively equipped with described wheel support, the upper end of described wheel support with The described collapsible connection of middle cover plate, the lower end of described wheel support is provided with described pulley, described pulley with Described track forms the length in sliding pair, the left and right line of travel of described middle cover plate and described concrete tunnel Degree direction is identical;
On two ends end cover plate to middle cover plate, the length of wheel support increases successively, described pulley with Track one_to_one corresponding, be arranged in parallel between adjacent orbit.
2. underground based on hydraulic jack and the pulley mechanism as claimed in claim 1 aboveground lid arrangement of work, it is special Levy and be: the bottom at the two ends of each middle cover plate is respectively equipped with two pulley assemblies, with two of one end The pulley of pulley assembly forms sliding pair with same track.
3. underground based on hydraulic jack and the pulley mechanism as claimed in claim 1 or 2 aboveground lid arrangement of work, It is characterized in that: described concrete tunnel is respectively equipped with erecting bed on two inwalls of length direction, described Hydraulic jack is fixed on described erecting bed on the side away from concrete tunnel inwall;Described track installation At described erecting bed on the side near concrete tunnel inwall.
4. underground based on hydraulic jack and pulley mechanism as claimed in claim 1 or 2 work aboveground lid dress Put, it is characterised in that: each cover plate block be respectively arranged at two ends with head lawn, before and after described head lawn Length is sequentially reduced to middle cover plate from two ends end cover plate, and before and after each cover plate block, length adds phase Answer the total length of length before and after head lawn identical.
5. underground based on hydraulic jack and the pulley mechanism as claimed in claim 4 aboveground lid arrangement of work, its It is characterised by: the number of described cover plate block is 2n, and n is the natural number more than or equal to 1, described middle cover Plate includes left cap plate, LC cover plate block, right central cover block and right cap plate, from left end cap Plate is to the two ends of left cap plate and is provided with institute respectively to the two ends of right cap plate from right end cap plate Stating head lawn, described LC cover plate block is arranged side by side with right central cover block and anterior-posterior length is identical, from Left end cap plate to length before and after left cap plate plus length before and after corresponding head lawn, from right-hand member Cover plate block is all left with described plus length before and after corresponding head lawn to length before and after right cap plate Before and after heart cover plate block, right central cover block, length is identical.
6. underground based on hydraulic jack and the pulley mechanism as claimed in claim 5 aboveground lid arrangement of work, its It is characterised by: the number of described cover plate block is 12, wherein, described left end cap plate and right end cap plate Being one, the number of described middle cover plate is ten, and the inwall in the same side, concrete tunnel gets on the right track Number be five.
CN201610383842.9A 2016-06-01 2016-06-01 Underground work well capping device based on hydraulic jack and pulley mechanism Active CN105858540B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610383842.9A CN105858540B (en) 2016-06-01 2016-06-01 Underground work well capping device based on hydraulic jack and pulley mechanism

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610383842.9A CN105858540B (en) 2016-06-01 2016-06-01 Underground work well capping device based on hydraulic jack and pulley mechanism

Publications (2)

Publication Number Publication Date
CN105858540A true CN105858540A (en) 2016-08-17
CN105858540B CN105858540B (en) 2018-01-09

Family

ID=56675796

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610383842.9A Active CN105858540B (en) 2016-06-01 2016-06-01 Underground work well capping device based on hydraulic jack and pulley mechanism

Country Status (1)

Country Link
CN (1) CN105858540B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111042202A (en) * 2019-12-31 2020-04-21 武汉武船重型装备工程有限责任公司 Movable sealing cover plate for well mouth
CN112064682A (en) * 2020-09-18 2020-12-11 国网江苏省电力有限公司宝应县供电分公司 Reinforced cable well
CN112095673A (en) * 2020-09-18 2020-12-18 国网江苏省电力有限公司宝应县供电分公司 Electric power protection safety alarm device

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2401596Y (en) * 2000-01-03 2000-10-18 曹宇 Lifting/lowering type cover for manhole
CN102701111A (en) * 2012-06-13 2012-10-03 青岛四方车辆研究所有限公司 Segmental turning cover plate device for foundation pit type car lifter
CN102943923A (en) * 2012-11-21 2013-02-27 浙江大学 Anti-floating box culvert structure for pipelines in soft soil
CN104085655A (en) * 2014-06-30 2014-10-08 成都飞机工业(集团)有限责任公司 Self-covering guide rail device and transporter formed by self-covering guide rail device
CN204385766U (en) * 2014-11-06 2015-06-10 潘正云 The safe barrier covering plate structure of existing road piping shaft
CN205773101U (en) * 2016-06-01 2016-12-07 浙江工业大学义乌科学技术研究院有限公司 Underground based on hydraulic jack and the pulley mechanism aboveground lid arrangement of work

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2401596Y (en) * 2000-01-03 2000-10-18 曹宇 Lifting/lowering type cover for manhole
CN102701111A (en) * 2012-06-13 2012-10-03 青岛四方车辆研究所有限公司 Segmental turning cover plate device for foundation pit type car lifter
CN102943923A (en) * 2012-11-21 2013-02-27 浙江大学 Anti-floating box culvert structure for pipelines in soft soil
CN104085655A (en) * 2014-06-30 2014-10-08 成都飞机工业(集团)有限责任公司 Self-covering guide rail device and transporter formed by self-covering guide rail device
CN204385766U (en) * 2014-11-06 2015-06-10 潘正云 The safe barrier covering plate structure of existing road piping shaft
CN205773101U (en) * 2016-06-01 2016-12-07 浙江工业大学义乌科学技术研究院有限公司 Underground based on hydraulic jack and the pulley mechanism aboveground lid arrangement of work

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111042202A (en) * 2019-12-31 2020-04-21 武汉武船重型装备工程有限责任公司 Movable sealing cover plate for well mouth
CN111042202B (en) * 2019-12-31 2021-09-07 武汉武船重型装备工程有限责任公司 Movable sealing cover plate for well mouth
CN112064682A (en) * 2020-09-18 2020-12-11 国网江苏省电力有限公司宝应县供电分公司 Reinforced cable well
CN112095673A (en) * 2020-09-18 2020-12-18 国网江苏省电力有限公司宝应县供电分公司 Electric power protection safety alarm device
CN112095673B (en) * 2020-09-18 2021-11-26 国网江苏省电力有限公司宝应县供电分公司 Electric power protection safety alarm device

Also Published As

Publication number Publication date
CN105858540B (en) 2018-01-09

Similar Documents

Publication Publication Date Title
CN104453231B (en) Gantry type building construction lifting device as well as manufacturing method and construction method thereof
CN205171378U (en) Assembling lifting type construction platform for pier column construction
CN105129627A (en) Folding type suspension arm device supported by electric pole
CN105858540A (en) Underground well covering device based on hydraulic jack and pulley mechanism
CN203412273U (en) Full-circular orbit type lifting work platform of storage tank
CN202850498U (en) Hydraulic support system used for elevator shaft mold
CN106002876B (en) A kind of various dimensions rotation maintenance platform
CN205773101U (en) Underground based on hydraulic jack and the pulley mechanism aboveground lid arrangement of work
CN112663516A (en) Construction method of bridge thin-wall hollow pier column
CN103061313B (en) Channel slope concrete plastering troweling machine with vibration and rolling functions
CN206941413U (en) A kind of support integral slipping system for concrete girder construction
CN102852357A (en) Structural mode of independently-arranged household hydraulic miniature double parking place three-dimensional garage
CN206625845U (en) A kind of inverted arch trestle
CN210858185U (en) Transformer oil pool overhauling operation platform for high-speed railway traction substation pavilion
CN208121589U (en) Large-tonnage highway ramp spells wide beam construction equipment
CN202023149U (en) Hanging basket used in construction
CN205474847U (en) Bridge water -drain mast installation platform truck
CN204982776U (en) A plurality of large -scale concrete buttress synchronous construction slipform systems
CN207209829U (en) A kind of oil tank transport, installation integrated apparatus
CN208022659U (en) A kind of civil engineering elevator
CN102182336A (en) Underground garage
CN207377568U (en) The low vcehicular tunnel maintenance and reinforcement platform and device for influencing traffic
CN206202477U (en) A kind of crawler type sprays anchor operation mobile platform
CN102127984B (en) Underground garage
CN205712226U (en) The model test apparatus that adjacent building basis is affected by open-cut foundation ditch

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant