CN208563131U - A kind of ground line mobile formwork - Google Patents
A kind of ground line mobile formwork Download PDFInfo
- Publication number
- CN208563131U CN208563131U CN201821163005.6U CN201821163005U CN208563131U CN 208563131 U CN208563131 U CN 208563131U CN 201821163005 U CN201821163005 U CN 201821163005U CN 208563131 U CN208563131 U CN 208563131U
- Authority
- CN
- China
- Prior art keywords
- mould
- large tank
- vertical large
- fixedly installed
- line mobile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000009415 formwork Methods 0.000 title claims description 11
- 239000003381 stabilizer Substances 0.000 claims description 3
- 230000005611 electricity Effects 0.000 claims 1
- 239000004567 concrete Substances 0.000 abstract description 7
- 230000005540 biological transmission Effects 0.000 description 8
- 239000011150 reinforced concrete Substances 0.000 description 2
- 210000004279 Orbit Anatomy 0.000 description 1
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 239000010410 layer Substances 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000002356 single layer Substances 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Abstract
The utility model discloses a kind of ground line mobile formworks for pouring concrete beam technical field, including track, the top of track is uniformly equipped with three groups of vertical large tank systems from left to right, the top of vertical large tank system is welded with bracket loop, and the bottom wall of bracket loop is equipped with walking system by bolt group, the roof of vertical large tank system top end holder circle is fixedly installed with lifting support system, the top of lifting support system is fixedly installed with support beam, wing mould fold system is hinged with before and after support beam top, the top of support beam is fixedly installed with mould bed system, the present apparatus compared to traditional mould bases for, it constructs more safe and reliable, main screw lift is light, it is at low cost.
Description
Technical field
The utility model discloses a kind of ground line mobile formworks, specially pour concrete beam technical field.
Background technique
Concrete beam is also referred to as reinforced beam, and reinforced beam is the beam made of Reinforced Concrete Materials, reinforced concrete
Tu Liang can both be made isolated beam, the board-like superstructure of beam-that can also be integral with armoured concrete slab group, or with reinforced column group
Integral single-layer or multi-layer frame, reinforced beam form is varied, is the engineering structures such as building construction, bridge construction
In most basic supporting member, application range is extremely wide, traditional mould bases, and mould bed is needed through the big stringer power transmission of two Pin at bridge pier
Pier-side bracket, then by pier-side bracket power transmission in bridge pier, main screw lift weight, at high cost, safety coefficient is low.
Utility model content
It is mentioned above in the background art to solve the purpose of this utility model is to provide a kind of ground line mobile formwork
Traditional mould bases, mould bed need the pier-side bracket by the big stringer power transmission of two Pin at bridge pier, then by pier-side bracket power transmission in
Bridge pier, main screw lift weight is at high cost, the low problem of safety coefficient.
To achieve the above object, the utility model provides the following technical solutions: a kind of ground line mobile formwork, including rail
Road, the top of the track are uniformly equipped with three groups of vertical large tank systems, the top of the vertical large tank system from left to right
End is welded with bracket loop, and the bottom wall of bracket loop is equipped with walking system, the straight length of the walking system by bolt group
Greater than the straight length of vertical large tank system, the roof of the vertical large tank system top end holder circle is fixedly installed with lifting
Support system, the top of the lifting support system are fixedly installed with support beam, and the support beam top front and back is hinged
There is wing mould to turn down system, the top of the support beam is fixedly installed with mould bed system, and the mould bed system is located at two groups of wing moulds
The centre of fold system, one end of the fold system of wing mould described in two groups and the bottom wall of mould bed system are hinged.
Preferably, the inner cavity of the lifting support system is bolted with stabiliser bar.
Preferably, gag lever post is bolted between the vertical large tank system top end holder circle and track bottom wall front and back.
Preferably, the walking system passes through motor driven.
Compared with prior art, the utility model has the beneficial effects that
1) present apparatus active force is directly and clear: compared to traditional mould bases, mould bed needs to pass by the big stringer of two Pin
Pier-side bracket of the power at bridge pier, then by pier-side bracket power transmission in bridge pier, and in the present apparatus, mould bed passes through support beam, liter
In ground, active force is directly and clear for descending branch support system and the direct power transmission of vertical large tank;
2) mould bases vertical shift via hole is more safe and reliable: compared to mould bases is passed, vertical shift via hole needs to carry out walking in high-altitude
Oil cylinder pushing tow vertical shift, and line mould bases vertical shift via hole in ground need only be laid with continuous orbit on ground, directly be walked by running motor
To it is next across;
3) main screw lift is light: because the direct power transmission of mobile formwork eliminates the big vertical of traditional mobile formwork in ground
Beam, main screw lift are lighter than traditional mould bases, and therefore, ground row mould bases main screw lift is light, and at low cost, the present apparatus is compared to traditional mould bases
For, it constructs more safe and reliable, main screw lift is light, at low cost.
Detailed description of the invention
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is the utility model mould bases left view cross-sectional view;
Fig. 3 is the utility model mould bases vertical shift schematic diagram.
In figure: 1 walking system, 2 vertical large tank systems, 3 lifting support systems, 4 support beams, 5 mould bed systems, 6 wings
Mould turns down system, 7 tracks.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
The utility model provides a kind of technical solution: a kind of ground line mobile formwork, including track 7 referring to FIG. 1-2,
The top of track 7 is uniformly equipped with three groups of vertical large tank systems 2 from left to right, and the top of vertical large tank system 2 is welded with
Bracket loop, and the bottom wall of bracket loop is equipped with walking system 1 by bolt group, the straight length of walking system 1 is greater than vertical big
The straight length of cylinder system 2, the roof of vertical 2 top end holder circle of large tank system are fixedly installed with lifting support system 3, rise
The top of descending branch support system 3 is fixedly installed with support beam 4, and wing mould fold system 6 is hinged with before and after 4 top of support beam,
The top of support beam 4 is fixedly installed with mould bed system 5, and mould bed system 5 is located at the centre of two groups of wing moulds fold systems 6, and two groups
One end of wing mould fold system 6 and the bottom wall of mould bed system 5 are hinged.
Wherein, the inner cavity for going up and down support system 3 is bolted with stabiliser bar, improves the stability of lifting support system 3, avoid because
Preponderance leads to the damage for going up and down support system 3, between vertical 2 top end holder circle of large tank system and 7 bottom wall of track front and back
It is bolted with gag lever post, when pouring, the stability between vertical large tank system 2 and track 7 is improved, prevents from moving, walking system 1
Pass through motor driven.
Working principle: mould bases accurately adjusts mould bed system 5 in place, pours concrete beam;The maintenance of concrete beam, wearing steel hinge line, simultaneously tensioning is complete
At;Complete machine is unloaded by vertical large tank system 2 and is completed;External mold turns down system 6 by wing mould and shrinks external mold size;Complete machine passes through
Going up and down support system 3 reduces the height of mould bases;Mould bases by walking system 1 to it is next across pour position;The movement of mould bases another mistake rises
Descending branch support system 3 and the wing mould fold system 6 by 5 coarse adjustment of mould bed system in place;Mould bases is finally accurately adjusted in place again, prepares to pour
Concrete beam completes the working cycles of a standard.It pours under operating condition, mould bed system 5 passes through support beam 4, lifting 3 and of support system
Under track 7, vertical shift operating condition, mould bed system 5 first passes through wing mould fold system 6 and shrinks outside the direct power transmission of vertical large tank system 2
Mould size, then reduce by lifting support system 3 height of mould bases, then by the walking system 1 of mould bases to it is next across pour
Position is built, last another mistake movement lifting support system 3 and wing mould turn down system 6, mould bases made to complete a standard working cycles.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired
Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.
Claims (4)
1. a kind of ground line mobile formwork, including track (7), it is characterised in that: the top of the track (7) is uniform from left to right
Three groups of vertical large tank systems (2) are installed, the top of the vertical large tank system (2) is welded with bracket loop, and bracket loop
Bottom wall be equipped with walking system (1) by bolt group, the straight length of the walking system (1) is greater than vertical large tank system
(2) straight length, the roof of vertical large tank system (2) the top end holder circle are fixedly installed with lifting support system (3),
The top of lifting support system (3) is fixedly installed with support beam (4), hinged before and after support beam (4) top
There is wing mould to turn down system (6), the top of the support beam (4) is fixedly installed with mould bed system (5), the mould bed system (5)
Positioned at the centre of two groups of wing mould folds system (6), wing mould described in two groups turns down the one end of system (6) and the bottom of mould bed system (5)
Wall is hinged.
2. line mobile formwork in a kind of ground according to claim 1, it is characterised in that: lifting support system (3)
Inner cavity is bolted with stabiliser bar.
3. line mobile formwork in a kind of ground according to claim 1, it is characterised in that: the vertical large tank system (2)
Gag lever post is bolted between before and after top end holder circle and track (7) bottom wall.
4. line mobile formwork in a kind of ground according to claim 1, it is characterised in that: the walking system (1) passes through electricity
Machine driving.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821163005.6U CN208563131U (en) | 2018-07-23 | 2018-07-23 | A kind of ground line mobile formwork |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821163005.6U CN208563131U (en) | 2018-07-23 | 2018-07-23 | A kind of ground line mobile formwork |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208563131U true CN208563131U (en) | 2019-03-01 |
Family
ID=65447196
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821163005.6U Active CN208563131U (en) | 2018-07-23 | 2018-07-23 | A kind of ground line mobile formwork |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208563131U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112064505A (en) * | 2020-03-31 | 2020-12-11 | 中铁大桥局集团第二工程有限公司 | Amplitude-variable type movable support and construction method thereof |
-
2018
- 2018-07-23 CN CN201821163005.6U patent/CN208563131U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112064505A (en) * | 2020-03-31 | 2020-12-11 | 中铁大桥局集团第二工程有限公司 | Amplitude-variable type movable support and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201003145Y (en) | Upward and self-walking type mobile die carrier | |
CN203768814U (en) | High-pier minor-radius curve cast-in-situ box girder novel moving die carrier | |
CN102094392B (en) | Lower supported hanging basket in bridge construction and application thereof | |
CN208087078U (en) | A kind of boom hoisting of large span steel reinforced concrete combination beam Bridge Erector | |
CN109403374A (en) | Factorial construction method for open trench tunnel integral tunnel lining | |
CN202991063U (en) | Large-section tunnel hydraulic trolley | |
CN102022123A (en) | Integral lining method for tunnel with altered diameter by model board trolley | |
CN105386411A (en) | Multifunctional portal device of suspension bridge pillar top | |
CN208533370U (en) | A kind of Bridge Erector of large span steel reinforced concrete combination beam erection construction | |
CN103498421B (en) | A kind of mobile formwork of constructing for U-shaped water conservancy aqueduct | |
CN202658534U (en) | Efficient and fast moving formwork | |
CN208563131U (en) | A kind of ground line mobile formwork | |
CN109026073A (en) | Arched tunnel secondary lining reinforcing bar binding device | |
CN203248170U (en) | Lining trolley for secondary lining construction of pedestrian crosswalk | |
CN104110002A (en) | Method for replacing bridge deck slabs of steel truss girder bridge | |
CN103526697B (en) | Self-propelled movable formwork for construction of double-rectangle water conservancy aqueduct | |
CN205669205U (en) | A kind of unilateral formula rock anchorage beam concreting chassis | |
CN203514207U (en) | Self-propelled movable formwork for double-rectangular water conservancy aqueduct construction | |
CN113235472A (en) | Concrete placement platform truck is contained to apron | |
CN108098979A (en) | A kind of PK sections concrete box girder precast segment template | |
CN211547804U (en) | Cantilever type retaining wall rapid construction device | |
CN208717748U (en) | A kind of large span steel reinforced concrete combination beam Bridge Erector support leg device | |
CN204112226U (en) | A kind of holes connects does section assembling bridge manufacturing machine | |
CN207987749U (en) | Ride cable-styled erection crane | |
CN205894081U (en) | Symmetry formula rock -anchored beam concrete placement platform truck |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |