CN205676897U - One is positioned at original ground following pier stud constructing device - Google Patents

One is positioned at original ground following pier stud constructing device Download PDF

Info

Publication number
CN205676897U
CN205676897U CN201620621582.XU CN201620621582U CN205676897U CN 205676897 U CN205676897 U CN 205676897U CN 201620621582 U CN201620621582 U CN 201620621582U CN 205676897 U CN205676897 U CN 205676897U
Authority
CN
China
Prior art keywords
pier stud
casing
pile foundation
built
original ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620621582.XU
Other languages
Chinese (zh)
Inventor
符强
吕芝林
郝委委
骆军
孙向楠
薛伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Gezhouba Group No 5 Engineering Co Ltd
Original Assignee
China Gezhouba Group No 5 Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Gezhouba Group No 5 Engineering Co Ltd filed Critical China Gezhouba Group No 5 Engineering Co Ltd
Priority to CN201620621582.XU priority Critical patent/CN205676897U/en
Application granted granted Critical
Publication of CN205676897U publication Critical patent/CN205676897U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

The utility model provides one and is positioned at original ground following pier stud constructing device, its required pile foundation construction oversheath setting when including pile foundation construction, its internal built-in casing is placed when being placed with pier stud construction inside described pile foundation construction oversheath, the top of described built-in casing is provided with back-pressure shaped steel, described back-pressure shaped steel is fixing with original ground prevent pier stud when pouring built-in casing float.Described built-in casing size is equivalently-sized with Pier Formwork, is provided with baffle plate bottom it.Purpose is to combine the feature that pier stud is smaller in size than pile foundation size, provides one to relocate without large area, construction simple and fast, low cost, and is applicable to the pier stud constructing device that any pier stud is positioned at below original ground.

Description

One is positioned at original ground following pier stud constructing device
Technical field
The utility model relates to a kind of steel pile casting leading truck, is positioned at original ground following pier stud construction dress particularly to one Put.
Background technology
Day by day perfect with China's traffic network, many original roads need to relocate down to wear newly-built road network, for newly-built The situation that road network pier stud is positioned on original road also gets more and more, and excavation of often taking during construction temporarily to relocate original road is executed Work newly-built road network pier stud basis, but earth clearance and expense of relocating are relatively big, and construction period is longer.
Utility model content
The purpose of this utility model is: combines pier stud and is smaller in size than the feature of pile foundation size, provides one to be not necessarily to large area Relocate, construction simple and fast, low cost, and it is applicable to the pier stud constructing device that any pier stud is positioned at below original ground.
In order to realize above-mentioned technical characteristic, the purpose of this utility model be achieved in that one be positioned at original ground with Lower pier stud constructing device, its required pile foundation construction oversheath setting when including pile foundation construction, in described pile foundation construction oversheath Its internal built-in casing is placed in portion when being placed with pier stud construction, the top of described built-in casing is provided with back-pressure shaped steel, described Back-pressure shaped steel and original ground be fixing prevent pier stud when pouring built-in casing float.
Described built-in casing size is equivalently-sized with Pier Formwork, is provided with baffle plate bottom it.
It is provided with packing material between described built-in casing and the outer casing of pile foundation construction, prevent pier stud built-in casing change when pouring Shape.
The top of described built-in casing is provided with opening, and described opening matches with back-pressure shaped steel.
Being provided with baffle plate pad on described pile foundation construction oversheath, baffle plate pad is combined formation and seals structure with baffle plate.
It is placed with pile foundation steel bar cage and pier stud reinforcing bar inside described pile foundation construction oversheath.
The utility model has the advantages that:
First set the outer casing of pile foundation construction at original ground, complete pile foundation construction, broken in being manually entered the outer casing of pile foundation construction Except pile crown and clear up residue and weld baffle plate pad in addition to pile foundation construction on casing, pull folding pile crown reinforcing bar install pier by design requirement Post reinforcing bar, transfers built-in casing, and is positioned over its bottom baffle on the outer casing baffle plate pad of pile foundation construction, bottom back-pressure shaped steel Carry out back-pressure, at the outer packing material between casing and built-in casing of pile foundation construction, complete to pour pier stud concrete construction.In conjunction with pier stud It is smaller in size than the feature of pile foundation size, provide one to relocate without large area, construction simple and fast, low cost, and be applicable to appoint What pier stud is positioned at the pier stud constructing device of below original ground.
Brief description
The utility model is described in further detail with embodiment below in conjunction with the accompanying drawings.
Fig. 1 is overall structure schematic diagram of the present utility model.
In figure: back-pressure shaped steel the 1st, built-in casing the 2nd, pile foundation construction oversheath the 3rd, baffle plate the 4th, baffle plate pad the 5th, original ground the 6th, foot stall steel Muscle the 7th, pile foundation steel bar cage 8.
Detailed description of the invention
Below in conjunction with the accompanying drawings embodiment of the present utility model is described further.
Seeing Fig. 1, one is positioned at original ground following pier stud constructing device, its required pile foundation setting when including pile foundation construction Construction oversheath 3, internal being placed with when pier stud is constructed of described pile foundation construction oversheath 3 places its internal built-in casing 2, described The top of built-in casing 2 is provided with back-pressure shaped steel 1, described back-pressure shaped steel 1 and original ground 6 is fixing prevents that pier stud is built-in when pouring to be protected Cylinder 2 floats.
Further, described built-in casing 2 size is equivalently-sized with Pier Formwork, is provided with baffle plate 4 bottom it.
Further, it is provided with packing material between described built-in casing 2 and pile foundation construction oversheath 3, prevent pier stud from pouring When built-in casing 2 deform.
Further, the top of described built-in casing 2 is provided with opening, and described opening matches with back-pressure shaped steel 1.
Further, described pile foundation construction oversheath 3 being provided with baffle plate pad 5, it is close that baffle plate pad 5 is combined formation with baffle plate 4 Seal structure.
Further, described pile foundation construction oversheath 3 is internal is placed with pile foundation steel bar cage 8 and pier stud reinforcing bar 7.
Use of the present utility model and work progress are as follows:
First set the outer casing 3 of pile foundation construction at original ground, complete pile foundation construction, be manually entered in the outer casing 3 of pile foundation construction Abolish pile crown and clear up residue, welding baffle plate pad 5 on the outer casing of pile foundation construction, pulled folding pile crown reinforcing bar by design requirement and installed Pier stud reinforcing bar 7, transfers built-in casing 2, and is positioned over its bottom baffle 4 on the outer casing 3 baffle plate pad 5 of pile foundation construction, and bottom is used Back-pressure shaped steel 1 carries out back-pressure, at the outer packing material between casing 3 and built-in casing 2 of pile foundation construction, completes to pour pier stud coagulation soil application Work.
The above embodiments are only optimal technical scheme of the present utility model, and are not construed as limit of the present utility model System, the technical scheme that protection domain of the present utility model should be recorded with claim, including the technical scheme that claim is recorded The equivalents of middle technical characteristic is protection domain.Equivalent i.e. within this range is improved, also at the utility model Protection domain within.

Claims (6)

1. one kind is positioned at original ground following pier stud constructing device, it is characterised in that: its required stake setting when including pile foundation construction Base construction oversheath (3), internal being placed with when pier stud is constructed of described pile foundation construction oversheath (3) places its internal built-in casing (2), the top of described built-in casing (2) is provided with back-pressure shaped steel (1), and described back-pressure shaped steel (1) is fixing with original ground (6) to prevent When pier stud pours, built-in casing (2) floats.
2. one is positioned at original ground following pier stud constructing device according to claim 1, it is characterised in that: described built-in casing (2) size is equivalently-sized with Pier Formwork, is provided with baffle plate (4) bottom it.
3. one is positioned at original ground following pier stud constructing device according to claim 1, it is characterised in that: described built-in casing (2) it and is provided with packing material between pile foundation construction oversheath (3), prevent pier stud built-in casing (2) deformation when pouring.
4. one is positioned at original ground following pier stud constructing device according to claim 1, it is characterised in that: described built-in casing (2) top is provided with opening, and described opening matches with back-pressure shaped steel (1).
5. one is positioned at original ground following pier stud constructing device according to claim 1, it is characterised in that: described pile foundation construction Being provided with baffle plate pad (5) on oversheath (3), baffle plate pad (5) and baffle plate (4) combine to be formed and seal structure.
6. one is positioned at original ground following pier stud constructing device according to claim 1, it is characterised in that: described pile foundation construction Oversheath (3) is internal is placed with pile foundation steel bar cage (8) and pier stud reinforcing bar (7).
CN201620621582.XU 2016-06-22 2016-06-22 One is positioned at original ground following pier stud constructing device Expired - Fee Related CN205676897U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620621582.XU CN205676897U (en) 2016-06-22 2016-06-22 One is positioned at original ground following pier stud constructing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620621582.XU CN205676897U (en) 2016-06-22 2016-06-22 One is positioned at original ground following pier stud constructing device

Publications (1)

Publication Number Publication Date
CN205676897U true CN205676897U (en) 2016-11-09

Family

ID=57431555

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620621582.XU Expired - Fee Related CN205676897U (en) 2016-06-22 2016-06-22 One is positioned at original ground following pier stud constructing device

Country Status (1)

Country Link
CN (1) CN205676897U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113622454A (en) * 2021-07-28 2021-11-09 济南市市政工程设计研究院(集团)有限责任公司 Ductile earthquake-resistant structure with additional isolation pile casing single pile and single column and construction method
CN114561873A (en) * 2022-03-16 2022-05-31 杭州萧山交通建设管理有限公司 Bridge high pier construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113622454A (en) * 2021-07-28 2021-11-09 济南市市政工程设计研究院(集团)有限责任公司 Ductile earthquake-resistant structure with additional isolation pile casing single pile and single column and construction method
CN114561873A (en) * 2022-03-16 2022-05-31 杭州萧山交通建设管理有限公司 Bridge high pier construction method
CN114561873B (en) * 2022-03-16 2023-08-08 杭州萧山交通建设管理有限公司 Bridge high pier construction method

Similar Documents

Publication Publication Date Title
CN106087629B (en) Without the prefabricated baffle foam concrete light road bank structure of conical slope and construction method
CN205742175U (en) A kind of steel construction protection wall of bored pile
CN107268807A (en) A kind of Prefabricated concrete-filled steel tube superposed column
CN206376287U (en) Subway station main body and the float Structure of accessory structure interface
CN205999900U (en) Annular occlusion campshed section steel beam inner support type foundation pit supporting construction
CN205676897U (en) One is positioned at original ground following pier stud constructing device
CN203834511U (en) Bolting-grouting retaining wall with specially-shaped section
CN205839790U (en) A kind of anchor jacked pile envelope pilework for thin plate basis
CN208456610U (en) A kind of open cut tunnel composite structure for tunnel portal section complicated geological
CN204456160U (en) A kind of bridge prefabrication cushion cap
CN204753261U (en) Light -duty road bed of a doublestage shelves structure
CN212612585U (en) Anti-freezing pile foundation in severe cold area
CN205676902U (en) Arched framework slope protection construction typified form
CN205000251U (en) Complete embedding circular cushion cap construction structures in only pier river course shallow water of single pile
CN209652990U (en) The antiseepage plugging structure of the hole for hoist of basement computer room
CN207143985U (en) Tower crane
CN107288141B (en) A kind of seamless flexible water construction technology of contrary sequence method
CN205894118U (en) Pier protective structure
CN214737995U (en) A contrary structure of doing for excavation road bed overline bridge pile column is under construction fast
CN206385526U (en) A kind of highway subgrade broken stone pile
CN206110155U (en) Open caisson secondary back cover structure
CN209353327U (en) The quick pile extension device of rotary digging stake in small space
CN209585098U (en) A kind of substation equipment bracket novel steel tube short column pile foundation
CN206801597U (en) A kind of flood mine chamber waterproof construction
CN203080480U (en) Upstream blanket structure of concrete face rockfill dam

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161109

Termination date: 20210622

CF01 Termination of patent right due to non-payment of annual fee