CN205474700U - Synthetic track - Google Patents

Synthetic track Download PDF

Info

Publication number
CN205474700U
CN205474700U CN201620204747.3U CN201620204747U CN205474700U CN 205474700 U CN205474700 U CN 205474700U CN 201620204747 U CN201620204747 U CN 201620204747U CN 205474700 U CN205474700 U CN 205474700U
Authority
CN
China
Prior art keywords
layer
plastic cement
race track
geotechnique
cloth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620204747.3U
Other languages
Chinese (zh)
Inventor
陈丙山
赵建伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG HUACHENG HIGH-TECH ADHESIVE Co Ltd
Original Assignee
SHANDONG HUACHENG HIGH-TECH ADHESIVE Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG HUACHENG HIGH-TECH ADHESIVE Co Ltd filed Critical SHANDONG HUACHENG HIGH-TECH ADHESIVE Co Ltd
Priority to CN201620204747.3U priority Critical patent/CN205474700U/en
Application granted granted Critical
Publication of CN205474700U publication Critical patent/CN205474700U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model provides a simple structure, construction convenience and low cost's synthetic track. A synthetic track, includes basic processing layer, sticky stone layer and synthetic track layer, and basic processing lays on the layer on plain soil layer, and mat formation on the basic processing layer in sticky stone layer, and synthetic track mats formation on the layer on sticky stone layer. The utility model discloses utilize basic processing layer and sticky stone layer to substitute concrete foundation and pitch basis, the cost is low, and the construction is simple, and curing time is short, can carry out synthetic track after 24 hours and mat formation, but about 10 days reductions of erection time, economic value and time value is obvious.

Description

Plastic cement race track
Technical field
This utility model relates to a kind of runway, is specifically related to a kind of plastic cement race track.
Background technology
Along with carrying out of nationwide fitness programs, the demand in stadium is also got more and more.Polyurethane spreading material has excellent wear-resistance and oil-resistance ageing-resistant, hardness range width anti-skidding, fire-retardant, elastic suitable, the feature such as shock-absorbing performance is excellent, color is attractive in appearance, is widely used in laying large, medium and small and kindergarten place.
Lay polyurethane runway and typically require good basis, basis generally concrete foundation and Colophonium basis, concrete foundation construction has the shortcomings such as material usage is big, the amount of labour is big, and curing cycle is long, generally 7-14 days, typically require that ground construction just can start plastic cement race track construction after complete 28 days.Although and Colophonium basis speed of application is fast, needing large-scale spreading machine, the compacted machine and professional and technical personnel, new Colophonium basis natural curing is no less than 28 days, makes high boiling point volatile matter volatilization in Colophonium complete, long construction period.
Utility model content
This utility model purpose is to provide a kind of simple in construction, easy construction and plastic cement race track with low cost.
To achieve these goals, this utility model is by the following technical solutions:
A kind of plastic cement race track, including based process layer, gluing rock layers and plastic cement race track layer, based process layer is laid on element soil layer, and gluing rock layers is mated formation on based process layer, and plastic cement race track layer is mated formation in gluing rock layers.
Above-mentioned plastic cement race track, gluing rock layers includes filled stone and adhesive, is mutually close to bonding by adhesive between filled stone, and adhesive includes epoxyn, polyurethane adhesive, single-component adhesive, two-component adhesive or resinae adhesive.
Above-mentioned plastic cement race track, based process layer is waterproof polymer thin layer or/and more than one layer geotechnique's layer of cloth.
Above-mentioned plastic cement race track, based process layer includes first geotechnique's layer of cloth, waterproof polymer thin layer and second geotechnique's layer of cloth, first geotechnique's layer of cloth is laid on element soil layer, and waterproof polymer thin layer is laid on first geotechnique's layer of cloth, and second geotechnique's layer of cloth is laid on waterproof polymer thin layer.
Above-mentioned plastic cement race track, gluing rock layers thickness is 0.5-10cm.
Above-mentioned plastic cement race track, gluing rock layers thickness is 2-3cm.
The beneficial effects of the utility model are:
Utilizing based process layer and gluing rock layers to substitute concrete foundation and Colophonium basis, cost is low, and construction is simple, and hardening time is short, can carry out plastic cement race track and mat formation after 24 hours, can about 10 days reduction of erection time, economic worth and the time value are obvious.
Accompanying drawing explanation
Below in conjunction with the accompanying drawings for plastic cement race track is described further:
Fig. 1 is plastic cement race track structural representation.
In figure: 1. element soil layer, 2. first geotechnique's layer of cloth, 3. waterproof polymer thin layer, 4. second geotechnique's layer of cloth, the most gluing rock layers, 6. plastic cement race track layer.
Detailed description of the invention
For making the purpose of this utility model, technical scheme and advantage clearer, develop simultaneously embodiment referring to the drawings, further describes this utility model.
A kind of plastic cement race track, including first geotechnique's layer of cloth 2, waterproof polymer thin layer the 3, second geotechnique layer of cloth 4, gluing rock layers 5 and plastic cement race track layer 6, first geotechnique's layer of cloth 2 is laid on element soil layer 1, waterproof polymer thin layer 3 is laid on first geotechnique's layer of cloth 2, second geotechnique's layer of cloth 4 is laid on waterproof polymer thin layer 3, gluing rock layers 5 is mated formation on second geotechnique's layer of cloth 4, and plastic cement race track layer 6 is mated formation in gluing rock layers 5.
The present embodiment, gluing rock layers 5 includes filled stone and adhesive, is mutually close to bonding by adhesive between filled stone, and adhesive includes epoxyn, polyurethane adhesive, single-component adhesive, two-component adhesive or resinae adhesive.
The present embodiment, gluing rock layers 5 thickness is 0.5-10cm, preferred version, and gluing rock layers 5 thickness is 2-3cm.
This utility model method for paving comprises the steps: after element soil layer 1 flattens, is compacted, lay first geotechnique's layer of cloth 2, then waterproof polymer thin layer 3 is laid, the waterproof polymer thin layer 3 that first geotechnique's layer of cloth 2 is laid above for fixing soil and protection, re-lay second geotechnique's layer of cloth 4, second geotechnique's layer of cloth 4 for protecting waterproof polymer thin layer 3 from upside, after laying completes, lay gluing rock layers 5, gluing rock layers 5 be stirred common stone by high-strength structureal adhesives after mat formation and form, can go up people after 24 hours and equipment is mated formation plastic cement race track layer 6.The runway type utilizing this utility model structure to lay includes mixed type runway, compound runway or vapor-permeable type runway etc..
Above-mentioned detailed description of the invention is only concrete case of the present utility model, being not the restriction that this utility model is made other form, any those skilled in the art are changed possibly also with the technology contents of the disclosure above or are modified as the equivalent implementations of equivalent variations.But every without departing from this utility model know-why on the premise of, any simple modification, equivalent variations and remodeling embodiment of above made according to technical spirit of the present utility model, all should fall into scope of patent protection of the present utility model.

Claims (6)

1. a plastic cement race track, it is characterised in that: including based process layer, gluing rock layers and plastic cement race track layer, based process layer is laid on element soil layer, and gluing rock layers is mated formation on based process layer, and plastic cement race track layer is mated formation in gluing rock layers.
Plastic cement race track the most according to claim 1, it is characterized in that: gluing rock layers includes filled stone and adhesive, mutually being close to bonding by adhesive between filled stone, adhesive includes epoxyn, polyurethane adhesive, single-component adhesive, two-component adhesive or resinae adhesive.
Plastic cement race track the most according to claim 1, it is characterised in that: based process layer is waterproof polymer thin layer or/and more than one layer geotechnique's layer of cloth.
Plastic cement race track the most according to claim 3, it is characterized in that: based process layer includes first geotechnique's layer of cloth, waterproof polymer thin layer and second geotechnique's layer of cloth, first geotechnique's layer of cloth is laid on element soil layer, waterproof polymer thin layer is laid on first geotechnique's layer of cloth, and second geotechnique's layer of cloth is laid on waterproof polymer thin layer.
5. according to plastic cement race track described in any one of Claims 1-4, it is characterised in that: gluing rock layers thickness is 0.5-10cm.
Plastic cement race track the most according to claim 5, it is characterised in that: gluing rock layers thickness is 2-3cm.
CN201620204747.3U 2016-03-17 2016-03-17 Synthetic track Active CN205474700U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620204747.3U CN205474700U (en) 2016-03-17 2016-03-17 Synthetic track

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620204747.3U CN205474700U (en) 2016-03-17 2016-03-17 Synthetic track

Publications (1)

Publication Number Publication Date
CN205474700U true CN205474700U (en) 2016-08-17

Family

ID=56653469

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620204747.3U Active CN205474700U (en) 2016-03-17 2016-03-17 Synthetic track

Country Status (1)

Country Link
CN (1) CN205474700U (en)

Similar Documents

Publication Publication Date Title
CN101680202B (en) Earth-supported structure with fasteners
CN104264692A (en) Ecological restoration method of slope
CN205474700U (en) Synthetic track
CN205474705U (en) Artificial lawn
CN205474701U (en) Silicon PU court
CN206529667U (en) A kind of novel tree pond
CN105230308B (en) Raw soil underground cave dwelling roof vegetation plantation base structure and construction technology thereof
CN207143630U (en) A kind of permeable, anti-settling pavement bricks
CN206266987U (en) A kind of IPU plastic cement race tracks
CN203890837U (en) Artificial turf of football field
CN205082273U (en) Basic unit's structure is planted to immature soil pit kiln kiln crown vegetation
CN206721606U (en) A kind of carbon fiber plastic cement race track
FR2315570A1 (en) Acrylic resin based top dressings for tennis courts - for a smooth sealed surface of controlled roughness
CN201305809Y (en) Pervious brick for rapidly permeable stopping pad
CN206971030U (en) A kind of multifunctional ecological permeable terrace
CN201685646U (en) Novel artificial hill
CN203373628U (en) Novel floor tile and pin lock type floor tile formed by same
CN110145107A (en) The method for paving of stone floor
CN206279716U (en) A kind of parian glass moulds floor
CN205804070U (en) A kind of red sand rock road structure
CN104674980A (en) Recycled-concrete composite moisturizing brick mortise-tenon string pipe wall body constructing method
CN201071574Y (en) Cement surface compound glass fiber reinforced plastics protection layer
CN205295833U (en) Brick permeates water in gap convenient to drainage
CN109853327A (en) A kind of production method of the natural Football pitch based on permanent line of demarcation
CN218643112U (en) Landscape footpath

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant