CN205894099U - Be applied to underground pipe gallery's portable sliding template device - Google Patents
Be applied to underground pipe gallery's portable sliding template device Download PDFInfo
- Publication number
- CN205894099U CN205894099U CN201620563732.6U CN201620563732U CN205894099U CN 205894099 U CN205894099 U CN 205894099U CN 201620563732 U CN201620563732 U CN 201620563732U CN 205894099 U CN205894099 U CN 205894099U
- Authority
- CN
- China
- Prior art keywords
- girder
- utility
- model
- portable
- pipe gallery
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model relates to a be applied to underground pipe gallery's portable sliding template device, it includes mobile Workbench and sliding template device, mobile Workbench includes floorbar, stand roof beam, girder and tie -beam, and at floorbar bottom installation walking wheel, the walking wheel is connected with drive arrangement, the sliding template device includes guide rail, hoist device and template, the utility model discloses can remove by whole length direction along the piping lane in pipe well body's corridor, need not dismantle an ampere die plate repeatedly, labour saving and time saving, deviation correcting device makes the utility model discloses the moving as a whole does not misplace in the corridor, guarantees construction precision, uses the utility model discloses the device can make the process simplify, and construction speed is fast, keeps continuous construction operation.
Description
Technical field
The utility model is related to a kind of portable sleiding form device being applied to underground pipe gallery.
Background technology
Underground pipe gallery can accommodate multiple pipelines, and water, gas and electricity, communication, pipeline used by heating all can share same piping lane.This
Sample, more convenient in pipe inspection, maintenance, replacing or increase and decrease, gallery gut line can be placed in bottom it is also possible to support etc. is solid
It is fixed that due to being protected by gallery, pipeline is hardly affected by external factor such as ground pressure, traffic above-ground loads on the wall, and
Build and run overall low cost, environmental protection, sustainable development etc. are with the obvious advantage.Start to greatly develop pipe in some cities of China at present
Corridor is built, and in the construction of Urban Underground piping lane, needs scene carries out segmentation pouring construction, because Pipe rack is complicated, volume
Huge, need substantial amounts of workmen to set up scaffold and operation platform, then carry out coagulation by operation platform and scaffold
Native pouring construction, scaffold is removed in construction again after finishing and operation platform carries out the construction of next section, and the carrying out of so interruption mixes
Solidifying soil pours, and can increase a lot of construction joints, makes building discontinuous, quality cannot be guaranteed;And this method consume a large amount of
Manpower and construction material, produce substantial amounts of waste material, improve construction costs, waste time and energy, and speed of application is slow, operating efficiency
Low.
Utility model content
Technical problem to be solved in the utility model be provide a kind of operation to simplify, time saving and energy saving, safe and reliable and apply
The fireballing portable sleiding form device being applied to underground pipe gallery of work.
The utility model adopts the following technical scheme that
The utility model includes mobile work platform and the sleiding form more than two being arranged on mobile work platform bottom
Device;Described mobile work platform includes more than one group of bottom girder, is spaced the column beam being fixedly mounted on bottom girder, is fixedly mounted on
The girder in column back portion and be fixedly mounted on tie-beam between adjacent two girder, installs walking in bottom girder bottom
Wheel, described road wheel is connected with the driving means being arranged on bottom girder;Described sleiding form device includes being fixedly mounted on girder
The guide rail of bottom, the hanging apparatus being arranged on guide rail and the template being arranged on hanging apparatus bottom;In two adjacent companies
Connect loading stand between beam.
The utility model installs deviation correcting device in described column beam two bottom sides.
Deviation correcting device described in the utility model includes being symmetrically and fixedly mounted to the installing rack of column beam both sides, is horizontally arranged at
Sleeve pipe in installing rack, the leading screw with nut being arranged in sleeve pipe, it is arranged on the fixed mount on leading screw top, is arranged on sleeve end
Adjusting spring, being fixedly mounted on the crown wall wheel on fixed mount top and be arranged on below fixed mount top outside portion and fixed mount
Support wheel;Described crown wall wheel and the sidewall contact of piping lane, described support wheel is contacted with the diapire of piping lane with road wheel.
The utility model bottom girder, column beam, girder and tie-beam are Vierendeel girder.
The utility model fixedly mounts guardrail on the described girder in outside.
The reductor with motor connection that driving means described in the utility model include being fixedly mounted on bottom girder, it is arranged on
Head sprocket on decelerator, the driven sprocket being arranged on live axle and be arranged on the chain on head sprocket and driven sprocket
Bar.
Hanging apparatus described in the utility model include the assembly pulley being fixed on guide rail and are arranged on assembly pulley lower end
Chain block.
The utility model good effect is as follows: due to being provided with, in bottom girder bottom, the road wheel being driven by driving means, this
Utility model can move the overall length direction along piping lane in the gallery of piping lane body, and model sheetinstallat, can below chain block
Lifted according to the height of piping lane wall and installed, in mobile work platform, corresponding piping lane wall is poured after installing
Build, pour the template completing to dismantle and move to away from piping lane wall direction along guide rail, to next work of constructing under the drive of road wheel
Duan Yidong constructs, and without repeatedly removing and installing template, time saving and energy saving, deviation correcting device makes this practicality under the guiding of two ends crown wall wheel
New moving integrally in gallery does not misplace it is ensured that construction precision, and the utility model only uses a set of template in construction, without
Still further formwork supporting plate and set up scaffold, can save lot of materials and artificial.Operation can be made to simplify using the utility model device,
Speed of application is fast, keeps continuous construction operation.
Brief description
Accompanying drawing 1 is the utility model structural representation;
Accompanying drawing 2 is the utility model model sheetinstallat structural representation;
Accompanying drawing 3 is the utility model driving device structure schematic diagram;
Accompanying drawing 4 the utility model deviation correcting device structural representation.
In the accompanying drawings: 1 bottom girder, 2 column beams, 3 girders, 4 tie-beams, 5 guide rails, 6 assembly pulleys, 7 templates, 8 road wheels, 9 peaces
Shelve, 10 crown wall wheels, 11 support wheels, 12 guardrails, 13 decelerators, 14 head sprockets, 15 driven sprockets, 16 chains, 17 leading screws, 18 solid
Determine frame, 19 piping lane bodies, 20 gallerys, 21 platens, 22 chain blocks, 23 regulation springs, 24 sleeve pipes.
Specific embodiment
As shown in Figure 1, the utility model include mobile work platform and be arranged on two groups of mobile work platform bottom with
On sleiding form device;The column that described mobile work platform includes more than one group of bottom girder 1, interval is fixedly mounted on bottom girder
Beam 2, it is fixedly mounted on the column beam 2 top girder 3 vertical with bottom girder 1 and is fixedly mounted between adjacent two girder 3
Tie-beam 4, described tie-beam 4 is parallel with bottom girder 1;Bottom girder 1 bottom install road wheel 8, described road wheel 8 be arranged on bottom
Driving means on beam 1 connect;Described sleiding form device includes being fixedly mounted on the guide rail 5 of girder 3 bottom, is arranged on guide rail
Hanging apparatus on 5 and the template 7 being arranged on hanging apparatus bottom;Described hanging apparatus include the cunning being fixed on guide rail 5
Wheel group 6 and the chain block 22 being arranged on assembly pulley 6 lower end, described chain block 22 lifts described template 7.Adjacent two
Loading stand 21 between individual tie-beam 4, is constructed thereon for personnel and is placed construction material.Described bottom girder 1 and connection
Beam 4 is installed along the length direction of piping lane body 19, and described girder 3 is installed along the width of piping lane body 19;Bottom girder 1, column beam 2, girder 3
And tie-beam 4 is Vierendeel girder, the described girder 3 in two outsides in piping lane body length direction fixedly mounts guardrail 12.
As shown in accompanying drawing 2,4, the utility model installs deviation correcting device in described column beam 2 two bottom sides;Described correction dress
Put the sleeve pipe 24 including the installing rack 9 being symmetrically and fixedly mounted to column beam 2 both sides, being horizontally arranged in installing rack 9, be arranged on set
The leading screw 17 with nut in pipe 24, it is arranged on the fixed mount 18 on leading screw 17 top, is arranged on sleeve pipe 24 end and fixed mount 18
Outside adjust spring 23, be fixedly mounted on the crown wall wheel 10 on fixed mount 18 top and be arranged on below fixed mount 18 top
Support wheel 11, described regulation spring 23 is sleeved on leading screw 17.
As shown in Figure 3, driving means described in the utility model include being fixedly mounted on bottom girder 1 with motor connection
Reductor 13, the head sprocket 14 being arranged on decelerator 13, the driven sprocket 15 being arranged on road wheel 8 axle and be arranged on master
Chain 16 on sprocket wheel 14 and driven sprocket 15.
The utility model girder 3 and tie-beam 4 can be saved using standard knot one according to the length of underground pipe gallery and carry out group
Dress, is used for setting up workbench, is arranged on column beam 2 by flange, and column beam 2 can be according to the height of piping lane body 19, by mark
Quasi- section with increase section and be adjusted, column beam 2 be main supporting part and by pressure transmission to bottom girder 1, column beam 2 is by flanged plate
It is connected with bottom girder 1.
The workshop section pouring in need, vertical formwork is corresponded to two-by-two and slides into piping lane wall both sides by guide rail 5 and fix, then
On the table piping lane is poured, pour the template 7 completing to dismantle and move away from direction to piping lane wall along guide rail 5, pass through
Remote control starts motor, makes the utility model device overall to next construction workshop section movement, without repeatedly under the drive of road wheel 8
Remove and install template 7, time saving and energy saving, after situation about wandering off in road wheel 8, by the nut on adjusting screw 17, change
The position of crown wall wheel 10, if slight error in wall flatness during movement, is adjusted by adjusting spring 23
To realize the effect rectified a deviation.
Due to being provided with, in bottom girder 1 bottom, the road wheel 8 being driven by driving means, the utility model can be in piping lane body 19
In gallery 20, the overall length direction along piping lane body 19 moves, and template 7 is arranged on below chain block 22, can be according to piping lane wall
Highly lifted and installed, in mobile work platform, corresponding piping lane wall is poured after installing, pour and complete to tear open
The template 7 unloaded moves along guide rail 5 to away from piping lane wall direction, to next mobile construction of construction workshop section under the drive of road wheel 8,
Without repeatedly removing and installing template 7, time saving and energy saving, deviation correcting device makes the utility model in corridor under the guiding of two ends crown wall wheel 10
Move integrally in road 20 and do not misplace it is ensured that construction precision, the utility model only uses a set of template in construction, without still further
Formwork supporting plate and set up scaffold, can save lot of materials and artificial.Operation can be made to simplify using the utility model device, construction speed
Degree is fast, keeps continuous construction operation.
The above embodiment is only preferred embodiment of the present utility model, and not the utility model possible embodiments
Exhaustion.For persons skilled in the art, to its institute on the premise of without departing substantially from the utility model principle and spirit
Any obvious change made, all should be contemplated as falling with claims of the present utility model.
Claims (7)
1. a kind of portable sleiding form device being applied to underground pipe gallery is it is characterised in that it includes mobile work platform and peace
It is contained in the sleiding form device more than two of mobile work platform bottom;
Described mobile work platform includes more than one group of bottom girder (1), is spaced the column beam (2) being fixedly mounted on bottom girder (1), consolidates
Dingan County is contained in the girder (3) at column beam (2) top and is fixedly mounted on tie-beam (4) between adjacent two girder (3),
In bottom girder (1) bottom, road wheel (8) is installed, described road wheel (8) is connected with the driving means being arranged on bottom girder (1);
Described sleiding form device includes being fixedly mounted on the guide rail (5) of girder (3) bottom, the lifting being arranged on guide rail (5)
Device and the template (7) being arranged on hanging apparatus bottom;Loading stand (21) between two adjacent tie-beams (4).
2. a kind of portable sleiding form device being applied to underground pipe gallery according to claim 1 it is characterised in that
Described column beam (2) two bottom sides install deviation correcting device.
3. a kind of portable sleiding form device being applied to underground pipe gallery according to claim 2 is it is characterised in that institute
State deviation correcting device to include being symmetrically and fixedly mounted to the installing rack (9) of column beam (2) both sides, be horizontally arranged in installing rack (9)
Sleeve pipe (24), the leading screw with nut (17) being arranged in sleeve pipe (24), the fixed mount (18) being arranged on leading screw (17) top, peace
It is contained in the regulation spring (23) outside sleeve pipe (24) end and fixed mount (18), be fixedly mounted on the crown wall on fixed mount (18) top
Take turns (10) and be arranged on the support wheel (11) below fixed mount (18) top;
Described crown wall wheel (10) and the sidewall contact of piping lane, described support wheel (11) is contacted with the diapire of piping lane with road wheel (8).
4. a kind of portable sleiding form device being applied to underground pipe gallery according to claim 3 is it is characterised in that bottom
Beam (1), column beam (2), girder (3) and tie-beam (4) are Vierendeel girder.
5. a kind of portable sleiding form device being applied to underground pipe gallery according to claim 1,2,3 or 4, its feature
It is fixed installation guardrail (12) on the described girder (3) in outside.
6. a kind of portable sleiding form device being applied to underground pipe gallery according to claim 5 is it is characterised in that institute
State the reductor (13) with motor connection that driving means include being fixedly mounted on bottom girder (1), be arranged on decelerator (13)
Head sprocket (14), the driven sprocket (15) being arranged on road wheel (8) axle and be arranged on head sprocket (14) and driven sprocket
(15) chain (16) on.
7. a kind of portable sleiding form device being applied to underground pipe gallery according to claim 6 is it is characterised in that institute
State hanging apparatus and include the assembly pulley (6) being fixed on guide rail (5) and the chain block being arranged on assembly pulley (6) lower end
(22).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620563732.6U CN205894099U (en) | 2016-06-13 | 2016-06-13 | Be applied to underground pipe gallery's portable sliding template device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620563732.6U CN205894099U (en) | 2016-06-13 | 2016-06-13 | Be applied to underground pipe gallery's portable sliding template device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205894099U true CN205894099U (en) | 2017-01-18 |
Family
ID=57767343
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620563732.6U Expired - Fee Related CN205894099U (en) | 2016-06-13 | 2016-06-13 | Be applied to underground pipe gallery's portable sliding template device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205894099U (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108798714A (en) * | 2018-05-28 | 2018-11-13 | 广西路建工程集团有限公司 | A kind of working portable shifting formwork trolley of channel wall body and its construction method |
CN109339098A (en) * | 2018-11-08 | 2019-02-15 | 北京场道市政工程集团有限公司 | A kind of underground pipe gallery removable support template |
CN111218951A (en) * | 2020-02-10 | 2020-06-02 | 中国十七冶集团有限公司 | Grouting method of fan foundation concrete grouting device |
CN113982100A (en) * | 2021-11-11 | 2022-01-28 | 防城港中一重工有限公司 | Overall sliding installation method for steel gallery in complex environment |
CN114193586A (en) * | 2021-12-10 | 2022-03-18 | 中交二公局第六工程有限公司 | Formula of sinking piping lane pouring system |
CN114960926A (en) * | 2022-05-16 | 2022-08-30 | 中国化学工程第四建设有限公司 | Chemical pipe gallery structure and pipeline replacement method |
-
2016
- 2016-06-13 CN CN201620563732.6U patent/CN205894099U/en not_active Expired - Fee Related
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108798714A (en) * | 2018-05-28 | 2018-11-13 | 广西路建工程集团有限公司 | A kind of working portable shifting formwork trolley of channel wall body and its construction method |
CN109339098A (en) * | 2018-11-08 | 2019-02-15 | 北京场道市政工程集团有限公司 | A kind of underground pipe gallery removable support template |
CN109339098B (en) * | 2018-11-08 | 2023-09-22 | 北京场道市政工程集团有限公司 | Portable support template of utility tunnel |
CN111218951A (en) * | 2020-02-10 | 2020-06-02 | 中国十七冶集团有限公司 | Grouting method of fan foundation concrete grouting device |
CN113982100A (en) * | 2021-11-11 | 2022-01-28 | 防城港中一重工有限公司 | Overall sliding installation method for steel gallery in complex environment |
CN114193586A (en) * | 2021-12-10 | 2022-03-18 | 中交二公局第六工程有限公司 | Formula of sinking piping lane pouring system |
CN114960926A (en) * | 2022-05-16 | 2022-08-30 | 中国化学工程第四建设有限公司 | Chemical pipe gallery structure and pipeline replacement method |
CN114960926B (en) * | 2022-05-16 | 2023-05-02 | 中国化学工程第四建设有限公司 | Chemical pipe gallery structure and pipe replacement method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205894099U (en) | Be applied to underground pipe gallery's portable sliding template device | |
CN106013233B (en) | Sliding system and its construction method for underground pipe gallery cast-in-place construction | |
CN204457802U (en) | Formed by integrally casting formula formwork jumbo | |
CN104632251A (en) | Integrally cast type mould plate trolley and construction method of concrete pouring of underground passage | |
CN206092022U (en) | Be used for lining cutting rectangular -section or radiation gradual change rectangular -section formula operation car of crawling | |
CN204510844U (en) | A kind of large-span steel girder high-altitude mounting slip device | |
CN104453951B (en) | Combined type subway station lining template trolley for baffle | |
CN104110002B (en) | A kind of method for changing steel truss girder bridge floorings | |
CN201746779U (en) | Prestressed tension jack moving frame | |
CN205936645U (en) | A full liquid die plate system for culvert is pour | |
CN105544397A (en) | High concrete pier construction formwork device | |
CN109355983B (en) | Trackless construction method for urban rail | |
CN100542944C (en) | The method of lowering overweight structure by connecting two jacks in series | |
CN202401753U (en) | Sliding die device | |
CN205205683U (en) | High mound construction formwork device of concrete | |
CN104929375B (en) | Large-span truss short distance hydraulic jack synchronization-sliding method and device | |
CN106013234B (en) | The construction method of underground pipe gallery | |
CN206769343U (en) | It is a kind of to be used for the travelling bridge that guardrail is constructed that builds a bridge | |
CN211496656U (en) | Purlin hangs equipment | |
CN205954496U (en) | Simple and easy creeping formwork device of pier | |
CN201963312U (en) | Automatic walking device used for walking on uneven ground | |
CN210794552U (en) | Net rack color steel plate profiling rapid conveying device | |
CN205934962U (en) | A system of sliding for underground pipe gallery cast -in -situ construction | |
CN201212250Y (en) | Mobile wheel track installation platform for large-sized network frame engineering | |
CN208266685U (en) | A kind of safe work platform of beam bridge steel web coating |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170118 Termination date: 20210613 |