CN205399446U - Novel hasp steel pipe cofferdam structure - Google Patents

Novel hasp steel pipe cofferdam structure Download PDF

Info

Publication number
CN205399446U
CN205399446U CN201620225659.1U CN201620225659U CN205399446U CN 205399446 U CN205399446 U CN 205399446U CN 201620225659 U CN201620225659 U CN 201620225659U CN 205399446 U CN205399446 U CN 205399446U
Authority
CN
China
Prior art keywords
steel pipe
steel
pipe
main
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620225659.1U
Other languages
Chinese (zh)
Inventor
谢开仲
陈光强
王红伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi University
Original Assignee
Guangxi University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi University filed Critical Guangxi University
Priority to CN201620225659.1U priority Critical patent/CN205399446U/en
Application granted granted Critical
Publication of CN205399446U publication Critical patent/CN205399446U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The utility model discloses a novel hasp steel pipe cofferdam structure, include the steel -tube framework who constitutes by a plurality of main steel pipes the pipe wall of main steel pipe has a I -steel along the welding of pipe diameter orientation, and it has the steel pipe of connection to weld in another pipe wall department that corresponds the main steel pipe of side with the I -steel, connect and to be provided with a longitudinal opening groove on the lateral surface of steel pipe corresponding to the face of weld, arbitrary main steel pipe pass through on I -steel and another main steel pipe be connected the steel pipe connect fixed, the I -steel with be connected the packing of steel pipe junction and have a packing material, the utility model discloses simple structure, convenient for material collection, through welding and the I -steel of main steel pipe both sides and is connected steel pipe interconnect and forms steel -tube framework, the I -steel with be connected the packing of steel pipe junction and have the saw -dust, can play the fine effect of blocking water, seal effectually, steel pipe convenient to detach can reuse.

Description

A kind of Novel lock catch steel pipe cofferdam structure
Technical field
This utility model relates to foundation engineering and the hydraulic engineering technical field of science of bridge building, is specifically related to a kind of Novel lock catch steel pipe cofferdam structure.
Background technology
Cofferdam refers in the foundation engineering and hydraulic engineering construction of bridge, for building permanent water conservancy projects, and the provisional building enclosure built.Its effect is to prevent what water and soil from entering building to build position, in order at cofferdam internal drainage, and excavation pit builds building.Generally being mainly used in foundation engineering and the waterwork of bridge, except the part as formal building, cofferdam is removed after being typically in being finished.
The effect that prior art prevention moisture enters cofferdam is bad, it is necessary to water pump is a large amount of drainings from cofferdam, and working security is not high.
Utility model content
(1) to solve the technical problem that
In order to overcome prior art not enough, it is proposed that a kind of Novel lock catch steel pipe cofferdam structure, inflow is greatly reduced, and water pump displacement from cofferdam is greatly decreased, and working security is higher, makes simple, draws materials conveniently.
(2) technical scheme
Of the present utility model it is achieved through the following technical solutions: the utility model proposes a kind of Novel lock catch steel pipe cofferdam structure, including the steel pipe frame being made up of some main steel pipes, tube wall at described main steel pipe is welded with an I-steel along caliber direction, it is welded with a joint steel pipe at another tube wall place with the main steel pipe of I-steel respective side, described joint steel pipe is corresponding to being provided with a longitudinal opening groove on the lateral surface of solder side, arbitrary main steel pipe is connected fixing by I-steel with the joint steel pipe on another main steel pipe, it is filled with fill material in I-steel and joint steel pipe junction.
As further improvement, described longitudinal opening well width is slightly larger than the perpendicular rib width of I-steel.
As further improvement, described fill material is wood flour.
(3) beneficial effect
This utility model, relative to prior art, has the advantages that
A kind of Novel lock catch steel pipe cofferdam structure that this utility model is mentioned, its simple in construction, draw materials conveniently, it is interconnected to form steel pipe frame by the I-steel of welding and main steel pipe both sides and joint steel pipe, it is filled with wood flour, it is possible to play good resistance effect, good sealing effect in I-steel and joint steel pipe junction, steel pipe is readily accessible, it is possible to recycling.
Accompanying drawing explanation
Fig. 1 is this utility model structural representation.
The main steel pipe of 1-;2-I-steel;3-joint steel pipe;4-fill material;31-longitudinal opening groove.
Detailed description of the invention
In order to make the purpose of this utility model, technical scheme and advantage clearly understand, below in conjunction with drawings and Examples, this utility model is further elaborated.Should be appreciated that specific embodiment described herein is only in order to explain this utility model, be not used to limit this utility model.
A kind of Novel lock catch steel pipe cofferdam structure as shown in Figure 1, including the steel pipe frame being made up of some main steel pipes 1, an I-steel 2 it is welded with along caliber direction at the tube wall of described main steel pipe 1, it is welded with a joint steel pipe 3 at another tube wall place with the main steel pipe 1 of I-steel 2 respective side, described joint steel pipe 3 is corresponding to being provided with a longitudinal opening groove 31 on the lateral surface of solder side, arbitrary main steel pipe 1 is connected fixing by I-steel 2 with the joint steel pipe 3 on another main steel pipe 1, is filled with fill material 4 in I-steel 2 and joint steel pipe 3 junction.
Wherein, described longitudinal opening groove 31 width erects rib width slightly larger than I-steel 2;Described fill material 4 is wood flour.
A kind of Novel lock catch steel pipe cofferdam structure that this utility model is mentioned, it is when specifically used, and each main steel pipe 1 opposite sides is respectively welded a joint steel pipe 3 and an I-steel 2, and this is one and connects unit;The joint steel pipe 3 that one connects on unit is sheathed on another and connects on the cross rib of I-steel 2 lateral surface on unit, longitudinal opening groove 31 card on joint steel pipe 3 is embedded in the perpendicular rib place in the middle part of I-steel 2, it is cross-linked successively, some connection unit form steel pipe frame, effective Fence structure can be formed in water conservancy construction process, joint steel pipe 3 is at the wood flour filled with I-steel 2 joint gap place, can play, after the wet water soaking of wood flour, the sealing effectiveness that well blocks water, most importantly wood flour is drawn materials relatively wide, and low price.
This utility model simple in construction, facilitates installing/dismounting, it is possible to recycling, construction effect is good, it is ensured that underwater construction safety.
Embodiment described above is only that preferred implementation of the present utility model is described, and not design of the present utility model and scope is defined.Under the premise without departing from this utility model design concept; various modification that the technical solution of the utility model is made by this area ordinary person and improvement; protection domain of the present utility model all should be dropped into, the technology contents that this utility model is claimed, all record in detail in the claims.

Claims (3)

1. a Novel lock catch steel pipe cofferdam structure, including the steel pipe frame being made up of some main steel pipes (1), it is characterized in that: be welded with an I-steel (2) along caliber direction at the tube wall of described main steel pipe (1), it is welded with a joint steel pipe (3) at another tube wall place of the main steel pipe (1) with I-steel (2) respective side, described joint steel pipe (3) is corresponding to being provided with a longitudinal opening groove (31) on the lateral surface of solder side, arbitrary main steel pipe (1) is connected fixing by I-steel (2) with the joint steel pipe (3) on another main steel pipe (1), it is filled with fill material (4) in I-steel (2) and joint steel pipe (3) junction.
2. a kind of Novel lock catch steel pipe cofferdam structure according to claim 1, it is characterised in that: described longitudinal opening groove (31) width is slightly larger than the perpendicular rib width of I-steel (2).
3. a kind of Novel lock catch steel pipe cofferdam structure according to claim 1, it is characterised in that: described fill material (4) is wood flour.
CN201620225659.1U 2016-03-23 2016-03-23 Novel hasp steel pipe cofferdam structure Expired - Fee Related CN205399446U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620225659.1U CN205399446U (en) 2016-03-23 2016-03-23 Novel hasp steel pipe cofferdam structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620225659.1U CN205399446U (en) 2016-03-23 2016-03-23 Novel hasp steel pipe cofferdam structure

Publications (1)

Publication Number Publication Date
CN205399446U true CN205399446U (en) 2016-07-27

Family

ID=56422765

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620225659.1U Expired - Fee Related CN205399446U (en) 2016-03-23 2016-03-23 Novel hasp steel pipe cofferdam structure

Country Status (1)

Country Link
CN (1) CN205399446U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106592603A (en) * 2016-12-30 2017-04-26 江苏麦廊新材料科技有限公司 Foundation pit fender pile and foundation pit baffle
CN106592575A (en) * 2016-11-25 2017-04-26 江苏麦廊新材料科技有限公司 Support pile for foundation pit or underground corridor body
CN108442395A (en) * 2018-05-14 2018-08-24 中铁八局集团第二工程有限公司 Latch steel pipe pile cofferdam construction method
CN110563396A (en) * 2019-09-16 2019-12-13 毛景权 Steel sheet pile cofferdam lead hole backfill material, preparation method and backfill method
CN110924313A (en) * 2019-12-25 2020-03-27 核工业西南建设集团有限公司 Construction method of bridge foundation cofferdam

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106592575A (en) * 2016-11-25 2017-04-26 江苏麦廊新材料科技有限公司 Support pile for foundation pit or underground corridor body
CN106592603A (en) * 2016-12-30 2017-04-26 江苏麦廊新材料科技有限公司 Foundation pit fender pile and foundation pit baffle
CN108442395A (en) * 2018-05-14 2018-08-24 中铁八局集团第二工程有限公司 Latch steel pipe pile cofferdam construction method
CN110563396A (en) * 2019-09-16 2019-12-13 毛景权 Steel sheet pile cofferdam lead hole backfill material, preparation method and backfill method
CN110924313A (en) * 2019-12-25 2020-03-27 核工业西南建设集团有限公司 Construction method of bridge foundation cofferdam
CN110924313B (en) * 2019-12-25 2021-08-10 核工业西南建设集团有限公司 Construction method of bridge foundation cofferdam

Similar Documents

Publication Publication Date Title
CN205399446U (en) Novel hasp steel pipe cofferdam structure
CN101798939A (en) Maintainable tunnel drainage system
CN102051869B (en) High polymer heavy curtain grouting technology
CN103132504A (en) Pre-set water-proof stakes and inserting and pulling construction method thereof
CN105888693A (en) Treating construction method for water burst of small underground river of highway tunnel
CN204626427U (en) Assembling cofferdam
CN106498905B (en) A kind of concrete gravity dam transverse joint water seepage treatment structure and processing method
CN206157860U (en) Drainage pipeline
CN106759112B (en) The manufacturing method of concrete works sealing swaging die with reinforcing fiber
CN205444232U (en) Stock - gravity type infiltration retaining wall
CN205035761U (en) Automatic warning high strength anti -flood wall
CN208618430U (en) It is a kind of for wearing the structure of shutting off in river under shield tunnel
CN207277349U (en) A kind of highway bridge construction cofferdam device
CN106223351A (en) Self priming pump reduces local groundwater level construction method
CN215486037U (en) Water-rich sand layer sand flow-proof water burst working well
CN202247924U (en) Assembled steel structure open caisson in pipe jacking construction
CN109610476A (en) Steel pipe Larsen sheet pile precipitation building enclosure
CN106759526B (en) A kind of purlin before Brace in Deep Footing Groove beam demolition blasting protects preprocess method
CN201459770U (en) Joint structure between two different fender bodies in deep foundation pit
CN211395768U (en) Outer wall post-cast strip is enclosed construction in advance
CN211973461U (en) Buckled composite steel pile continuous wall
CN205116035U (en) Simply close steel bushing case of no end of water
CN208088305U (en) A kind of foundation pit water burst fast plugging device
CN206887885U (en) A kind of hydraulic engineering ecological revetment
CN206800351U (en) A kind of Tailings Dam drains off floodwaters culvert

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160727

Termination date: 20170323