CN205576730U - Bridge beam supports changes punishment system - Google Patents

Bridge beam supports changes punishment system Download PDF

Info

Publication number
CN205576730U
CN205576730U CN201620401945.9U CN201620401945U CN205576730U CN 205576730 U CN205576730 U CN 205576730U CN 201620401945 U CN201620401945 U CN 201620401945U CN 205576730 U CN205576730 U CN 205576730U
Authority
CN
China
Prior art keywords
wedge
punishment system
steel plate
steel sheet
shaped steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active - Reinstated
Application number
CN201620401945.9U
Other languages
Chinese (zh)
Inventor
刘涛
马志强
吕船
郭殿军
原国华
陈军军
何广宝
邓秦峰
宋萍
杨平波
李青
安定宇
赵云川
和兆建
姚剑
安鹏
靳秀红
牟开
王程宏
张坤
陈亚军
赵博文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Branch Bridge Tunnel Reinforcement And Maintenance Engineering Co Ltd
Original Assignee
Shanxi Branch Bridge Tunnel Reinforcement And Maintenance Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Branch Bridge Tunnel Reinforcement And Maintenance Engineering Co Ltd filed Critical Shanxi Branch Bridge Tunnel Reinforcement And Maintenance Engineering Co Ltd
Priority to CN201620401945.9U priority Critical patent/CN205576730U/en
Application granted granted Critical
Publication of CN205576730U publication Critical patent/CN205576730U/en
Active - Reinstated legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model belongs to the technical field of bridge engineering, particularly, involve a bridge beam supports changes punishment system. It includes support, wedge steel sheet and glues the steel glue film to change the punishment system, on the support was located support base stone, its upper surface was equipped with the wedge steel sheet, wedge steel sheet surface is equipped with glues the steel glue film, it closely connected and bond firmly to glue steel glue film and girder bottom surface. Compared with the prior art, bridge beam supports changes punishment system has following advantage: 1 )It is easy and simple to handle, easily realize, 2 )The outward appearance is pleasing to the eye, guarantees the even atress of support, 3 )The wedge steel sheet bonds firmly with the girder bottom surface, and the later stage can not slided and drop, 4 )The wedge steel sheet is according to the processing of measured data mill, and the precision is high, and the quality is easily guaranteed.

Description

A kind of Bridge Support Replacement punishment system
Technical field
This utility model belongs to technical field of bridge engineering, it particularly relates to arrive at a kind of Bridge Support Replacement Control system.
Background technology
To Bridge Support Replacement, adjustment and beam body is raised, translate the construction such as transformation time, be required to use thousand Jin top carries out jacking to beam body.Due to deck profile grade, horizontal wall inscription and beam body construction of bottom plates error, Bridge Beam Body bottom surface is frequently not level.And during bridge jacking, it is desirable to jack bearing up-down force face all keeps water Plane.In order to ensure jack bearing up-down force face level, at present use in jack end face and beam body bottom surface it more Between cushioning steel-sheet method.But this method is limited by operator's experience and sensation, its effect is also paid no attention to Thinking, it is easy to cause jack unbalance stress, long-time use causes damage of jack, the stability to beam body Also it is disadvantageous.
Summary of the invention
For solving above-mentioned technical problem, this utility model provides a kind of simple in construction, the obvious bridge of effect props up Seat changes punishment system.
A kind of Bridge Support Replacement punishment system described in the utility model, described replacing punishment system includes bearing 4, wedge-shaped steel plate 3 and steel bonding glue-line 2;Described bearing 4 is positioned on bearing pad stone 5, and its upper surface is provided with wedge Shape steel plate 3;Described wedge-shaped steel plate 3 surface is provided with steel bonding glue-line 2;Described steel bonding glue-line 2 is close with bottom plane of main girder 1 Paste and be firmly bonded.
A kind of Bridge Support Replacement punishment system described in the utility model, the thick 3-5mm of described steel bonding glue-line 2.
A kind of Bridge Support Replacement punishment system described in the utility model, the left end of described wedge-shaped steel plate 3 is provided with Penetrate the screwed hole of upper and lower surface.For steel bonding glue, the special circumstances that bonding is unstable occur, can use screw to Girder is fixed.
A kind of Bridge Support Replacement punishment system described in the utility model, the right-hand member of described wedge-shaped steel plate 3 is provided with Groove, can put into Magnet in this groove.
During operation, first, to four angle points of bearing pad stone and the bottom plane of main girder corresponding position elevation intending replacing time Measure in detail, determine new replacing time model, specification, size and the size of wedge-shaped steel plate;Second step, According to measured data at the processing wedged steel plate of processing factory;3rd step, selects suitable thousand according to the top lift calculated Jin jacking row girder jacking;4th step, removes original bearing;5th step, repairs pinner end face, Guarantee pinner end face level;6th step, at wedge-shaped steel plate surface uniform application 3~5mm thickness steel bonding glue, by its with Bottom plane of main girder is closely connected, be firmly bonded;Finally, erection support, fall jack, complete punishment.
Compared with prior art, Bridge Support Replacement described in the utility model punishment system has the advantage that 1) It is easy and simple to handle, it is easy to accomplish;2) appearance looks elegant, it is ensured that bearing uniform stressed;3) at the bottom of wedge-shaped steel plate and girder Face is firmly bonded, and the later stage will not slip and fall out;4) wedge-shaped steel plate is according to measured data factory process, and precision is high, Quality is prone to ensure.
Accompanying drawing explanation
Fig. 1: Bridge Support Replacement punishment system schematic;Fig. 2: wedge-shaped steel plate schematic diagram;Girder-1, steel bonding Glue-line-2, wedge-shaped steel plate-3, bearing-4, bearing pad stone-5.
Detailed description of the invention
Below in conjunction with specific embodiment, Bridge Support Replacement described in the utility model punishment system is done further Illustrate, but protection domain of the present utility model is not limited to this.
Embodiment 1
A kind of Bridge Support Replacement punishment system, described replacing punishment system includes bearing 4, wedge-shaped steel plate 3 and glues Steel glue-line 2;Described bearing 4 is positioned on bearing pad stone 5, and its upper surface is provided with wedge-shaped steel plate 3;Described wedge shape Steel plate 3 surface is provided with steel bonding glue-line 2;Described steel bonding glue-line 2 is closely connected with bottom plane of main girder 1 and is firmly bonded.Described The thick 3-5mm of steel bonding glue-line 2.The left end of described wedge-shaped steel plate 3 is provided with the screwed hole penetrating upper and lower surface.For There are the special circumstances that bonding is unstable in steel bonding glue, and screw can be used to fix to girder.Described wedge-shaped steel plate 3 Right-hand member is provided with groove, can put into Magnet in this groove.
During operation, first, to four angle points of bearing pad stone and the bottom plane of main girder corresponding position elevation intending replacing time Measure in detail, determine new replacing time model, specification, size and the size of wedge-shaped steel plate;Second step, According to measured data at the processing wedged steel plate of processing factory;3rd step, selects suitable thousand according to the top lift calculated Jin jacking row girder jacking;4th step, removes original bearing;5th step, repairs pinner end face, Guarantee pinner end face level;6th step, at wedge-shaped steel plate surface uniform application 4mm thickness steel bonding glue, by it with main Soffit is closely connected, be firmly bonded;Finally, erection support, fall jack, complete punishment.
Compared with prior art, Bridge Support Replacement described in the utility model punishment system has the advantage that 1) It is easy and simple to handle, it is easy to accomplish;2) appearance looks elegant, it is ensured that bearing uniform stressed;3) at the bottom of wedge-shaped steel plate and girder Face is firmly bonded, and the later stage will not slip and fall out;4) wedge-shaped steel plate is according to measured data factory process, and precision is high, Quality is prone to ensure.

Claims (4)

1. a Bridge Support Replacement punishment system, it is characterised in that described replacing punishment system includes bearing (4), wedge-shaped steel plate (3) and steel bonding glue-line (2);Described bearing (4) is positioned on bearing pad stone (5), and its upper surface sets There is wedge-shaped steel plate (3);Described wedge-shaped steel plate (3) surface is provided with steel bonding glue-line (2);Described steel bonding glue-line (2) and girder Bottom surface (1) is closely connected and is firmly bonded.
A kind of Bridge Support Replacement punishment system the most according to claim 1, it is characterised in that described The thick 3-5mm of steel bonding glue-line (2).
A kind of Bridge Support Replacement punishment system the most according to claim 1, it is characterised in that described The left end of wedge-shaped steel plate (3) is provided with the screwed hole penetrating upper and lower surface.
A kind of Bridge Support Replacement punishment system the most according to claim 1, it is characterised in that described The right-hand member of wedge-shaped steel plate (3) is provided with groove, can put into Magnet in this groove.
CN201620401945.9U 2016-05-05 2016-05-05 Bridge beam supports changes punishment system Active - Reinstated CN205576730U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620401945.9U CN205576730U (en) 2016-05-05 2016-05-05 Bridge beam supports changes punishment system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620401945.9U CN205576730U (en) 2016-05-05 2016-05-05 Bridge beam supports changes punishment system

Publications (1)

Publication Number Publication Date
CN205576730U true CN205576730U (en) 2016-09-14

Family

ID=56856415

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620401945.9U Active - Reinstated CN205576730U (en) 2016-05-05 2016-05-05 Bridge beam supports changes punishment system

Country Status (1)

Country Link
CN (1) CN205576730U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109183623A (en) * 2018-09-20 2019-01-11 中建市政工程有限公司 A kind of precast beam bottom longitudinal slope construction method and its device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109183623A (en) * 2018-09-20 2019-01-11 中建市政工程有限公司 A kind of precast beam bottom longitudinal slope construction method and its device

Similar Documents

Publication Publication Date Title
CN204530742U (en) A kind of adjustable suspension column
CN205576730U (en) Bridge beam supports changes punishment system
CN205591125U (en) Bridge jacking jack stress surface adjusting device
CN103967331A (en) Surrounding separation plate capable of ascending and descending
CN204510842U (en) A kind of steel crane beam installed height mark adjusting device
CN202174130U (en) Embedded part corrector
CN109610287A (en) Slope self-regulating presses holder base plate, slope self-regulating bridge and its installation method
CN103572774A (en) Leveling ruler flat underboarding mortar bedding method
CN201738248U (en) Embedded part installation device for bridge bearing
CN104631309B (en) The method of precast beam bottom surface leveling installed by a kind of bridge pad
CN103510700A (en) Novel jacking structure
CN110206156A (en) A kind of jack-up system of jacking type building roof platform
CN201915507U (en) Adjustable setting mould
CN106401176A (en) Steel-wood combination roof moldboard framework construction method
CN101871258B (en) Implement for quickly and accurately pasting sanitary wall tiles and method of reserving gaps, arranging tiles, filling mortar and pasting tiles
CN209555747U (en) Slope self-regulating presses holder base plate and slope self-regulating bridge
CN103132461A (en) Flexible bracket device for steel truss girder bridge cantilever construction
CN208276888U (en) A kind of device for the quick accurate integral marking of transverse and longitudinal beam
CN203034378U (en) Transverse adjusting and limiting device
CN204040264U (en) Stone curtain wall fixed structure
CN206385444U (en) It is a kind of to it is pull-type fall girder construction
CN205428976U (en) In same direction as rail type solar cell panel notacoria fixing device
CN104863091A (en) Repair method and structure for aged hydraulic engineering asphaltic concrete anti-seepage face slab
CN204825631U (en) Overpass expansion joint steel beam mounting levelling device
CN204924881U (en) Test device that concrete sulphate that draws compressive stress corrodes can apply simultaneously

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160914

Termination date: 20190505

RR01 Reinstatement of patent right
RR01 Reinstatement of patent right

Former decision: termination of patent right due to unpaid annual fee

Former decision publication date: 20200424