CN205638481U - Tunnel invert fills slot and removes mould - Google Patents

Tunnel invert fills slot and removes mould Download PDF

Info

Publication number
CN205638481U
CN205638481U CN201620310239.3U CN201620310239U CN205638481U CN 205638481 U CN205638481 U CN 205638481U CN 201620310239 U CN201620310239 U CN 201620310239U CN 205638481 U CN205638481 U CN 205638481U
Authority
CN
China
Prior art keywords
groove
tunnel
inverted arch
running gear
model
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620310239.3U
Other languages
Chinese (zh)
Inventor
梁旋
王国炜
罗久旭
杨寒
向勇
沈廷忠
唐志林
易锋
郑信章
王新春
徐成华
杨小刚
周莉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Second Bureau Construction Co ltd
China Railway No 2 Engineering Group Co Ltd
China Railway Erju 1st Engineering Co Ltd
Original Assignee
China Railway No 2 Engineering Group Co Ltd
China Railway Erju 1st Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 2 Engineering Group Co Ltd, China Railway Erju 1st Engineering Co Ltd filed Critical China Railway No 2 Engineering Group Co Ltd
Priority to CN201620310239.3U priority Critical patent/CN205638481U/en
Application granted granted Critical
Publication of CN205638481U publication Critical patent/CN205638481U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to a tunnel construction field, concretely relates to tunnel invert fills slot and removes mould, the die carrier that forms including a plurality of leg joints, packing slot model, running gear, elevating gear and fixing device, packing slot model, running gear, elevating gear and fixing device and all connect on the die carrier, each device cooperation is used to let and is packed the slot model and locate into the die matching in packing portion and go out to pack the slot, and concreting makes and packs the slot shaping. The application a tunnel invert fills slot and removes mould, completion tunnel invert that can be quick fills the construction of slot, the inverted arch of accomplishing is filled slot construction quality and high and can not cause the damage to existing concrete structure, structural design is simple and easy and simple to handle, facilitate promotion, saving construction cost and engineering time.

Description

A kind of tunnel inverted arch is filled groove and is moved moulds
Technical field
This utility model relates to constructing tunnel field, and particularly a kind of tunnel inverted arch is filled groove and moved moulds.
Background technology
The inverted arch of railway ballastless Tunnel Design is filled groove and is positioned at inverted arch filling top and molded groove concrete The junction of platform sidewall, the effect of groove filled by railway ballastless tunnel inverted arch is draining;At present, railway ballastless Tunnel inverted arch is filled trench design and is poured molding with inverted arch filling simultaneously, mainly uses two ways to carry out Construction, mode one is positioned over mixed for utilizing inverted arch to fill ditch groove mould after inverted arch fill concrete has poured Utilizing artificial roller-compaction on solidifying soil, mode two is multiple for drilling through on lateral wall, molded groove coagulation earthen platform Boring, and insert the rod members such as reinforcing bar, fill ditch groove mould with fixing inverted arch and carry out concreting.
But existing railway ballastless tunnel inverted arch is filled groove construction molding and be there is certain limitation:
Employing mode one is executed man-hour requirement and is strictly controlled mould and roll the time, and uses and manually roll trench line Shape is wayward, and groove Forming Quality is the highest;Existing concrete structure can be caused when employing mode two is constructed Damage and mould peace tear inconvenience open, and it is longer that peace tears the time open.
Utility model content
Goal of the invention of the present utility model is: the existing railway ballastless tunnel inverted arch existed for prior art Fill groove construction molding otherwise manually roll groove linear wayward, groove Forming Quality is the highest, or Existing concrete structure can be caused that damage and mould peace tear inconvenience open, that peace tears the time open is longer by the fixing mould of boring Problem, it is provided that ditch groove mould filled by a kind of structure design railway ballastless tunnel simple and easy and simple to handle inverted arch.
To achieve these goals, the technical solution adopted in the utility model is:
A kind of tunnel inverted arch is filled groove and is moved moulds, the mould bases being formed by connecting including some supports and filling ditch Channel mould type, it is characterised in that also include:
Running gear, is used for moving described mould bases to construction location;
Lowering or hoisting gear, lifts described filling groove model after described mould bases arrives construction location, allows described The filling groove filling groove model end face and surveying and locating inverted arch pours elevation line in same level;
Fixing device, for described mould bases being moved and lifted the overall fastening after putting in place, prevents subsequent construction The described mould bases displacement when filling part casting concrete;
Described filling groove model, running gear, lowering or hoisting gear and fixing device are both connected on described mould bases, Described filling groove model matches described filling groove for molding at described filling part.
Using mould described in the utility model, mould is moved to specific bit and postpones by running gear, and regulation rises Falling unit drives fills moving up and down of groove model, it is ensured that fills groove model lays precision, then uses Whole mould is fastened by fixing device with molded coagulation earthen platform, then at filling part casting concrete, it is possible to fast The construction of groove filled by the tunnel inverted arch of completing of speed, and it is high and will not that groove construction quality filled by the inverted arch completed Existing concrete structure causes damage, and structure design is simple and easy and simple to handle, it is simple to promote, and saves construction Cost and engineering time.
Preferably, described running gear includes vertical running gear and lateral running gear.
Use lateral running gear in addition to being easy to the movement of whole mould bases, moreover it is possible at whole mould bases walking process In prevent about mould bases offset.
Preferably, described lowering or hoisting gear includes lifting screw and stop nut.
Preferably, described fixing device includes adjusting screw rod, adjusting nut and backing plate.
Use backing plate to be close to surface, molded groove coagulation earthen platform, increase active area, effectively guarantee whole Mobility model fixing, when preventing follow-up casting concrete, mould bases floats.
Preferably, described vertical running gear includes connecting rod, wheel carrier and wheel.
Preferably, described lateral running gear includes adjusting screw rod, adjusting nut, walking wheel carrier and road wheel.
Preferably, what the described connecting rod on described vertical running gear was connected on described lowering or hoisting gear is described Lifting screw.
Preferably, described mould bases acts on the molded groove on molded groove coagulation earthen platform.
In sum, owing to have employed technique scheme, the beneficial effects of the utility model are:
Using a kind of tunnel described in the utility model inverted arch to fill groove to move moulds, running gear is by mould Moving to specific bit postpone, regulation lowering or hoisting gear drives fills moving up and down of groove model, it is ensured that fill ditch Channel mould type lay precision, then by fixing device, whole mould and molded coagulation earthen platform are fastened, then Filling part casting concrete, it is possible to quickly finish tunnel inverted arch and fill the construction of groove, the inverted arch completed Filling groove construction quality height and existing concrete structure will not cause damage, structure design is simple and operates Easy, it is simple to promote, save construction cost and engineering time.
Accompanying drawing explanation
Fig. 1 is structural front view of the present utility model;
Fig. 2 is structure left view of the present utility model;
Fig. 3 is operation principle schematic diagram of the present utility model.
Labelling in figure: 1-support, 2-fills groove model, the vertical running gear of 3-, the lateral running gear of 4-, 41-adjusts screw rod, 42-adjusting nut, and 43-walks wheel carrier, and 44-road wheel, 5-fixing device, 51-regulates spiral shell Bar, 52-adjusting nut, 53-backing plate, 6-lowering or hoisting gear, 61-lifting screw, 62-stop nut, 7-becomes Type groove coagulation earthen platform, the molded groove of 8-, 9-fills groove, 10-filling part.
Detailed description of the invention
Below in conjunction with the accompanying drawings, this utility model is described in detail.
In order to make the purpose of this utility model, technical scheme and advantage clearer, below in conjunction with accompanying drawing And embodiment, this utility model is further elaborated.Should be appreciated that described herein specifically Embodiment, only in order to explain this utility model, is not used to limit this utility model.
Embodiment
As shown in Figure 1-2, the structure that a kind of tunnel described in the utility model inverted arch filling groove moves moulds is shown It is intended to, including support 1, fills groove model 2, vertical running gear 3, lateral running gear 4, adjustment Screw rod 41, adjusting nut 42, walking wheel carrier 43, road wheel 44, fixing device 5, adjusting screw rod 51, Adjusting nut 52, backing plate 53, lowering or hoisting gear 6, lifting screw 61 and stop nut 62.
Three fixing shaped steel rod member composition door shaped steel frames connected, four road door frames are arranged in parallel, four sects The spacing of frame can be actually needed according to construction and be adjusted, then is composed of a fixed connection with three longitudinal type steel rod elements Support 1;Two groups of lowering or hoisting gears 6 are respectively arranged in the middle part of two door frame crossbeams of support 1 outermost layer, and two groups vertical Connecting rod one end of running gear 3 is provided with circular notch, and lifting screw 61 one end coupling of lowering or hoisting gear 6 is even It is connected to this notch, so that vertical running gear 3 is connected to lowering or hoisting gear 6, by lifting screw 61 and limit The coupling adjustable vertical height to running gear 3 of position nut 62, thus regulate the height of whole support 1; Each correspondence of four vertical shaped steel rod members of support 1 two door frames of outermost layer is fixedly installed one group and laterally walks Device 4, the road wheel 44 of lateral running gear 4 is towards in door frame, and road wheel 44 is connected to wheel carrier of walking 43, walking wheel carrier 43 connects adjustment screw rod 41, adjusts the screw rod 41 Matching and modification nut 42 lateral row of adjustable The position of walking apparatus 4;Each correspondence of eight vertical shaped steel rod members of four road door frames is fixedly installed one group and fixes Device 5, the backing plate 53 of fixing device 5 is towards in door frame, and backing plate 53 is connected to adjusting screw rod 51, regulation Screw rod 51 mates the position of adjusting nut 52 adjustable fixing device 5;Fill the fixing connection of groove model 2 In four road door frames, four vertical shaped steel rod member ends on one side, it is semicircle for filling groove model 2 cross section, and And cross section straight flange circular arc upward is down.
The operation principle as it is shown on figure 3, a kind of tunnel described in the utility model inverted arch filling groove moves moulds Schematic diagram, including all structures of above-mentioned mould, molded groove coagulation earthen platform 7, molded groove 8, fills Groove 9 and filling part 10.
The vertical running gear 3 of mould acts on molded groove 8 on molded groove coagulation earthen platform 7, laterally Running gear 4 acts on two concrete sides on molded groove coagulation earthen platform 7, by vertical running gear 3 Moving integrally of mould can be met with lateral running gear 4;When mould moves to specify construction location, adjust Joint lowering or hoisting gear 6 makes mould move up and down, and drives filling groove model 2 to move up and down filling groove model 2 End face pours elevation line in same level with the filling groove 9 of surveying and locating inverted arch;Presetting adjusting screw rod 51 Making backing plate 53 touch the concrete side on molded groove coagulation earthen platform 7, then twisting adjusts screw rod 41 Road wheel 44 is made to depart from the concrete side on molded groove coagulation earthen platform 7;Twisting adjusting screw rod 51 makes Backing plate 53 is close to the concrete side on molded groove coagulation earthen platform 7, is fixed mould, prevents follow-up watering When building concrete, mould floats;Casting concrete at filling part 10, and maintenance is to some strength, unclamps solid Determining device 5, twisting lowering or hoisting gear 6 makes filling groove model 2 move up certain altitude, then twists lateral row Walking apparatus 4 contacts the concrete side on type groove coagulation earthen platform 7, whole mould is moved to next and executes Station is put.
The foregoing is only preferred embodiment of the present utility model, not in order to limit this utility model, All any amendment, equivalent and improvement etc. made within spirit of the present utility model and principle, all should Within being included in protection domain of the present utility model.

Claims (8)

1. a tunnel inverted arch filling groove moves moulds, the mould bases being formed by connecting including some supports (1) and filling groove model (2), it is characterised in that also include:
Running gear, is used for moving described mould bases to construction location;
Lowering or hoisting gear (6), after described mould bases arrives construction location, lift described filling groove model (2), allow described filling groove model (2) end face pour elevation line in same level with the filling groove (9) of surveying and locating inverted arch;
Fixing device (5), for described mould bases being moved and lifted the overall fastening after putting in place, prevents subsequent construction described mould bases displacement when filling part (10) casting concrete;
Described filling groove model (2), running gear, lowering or hoisting gear (6) and fixing device (5) are both connected on described mould bases, and described filling groove model (2) is for matching described filling groove (9) in described filling part (10) place's molding.
A kind of tunnel the most according to claim 1 inverted arch is filled groove and is moved moulds, it is characterised in that described running gear includes vertical running gear (3) and lateral running gear (4).
A kind of tunnel the most according to claim 2 inverted arch is filled groove and is moved moulds, it is characterised in that described lowering or hoisting gear (6) includes lifting screw (61) and stop nut (62).
A kind of tunnel the most according to claim 1 inverted arch is filled groove and is moved moulds, it is characterised in that described fixing device (5) includes adjusting screw rod (51), adjusting nut (52) and backing plate (53).
A kind of tunnel the most according to claim 3 inverted arch is filled groove and is moved moulds, it is characterised in that described vertical running gear (3) includes connecting rod, wheel carrier and wheel.
A kind of tunnel the most according to claim 2 inverted arch is filled groove and is moved moulds, it is characterized in that, described lateral running gear (4) includes adjusting screw rod (41), adjusting nut (42), walking wheel carrier (43) and road wheel (44).
A kind of tunnel the most according to claim 5 inverted arch is filled groove and is moved moulds, it is characterized in that, the described connecting rod on described vertical running gear (3) is connected to the described lifting screw (61) on described lowering or hoisting gear (6).
8. fill groove according to the arbitrary described a kind of tunnel inverted arch of claim 1-7 to move moulds, it is characterised in that described mould bases acts on the molded groove (8) on molded groove coagulation earthen platform (7).
CN201620310239.3U 2016-04-14 2016-04-14 Tunnel invert fills slot and removes mould Expired - Fee Related CN205638481U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620310239.3U CN205638481U (en) 2016-04-14 2016-04-14 Tunnel invert fills slot and removes mould

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620310239.3U CN205638481U (en) 2016-04-14 2016-04-14 Tunnel invert fills slot and removes mould

Publications (1)

Publication Number Publication Date
CN205638481U true CN205638481U (en) 2016-10-12

Family

ID=57065239

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620310239.3U Expired - Fee Related CN205638481U (en) 2016-04-14 2016-04-14 Tunnel invert fills slot and removes mould

Country Status (1)

Country Link
CN (1) CN205638481U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109235209A (en) * 2018-11-05 2019-01-18 中铁五局集团路桥工程有限责任公司 A kind of concrete road shoulder construction equipment for cutting
CN109235208A (en) * 2018-11-05 2019-01-18 中铁五局集团路桥工程有限责任公司 A kind of concrete road shoulder constructing device for embankment
CN111561165A (en) * 2020-04-30 2020-08-21 中国五冶集团有限公司 Movable formwork groove positioner
CN114808615A (en) * 2022-04-15 2022-07-29 中铁六局集团有限公司 Continuous casting equipment for tunnel special-shaped sewage ditch and using method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109235209A (en) * 2018-11-05 2019-01-18 中铁五局集团路桥工程有限责任公司 A kind of concrete road shoulder construction equipment for cutting
CN109235208A (en) * 2018-11-05 2019-01-18 中铁五局集团路桥工程有限责任公司 A kind of concrete road shoulder constructing device for embankment
CN111561165A (en) * 2020-04-30 2020-08-21 中国五冶集团有限公司 Movable formwork groove positioner
CN114808615A (en) * 2022-04-15 2022-07-29 中铁六局集团有限公司 Continuous casting equipment for tunnel special-shaped sewage ditch and using method
CN114808615B (en) * 2022-04-15 2024-05-14 中铁六局集团有限公司 Continuous pouring equipment for special-shaped sewage ditch of tunnel and use method

Similar Documents

Publication Publication Date Title
CN205638481U (en) Tunnel invert fills slot and removes mould
CN107905254A (en) The construction method of mould trolley in a kind of pipe gallery formwork integrated hydraulic
CN103774561B (en) The job execution of speedway prefabricated small box girder frock method streamlined
CN110273695A (en) A kind of Tunnel Second Lining formwork jumbo and its stage molding pouring procedure
CN207212365U (en) A kind of wall arch is separable can Monolithic lining chassis
CN210066671U (en) Novel rectangular gallery structure
CN106120584A (en) A kind of box culvert slip form construction device and method
CN102518046B (en) Method for eliminating secondary internal force of sinking of support saddle of continuous beam during cantilever construction
CN201648978U (en) Tied arch support of bridge location cast-in-situ prestressed concrete continuous beam
CN210766280U (en) Curb prefabricated assembly side form
CN201865053U (en) Continuous steel beam template
CN206144574U (en) Tunnel center escape canal formworking jumbo
CN110439569B (en) Slideway system for jacking frame and construction method thereof
CN210530866U (en) Tunnel invert side wall concrete self-propelled pours device
CN206015540U (en) A kind of box culvert slip form construction device
CN205576926U (en) Device is pour to road bed concrete bank protection
CN210256628U (en) Self-adaptive outer mold system for prefabricating concrete
CN107191205A (en) Tunnel side wall inverted arch concrete cyclization cast automatic moving full arc template
CN109653445B (en) Thickness adjusting device and method for steel bar protection layer
CN211948026U (en) Cast-in-place splayed wall template system of apron culvert
CN206873310U (en) A kind of arch bridge main girder construction Hanging Basket
CN207033471U (en) Tunnel side wall inverted arch concrete cyclization cast automatic moving full arc template
CN208563131U (en) A kind of ground line mobile formwork
CN207415622U (en) The prefabricated anti-bank support device for hanging mould
CN205870814U (en) A die block that is used for precasting yard roof beam, board to prefabricate

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Co-patentee after: CHINA RAILWAY ERJU 1ST ENGINEERING Co.,Ltd.

Patentee after: China Railway Second Bureau Construction Co.,Ltd.

Address before: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Co-patentee before: CHINA RAILWAY ERJU 1ST ENGINEERING Co.,Ltd.

Patentee before: CHINA RAILWAY NO.2 ENGINEERING GROUP Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190808

Address after: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Co-patentee after: CHINA RAILWAY ERJU 1ST ENGINEERING Co.,Ltd.

Patentee after: CHINA RAILWAY NO.2 ENGINEERING GROUP Co.,Ltd.

Address before: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Co-patentee before: CHINA RAILWAY ERJU 1ST ENGINEERING Co.,Ltd.

Patentee before: China Railway Second Bureau Construction Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161012