CN106401176A - Steel-wood combination roof moldboard framework construction method - Google Patents

Steel-wood combination roof moldboard framework construction method Download PDF

Info

Publication number
CN106401176A
CN106401176A CN201510464090.4A CN201510464090A CN106401176A CN 106401176 A CN106401176 A CN 106401176A CN 201510464090 A CN201510464090 A CN 201510464090A CN 106401176 A CN106401176 A CN 106401176A
Authority
CN
China
Prior art keywords
square steel
secondary joist
joist square
template
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510464090.4A
Other languages
Chinese (zh)
Inventor
王振兴
许龙迪
王卫新
曾辉
魏燕
安然
彭景祥
张暤
焦晨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING URBAN CONSTRUCTION NORTH CONSTRUCTION Co Ltd
Original Assignee
BEIJING URBAN CONSTRUCTION NORTH CONSTRUCTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING URBAN CONSTRUCTION NORTH CONSTRUCTION Co Ltd filed Critical BEIJING URBAN CONSTRUCTION NORTH CONSTRUCTION Co Ltd
Priority to CN201510464090.4A priority Critical patent/CN106401176A/en
Publication of CN106401176A publication Critical patent/CN106401176A/en
Pending legal-status Critical Current

Links

Landscapes

  • Floor Finish (AREA)

Abstract

The invention belongs to a steel-wood combination roof moldboard framework construction method comprising the following steps: pre-construction preparation; erecting scaffolds according to a floor support system design scheme; installing an adjustable jacking; installing a main keel square steel layer; installing a secondary keel square steel layer; installing each moldboard. The steel-wood combination roof moldboard framework construction method is simple and practical in application, saves time and laboring, saves labors and materials, is low in construction cost, environmental protection and pollution-free, high in efficiency, good in quality, and fast in construction period.

Description

A kind of steel and wood composite roof plate template system construction method
Technical field
The invention belongs to a kind of steel and wood composite roof plate template system construction method.
Background technology
At present, in the laminate of building is constructed, conventional construction method, main flitch is as the dragon of roof plate template Bone supports, and not only needs to expend a large amount of timber for this, and due to flitch variable thickness it is difficult to make template upper surface Identical with design face, lead to the laminate presentation quality of building poor, due also to wooden keel rigidity is limited, Yi Zao Become rise mould, poor flatness, absolute altitude of concrete roof wayward.And flitch is in use, only can week Turn 5 times about, that is, as waste disposal, not can be utilized, pollute environment, be also consumed by substantial amounts of natural resources. By this construction method, exist building laminate construction cost when expense side, the wasting of resources is many, construction cost is high, effect The problem that rate is low, of poor quality and the duration is slow.
Content of the invention
It is an object of the invention to provide a kind of steel and wood composite roof plate template system construction method, there is construction method side Just simple and practical, time saving and energy saving, save artificial and material, environment friendly and pollution-free, it is constructed into low, efficiency high, quality Advantage good and that the duration is fast.
For this reason, the method for the present invention comprises the steps:
(1) prepare before constructing, prepare secondary joist square steel, main joist square steel, leveling secondary joist square steel, connection time Keel square steel or connect the secondary joist lumps of wood, each template, prepare horizon bar, vertical rod, bar of sweeping the floor, adjustable jack and Connected nail;
(2) setting up of scaffold is carried out according to beam plate supporting system design, including vertical rod, horizon bar, sweep The thin end of the scroll, the setting up of drawknot bar;
(3) installation of adjustable jack, described adjustable jack by the jacking positioned at adjustment screw rod upper end and with adjustment The lifting chuck that screw rod is spirally connected is constituted, and is located at the tune of lifting chuck lower end in the top steel pole in the hole insertion of vertical rod Whole screw rod, the lower end of lifting chuck is stuck on rod end steel pole hole, in adjustment screw rod insertion rod end steel pipe The not little 150mm of length, the adjustment screw rod of lifting chuck upper end highly must not exceed 200mm, the freedom of adjustment jacking End height is to designed elevation, and presses code requirement setting camber;
(4) carry out the installation of main joist square steel layer, main joist square steel layer is located at the lower end of secondary joist square steel layer and props up Support secondary joist square steel layer, the main joist square steel that two are arranged side by side is supported by jacking and forms row main joist square steel, is in Parallel and spacing distance setting several rows main joist square steel forms main joist square steel layer, two main joist square steel terminations Lap-joint is arranged at adjacent two adjustable jack;
(5) carry out the installation of secondary joist square steel layer, secondary joist square steel layer be located at main joist square steel layer upper end, one Root secondary joist square steel is vertically arranged with row main joist square steel, and secondary joist square steel is in straight with the angle of row main joist square steel Angle, forms secondary joist square steel layer, two secondary joist sides in parallel and spacing distance setting several rows secondary joist square steel Steel termination lap-joint is arranged on the upper end of main joist square steel termination lap-joint, makes secondary joist with leveling secondary joist square steel The upper surface of square steel layer is plane;
(6) installation of each template, described each template includes beam bottom mother plate, plate bed die plate, side template, respectively The installation of template, sets up connection secondary joist square steel on the main joist square steel that adjacent each template connects edge joint position lower end Or connect the secondary joist lumps of wood, using connected nail by adjacent each template connect edge joint position be connected secondary joist square steel or Connect the secondary joist lumps of wood to fix it is ensured that the tight not spillage of this seam crossing, complete steel and wood composite roof plate template system and apply Work.
Described each template is that end face is provided with adherent layer thereon for iron plate or bamboo and wood composite material plate, each template Edge is provided with connecting hole in spacing distance.Described adherent layer is PEF plastic layer or is polypropylene plastic layer.
The lower end of described leveling secondary joist square steel is provided with the screw rod that upper end is spirally connected, spiral shell with its lower end in spacing distance The lower end of bar is provided with leveling support.It is in spacing distance on described connection secondary joist square steel or the connection secondary joist lumps of wood It is provided with perforation.Described jacking U-shaped profile.
Said method has reached the purpose of the present invention.
The construction method of the present invention facilitate simple and practical, time saving and energy saving, save artificial and material, be constructed into low, ring Protect pollution-free, efficiency high, the advantage that quality is good and the duration is fast.The construction method of the present invention can effectively ensure that top board The flatness of concrete and absolute altitude, and primary and secondary keel square steel can be used in turn 300 times about, can be without flitch Keel, primary and secondary keel square steel also may be recovered utilization, green low-carbon environment-friendly.
Can guarantee that the flatness of concrete roof and the quality of absolute altitude are excellent according to the measuring and calculating present invention, compared with conventional method Construction cost declines 50%, and the duration shortens 60%, and primary and secondary keel square steel recycling rate is 100%, has green Low-carbon environment-friendly, free of contamination advantage.
Brief description
Fig. 1 is the partial structural diagram of the present invention.
Fig. 2 is the structural representation of the adjustable jack of the present invention.
Fig. 3 is the partial structural diagram of the primary and secondary keel square steel layer of the present invention.
Fig. 4 is plate bed die plate and the leveling of the present invention, is connected secondary joist square steel partial structural diagram.
Fig. 5 is the structural representation of the leveling secondary joist square steel of the present invention.
Specific embodiment
As shown in Figures 1 to 5, a kind of steel and wood composite roof plate template system construction method, the method includes walking as follows Suddenly:
(1) prepare before constructing.Prepare secondary joist square steel 1, main joist square steel 4, leveling secondary joist square steel 15, connect Connect secondary joist square steel 2 or connect the secondary joist lumps of wood, each template 3, prepare horizon bar 6, vertical rod 7, bar 8 of sweeping the floor, Adjustable jack and connected nail 11.
(2) setting up of scaffold is carried out according to beam plate supporting system design.Including vertical rod, horizon bar, sweep The thin end of the scroll, the setting up of drawknot bar.
(3) installation of adjustable jack.Described adjustable jack by positioned at adjustment screw rod 5 upper end jacking 10 and with tune The lifting chuck 9 that whole screw rod is spirally connected is constituted.Lifting chuck can adjustment screw rod on rotation move, with adjust jacking with The distance between top of vertical rod, thus adjust the flatness of main joist square steel aspect.Top steel pole in vertical rod In the hole insertion is located at the adjustment screw rod of lifting chuck lower end, and the lower end of lifting chuck is stuck in rod end steel pole hole On.The not little 150mm of length in adjustment screw rod insertion rod end steel pipe, the adjustment screw rod of lifting chuck upper end is high Degree must not exceed 200mm, to protect the stationarity of support seized with terror.Adjustment jacking free end height to designed elevation, And press code requirement setting camber, that is, press design specification requirement and drawing requirement arranges camber.
(4) carry out the installation of main joist square steel layer.Main joist square steel layer is located at the lower end of secondary joist square steel layer and props up Support secondary joist square steel layer.The main joist square steel that two are arranged side by side is supported by jacking and forms row main joist square steel 4. Form main joist square steel layer in parallel and spacing distance setting several rows main joist square steel.Two main joist square steel ends Head lap-joint 41 is arranged at adjacent two adjustable jack.
(5) carry out the installation of secondary joist square steel layer.Secondary joist square steel layer is located at the upper end of main joist square steel layer.One Root secondary joist square steel is vertically arranged with row main joist square steel, and secondary joist square steel is in straight with the angle of row main joist square steel Angle.Form secondary joist square steel layer, two secondary joist sides in parallel and spacing distance setting several rows secondary joist square steel Steel termination lap-joint 12 is arranged on the upper end of main joist square steel termination lap-joint.Made secondary with leveling secondary joist square steel 15 The upper surface of keel square steel layer is plane, or is and design requirement identical faces.During leveling, only need to rotate leveling and prop up Seat drives screw rod so that it is screwed out or screw in leveling secondary joist square steel, and leveling support is located at the main dragon of its lower end On bone square steel, you can.
(6) installation of each template.Described each template includes beam bottom mother plate, plate bed die plate, side template, respectively The installation of template.Connection secondary joist square steel is set up on the main joist square steel that adjacent each template connects edge joint position lower end Or connect the secondary joist lumps of wood, also can use connection secondary joist square steel or the connection secondary joist lumps of wood to substitute the secondary joist at this Square steel.For environmental protection most preferably from connection secondary joist square steel.Using connected nail 11 by adjacent each template in the piece that connects Place with is connected secondary joist square steel or the connection secondary joist lumps of wood is fixed, will connected nail through the company in adjacent each template Connect the corresponding perforation 21 connecting on secondary joist square steel of Kong Zaiyu fixing, you can.Connected nail can be screw, pin.
Ensure the tight not spillage of this seam crossing, complete the construction of steel and wood composite roof plate template system.Then, in each mould Casting concrete roof on plate, or beam concrete, you can.After concrete dry, reverse operating, form removal.Preserve In case using again.
Described each template is that end face is provided with adherent layer 31, each template thereon for iron plate or bamboo and wood composite material plate Edge be provided with connecting hole 32 in spacing distance.Described adherent layer is PEF plastic layer or moulds for polypropylene The bed of material.So, casting concrete roof thereon, or beam concrete is after dry it is also possible to be easy to and each mould Plate separates.And also ensure concrete roof, or beam concrete is in contact with it the flat appearance in face and attractive in appearance.
The lower end of described leveling secondary joist square steel is provided with, in spacing distance, the screw rod 13 that upper end is spirally connected with its lower end, The lower end of screw rod is provided with leveling support 14.
It is provided with perforation 21 in spacing distance on described connection secondary joist square steel or the connection secondary joist lumps of wood.
Described jacking U-shaped profile.Jacking can clamping two main joist square steel side by side.
Obviously, connect the secondary joist square steel alternative connection secondary joist lumps of wood.So that the present invention is without timber.
In a word, the construction method of the present invention facilitate simple and practical, time saving and energy saving, save artificial and material, be constructed into Low, environment friendly and pollution-free, efficiency high, the advantage that quality is good and the duration is fast.

Claims (6)

1. a kind of steel and wood composite roof plate template system construction method it is characterised in that:The method includes walking as follows Suddenly,
(1) prepare before constructing, prepare secondary joist square steel, main joist square steel, leveling secondary joist square steel, connection time Keel square steel or the connection secondary joist lumps of wood, each template, prepare horizon bar, vertical rod, bar of sweeping the floor, adjustable jack And connected nail;
(2) setting up of scaffold is carried out according to beam plate supporting system design, including vertical rod, horizon bar, sweep The thin end of the scroll, the setting up of drawknot bar;
(3) installation of adjustable jack, described adjustable jack by the jacking positioned at adjustment screw rod upper end and with adjustment The lifting chuck that screw rod is spirally connected is constituted, and is located at lifting chuck lower end in the top steel pole in the hole insertion of vertical rod Adjustment screw rod, the lower end of lifting chuck is stuck on rod end steel pole hole, adjustment screw rod insertion rod end steel The not little 150mm of length in pipe, the adjustment screw rod of lifting chuck upper end highly must not exceed 200mm, adjusts jacking Free end height to designed elevation, and press code requirement setting camber;
(4) carry out the installation of main joist square steel layer, main joist square steel layer is located at the lower end of secondary joist square steel layer and props up Support secondary joist square steel layer, the main joist square steel that two are arranged side by side is supported by jacking and forms row main joist square steel, Form main joist square steel layer, two main joist square steel in parallel and spacing distance setting several rows main joist square steel Termination lap-joint is arranged at adjacent two adjustable jack;
(5) carry out the installation of secondary joist square steel layer, secondary joist square steel layer be located at main joist square steel layer upper end, one Root secondary joist square steel is vertically arranged with row main joist square steel, and secondary joist square steel with the angle of row main joist square steel is in Right angle, forms secondary joist square steel layer, twice dragons in parallel and spacing distance setting several rows secondary joist square steel Bone square steel termination lap-joint is arranged on the upper end of main joist square steel termination lap-joint, is made with leveling secondary joist square steel The upper surface of secondary joist square steel layer is plane;
(6) installation of each template, described each template includes beam bottom mother plate, plate bed die plate, side template, respectively The installation of template, sets up connection secondary joist side on the main joist square steel that adjacent each template connects edge joint position lower end Adjacent each template is being connected edge joint position and is being connected secondary joist side using connected nail by steel or the connection secondary joist lumps of wood Steel or the connection secondary joist lumps of wood are fixed it is ensured that the tight not spillage of this seam crossing, complete steel and wood composite roof plate template System is constructed.
2. method according to claim 1 it is characterised in that:Described each template is iron plate or bamboo and wood End face is provided with adherent layer to synthetic material plate thereon, and the edge of each template is provided with connecting hole in spacing distance.
3. method according to claim 2 it is characterised in that:Described adherent layer be PEF plastic layer, Or be polypropylene plastic layer.
4. method according to claim 1 it is characterised in that:The lower end of described leveling secondary joist square steel It is provided with the screw rod that upper end is spirally connected with its lower end in spacing distance, the lower end of screw rod is provided with leveling support.
5. method according to claim 1 it is characterised in that:Described connection secondary joist square steel or connection It is provided with perforation in spacing distance on the secondary joist lumps of wood.
6. method according to claim 1 it is characterised in that:Described jacking U-shaped profile.
CN201510464090.4A 2015-08-03 2015-08-03 Steel-wood combination roof moldboard framework construction method Pending CN106401176A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510464090.4A CN106401176A (en) 2015-08-03 2015-08-03 Steel-wood combination roof moldboard framework construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510464090.4A CN106401176A (en) 2015-08-03 2015-08-03 Steel-wood combination roof moldboard framework construction method

Publications (1)

Publication Number Publication Date
CN106401176A true CN106401176A (en) 2017-02-15

Family

ID=58007246

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510464090.4A Pending CN106401176A (en) 2015-08-03 2015-08-03 Steel-wood combination roof moldboard framework construction method

Country Status (1)

Country Link
CN (1) CN106401176A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108661312A (en) * 2018-03-23 2018-10-16 中国十七冶集团有限公司 A kind of laminated floor slab Construction Supporting System
CN114753619A (en) * 2022-04-15 2022-07-15 广东博嘉拓建筑科技有限公司 Top support for engineering construction wood formwork system and construction method thereof
CN114856170A (en) * 2022-05-30 2022-08-05 北京城建集团有限责任公司 Roof formwork construction process

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101871262A (en) * 2010-06-25 2010-10-27 中天建设集团有限公司天津分公司 Method for constructing beam plate supporting system having post-cast strip
CN102277959A (en) * 2011-05-13 2011-12-14 中国新兴保信建设总公司 Standard steel frame formwork system for concrete floor slabs and construction method thereof
CN102691411A (en) * 2012-06-21 2012-09-26 中国建筑第五工程局有限公司 Beam plate post-cast strip template support system and construction method thereof
CN202530755U (en) * 2012-03-27 2012-11-14 虞建放 Beam slab template structure
CN202530756U (en) * 2012-03-27 2012-11-14 虞建放 Early-removed template support structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101871262A (en) * 2010-06-25 2010-10-27 中天建设集团有限公司天津分公司 Method for constructing beam plate supporting system having post-cast strip
CN102277959A (en) * 2011-05-13 2011-12-14 中国新兴保信建设总公司 Standard steel frame formwork system for concrete floor slabs and construction method thereof
CN202530755U (en) * 2012-03-27 2012-11-14 虞建放 Beam slab template structure
CN202530756U (en) * 2012-03-27 2012-11-14 虞建放 Early-removed template support structure
CN102691411A (en) * 2012-06-21 2012-09-26 中国建筑第五工程局有限公司 Beam plate post-cast strip template support system and construction method thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
孙振领: "《高支撑模板系统施工专题方案》", 《百度文库》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108661312A (en) * 2018-03-23 2018-10-16 中国十七冶集团有限公司 A kind of laminated floor slab Construction Supporting System
CN114753619A (en) * 2022-04-15 2022-07-15 广东博嘉拓建筑科技有限公司 Top support for engineering construction wood formwork system and construction method thereof
CN114856170A (en) * 2022-05-30 2022-08-05 北京城建集团有限责任公司 Roof formwork construction process
CN114856170B (en) * 2022-05-30 2023-07-25 北京城建集团有限责任公司 Construction process of top plate template

Similar Documents

Publication Publication Date Title
CN106401176A (en) Steel-wood combination roof moldboard framework construction method
CN203834926U (en) Formwork erecting structure for bare concrete basement exterior wall
CN203878995U (en) Side wall stair formwork
CN204510816U (en) The stair template of adjustable angle
CN205259592U (en) Template structure of steel construction floor
CN204186029U (en) A kind of building wall board study plot keel device with horizontal adjustment base
CN201428240Y (en) Template with arc steps
CN205259593U (en) Whole spelling formula template of cast -in -place floor and support system
CN101886470B (en) Construction method of exposed concrete ribbed beams
CN204715741U (en) A kind of wall form for building
CN102926537A (en) Method and device for fixing root of external wall formwork
CN101871258B (en) Implement for quickly and accurately pasting sanitary wall tiles and method of reserving gaps, arranging tiles, filling mortar and pasting tiles
CN210263116U (en) Rapid mounting and dismounting shaping template for concrete reverse filling of lower independent foundation
CN203795854U (en) Preformed hole formwork fixing device for bare concrete floor
CN203008363U (en) Device for fixing root part of outer wall template
CN203769332U (en) Building form or floor construction control device
CN108360784B (en) Assembled indoor dry-hanging wall brick and construction method thereof
CN204804322U (en) Board construction equipment falls in instrument formula building
CN104947703A (en) Self-locking secondary grouting formwork for high-level independent foundation and using method of self-locking secondary grouting formwork
CN105317216A (en) Wall body reversed construction method and wall body and concrete framework casting structure
CN208899853U (en) A kind of aluminum alloy pattern plate construction joint joint part processing unit
CN204370834U (en) Supporting tool at the bottom of superposed beam beam
CN204609291U (en) Formwork system
CN202577968U (en) Suspending die suitable for pouring steps
CN204163367U (en) Cat ladder frame operating platform

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination