CN205188982U - Removable system of strutting of rectangle work well - Google Patents
Removable system of strutting of rectangle work well Download PDFInfo
- Publication number
- CN205188982U CN205188982U CN201520991432.3U CN201520991432U CN205188982U CN 205188982 U CN205188982 U CN 205188982U CN 201520991432 U CN201520991432 U CN 201520991432U CN 205188982 U CN205188982 U CN 205188982U
- Authority
- CN
- China
- Prior art keywords
- steel
- support system
- steel pipe
- vertical steel
- rectangle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 86
- 239000010959 steel Substances 0.000 claims abstract description 86
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims 6
- 229910052742 iron Inorganic materials 0.000 claims 3
- 230000015572 biosynthetic process Effects 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 10
- 238000004064 recycling Methods 0.000 abstract 1
- 238000000034 method Methods 0.000 description 6
- 239000002689 soil Substances 0.000 description 5
- 238000010586 diagram Methods 0.000 description 3
- 238000009412 basement excavation Methods 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 239000012467 final product Substances 0.000 description 1
- 238000005457 optimization Methods 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 239000011378 shotcrete Substances 0.000 description 1
Landscapes
- Foundations (AREA)
Abstract
本实用新型公开了一种工作井的支护体系,属于顶管工程领域,具体涉及一种矩形工作井的可拆式支护体系,包括钢骨架;钢骨架呈长方体结构,长方体结构由多层矩形框通过垂直钢连接而成,每一层矩形框由四道横梁构成,横梁两端安装有连接角,连接角上下两端由垂直钢夹紧,垂直钢与垂直钢相互套接形成柱。本实用新型解决了现有支护体系空间利用率低,容易给施工带来不便等问题,可实现抗压抗剪以及沉降等理论要求,安全系数较高,同时施工周期短,投资小,可回收重复利用,空间利用率高。
The utility model discloses a support system for a working well, which belongs to the field of pipe jacking engineering, and in particular relates to a detachable support system for a rectangular working well, including a steel skeleton; The rectangular frame is connected by vertical steel. Each layer of rectangular frame is composed of four beams. The two ends of the beam are equipped with connecting angles. The upper and lower ends of the connecting angle are clamped by vertical steel. The utility model solves the problem of low space utilization rate of the existing support system, which is easy to bring inconvenience to the construction, and can realize the theoretical requirements of compressive resistance, shear resistance, and settlement, etc., has a high safety factor, and at the same time, the construction period is short and the investment is small. Recycling and reuse, high space utilization.
Description
技术领域technical field
本实用新型公开了一种工作井的支护体系,属于顶管工程领域,具体涉及一种矩形工作井的可拆式支护体系。The utility model discloses a support system for a working well, which belongs to the field of pipe jacking engineering, and in particular relates to a detachable support system for a rectangular working well.
背景技术Background technique
工作井一般是指在地质及水文条件、周围建筑环境以及地下管线较简单的场地内,开挖深度小于5米,或者地下结构三层以下的小基坑。工作井在顶管工程领域里至关重要,其支护的优化问题值得探讨与研究。目前工作井可采用地下连续墙、钢板桩、钻孔灌注桩、沉井、SMW工法和钢筋混凝土喷锚逆作法等作为围护结构。然而这些支护形式存在施工周期长、投资大、资源不可回收利用等不足,增加工程造价并影响施工进度。A working well generally refers to a small foundation pit with an excavation depth of less than 5 meters or an underground structure below the third floor in a site with relatively simple geological and hydrological conditions, surrounding building environment, and underground pipelines. The working well is very important in the field of pipe jacking engineering, and the optimization of its support is worthy of discussion and research. At present, the working well can use underground diaphragm wall, steel sheet pile, bored pile, caisson, SMW construction method and reinforced concrete shotcrete anchor reverse method as the enclosure structure. However, these support forms have shortcomings such as long construction period, large investment, and non-recyclable resources, which increase the project cost and affect the construction progress.
工作井现有的新型支护方式有小直径圆形可拆式基坑支护体系,虽然可重复回收利用,然而资料显示,工作井形状中矩形最为常见,且圆形支护体系空间利用率低。部分设计的小基坑支护体系虽然是矩形的,但是其为内撑式支护结构,空间利用率低,容易给施工带来不便。因此工作井现有的新型支护方式仍有待优化,需要设计更加合适的支护方案。The existing new support methods for working wells include small-diameter circular detachable foundation pit support systems. Although they can be recycled and reused, the data shows that rectangles are the most common shape in working wells, and the space utilization of circular support systems Low. Although some designed small foundation pit support systems are rectangular, they are internal support structures with low space utilization and may cause inconvenience to construction. Therefore, the existing new support methods of working wells still need to be optimized, and more suitable support schemes need to be designed.
实用新型内容Utility model content
为了克服工作井现有的新型支护方式技术的不足,本实用新型提供了一种矩形工作井的可拆式支护体系,该体系可实现抗压抗剪以及沉降等理论要求,安全系数较高,同时施工周期短,投资小,可回收重复利用,空间利用率高。In order to overcome the deficiencies of the existing new support methods for working wells, the utility model provides a detachable support system for rectangular working wells. At the same time, the construction period is short, the investment is small, it can be recycled and reused, and the space utilization rate is high.
本实用新型采用如下的技术方案实现:The utility model adopts following technical scheme to realize:
一种矩形工作井的可拆式支护体系,包括钢骨架;钢骨架呈长方体结构,长方体结构由多层矩形框通过垂直钢连接而成,每一层矩形框由四道横梁构成,横梁两端安装有连接角,连接角上下两端由垂直钢夹紧,垂直钢与垂直钢相互套接形成柱。横梁、连接角、垂直钢相互连接组成一个稳定的钢骨架,钢骨架支撑来自周围土的压力,提高工作井的空间利用率并保证施工过程的安全;钢骨架结构简单,容易组装和拆卸,施工周期短,效率高。A detachable support system for a rectangular working well, including a steel skeleton; the steel skeleton is a cuboid structure, and the cuboid structure is formed by connecting multiple layers of rectangular frames through vertical steel. Each layer of rectangular frames is composed of four beams, and the beams The end is equipped with a connection angle, and the upper and lower ends of the connection angle are clamped by vertical steel, and the vertical steel and vertical steel are socketed to form a column. Beams, connection angles, and vertical steel are interconnected to form a stable steel skeleton. The steel skeleton supports the pressure from the surrounding soil, improves the space utilization of the working well and ensures the safety of the construction process; the steel skeleton structure is simple, easy to assemble and disassemble, and the construction The cycle is short and the efficiency is high.
所述横梁主体为工字钢,工字钢两端焊接有与工字钢断面一致的连接块,连接块上设置有固定孔,所述连接角两端设置有突出部分,突出部分设置有和连接块相对应的固定孔。采用工字钢,降低整个支护体系的重量,减少工人的劳动力,同时工字钢承载力较好,保证工作井的安全;采用螺栓通过固定孔将连接角和连接块紧密的连接起来,保证钢骨架的稳定。The main body of the crossbeam is I-beam, and the two ends of the I-beam are welded with connecting blocks consistent with the section of the I-beam. The connecting block is provided with fixing holes, and the two ends of the connecting angle are provided with protruding parts, and the protruding parts are provided with and Corresponding fixing holes of the connection block. The use of I-beams reduces the weight of the entire support system and reduces the labor force of workers. At the same time, the I-beams have a better bearing capacity and ensure the safety of the working well; bolts are used to connect the connection angle and the connection block tightly through the fixing holes to ensure The stability of the steel skeleton.
所述垂直钢分为三部分,分别是上钢管、中钢管、下钢管;中钢管较粗,上钢管插入到相邻垂直钢的下钢管内,所述连接角中部设置有与下钢管相对应的通孔。下钢管穿过连接角的通孔,插入到相邻垂直钢的上钢管内,依次连接,形成柱。The vertical steel is divided into three parts, namely the upper steel pipe, the middle steel pipe and the lower steel pipe; the middle steel pipe is relatively thick, and the upper steel pipe is inserted into the lower steel pipe of the adjacent vertical steel; through holes. The lower steel pipe passes through the through hole of the connecting angle, is inserted into the upper steel pipe of the adjacent vertical steel, and is connected in sequence to form a column.
所述的支护体系四个侧面均竖直安装有挡土木板,挡土木板呈条形状;所述横梁底端多处安装有支撑钢管。挡土木板能防止土进入到工作井;支撑钢管具有较高的抗弯强度,固定钢骨架于工作井井壁上,方便拆卸。Earth-retaining planks are vertically installed on four sides of the support system, and the earth-retaining planks are in the shape of strips; supporting steel pipes are installed at multiple places at the bottom of the beam. The soil retaining board can prevent soil from entering the working well; the supporting steel pipe has high bending strength, and the steel skeleton is fixed on the working well wall for easy disassembly.
本实用新型的优点是:The utility model has the advantages of:
该体系可实现抗压抗剪以及沉降等理论要求,安全系数较高,同时施工周期短,投资小,可回收重复利用,空间利用率高,符合发展需求。The system can meet the theoretical requirements of compressive shear resistance and settlement, and has a high safety factor. At the same time, the construction period is short, the investment is small, it can be recycled and reused, and the space utilization rate is high, which meets the development needs.
附图说明Description of drawings
下面结合附图和实施例对本实用新型作进一步说明。Below in conjunction with accompanying drawing and embodiment the utility model is further described.
图1是本实用新型剖面图;Fig. 1 is a sectional view of the utility model;
图2是本实用新型俯视图;Fig. 2 is a top view of the utility model;
图3是本实用新型横梁一端结构示意图;Fig. 3 is a structural schematic diagram of one end of the beam of the utility model;
图4是本实用新型工字钢截面图;Fig. 4 is a sectional view of the utility model I-beam;
图5是本实用新型连接角结构示意图;Fig. 5 is a structural schematic diagram of the connection angle of the utility model;
图6是本实用新型垂直钢结构示意图。Fig. 6 is a schematic diagram of the vertical steel structure of the utility model.
图中符号说明:1、横梁;1.1、工字钢;1.2、连接块;2、连接角;2.1、突出部分;2.2、通孔;2.3、固定孔;3、柱;3.1、垂直钢;3.1.1、上钢管;3.1.2、中钢管;3.1.3、下钢管;4、挡土木板;5、支撑钢管。Explanation of symbols in the figure: 1, beam; 1.1, I-beam; 1.2, connection block; 2, connection angle; 2.1, protruding part; 2.2, through hole; 2.3, fixing hole; 3, column; 3.1, vertical steel; 3.1 .1. Upper steel pipe; 3.1.2. Middle steel pipe; 3.1.3. Lower steel pipe; 4. Soil retaining board; 5. Supporting steel pipe.
具体实施方式detailed description
一种矩形工作井的可拆式支护体系,包括钢骨架;钢骨架呈长方体结构,长方体结构由多层矩形框通过垂直钢3.1连接而成,每一层矩形框由四道横梁1构成,横梁1两端安装有连接角2,连接角2上下两端由垂直钢3.1夹紧,垂直钢3.1与垂直钢3.1相互套接形成柱。A detachable support system for a rectangular working well, including a steel skeleton; the steel skeleton is a cuboid structure, and the cuboid structure is formed by connecting multiple layers of rectangular frames through vertical steel 3.1, and each layer of rectangular frames is composed of four beams 1, The two ends of the crossbeam 1 are equipped with connection angles 2, and the upper and lower ends of the connection angle 2 are clamped by vertical steel 3.1, and the vertical steel 3.1 and the vertical steel 3.1 are nested to form a column.
所述横梁1主体为工字钢1.1,工字钢1.1两端焊接有与工字钢1.1断面一致的连接块1.2,在连接块1.2上设置有固定孔2.3。The main body of the beam 1 is an I-beam 1.1, and the two ends of the I-beam 1.1 are welded with a connecting block 1.2 consistent with the section of the I-beam 1.1, and a fixing hole 2.3 is arranged on the connecting block 1.2.
所述垂直钢3.1分为三部分,分别是上钢管3.1.1、中钢管3.1.2、下钢管3.1.3;中钢管3.1.2较粗,上钢管3.1.1插入到相邻垂直钢3.1的下钢管3.1.3内。The vertical steel pipe 3.1 is divided into three parts, namely the upper steel pipe 3.1.1, the middle steel pipe 3.1.2, and the lower steel pipe 3.1.3; the middle steel pipe 3.1.2 is relatively thick, and the upper steel pipe 3.1.1 is inserted into the adjacent vertical steel pipe 3.1 The lower steel pipe is within 3.1.3.
所述连接角2中部设置有与下钢管3.1.3相对应的通孔2.2,连接角2两端设置有突出部分2.1,突出部分2.1设置有和连接块1.2相对应的固定孔2.3。The middle part of the connection angle 2 is provided with a through hole 2.2 corresponding to the lower steel pipe 3.1.3, the two ends of the connection angle 2 are provided with a protruding part 2.1, and the protruding part 2.1 is provided with a fixing hole 2.3 corresponding to the connection block 1.2.
所述的支护体系四个侧面均竖直安装有挡土木板4,挡土木板4呈条形状。The four sides of the support system are all vertically equipped with earth retaining planks 4, and the earth retaining planks 4 are in the shape of strips.
所述横梁1底端多处安装有支撑钢管5。The bottom end of the beam 1 is provided with supporting steel pipes 5 at multiple places.
模具组装方案:Mold assembly scheme:
(1)按照图纸放线,选择好四个角,然后在四个角形成的矩形区域内开挖至0.5m;(1) Lay out the line according to the drawing, select the four corners, and then excavate to 0.5m in the rectangular area formed by the four corners;
(2)将连接角2套接在垂直钢3.1上,垂直钢3.1与垂直钢3.1套接形成柱3;将横梁1架在连接角2上,并用螺栓横向竖向校紧固定,形成多层矩形框,多层矩形框与柱组成高度为0.5m的钢骨架,调节钢骨架,将钢骨架安装于工作井内;(2) Connect the connecting angle 2 to the vertical steel 3.1, and the vertical steel 3.1 and the vertical steel 3.1 are socketed to form a column 3; set the beam 1 on the connecting angle 2, and use bolts to fix it horizontally and vertically to form a multi-layer Rectangular frame, multi-layer rectangular frame and columns form a steel frame with a height of 0.5m, adjust the steel frame, and install the steel frame in the working well;
(3)再向下开挖0.5m,使得钢骨架下沉,重复步骤(2),从钢骨架上端加高钢骨架;(3) Excavate 0.5m downwards to make the steel skeleton sink, repeat step (2), and increase the height of the steel skeleton from the upper end of the steel skeleton;
(4)重复步骤(2)、(3),直到工作井达到1.5m,在钢骨架外侧竖直安装挡土木板4,进行挡土;直到到达要求的深度,在横梁1底端打入支撑钢管5即可。(4) Repeat steps (2) and (3) until the working well reaches 1.5m, install the retaining board 4 vertically outside the steel frame to retain the soil; until the required depth is reached, drive the support at the bottom of the beam 1 Steel pipe 5 gets final product.
模具拆卸方案:Mold disassembly scheme:
(1)从最底层开始,将最底层的四根横梁1、连接角2、垂直钢3.1依次拆除并运送到地面,再将第二层横梁1、连接角2、垂直钢3.1依次拆除并运送到地面,拔出已拆的横梁1底端的支撑钢管5;(1) Starting from the bottom layer, remove and transport the bottom four beams 1, connection angle 2, and vertical steel 3.1 to the ground in sequence, and then remove and transport the second layer of beams 1, connection angle 2, and vertical steel 3.1 in sequence To the ground, pull out the supporting steel pipe 5 at the bottom of the dismantled beam 1;
(2)回填工作井至一个垂直钢3.1的高度,将挡土木板4从工作井外向上抽出一个垂直钢的高度;(2) Backfill the working well to the height of a vertical steel 3.1, and pull out the retaining plank 4 from the outside of the working well to a height of vertical steel;
(3)重复步骤(1)、(2),直至整个钢骨架被拆除,填埋并压实工作井。(3) Repeat steps (1) and (2) until the entire steel skeleton is removed, and the working well is filled and compacted.
最后应说明的是:显然,上述实施例仅仅是为清楚地说明本实用新型所作的举例,而并非对实施方式的限定。对于所属领域的普通技术人员来说,在上述说明的基础上还可以做出其它不同形式的变化或变动。这里无需也无法对所有的实施方式予以穷举。而由此所引伸出的显而易见的变化或变动仍处于本实用新型的保护范围之中。Finally, it should be noted that obviously, the above-mentioned embodiments are only examples for clearly illustrating the utility model, rather than limiting the implementation manner. For those of ordinary skill in the art, other changes or changes in different forms can be made on the basis of the above description. It is not necessary and impossible to exhaustively list all the implementation manners here. And the obvious changes or changes derived therefrom are still within the protection scope of the present utility model.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520991432.3U CN205188982U (en) | 2015-12-04 | 2015-12-04 | Removable system of strutting of rectangle work well |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201520991432.3U CN205188982U (en) | 2015-12-04 | 2015-12-04 | Removable system of strutting of rectangle work well |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN205188982U true CN205188982U (en) | 2016-04-27 |
Family
ID=55781984
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201520991432.3U Expired - Fee Related CN205188982U (en) | 2015-12-04 | 2015-12-04 | Removable system of strutting of rectangle work well |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN205188982U (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110593113A (en) * | 2019-09-26 | 2019-12-20 | 南昌大学 | A portable telescopic anti-compression and anti-bending bracket and installation method |
| CN112282764A (en) * | 2020-11-04 | 2021-01-29 | 西安市恒兴市政工程公司 | Rectangular circulating support working well and construction method thereof |
-
2015
- 2015-12-04 CN CN201520991432.3U patent/CN205188982U/en not_active Expired - Fee Related
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110593113A (en) * | 2019-09-26 | 2019-12-20 | 南昌大学 | A portable telescopic anti-compression and anti-bending bracket and installation method |
| CN110593113B (en) * | 2019-09-26 | 2024-03-29 | 南昌大学 | Portable telescopic compression-resistant bending-resistant bracket and installation method |
| CN112282764A (en) * | 2020-11-04 | 2021-01-29 | 西安市恒兴市政工程公司 | Rectangular circulating support working well and construction method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103696429B (en) | A kind of concrete of special-shaped foundation ditch supports the combined support system and the construction method that add fish belly sill | |
| CN102286980B (en) | Steel truss foundation pit supporting structure | |
| CN108278115A (en) | A kind of three step Rapid Construction of Tunnels method of big arch springing and structure based on pre-timbering with tubular prop | |
| CN103195085B (en) | Downward story-adding basement and construction method thereof | |
| CN105155549A (en) | Partition support system for large-area deep foundation pit under forward and backward working condition, and construction method thereof | |
| CN103790393B (en) | A kind of construction method of existing building structure integral replacement | |
| CN101775844A (en) | Connecting joint of ring beam of steel core concrete column used for topdown construction method foundation pit engineering | |
| CN203654294U (en) | Foundation pit supporting structure used in reverse building method | |
| CN110878555A (en) | Large-span underground space deep foundation pit supporting system and construction method | |
| CN201972155U (en) | Topdown-construction-method foundation pit supporting structure of steel plate pile | |
| CN104005414B (en) | Large-size rebar cast in place concrete pile supports the constructional method of column | |
| CN103122642A (en) | Construction method of vertical post support change | |
| CN210737607U (en) | A hang braced system for reverse construction method beam slab construction | |
| CN211312570U (en) | Can have enough to meet need formula steel open caisson supporting device | |
| CN202830936U (en) | Supporting structure of foundation pit | |
| CN207714348U (en) | A kind of deep basal pit fast rainfall device | |
| CN205296177U (en) | Dado bearing structure suitable for hole friction pile stake hole is dug in manual work | |
| CN106088105A (en) | A kind of assembled foundation ditch Bracing Systems | |
| CN205421332U (en) | Contrary coincide underground continuous wall that does of a core section of thick bamboo | |
| CN212175797U (en) | Large-span underground space deep foundation pit supporting system | |
| CN104594358A (en) | Sequential construction and reversed construction Clockwise and counter-clockwise combined construction method of irregular planar deep foundation pit | |
| CN205532716U (en) | Block structure of ore bin bottom | |
| CN100406652C (en) | Rigid steel structure tower crane foundation | |
| CN207714336U (en) | A kind of deep basal pit closing fast rainfall guard system | |
| CN202157328U (en) | Steel truss type foundation pit supporting structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160427 Termination date: 20161204 |