CN201031704Y - Tunnel wireless laser stakeout device - Google Patents
Tunnel wireless laser stakeout device Download PDFInfo
- Publication number
- CN201031704Y CN201031704Y CNU200720085004XU CN200720085004U CN201031704Y CN 201031704 Y CN201031704 Y CN 201031704Y CN U200720085004X U CNU200720085004X U CN U200720085004XU CN 200720085004 U CN200720085004 U CN 200720085004U CN 201031704 Y CN201031704 Y CN 201031704Y
- Authority
- CN
- China
- Prior art keywords
- total station
- laser
- tunnel
- stakeout
- section
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000004065 semiconductor Substances 0.000 claims abstract description 9
- 230000003287 optical effect Effects 0.000 claims description 7
- 238000009412 basement excavation Methods 0.000 abstract description 23
- 238000010276 construction Methods 0.000 abstract description 15
- 238000005422 blasting Methods 0.000 abstract description 11
- 238000005553 drilling Methods 0.000 abstract description 10
- 238000005259 measurement Methods 0.000 abstract description 6
- 238000000034 method Methods 0.000 abstract description 5
- 230000008569 process Effects 0.000 abstract description 4
- 238000005516 engineering process Methods 0.000 description 6
- 230000005540 biological transmission Effects 0.000 description 4
- 238000004891 communication Methods 0.000 description 4
- 230000004044 response Effects 0.000 description 3
- 230000008859 change Effects 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000002159 abnormal effect Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000001228 spectrum Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 230000005641 tunneling Effects 0.000 description 1
Images
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
本实用新型公开了一种隧道无线激光放样装置,该激光放样装置由计算机、伺服型电子全站仪、半导体激光器和无线通信器组成。计算机串行口与无线通信器连接,全站仪与无线通信器通过串行口连接,半导体激光器安装在全站仪的测距转动部分内部。系统在计算机软件控制下完成系统自身定位,隧道轴线数据、开挖断面和钻爆方案数据输入,断面测量,断面轮廓及炮孔定位放样的工作流程。该仪可自动地处理任意的曲线隧道、任意断面形态及钻爆方案,快速准确地利用激光束指示开挖,适用于包括隧道开挖在内的各类地下工程施工。
The utility model discloses a tunnel wireless laser setting out device, which is composed of a computer, a servo electronic total station, a semiconductor laser and a wireless communicator. The serial port of the computer is connected with the wireless communicator, the total station is connected with the wireless communicator through the serial port, and the semiconductor laser is installed inside the ranging rotating part of the total station. Under the control of computer software, the system completes the workflow of system self-positioning, tunnel axis data, excavation section and drilling and blasting plan data input, section measurement, section profile and blast hole positioning and setting out. The instrument can automatically process arbitrary curved tunnels, arbitrary cross-section shapes and drilling and blasting schemes, quickly and accurately use laser beams to indicate excavation, and is suitable for various underground engineering constructions including tunnel excavation.
Description
技术领域technical field
本实用新型涉及一种地下工程开挖激光放样装置,更具体涉及一种隧道无线激光放样装置,尤其是钻爆法隧道施工中开挖断面轮廓线和炮孔定位放样的激光放样装置。The utility model relates to a laser stakeout device for underground engineering excavation, in particular to a wireless laser stakeout device for tunnels, in particular to a laser stakeout device for excavation section outlines and blasthole positioning stakeouts in drilling and blasting tunnel construction.
背景技术Background technique
目前在地下洞库隧道网络的钻爆法施工中,开挖工作面的定位放样普遍处于人工仪器中线测量、钢尺定位炮孔的状态,费时费力,工作效率低,不能满足庞大的工程任务在时间上的紧迫要求,而且定位放样精度差,容易造成超欠挖,影响施工质量、进度和造价。At present, in the drilling and blasting construction of the underground cavern tunnel network, the positioning and setting out of the excavation working face is generally in the state of measuring the centerline of the manual instrument and positioning the blast hole with a steel ruler, which is time-consuming and laborious, and the work efficiency is low, which cannot meet the huge engineering tasks. Due to the urgent requirement of time, and the poor accuracy of positioning and lofting, it is easy to cause over- and under-excavation, which affects the construction quality, progress and cost.
利用激光投射进行放样施工是一种很好的解决方式。目前的激光投射放样技术中,激光指向仪是简单实用的一种,利用安置在隧道顶部和边墙上的激光器,发射和隧道中线重合或者平行的激光光束,从而定位隧道的中线位置。该技术具有价格低廉、结构简单、发射可见光,不占用隧道交通空间影响施工等特点,能指示隧道掘进的方向和坡度、标定隧道中线位置,但是该仪器仅能指示中线,不能定位轮廓线和炮孔,难以处理弯曲的隧道,使用中尚需人工来确定丈量每一个炮孔,工作量很大,且不够精确。The use of laser projection for lofting construction is a good solution. In the current laser projection lofting technology, the laser pointing device is a simple and practical one. It uses lasers placed on the top and side walls of the tunnel to emit laser beams that coincide with or parallel to the centerline of the tunnel to locate the centerline of the tunnel. This technology has the characteristics of low price, simple structure, visible light emission, and does not occupy tunnel traffic space to affect construction. It can indicate the direction and slope of tunnel excavation, and calibrate the position of tunnel centerline. holes, it is difficult to deal with curved tunnels, and it is still necessary to manually determine and measure each blast hole during use, which is a heavy workload and not accurate enough.
近来出现了一种能灵活地进行隧道断面激光放样的技术——激光透镜扫描投射放样技术,例如中国发明专利公开号CN1262378A于2000年8月9日公开的激光隧道断面放样仪。该技术是通过步进电机带动物镜平移,改变仪器内固定激光器的激光束出射方向进行扫描,实现激光点投射指示出断面轮廓和开挖断面上定位轮廓线和多个炮眼点的功能。这一类技术及相应的仪器在实际应用中存在一些不足之处:自身定位较为困难,需要测量仪器配合,难以自由设站,比如只能放在中桩点上,占用了隧道交通空间,影响隧道施工;处理曲线隧道不方便;由于物镜的相对口径有限,扫描范围和距离受一定限制,例如需要放样的隧道断面若较大,则放样仪必须远离开挖工作面。Recently, there has been a technology that can flexibly carry out laser stakeout of tunnel section—laser lens scanning projection stakeout technology, such as the laser tunnel section stakeout instrument disclosed on August 9, 2000 by Chinese invention patent publication number CN1262378A. This technology uses a stepping motor to drive the objective lens to translate, change the laser beam output direction of the fixed laser in the instrument for scanning, and realize the functions of laser point projection indicating the profile of the section and positioning the outline and multiple blasthole points on the excavation section. This type of technology and corresponding instruments have some disadvantages in practical application: self-positioning is difficult, requires the cooperation of measuring instruments, and it is difficult to freely set up stations. For example, it can only be placed on the middle pile point, which occupies the tunnel traffic space and affects Tunnel construction; it is inconvenient to deal with curved tunnels; due to the limited relative aperture of the objective lens, the scanning range and distance are limited to a certain extent.
发明内容Contents of the invention
本实用新型的目的是在于提供一种隧道无线隧道激光放样装置,该仪能实现在隧道和其它地下工程施工中快速地激光定位放样;在使用中可以让仪器自身简便地定位,且激光扫描放样范围不受放样位置和距离限制,不影响隧道施工交通,定位放样精度高,可以简便自动地处理任意的曲线隧道、任意断面形态及钻爆方案。The purpose of this utility model is to provide a wireless tunnel laser stakeout device for tunnels, which can realize rapid laser positioning and stakeout in tunnels and other underground engineering constructions; in use, the instrument itself can be easily positioned, and the laser scan stakeout The range is not limited by the stakeout position and distance, and does not affect the tunnel construction traffic. The positioning and stakeout accuracy is high, and it can easily and automatically handle any curved tunnel, any cross-section shape and drilling and blasting scheme.
为达到上述目的,本实用新型采用以下技术措施:该放样装置由计算机、伺服型电子全站仪、半导体激光器、串口无线通信器组成。计算机内装有控制软件,计算机的串行口和伺服型电子全站仪的串行口分别连接上串口无线通信器,两个串口无线通信器之间进行数据和控制信号的连接传输;半导体激光器安装在全站仪测量转动部件的内部,激光光束从全站仪测量转动部件上开孔投射出来。在计算机软件控制下,放样装置通过无线通信控制全站仪的测量进行自身定位,通过控制全站仪转动使得激光投射到隧道开挖工作面上,达到放样目的。计算机软件已进行软件著作权登记,软件名称为“隧道掘进自动定位系统”,软件著作权登记号2007SR01366。其工作流程如下:In order to achieve the above purpose, the utility model adopts the following technical measures: the stakeout device is composed of a computer, a servo electronic total station, a semiconductor laser, and a serial port wireless communicator. The computer is equipped with control software, the serial port of the computer and the serial port of the servo electronic total station are respectively connected to the serial wireless communicator, and the connection and transmission of data and control signals are carried out between the two serial wireless communicators; the semiconductor laser is installed Inside the measuring rotating part of the total station, the laser beam is projected from the opening on the rotating part of the total station measuring. Under the control of computer software, the stakeout device controls the measurement of the total station for self-positioning through wireless communication. By controlling the rotation of the total station, the laser is projected onto the tunnel excavation face to achieve the purpose of stakeout. The computer software has been registered for software copyright. The name of the software is "Tunneling Automatic Positioning System", and the software copyright registration number is 2007SR01366. Its workflow is as follows:
(1)系统初始化,即开启计算机、无线通信器、激光器和全站仪,使它们处于工作状态,并确定无线通信器和全站仪正常工作;(1) System initialization, that is, turn on the computer, wireless communicator, laser and total station, make them in working condition, and confirm that the wireless communicator and total station are working normally;
(2)用全站仪观测己知的后视点,系统自动计算自身位置(北、东和高程)和方位(北方向);(2) Use the total station to observe the known backsight point, and the system automatically calculates its own position (north, east and elevation) and azimuth (north direction);
(3)在图形化界面下输入整个隧道的轴线几何数据,断面的形态数据以及钻爆方案(断面炮孔设计方案),包括直线和圆弧曲线型的任意多段隧道,任意形状的开挖断面和炮孔位置;(3) Input the axial geometric data of the entire tunnel, the shape data of the section and the drilling and blasting scheme (section blasting hole design scheme) under the graphical interface, including any multi-section tunnels of straight line and arc curve type, and excavation sections of any shape and blasthole location;
(4)控制全站仪旋转、测量当前开挖工作断面的距离和测量点的角度,对比已经输入的隧道轴线三维数据,计算开挖断面轮廓的特征点(起拱点,顶点和边墙正负零点等)以及炮孔的三维坐标;(4) Control the rotation of the total station, measure the distance of the current excavation work section and the angle of the measurement point, compare the three-dimensional data of the tunnel axis that has been input, and calculate the feature points of the excavation section outline (arch point, apex and side wall normal negative zero point, etc.) and the three-dimensional coordinates of the blast hole;
(5)根据放样装置自身定位的数据,计算开挖断面轮廓的特征点及炮孔对应的全站仪旋转水平H角和垂直V角;控制全站仪旋转,使激光束投射到需要定位的轮廓线点和炮孔位置,指导操作人员标记、钻孔。(5) According to the positioning data of the lofting device itself, calculate the feature points of the excavation section contour and the horizontal H angle and vertical V angle of the total station rotation corresponding to the blast hole; control the rotation of the total station so that the laser beam is projected to the position to be positioned Contour line points and blasthole positions guide operators to mark and drill holes.
(6)放样全部完成后,输出放样的结果图形和记录。(6) After all the stakeouts are completed, output the graphics and records of the stakeout results.
本实用新型具有以下的优点和效果:①放样系统自身定位简便;由于采用了计算机软件分析,利用全站仪高精度测量已知点,可以快速地确定系统本身的三维坐标,操作简便,对曲线复杂的隧道放样十分有利;因此系统可以自由设站,在施工中可以将放样系统安装在边墙高处或顶部,不影响隧道内的施工车辆交通,节约施工时间。②采用的无线通信方案使放样系统可以安装在任意位置,降低了对隧道内交通的影响;同时使得工作人员可以远离危险区域进行操作,更为安全。③放样精度高,由于采用了全站仪作为系统测量和转动定位的机械主体,测角精度可以达到1秒及以上,由此计算,在400米处断面放样精度约可达1mm。④内置的激光器,不影响电子全站仪的功能,使得全站仪这一施工和测绘单位原有的设备可以照常使用,从这一角度讲激光放样系统的成本很低;同时可以360度大范围旋转,放样适应性强。⑤系统适应于复杂钻爆方案,放样速度快。在室内计算机软件上事先处理、存储隧道断面的钻爆方案,现场施工时以图形界面操作,简明、快捷,节约了施工时间。The utility model has the following advantages and effects: ①The positioning of the stakeout system is simple and convenient; due to the use of computer software analysis and the use of a total station to measure known points with high precision, the three-dimensional coordinates of the system itself can be quickly determined, and the operation is simple. Complex tunnel stakeout is very beneficial; therefore, the system can be freely set up, and the stakeout system can be installed on the high side or top of the side wall during construction, without affecting the construction vehicle traffic in the tunnel and saving construction time. ②The wireless communication scheme adopted enables the stakeout system to be installed in any position, which reduces the impact on the traffic in the tunnel; at the same time, the staff can operate away from the dangerous area, which is safer. ③The stakeout accuracy is high. Since the total station is used as the main body of the system for measurement and rotation positioning, the angle measurement accuracy can reach 1 second or more. Based on this calculation, the stakeout accuracy of the section at 400 meters can reach about 1mm. ④The built-in laser does not affect the function of the electronic total station, so that the original equipment of the total station, a construction and surveying unit, can be used as usual. From this point of view, the cost of the laser stakeout system is very low; The range is rotated, and the stakeout is highly adaptable. ⑤ The system is suitable for complex drilling and blasting schemes, and the stakeout speed is fast. The drilling and blasting scheme of the tunnel section is pre-processed and stored on the indoor computer software, and the on-site construction is operated with a graphical interface, which is concise and fast, and saves construction time.
附图说明Description of drawings
图1为一种隧道无线激光放样装置示意图。Fig. 1 is a schematic diagram of a tunnel wireless laser stakeout device.
图2为一种隧道无线激光放样装置软件功能流程图。Fig. 2 is a software function flowchart of a tunnel wireless laser stakeout device.
具体实施方式Detailed ways
下面结合附图对本实用新型作进一步详细的说明:Below in conjunction with accompanying drawing, the utility model is described in further detail:
如图1所示,系统由计算机1、全站仪2、半导体激光器3和无线通信器4和5组成。计算机1内装有控制软件,计算机1与无线通信器4通过串行口7连接,全站仪2与无线通信器5通过串行口8连接,无线通信器4和5为配套双向传送通信器,计算机1的控制信号和全站仪2的数据信号通过无线通信器4和5译码、传送。具体实施时,计算机采用具备串行口的便携机或台式机;全站仪采用伺服型电子全站仪,可选用的型号有Topcon800系列、光谱FOCUS10系列、Trimble5600系列等;无线通信器采用串口无线数传单元,可选用的型号有Intech便携端口HPS-120、捷易无线数据传输终端和力创LQ9200等;As shown in Figure 1, the system consists of a computer 1, a total station 2, a semiconductor laser 3 and wireless communicators 4 and 5. The computer 1 is equipped with control software, the computer 1 is connected with the wireless communicator 4 through the serial port 7, the total station 2 is connected with the wireless communicator 5 through the serial port 8, and the wireless communicators 4 and 5 are supporting two-way transmission communicators. The control signal of the computer 1 and the data signal of the total station 2 are decoded and transmitted through wireless communicators 4 and 5 . During the specific implementation, the computer adopts a portable or desktop computer with a serial port; the total station adopts a servo electronic total station, and the optional models include Topcon800 series, spectrum FOCUS10 series, Trimble5600 series, etc.; the wireless communicator adopts a serial port wireless Data transmission unit, available models include Intech portable port HPS-120, Jieyi wireless data transmission terminal and Lichuang LQ9200, etc.;
半导体激光器3安装在全站仪2的测距转动头6内部,激光器3光轴与全站仪2测量光轴平行,安装位置使得激光光束可以从全站仪2原有孔或者另行开孔投射出来,激光器3光轴调整到与全站仪2的测量光轴平行。半导体激光器采用红光(波长在650nm左右)或者绿光激光器(波长在532nm左右)、发散角小,体积适合于全站仪内置即可,激光器的功率根据使用的隧道空气透明程度进行选择,20~50mw一般可满足钻爆法开挖现场500米投射需求,可选用型号有GP461激光定靶器,HqL04激光镭射瞄准器等。The semiconductor laser 3 is installed inside the ranging head 6 of the total station 2, the optical axis of the laser 3 is parallel to the measuring optical axis of the total station 2, and the installation position enables the laser beam to be projected from the original hole of the total station 2 or an additional hole out, the optical axis of the laser 3 is adjusted to be parallel to the measuring optical axis of the total station 2 . The semiconductor laser adopts red light (wavelength around 650nm) or green light laser (wavelength around 532nm), small divergence angle, and the volume is suitable for built-in total station. The power of the laser is selected according to the transparency of the air in the tunnel used. 20 ~50mw can generally meet the 500-meter projection requirements of the drilling and blasting excavation site. The optional models include GP461 laser target fixer, HqL04 laser laser sight, etc.
激光放样系统是在计算机1控制下工作的,其具体过程根据图2说明如下,其步骤是:The laser stakeout system works under the control of computer 1, and its specific process is described as follows according to Figure 2, and its steps are:
(1)系统初始化9,即开启计算机1、无线通信器4与5、激光器3和全站仪2,使之处于工作状态,然后计算机向全站仪2发送无线应答请求10,以确定无线通信器4与5和全站仪2是否正常工作;软件判断全站仪是否正常应答11,如果正常应答,执行了旋转操作,则可进入下一步骤;如果软件没有接收到正常应答,则进入出错处理12,提示排除无线通信器或者全站仪的不正常工作状态;(1)
(2)用全站仪观测已知的后视点(北、东和高程数据已知),系统自动计算自身位置(北、东和高程)和方位(北方向)系统自身定位13;具体操作为,输入两个已知的后视点三维坐标(北、东和高程),将全站仪依次旋转对准两点,测量其角度,软件自动计算系统自身位置,即测量光心的坐标(北、东和高程),并得到相对坐标系的北方向,然后自动将方位角数据清零,转向北方向,完成放样装置的自身定位。(2) Observing the known backsight point (north, east and elevation data known) with the total station, the system automatically calculates its own position (north, east and elevation) and azimuth (north direction) system self-
(3)在图形化界面下输入隧道轴线数据14,输入断面数据与钻爆方案15(断面炮孔设计方案);具体操作为,以表格填写的方式输入隧道的起始点坐标、类型(包括直线和圆弧型)、坡度和长度参数,圆弧型隧道还要输入圆心、半径参数,表格可输入任意多段隧道;然后以图形操作方式绘制断面的二维形状,输入特征点和炮孔位置(X、Y),以及隧道轴线与开挖断面交点的相对坐标X0、Y0;(3) Input
(4)测量断面距离、角度16,测量当前开挖工作断面的距离和测量点角度。控制全站仪旋转、指向当前开挖工作断面,配合棱镜测量距离和测量点角度;软件自动基于已经输入的隧道轴线三维数据,计算得到开挖断面轮廓的特征点(起拱点,顶点和边墙正负零点等)以及炮孔的三维坐标;(4) Measure the section distance and
(5)计算轮廓线特征点和炮孔的全站仪旋转角17。软件根据系统自身定位的数据,计算开挖断面轮廓的特征点及炮孔对应的全站仪旋转水平H角和垂直V角;在图形界面鼠标控制下根据放样点顺序依次向全站仪发送全站仪旋转请求18,判断全站仪是否旋转正常并应答19,如果全站仪没有正常应答,则进入出错处理,提示排除硬件故障或者更改软件设置,如放样的时间间隔等;在无线通信和全站仪工作正常情况下,激光束即可正确指示需要定位的轮廓线点和炮孔位置,开挖操作人员可据此进行标记、钻孔,然后判断是否所有点都己放样完毕21,如果尚有放样点待处理,则返回步骤17,计算相关数据,否则进入放样完成输出图形记录22。(5) Calculate the
(6)放样完成输出图形记录22,放样全部完成,软件自动输出放样的结果,以图形形式输出放样的轮廓线和炮孔,可打印存档,提供数据文件记录。(6)
上面描述的是完整的放样装置操作流程,当隧道开挖断面不断向前推进时,放样装置本身没有移动的情况下,在操作上则可以跳过步骤13、14、15,确定放样装置正常工作后,直接测量新的开挖断面16,进行新一轮放样操作。The above describes the complete operation process of the stakeout device. When the tunnel excavation section is constantly advancing and the stakeout device itself does not move, steps 13, 14, and 15 can be skipped in operation to ensure that the stakeout device is working normally. Afterwards, the
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CNU200720085004XU CN201031704Y (en) | 2007-05-31 | 2007-05-31 | Tunnel wireless laser stakeout device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CNU200720085004XU CN201031704Y (en) | 2007-05-31 | 2007-05-31 | Tunnel wireless laser stakeout device |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN201031704Y true CN201031704Y (en) | 2008-03-05 |
Family
ID=39163596
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CNU200720085004XU Expired - Fee Related CN201031704Y (en) | 2007-05-31 | 2007-05-31 | Tunnel wireless laser stakeout device |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN201031704Y (en) |
Cited By (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101067375B (en) * | 2007-05-31 | 2010-05-19 | 中国科学院武汉岩土力学研究所 | Tunnel wireless laser stakeout device |
| CN102155230A (en) * | 2011-02-15 | 2011-08-17 | 龚晓斌 | Tunnel curve segment lofting method based on circle coordinates |
| CN102564393A (en) * | 2011-12-28 | 2012-07-11 | 北京工业大学 | Method for monitoring and measuring full section of tunnel through three-dimensional laser |
| CN103175510A (en) * | 2013-03-13 | 2013-06-26 | 华中科技大学 | Smart laser profiler automatic in leveling and direction adjustment |
| CN107655406A (en) * | 2017-09-13 | 2018-02-02 | 刘志方 | The monitoring device and its real-time detection method of a kind of bridge vibration deformation |
| CN107816981A (en) * | 2017-10-20 | 2018-03-20 | 中建三局第建设工程有限责任公司 | Tunnel intelligent construction survey setting out method based on BIM |
| CN108360475A (en) * | 2018-01-30 | 2018-08-03 | 中国葛洲坝集团第工程有限公司 | Navigation & Hydropower Junction Engineering bulb-type tubular hydro set runner body control device and method |
| CN108387221A (en) * | 2018-01-17 | 2018-08-10 | 西安理工大学 | A kind of tunnel excavation speedy lofting device and setting out method |
| CN108425677A (en) * | 2018-02-05 | 2018-08-21 | 济南力稳岩土工程有限公司 | A kind of monitoring drilling of Tunnel Overbreak & Underbreak applies method |
| CN110146057A (en) * | 2019-05-30 | 2019-08-20 | 中国五冶集团有限公司 | A Method for Detecting Tunnel Section |
-
2007
- 2007-05-31 CN CNU200720085004XU patent/CN201031704Y/en not_active Expired - Fee Related
Cited By (13)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101067375B (en) * | 2007-05-31 | 2010-05-19 | 中国科学院武汉岩土力学研究所 | Tunnel wireless laser stakeout device |
| CN102155230A (en) * | 2011-02-15 | 2011-08-17 | 龚晓斌 | Tunnel curve segment lofting method based on circle coordinates |
| CN102564393A (en) * | 2011-12-28 | 2012-07-11 | 北京工业大学 | Method for monitoring and measuring full section of tunnel through three-dimensional laser |
| CN103175510A (en) * | 2013-03-13 | 2013-06-26 | 华中科技大学 | Smart laser profiler automatic in leveling and direction adjustment |
| CN103175510B (en) * | 2013-03-13 | 2015-06-03 | 华中科技大学 | Smart laser profiler automatic in leveling and direction adjustment |
| CN107655406A (en) * | 2017-09-13 | 2018-02-02 | 刘志方 | The monitoring device and its real-time detection method of a kind of bridge vibration deformation |
| CN107816981A (en) * | 2017-10-20 | 2018-03-20 | 中建三局第建设工程有限责任公司 | Tunnel intelligent construction survey setting out method based on BIM |
| CN108387221A (en) * | 2018-01-17 | 2018-08-10 | 西安理工大学 | A kind of tunnel excavation speedy lofting device and setting out method |
| CN108360475A (en) * | 2018-01-30 | 2018-08-03 | 中国葛洲坝集团第工程有限公司 | Navigation & Hydropower Junction Engineering bulb-type tubular hydro set runner body control device and method |
| CN108360475B (en) * | 2018-01-30 | 2023-12-01 | 中国葛洲坝集团第一工程有限公司 | Flow passage shape control device and method for air-armature button through-flow unit |
| CN108425677A (en) * | 2018-02-05 | 2018-08-21 | 济南力稳岩土工程有限公司 | A kind of monitoring drilling of Tunnel Overbreak & Underbreak applies method |
| CN110146057A (en) * | 2019-05-30 | 2019-08-20 | 中国五冶集团有限公司 | A Method for Detecting Tunnel Section |
| CN110146057B (en) * | 2019-05-30 | 2022-06-24 | 中国五冶集团有限公司 | A method of detecting tunnel section |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN201031704Y (en) | Tunnel wireless laser stakeout device | |
| CN101067375B (en) | Tunnel wireless laser stakeout device | |
| CN102322853B (en) | Tunnel over-under excavation control laser stakeout device | |
| CN104536008B (en) | A Laser Range Measurement and Positioning Method for Blasting Hole of Rock Drilling Rig | |
| JP3418682B2 (en) | Integrated surveying system for tunnels | |
| CN104101326B (en) | A kind of shield attitude method for automatic measurement based on space geometry analysis and device | |
| CN109358353B (en) | Rapid pit-dividing lofting method for current collection circuit foundation | |
| CN103994752B (en) | Automatic measurement and guidance system and automatic measurement and guidance method related to pipe pushing construction | |
| CN108387221A (en) | A kind of tunnel excavation speedy lofting device and setting out method | |
| CN104776843A (en) | Boom-type roadheader body and cutting head pose detection method | |
| CN204007587U (en) | A kind of automatic measurement guidance system about jacking construction | |
| CN110530358A (en) | Car body navigation positional device and navigation system and method | |
| CN104729501A (en) | Rotating-sector-laser-based position and pose measurement method of cantilever excavator | |
| CN107449407A (en) | Automatic measurement guidance system and method for balancing earth-pressure shielding machine | |
| CN205537635U (en) | Simple and easy control survey system in long distance straight line push pipe center | |
| CN115898414A (en) | Control system and method for tunnel blasting blast hole | |
| CN115979209A (en) | Elevation measurement system and method | |
| CN202177380U (en) | Tunnel monitoring measurement point and TSP (Tunnel Seismic Predication) blast hole arranging device | |
| CN113503834A (en) | Measuring device for blast hole inclination angle | |
| CN110686656A (en) | Automatic measuring device and method for rectangular jacking pipe | |
| CN216246370U (en) | A laser positioning device for tunnel excavation contour lines | |
| CN117868843A (en) | Cantilever heading machine, super-undermining monitoring method and section design contour determining method | |
| CN205593520U (en) | Sectional device of rotation type laser survey tunnel two dimension | |
| JPH0446366B2 (en) | ||
| JPH07113640A (en) | Method and equipment for measuring attitude of excavator by laser distance measurement |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| C17 | Cessation of patent right | ||
| CF01 | Termination of patent right due to non-payment of annual fee |