CN205206826U - Tunnel face blast construction system - Google Patents
Tunnel face blast construction system Download PDFInfo
- Publication number
- CN205206826U CN205206826U CN201521087038.3U CN201521087038U CN205206826U CN 205206826 U CN205206826 U CN 205206826U CN 201521087038 U CN201521087038 U CN 201521087038U CN 205206826 U CN205206826 U CN 205206826U
- Authority
- CN
- China
- Prior art keywords
- tunnel
- projection
- projector
- blasthole
- bracket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title abstract description 14
- 230000001143 conditioned effect Effects 0.000 claims 1
- 238000005422 blasting Methods 0.000 abstract description 18
- 238000005553 drilling Methods 0.000 description 7
- 238000009412 basement excavation Methods 0.000 description 6
- 238000000034 method Methods 0.000 description 6
- 238000010586 diagram Methods 0.000 description 5
- 239000011435 rock Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 244000309464 bull Species 0.000 description 1
- 238000007600 charging Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 238000004836 empirical method Methods 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
本实用新型涉及一种隧道掌子面爆破施工系统。装置部分主要投影装置及标杆装置,所述投影装置包括投影支架,投影支架上分别设有投影机和定位罗盘,所述投影机被调节旋钮调节投射方向;在投影支架上设置有炮眼模板,炮眼模板位于投影机的前方,投影机发出的光线通过炮眼模板后影像投射到掌子面上以确定炮眼位置。本装置通过设计全新的结构,能够利用投影设备实现炮眼位置在掌子面的精确投射。
The utility model relates to a tunnel face blasting construction system. The device part is mainly a projection device and a benchmark device. The projection device includes a projection bracket, and a projector and a positioning compass are respectively arranged on the projection bracket, and the projection direction of the projector is adjusted by an adjustment knob; The template is located in front of the projector, and the light emitted by the projector passes through the blasthole template and the image is projected onto the palm surface to determine the blasthole position. By designing a brand-new structure, the device can use projection equipment to realize accurate projection of the position of the blast hole on the face of the tunnel.
Description
技术领域technical field
本实用新型涉及土木工程相关技术设备领域,具体的说,是涉及一种隧道掌子面爆破施工系统。The utility model relates to the technical equipment field related to civil engineering, in particular to a tunnel face blasting construction system.
背景技术Background technique
在我国绝大多数隧道开挖掘进通常采用钻爆法施工,钻爆法通过钻孔、装药、爆破实现开挖岩石。钻孔前必须在开挖面划好炮眼轮廓线,按钻爆参数图布置炮眼位置。其中的炮眼中掏槽眼间距、辅助眼排距和行距以及周边眼间距,必须按钻爆参数要求确定。In most tunnels in my country, the drilling and blasting method is usually used for construction, and the drilling and blasting method realizes rock excavation through drilling, charging, and blasting. Before drilling, the contour line of the blasthole must be drawn on the excavation surface, and the location of the blasthole should be arranged according to the drilling and blasting parameter diagram. Among them, the cutting hole spacing in the blast hole, the auxiliary hole row spacing and row spacing, and the surrounding hole spacing must be determined according to the drilling and blasting parameters.
钻爆施工中炮眼的布置直接影响爆破质量,爆破设计不当容易造成超欠挖现象。The layout of blastholes in drilling and blasting directly affects the quality of blasting, and improper blasting design can easily lead to overbreak and underbreak.
然而,在隧道掌子面爆破作业中,多采用经验法对掌子面炮孔数量和炮眼布局进行设计,常常导致隧道围岩体的超欠挖以及隧道走线偏离设计路线等现象。However, in the blasting operation of the tunnel face, empirical methods are often used to design the number of blastholes and the layout of blastholes on the tunnel face, which often leads to over- and under-excavation of the surrounding rock mass of the tunnel and deviation of the tunnel alignment from the designed route.
以上的爆破弊端既减慢了施工进度又提高了施工成本。The above blasting disadvantages not only slow down the construction progress but also increase the construction cost.
因此,有必要设计一种能够快速高效确定隧道掌子面炮眼精确位置的装置,来解决上述问题。Therefore, it is necessary to design a device that can quickly and efficiently determine the precise position of the blast hole on the face of the tunnel to solve the above problems.
实用新型内容Utility model content
本实用新型的目的是为克服上述现有技术的不足,提供一种隧道掌子面爆破施工系统。本装置通过设计全新的结构,能够利用投影设备实现炮眼位置在掌子面的精确投射。The purpose of this utility model is to provide a tunnel face blasting construction system in order to overcome the above-mentioned deficiencies in the prior art. By designing a brand-new structure, the device can use projection equipment to realize accurate projection of the position of the blast hole on the face of the tunnel.
为了达成上述目的,本实用新型采用如下技术方案:In order to achieve the above object, the utility model adopts the following technical solutions:
一种隧道掌子面爆破施工系统,包括:A tunnel face blasting construction system, comprising:
投影装置及标杆装置,两装置通过连通管连接;Projection device and benchmarking device, the two devices are connected through a connecting pipe;
所述投影装置包括投影支架,投影支架上分别设有投影机和定位罗盘,所述投影机被调节旋钮调节投射方向;The projection device includes a projection bracket on which a projector and a positioning compass are respectively arranged, and the projection direction of the projector is adjusted by an adjustment knob;
在投影支架上设置有炮眼模板,炮眼模板位于投影机的前方,投影机发出的光线通过炮眼模板后影像投射到掌子面上以确定炮眼位置。A blasthole template is arranged on the projection bracket, and the blasthole template is located in front of the projector. After the light emitted by the projector passes through the blasthole template, the image is projected onto the palm surface to determine the position of the blasthole.
优选的,所述投影支架上还具有水准泡。Preferably, the projection support also has a vial.
优选的,所述标杆装置包括标杆支架,标杆支架上设有棱镜。Preferably, the pole device includes a pole bracket, and a prism is arranged on the pole bracket.
优选的,所述标杆支架上还具有水准泡。Preferably, the benchmark bracket also has a vial.
在提供上述施工系统的同时,本实用新型还提供了一种利用上述施工系统来确定炮眼位置的方法,主要包括如下步骤:While providing the above-mentioned construction system, the utility model also provides a method for using the above-mentioned construction system to determine the position of the blast hole, which mainly includes the following steps:
A、在隧道边墙与地面的交界线上确定三个点;A. Determine three points on the boundary line between the tunnel side wall and the ground;
B、分别以三个点为中心并以大于隧道半径且小于直径的线段为半径画圆弧,使得三个圆弧两两相交;B. Draw arcs with three points as the center and a line segment larger than the tunnel radius and smaller than the diameter as the radius, so that the three arcs intersect in pairs;
C、连接隧道内部的圆弧所得的交点,使所得的线段与步骤A中的三个点的两两连线相交,得到两个位于隧道中线上的交点,并将两个交点连线,即为隧道中线;C, the intersecting points obtained by connecting the circular arcs inside the tunnel, making the obtained line segment intersect with the pairwise connecting lines of the three points in step A to obtain two intersecting points located on the center line of the tunnel, and connecting the two intersecting points, namely is the center line of the tunnel;
D、将投影装置与标杆装置布置于隧道中线上;D. Arrange the projection device and the benchmark device on the center line of the tunnel;
F、利用标杆装置确定投影装置发出的激光与隧道中线平行;F. Use the benchmarking device to confirm that the laser emitted by the projection device is parallel to the center line of the tunnel;
G、撤掉标杆装置,利用投影机将炮眼模板上的炮眼布局图投射于隧道掌子面上。G. Remove the benchmark device, and use the projector to project the blasthole layout on the blasthole template onto the tunnel face.
优选的,步骤A中的三个点不在一条直线上。Preferably, the three points in step A are not on a straight line.
优选的,完成步骤C后,通过连通管使两装置处在同一水平面上,再进行步骤D。Preferably, after step C is completed, the two devices are placed on the same level through the connecting pipe, and then step D is performed.
本实用新型具有的有益效果是:The beneficial effect that the utility model has is:
可以快速简便定位隧道掌子面上炮眼布局,解决炮眼布置不当造成的隧道施工中超挖、欠挖现象,有效提高隧道爆破掘进施工精度,成本低且使用方法简单。It can quickly and easily locate the blasthole layout on the tunnel face, solve the over-excavation and under-excavation phenomena in tunnel construction caused by improper blasthole layout, and effectively improve the construction accuracy of tunnel blasting and excavation. It is low in cost and easy to use.
附图说明Description of drawings
图1为本实用新型的结构示意图;Fig. 1 is the structural representation of the utility model;
图2为本实用新型中隧道中线定位示意图;Fig. 2 is a schematic diagram of positioning the center line of the tunnel in the utility model;
图3本实用新型中炮孔影像的投射示意图;Fig. 3 is a schematic diagram of projection of blasthole images in the utility model;
图4投影装置结构示意图;Fig. 4 is a structural schematic diagram of the projection device;
图5标杆装置结构示意图;Figure 5 Schematic diagram of the structure of the benchmarking device;
其中:1、投影装置,2、标杆装置,3、设定炮孔,4、隧道中线,5、连通管;Among them: 1. Projection device, 2. Benchmark device, 3. Setting blast holes, 4. Tunnel centerline, 5. Connecting pipe;
6、圆弧,7、中线点,8、边界点;6. Arc, 7. Midline point, 8. Boundary point;
9、投影灯,10、炮眼模板,11、隧道掌子面;9. Projector lamps, 10. Blast hole templates, 11. Tunnel face;
12、投影机,13、定位罗盘,14、调节旋钮,15、水准泡,16、投影支架;12. Projector, 13. Positioning compass, 14. Adjustment knob, 15. Level bubble, 16. Projection bracket;
17、圆棱镜,18、辅助支架,19、水准泡,20、主支架。17, circular prism, 18, auxiliary support, 19, vial, 20, main support.
具体实施方式detailed description
下面将结合附图对本实用新型进行详细说明。The utility model will be described in detail below in conjunction with the accompanying drawings.
实施例:一种隧道掌子面爆破施工系统,其结构如图1、3、4和5所示:包括投影装置1及标杆装置2,投影装置1及标杆装置2通过连通管5连接;Embodiment: a tunnel face blasting construction system, its structure as shown in Figures 1, 3, 4 and 5: comprising a projection device 1 and a benchmark device 2, the projection device 1 and the benchmark device 2 are connected through a connecting pipe 5;
所述投影装置1包括投影支架16,投影支架16上分别设有投影机12、定位罗盘13和水准泡15,所述投影机12被调节旋钮14调节投射方向,投影机具有投影灯9;The projection device 1 includes a projection bracket 16, on which a projector 12, a positioning compass 13 and a vial 15 are respectively arranged, and the projection direction of the projector 12 is adjusted by an adjustment knob 14, and the projector has a projection lamp 9;
在投影机12的前方设有炮眼模板10,炮眼模板10上具有设计炮孔。A blasthole template 10 is provided in front of the projector 12, and the blasthole template 10 has a designed blasthole.
连通管5可以选择连通器软管。The connecting pipe 5 can be selected as a connecting hose.
所述标杆装置2包括标杆支架,标杆支架上设有圆棱镜17和水准泡19。标杆支架由主支架20和辅助支架18组成,二者配合实现高度的调节。The benchmarking device 2 includes a benchmarking bracket on which a circular prism 17 and a vial 19 are arranged. The benchmark support is made up of main support 20 and auxiliary support 18, and the two cooperate to realize the adjustment of height.
参考图2所示,本实用新型还提供了一种利用上述施工系统来确定炮眼位置的方法,具体为:Referring to Fig. 2, the utility model also provides a method for determining the position of the blast hole by using the above-mentioned construction system, specifically:
在隧道边墙与地面的交界面上确定三个边界点8,三个边界点8不能在同一条直线上;Determine three boundary points 8 on the interface between the tunnel side wall and the ground, and the three boundary points 8 cannot be on the same straight line;
然后,以三个边界点8为中心以大于隧道半径且小于直径的线段为半径画圆弧,使得三个圆弧两两相交;Then, take the three boundary points 8 as the center and draw a circular arc with a line segment larger than the tunnel radius and smaller than the diameter as the radius, so that the three circular arcs intersect in pairs;
连接隧道内部的两对圆弧6所得的交点,所得的两条线段分别与确定点之间的连线相交,最终得到的两个中线点7均位于隧道中线上,将两个中线点7连接后,可以确定隧道中线4位置;The intersection points obtained by connecting the two pairs of arcs 6 inside the tunnel, the two obtained line segments respectively intersect with the connection line between the determined points, and the two centerline points 7 finally obtained are located on the tunnel centerline, and the two centerline points 7 are connected After that, the position of tunnel center line 4 can be determined;
在确定隧道中线位置的前提下,将投影装置1和标杆装置2调平布置于隧道中线上,观察连通管5内液面的高度,然后二者进行调节,使投影支架16的顶面及主支架20的顶面处在同一水平面上;On the premise of determining the position of the center line of the tunnel, the projection device 1 and the benchmark device 2 are leveled and arranged on the center line of the tunnel, and the height of the liquid level in the connecting pipe 5 is observed, and then the two are adjusted so that the top surface of the projection bracket 16 and the main The top surface of the bracket 20 is on the same horizontal plane;
利用投影机12自带的激光头,打出激光,令激光光束正中圆棱镜的靶心。完成该步骤的原因是:将激光束视为一条直线,隧道中心也视为一条直线,当激光束正中靶心时,激光束恰巧能与隧道中线构成一个平面,且将激光束的延长线与隧道中线的延长线无限延长以后,二者也无法相交,用来确保投影机12的投射反向极为接近设定投射方向。Utilize the laser head that projector 12 carries, hit laser, make the bull's-eye of the circular prism right in the center of the laser beam. The reason for completing this step is: the laser beam is regarded as a straight line, and the center of the tunnel is also regarded as a straight line. When the laser beam hits the target, the laser beam can just form a plane with the center line of the tunnel, and the extension line of the laser beam and the tunnel After the extension line of the center line is infinitely extended, the two cannot intersect, so as to ensure that the projection reverse of the projector 12 is very close to the set projection direction.
完成了上述步骤后,撤掉标杆装置2,打开投影灯9并装配好预先设计的炮眼模板10,则投影机12发出的光线经过炮眼模板10后,就呈放大状投射到了隧道掌子面11上。影像上炮孔的位置,就是设定炮孔3的最佳位置。After the above steps are completed, the benchmarking device 2 is removed, the projection lamp 9 is turned on and the pre-designed blasthole template 10 is assembled, then the light emitted by the projector 12 passes through the blasthole template 10 and is projected onto the tunnel face 11 in an enlarged form. superior. The position of the blasthole on the image is the best position to set the blasthole 3.
需要值得注意的是,当隧道为弧形隧道时,需要根据投影机12所在隧道位置以及隧道走向,适当调节投影机12的投射方向,来实现曲线爆破。It should be noted that, when the tunnel is a curved tunnel, it is necessary to properly adjust the projection direction of the projector 12 according to the position of the tunnel where the projector 12 is located and the direction of the tunnel to realize curved blasting.
采用了上述结构与方法后,本装置能够快速高效的实现设计炮眼位置的投射,通过精准的定位系统能够方便快捷的将炮眼布局定位于隧道掌子面,提高爆破质量。After adopting the above-mentioned structure and method, the device can quickly and efficiently realize the projection of the designed blasthole position, and through the precise positioning system, the blasthole layout can be conveniently and quickly positioned on the tunnel face to improve the blasting quality.
对所公开的实施例的上述说明,使本领域专业技术人员能够实现或使用本实用新型。对实施例的多种修改对本领域的专业技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本实用新型的精神或范围的情况下,在其它实施例中实现,未予以详细说明和局部放大呈现的部分,为现有技术,在此不进行赘述。因此,本实用新型将不会被限制于本文所示的这些实施例,而是要符合与本文所公开的原理和特点相一致的最宽的范围。The above description of the disclosed embodiments enables those skilled in the art to realize or use the utility model. Various modifications to the embodiments will be obvious to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present invention. The part that is described in detail and partially enlarged and presented is the prior art, and will not be repeated here. Therefore, the present invention will not be limited to these embodiments shown herein, but will conform to the widest scope consistent with the principles and characteristics disclosed herein.
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201521087038.3U CN205206826U (en) | 2015-12-23 | 2015-12-23 | Tunnel face blast construction system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201521087038.3U CN205206826U (en) | 2015-12-23 | 2015-12-23 | Tunnel face blast construction system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN205206826U true CN205206826U (en) | 2016-05-04 |
Family
ID=55844551
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201521087038.3U Expired - Fee Related CN205206826U (en) | 2015-12-23 | 2015-12-23 | Tunnel face blast construction system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN205206826U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105606001A (en) * | 2015-12-23 | 2016-05-25 | 山东大学 | Tunnel face blast working system and method |
-
2015
- 2015-12-23 CN CN201521087038.3U patent/CN205206826U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105606001A (en) * | 2015-12-23 | 2016-05-25 | 山东大学 | Tunnel face blast working system and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105606001B (en) | A kind of tunnel tunnel face blast working system and method | |
CN102322853B (en) | Tunnel over-under excavation control laser stakeout device | |
CN107843244A (en) | A kind of borehole punching positioner and localization method | |
CN107014361A (en) | A kind of tunnel/quick scatterplot positioner of tunnel face borehole and method | |
CN206694031U (en) | A kind of tunnel tunnel face blasthole location position device | |
CN201031704Y (en) | Tunnel wireless laser stakeout device | |
CN102849092B (en) | Visible positioning monitoring system of tunnel trolley | |
CN206740090U (en) | One kind is applied to linear pattern canal axes positioning measuring device | |
CN205206826U (en) | Tunnel face blast construction system | |
CN109184702B (en) | Measuring method for controlling overbreak and underbreak under multi-curve and small-radius conditions of tunnel engineering | |
CN205840894U (en) | A kind of tunnel confined concrete bow member mechanized construction quickly positions one-above-the-other layout | |
CN211576110U (en) | Auxiliary orientation device for correcting single-side station point cloud space orientation based on wire drawing point cloud | |
CN105971641B (en) | A kind of tunnel confined concrete arch mechanized construction quickly positions one-above-the-other layout | |
CN204478951U (en) | Tunnelling borehole positioner | |
CN203869661U (en) | Hanging pillar central position locating device used for overhead contact line equipment construction in tunnel | |
CN205037896U (en) | Line appearance is thrown to angle | |
CN104964675A (en) | Under-point laser centering device for measuring underground construction | |
CN204388845U (en) | The quick out break in a kind of tunnel measures laser cross section instrument | |
CN112032520A (en) | A full-section blast hole positioning device and method based on the principle of central projection | |
CN210108333U (en) | Vault settlement measurement device based on precision laser rangefinder | |
CN210719180U (en) | Alignment and alignment system for theodolite or total station | |
CN216246370U (en) | Tunnel excavation contour line laser positioning device | |
CN207832188U (en) | A kind of borehole punching positioning device | |
CN204457821U (en) | A kind of for construction of tunnel preliminary bracing anchor pole position scriber | |
CN206556654U (en) | A kind of portable quick position level indication laser device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160504 Termination date: 20191223 |