CN104005414B - Large-size rebar cast in place concrete pile supports the constructional method of column - Google Patents
Large-size rebar cast in place concrete pile supports the constructional method of column Download PDFInfo
- Publication number
- CN104005414B CN104005414B CN201410258350.8A CN201410258350A CN104005414B CN 104005414 B CN104005414 B CN 104005414B CN 201410258350 A CN201410258350 A CN 201410258350A CN 104005414 B CN104005414 B CN 104005414B
- Authority
- CN
- China
- Prior art keywords
- cast
- pile
- support
- column
- place pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 239000004567 concrete Substances 0.000 title claims abstract description 36
- 238000000034 method Methods 0.000 title claims description 7
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 79
- 239000010959 steel Substances 0.000 claims abstract description 79
- 230000002787 reinforcement Effects 0.000 claims abstract description 50
- 238000011065 in-situ storage Methods 0.000 claims abstract description 31
- 238000010276 construction Methods 0.000 claims abstract description 20
- 239000011150 reinforced concrete Substances 0.000 claims abstract description 20
- 239000010410 layer Substances 0.000 claims abstract description 12
- 238000005452 bending Methods 0.000 claims abstract description 7
- 239000011241 protective layer Substances 0.000 claims abstract description 6
- 238000009417 prefabrication Methods 0.000 claims abstract description 5
- 238000009412 basement excavation Methods 0.000 claims description 11
- 230000000694 effects Effects 0.000 claims description 4
- 238000003466 welding Methods 0.000 claims description 4
- 238000010586 diagram Methods 0.000 description 8
- 239000002689 soil Substances 0.000 description 4
- 239000011435 rock Substances 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000007667 floating Methods 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000010865 sewage Substances 0.000 description 1
- 239000002699 waste material Substances 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
一种大直径钢筋混凝土灌注桩支撑立柱的施工方法,(1)预制:根据桩身配筋要求预制钢筋笼;(2)施工:在现地面施工成孔至设计桩底持力层标高,再吊入预制的钢筋笼,灌注桩芯混凝土;(3)连接:灌注桩与首层砼支撑连接处,凿开灌注桩桩头,将灌注桩纵筋伸入支撑钢筋笼内30倍钢筋直径,再浇灌支撑混凝土,将灌注桩与首层支撑连接在一起;(4)防水:灌注桩立柱与地下室底板交汇处,凿开保护层,沿灌注桩周边设置上下两道膨胀止水条,并将灌注桩立柱整浇在地下室底板内,地下室结构完成后破除上部灌注桩立柱。本发明解决了常规的钢格构立柱承载力不足、截面抗弯抗扭能力较差、易被机械碰撞损坏而导致支撑体系失稳的问题。
A construction method for large-diameter reinforced concrete cast-in-situ piles supporting columns, (1) prefabrication: prefabrication of reinforcement cages according to the reinforcement requirements of the pile body; Lift into the prefabricated reinforcement cage and pour the pile core concrete; (3) Connection: at the joint between the cast-in-place pile and the first layer of concrete support, cut open the pile head of the cast-in-place pile, and extend the longitudinal reinforcement of the cast-in-place pile into the supporting reinforcement cage for 30 times the diameter of the steel bar. Then pour the supporting concrete, and connect the cast-in-place pile with the support of the first floor; (4) Waterproof: at the intersection of the cast-in-place pile column and the basement floor, cut out the protective layer, set up two expansion waterstops along the periphery of the cast-in-place pile, and The cast-in-place pile columns are poured in the basement floor, and the upper cast-in-place pile columns are removed after the basement structure is completed. The invention solves the problems of insufficient bearing capacity of the conventional steel lattice column, poor bending and torsion resistance of the cross-section, and easily damaged by mechanical collisions, resulting in instability of the supporting system.
Description
技术领域 technical field
本发明涉及灌注桩,尤其是大直径钢筋混凝土灌注桩支撑立柱的施工方法。 The invention relates to a cast-in-place pile, in particular to a construction method for a large-diameter reinforced concrete cast-in-situ pile supporting a column.
背景技术 Background technique
目前公知的基坑开挖内支撑体系立柱,是采用预制的型钢构件插入大直径钢筋混凝土灌注桩(直径1000或1200mm)中形成的钢格构立柱,灌注桩首先在地面施工成孔至设计桩底标高,下放钢筋笼,灌注混凝土至基坑底标高,再起吊预制型钢格构插入桩芯砼中不小于2000mm,或将预制的型钢格构与灌注桩下部的钢筋笼焊接后一同吊入桩孔中,然后浇灌混凝土至地下室底板底设计标高,上部回填砂,便于基坑开挖后剥出钢格构。钢格构通常采用4条通长等边角钢14#~20#(厚14~20mm)与4块520×250×12mm的缀板焊接而成,缀板竖向间距1000mm,钢格构立柱截面为正方形,边长600~800mm。内支撑与钢立柱连接处,将内支撑的纵筋从钢格构两侧或两块角钢中间的空隙穿过,如无法穿过的地方则将内支撑的纵筋焊接在角钢上,再浇灌混凝土形成整体。钢立柱穿过地下室底板的位置,采用止水钢板将钢格构包住,并将钢格构浇注在地下室底板里面,地下室结构施工完成后割除上部钢格构。其主要缺点是施工工艺较复杂,钢格构柱需在厂家由专业技术人员加工制作,长度过大时(超过15m),其竖直度控制和运输难度大,在桩孔内吊装定位误差较大;二是钢格构立柱造价高,特别是对多层(超过3层)大跨度支撑体系,其自重大,型钢规格和等级高,用量多且难以重复使用而造成浪费;三是竖向承重能力以及截面抗弯能力相对较弱,大跨度、多层支撑体系或梁上超载时超重,或支撑体系内因水平力传递产生较大的平面外变形,容易导致钢格构截面扭曲变形,影响支撑体系稳定安全。另外钢格构立柱受机械撞击能力较差,在基坑开挖过程中容易被大型挖土机械碰撞致损。 The currently known support system columns in foundation pit excavation are steel lattice columns formed by inserting prefabricated steel members into large-diameter reinforced concrete pouring piles (diameter 1000 or 1200mm). bottom elevation, lower the reinforcement cage, pour concrete to the elevation of the bottom of the foundation pit, then lift the prefabricated steel lattice and insert it into the pile core concrete for no less than 2000mm, or weld the prefabricated steel lattice and the reinforcement cage at the lower part of the cast-in-place pile and hoist them into the pile together Then pour concrete to the design elevation of the bottom of the basement floor, and backfill the upper part with sand to facilitate the stripping of the steel lattice after excavation of the foundation pit. The steel lattice structure is usually welded by 4 full-length equilateral angle steel 14#~20# (thickness 14~20mm) and 4 slabs of 520×250×12mm, the vertical spacing of the slabs is 1000mm, the section of the steel lattice column It is a square with a side length of 600~800mm. At the connection between the inner support and the steel column, pass the longitudinal reinforcement of the inner support through the gap between the two sides of the steel lattice or the gap between the two angle steels. If it cannot pass through, weld the longitudinal reinforcement of the inner support to the angle steel, and then pour Concrete forms a whole. Where the steel column passes through the basement floor, the steel lattice structure is wrapped with water-proof steel plates, and the steel lattice structure is poured into the basement floor. After the construction of the basement structure is completed, the upper steel lattice structure is cut off. Its main disadvantage is that the construction process is more complicated. The steel lattice column needs to be processed and manufactured by professional technicians in the factory. Large; second, the cost of steel lattice columns is high, especially for multi-layer (more than 3 layers) long-span support systems, which are self-heavy, high-grade steel specifications and grades, and use a large amount and are difficult to reuse, resulting in waste; the third is vertical The load-bearing capacity and cross-section bending resistance are relatively weak, and the large-span, multi-layer support system or beams are overloaded when overloaded, or the support system produces large out-of-plane deformation due to horizontal force transmission, which will easily lead to distortion and deformation of the steel lattice section. The support system is stable and safe. In addition, the steel lattice column has poor mechanical impact ability, and is easily damaged by large-scale excavation machinery during the excavation process of the foundation pit.
发明内容 Contents of the invention
本发明所要解决的技术问题是提供一种大直径钢筋混凝土灌注桩支撑立柱的施工方法,以解决目前钢立柱施工和使用过程存在的问题。 The technical problem to be solved by the present invention is to provide a construction method of a large-diameter reinforced concrete pouring pile supporting a column, so as to solve the problems existing in the construction and use of the steel column at present.
为解决上述技术问题,本发明的技术方案是:一种大直径钢筋混凝土灌注桩支撑立柱的施工方法,包括以下步骤: In order to solve the above-mentioned technical problems, the technical solution of the present invention is: a construction method of a large-diameter reinforced concrete cast-in-place pile supporting a column, comprising the following steps:
(1)预制:根据桩身配筋要求预制钢筋笼,预埋与支撑的连接钢筋,需提前在钢筋笼上相应位置绑扎焊接预埋钢筋; (1) Prefabrication: Prefabricate the reinforcement cage according to the reinforcement requirements of the pile body, and the pre-embedded and supported connecting steel bars need to be bound and welded on the corresponding position of the steel cage in advance;
(2)施工:整平场地,测量确定立柱桩位置后,在现地面施工成孔至设计桩底持力层标高,再吊入预制的钢筋笼,灌注桩芯混凝土;在灌注桩成孔以及钢筋笼吊入时必须严格控制垂直度,垂直度要求不大于1%,桩位偏差不得大于50mm; (2) Construction: After leveling the site, measuring and determining the position of the column piles, constructing holes on the existing ground to the design elevation of the bearing layer at the bottom of the piles, then hoisting into the prefabricated steel cage, pouring pile core concrete; forming holes in the pouring piles and The verticality must be strictly controlled when the reinforcement cage is hoisted in. The verticality is required to be no more than 1%, and the pile position deviation must not be greater than 50mm;
(3)连接:灌注桩与首层砼支撑梁连接处,凿开灌注桩桩头,将灌注桩纵筋伸入支撑钢筋笼内30倍钢筋直径,再浇灌支撑混凝土,将灌注桩与首层支撑梁连接在一起;当设置数层砼内支撑梁时,灌注桩与内支撑梁交汇的地方预埋一定数量的钢筋,预埋钢筋的型号与数量需满足截面抗剪验算,施工开挖时凿开灌注桩保护层混凝土,将预埋的钢筋伸入支撑钢筋笼内并与支撑纵筋连接,预埋筋进入支撑钢筋笼内的长度不小于30倍钢筋直径,并将内支撑梁与灌注桩立柱交界处混凝土凿毛,最后浇灌内支撑的混凝土,从而将内支撑梁与灌注桩立柱连接起来; (3) Connection: At the joint between the cast-in-place pile and the concrete support beam on the first floor, cut out the pile head of the cast-in-place pile, extend the longitudinal reinforcement of the cast-in-place pile into the supporting reinforcement cage 30 times the diameter of the steel bar, then pour the supporting concrete, and connect the cast-in-place pile to the first floor The support beams are connected together; when several layers of concrete inner support beams are set, a certain number of steel bars are pre-embedded at the intersection of the cast-in-situ piles and the inner support beams. Cut out the concrete of the protective layer of cast-in-place piles, extend the pre-embedded steel bars into the supporting steel cage and connect them with the supporting longitudinal bars. The concrete at the junction of the pile and column is chiseled, and finally the concrete for the inner support is poured, so as to connect the inner support beam with the cast-in-situ pile column;
(4)防水:灌注桩立柱与地下室底板交汇处,凿开保护层,沿灌注桩周边设置上下两道膨胀止水条,并将灌注桩立柱整浇在地下室底板内,地下室结构完成后破除上部灌注桩立柱,确保地下室底板的防水效果不受影响。 (4) Waterproof: At the junction of the cast-in-place pile column and the basement floor, cut out the protective layer, set up and down two expansion water-stop strips along the periphery of the cast-in-place pile, and pour the cast-in-place pile column into the basement floor, and remove the upper part after the basement structure is completed. Cast-in-situ piles are used to ensure that the waterproof effect of the basement floor is not affected.
作为改进,在预制钢筋笼前,需根据内支撑体系布设立柱,分别验算单根立柱需分担的内支撑体系自重、支撑轴力和上部超载形成的竖向压力和水平分力,再根据《建筑桩基技术规范(JGJ94-2008)》进行竖向和水平承载力验算,确定灌注桩的直径和有效嵌固深度,灌注桩直径选用600~1000mm;根据灌注桩立柱分担的水平分力计算桩身弯矩,从而确定灌注桩桩身配筋。 As an improvement, before the prefabricated steel cage, it is necessary to lay out the columns according to the internal support system, and check and calculate the self-weight of the internal support system, the supporting axial force and the vertical pressure and horizontal component force formed by the upper overload of a single column, and then according to the "Building Pile Foundation Technical Specifications (JGJ94-2008)" to check the vertical and horizontal bearing capacity, determine the diameter and effective embedding depth of the cast-in-place pile, and select the diameter of the cast-in-situ pile to be 600~1000mm; calculate the pile body according to the horizontal component force shared by the cast-in-situ pile column Bending moment, so as to determine the reinforcement of cast-in-place pile.
作为改进,步骤(3)中,预埋钢筋与支撑主筋的连接方式为焊接或绑扎连接。 As an improvement, in step (3), the connection between the pre-embedded reinforcement and the supporting main reinforcement is welding or binding.
作为改进,步骤(3)中,灌注桩与内支撑梁为双向或多向支撑交汇,在桩外侧设置矢径600~800mm钢筋混凝土圆环,以增强支撑节点整体刚度,圆环内配筋满足最小配筋率即可。 As an improvement, in step (3), the cast-in-place pile and the inner support beam are intersected by two-way or multi-directional support, and a reinforced concrete ring with a sagittal diameter of 600-800mm is set outside the pile to enhance the overall stiffness of the support node, and the reinforcement in the ring meets The minimum reinforcement ratio is sufficient.
作为改进,步骤(3)中,在内支撑梁与灌注桩立柱交界处可采用植筋的方式代替浇灌混凝土,植筋的型号与数量需满足截面抗剪验算,植筋进入灌注桩立柱和支撑钢筋笼内的长度不小于35倍钢筋直径,对多向支撑交点可设置圆环。 As an improvement, in step (3), planting reinforcement can be used instead of pouring concrete at the junction of the inner support beam and the cast-in-situ pile column. The length of the steel cage is not less than 35 times the diameter of the steel bar, and rings can be set at the intersection of multi-directional supports.
作为改进,若内支撑体系采用的是钢管支撑,则将预制的钢托架用膨胀螺栓钉在灌注桩桩身上,从而托住钢管支撑。 As an improvement, if the internal support system uses steel pipe support, the prefabricated steel bracket is nailed to the cast-in-place pile with expansion bolts to support the steel pipe support.
本发明与现有技术相比所带来的有益效果是: The beneficial effect brought by the present invention compared with prior art is:
1、采用大直径钢筋混凝土灌注桩做立柱,钢筋笼在施工现场制作,灌注桩成孔、钢筋笼安放和混凝土灌注施工工艺成熟,操作简单,质量可控; 1. Large-diameter reinforced concrete cast-in-place piles are used as columns, and the steel cages are manufactured at the construction site. The construction technology of cast-in-place piles forming holes, placing steel cages and pouring concrete is mature, and the operation is simple and the quality is controllable;
2、其竖向、水平承载能力和截面抗弯抗扭能力均大大提高,有效解决了钢立柱因竖向承载力不够或在较强水平力作用下扭曲变形导致支撑体系失稳的问题; 2. Its vertical and horizontal bearing capacity and cross-section bending and torsion resistance are greatly improved, which effectively solves the problem of instability of the support system caused by insufficient vertical bearing capacity or distortion and deformation of the steel column under the action of strong horizontal force;
3、大直径灌注桩立柱抗碰撞和抗侧向土压的能力远远高于角钢及缀板焊接而成的钢格构立柱,解决了钢立柱在基坑土方开挖过程中容易被大型机械碰撞致损的问题; 3. The anti-collision and lateral soil pressure resistance of the large-diameter cast-in-situ pile column is much higher than that of the steel lattice column welded by angle steel and patch plate, which solves the problem that the steel column is easily damaged by large machinery during the excavation of the foundation pit. The problem of collision damage;
4、采用大直径灌注桩做立柱,整体性和稳定性强,同时可兼做地下室抗浮桩,实现一桩二用,节约工程造价; 4. Large-diameter cast-in-situ piles are used as columns, which have strong integrity and stability. At the same time, they can also be used as anti-floating piles in the basement, realizing one pile for two purposes, and saving project cost;
5、采用大直径灌注桩做立柱,桩身竖向荷载主要由混凝土承担,桩身弯矩较小,配筋率低,相比钢格构立柱,钢材用量大大减少,单根立柱的造价大大减少,基坑越深降低投资造价的效果越明显,平均节约造价约20~50%; 5. Large-diameter cast-in-situ piles are used as columns. The vertical load of the pile body is mainly borne by concrete. The bending moment of the pile body is small and the reinforcement ratio is low. Compared with steel lattice columns, the amount of steel is greatly reduced, and the cost of a single column is greatly reduced. The deeper the foundation pit, the more obvious the effect of reducing the investment cost, and the average cost saving is about 20-50%;
6、对多向支撑节点,在灌注桩立柱周边设置矢径600~800mm钢筋混凝土圆环,将各支撑节点与立柱桩整浇在一起,有效提高支撑节点刚度和稳定性,特别是对大跨度环形支撑体系,大大提高支撑体系抵抗不均匀变形的能力,增强支撑安全度。 6. For multi-directional support nodes, set a reinforced concrete ring with a diameter of 600~800mm around the column of the cast-in-place pile, and pour each support node and column pile together to effectively improve the stiffness and stability of the support node, especially for large-span The ring-shaped support system greatly improves the ability of the support system to resist uneven deformation and enhances the safety of support.
附图说明 Description of drawings
图1为灌注桩立柱桩示意图。 Figure 1 is a schematic diagram of cast-in-place piles.
图2为灌注桩立柱桩身配筋示意图。 Figure 2 is a schematic diagram of reinforcement of the cast-in-situ pile column.
图3为灌注桩立柱与首层砼支撑梁连接示意图。 Figure 3 is a schematic diagram of the connection between the cast-in-situ pile column and the first-floor concrete support beam.
图4为灌注桩立柱与砼支撑梁在桩身处连接示意图(一)。 Figure 4 is a schematic diagram of the connection between the cast-in-situ pile column and the concrete support beam at the pile body (1).
图5为灌注桩立柱与砼支撑梁在桩身处连接示意图(二)。 Figure 5 is a schematic diagram of the connection between the cast-in-situ pile column and the concrete support beam at the pile body (2).
图6为灌注桩立柱周边钢筋混凝土圆环节点示意图。 Fig. 6 is a schematic diagram of the nodes of the reinforced concrete rings around the column of the cast-in-place pile.
图7为灌注桩立柱与钢管支撑托架连接示意图。 Figure 7 is a schematic diagram of the connection between the cast-in-situ pile column and the steel pipe support bracket.
图8为灌注桩立柱与地下室底板连接示意图。 Figure 8 is a schematic diagram of the connection between the cast-in-situ pile column and the basement floor.
图9为本发明工艺流程图。 Fig. 9 is a process flow chart of the present invention.
具体实施方式 detailed description
下面结合说明书附图对本发明作进一步说明。 The present invention will be further described below in conjunction with the accompanying drawings of the description.
一种大直径钢筋混凝土灌注桩支撑立柱的施工方法,如图9所示,包括以下步骤: A construction method for a large-diameter reinforced concrete pouring pile supporting a column, as shown in Figure 9, comprising the following steps:
(1)设计与计算:如图1、2所示,根据内支撑体系布设立柱,分别验算单根立柱需分担的内支撑体系自重、支撑轴力和上部超载形成的竖向压力和水平分力,再根据《建筑桩基技术规范(JGJ94-2008)》进行竖向和水平承载力验算,确定灌注桩的直径D和有效嵌固深度H,灌注桩直径D选用600~1000mm;根据灌注桩立柱分担的水平分力计算桩身弯矩,从而确定灌注桩桩身配筋,如灌注桩纵筋1、螺旋筋3和加劲箍2。 (1) Design and calculation: As shown in Figures 1 and 2, according to the arrangement of the vertical columns of the internal support system, the self-weight of the internal support system, the support axial force and the vertical pressure and horizontal component force formed by the upper overload to be shared by a single column are checked and calculated respectively. , and then check the vertical and horizontal bearing capacity according to the "Technical Specifications for Building Pile Foundations (JGJ94-2008)" to determine the diameter D and effective embedding depth H of the cast-in-place pile. The shared horizontal component force is used to calculate the pile body bending moment, so as to determine the pile body reinforcement of the cast-in-situ pile, such as the longitudinal reinforcement 1, the spiral reinforcement 3 and the stiffening hoop 2 of the cast-in-place pile.
(2)预制:根据桩身配筋要求预制钢筋笼,预埋与支撑的连接钢筋,需提前在钢筋笼上相应位置绑扎焊接预埋钢筋; (2) Prefabrication: Prefabricate the reinforcement cage according to the reinforcement requirements of the pile body, and the pre-embedded and supported connecting steel bars need to be bound and welded on the corresponding position of the steel cage in advance;
(3)施工:整平场地,测量确定立柱桩位置后,在现地面施工成孔至设计桩底持力层标高,再吊入预制的钢筋笼10,灌注桩芯混凝土;在灌注桩成孔以及钢筋笼10吊入时必须严格控制垂直度,垂直度要求不大于1%,桩位偏差不得大于50mm; (3) Construction: After leveling the site, measuring and determining the position of the column piles, constructing holes on the existing ground to the design elevation of the bearing layer at the bottom of the pile, then hoisting the prefabricated steel cage 10, pouring pile core concrete; forming holes in the pouring piles And the verticality must be strictly controlled when the reinforcement cage 10 is hoisted in, the verticality is required to be no more than 1%, and the pile position deviation must not be greater than 50mm;
(4)连接:如图3所示,灌注桩7与首层砼支撑梁4连接处,凿开灌注桩7桩头,将灌注桩纵筋1伸入支撑钢筋笼10内30D(D为钢筋直径),再浇灌支撑混凝土,将灌注桩7与首层支撑梁4连接在一起;如图4所示,当设置数层砼内支撑梁4时,灌注桩7与内支撑梁4交汇的地方预埋一定数量的钢筋,预埋钢筋的型号与数量需满足截面抗剪验算,施工开挖时凿开灌注桩保护层5混凝土,将预埋的钢筋伸入支撑钢筋笼10内并与支撑梁纵筋6连接,预埋钢筋与支撑梁纵筋6的连接方式为焊接或绑扎连接,预埋筋进入支撑钢筋笼10内的长度不小于30D(D为钢筋直径),且在35D(D为钢筋直径)范围内有接头的受力钢筋面积不大于总面积的50%;如为双向或多向支撑交汇,可在桩外侧设置矢径600~800mm钢筋混凝土圆环,以增强支撑节点整体刚度,圆环内配筋满足最小配筋率即可;将内支撑梁4与灌注桩立柱71交界处混凝土凿毛,最后浇灌内支撑梁4的混凝土,从而将内支撑梁4与灌注桩立柱71连接起来;如图5所示,也可采用在内支撑梁4与灌注桩立柱71交界处植筋13的方式代替浇灌混凝土,植筋13的型号与数量需满足截面抗剪验算,植筋13进入灌注桩立柱71和支撑钢筋笼10内的长度不小于35D(D为钢筋直径),对多向支撑交点可设置圆环;如图6所示,如为多向支撑,可加设钢筋混凝土环箍9; (4) Connection: As shown in Figure 3, at the joint between the cast-in-place pile 7 and the concrete support beam 4 on the first floor, the pile head of the cast-in-place pile 7 is cut open, and the longitudinal reinforcement 1 of the cast-in-place pile is inserted into the supporting reinforcement cage 10 for 30D (D is the steel bar diameter), then pour the supporting concrete, and connect the cast-in-situ pile 7 and the first-floor support beam 4 together; A certain number of steel bars are pre-embedded, and the type and quantity of the pre-embedded steel bars need to meet the cross-section shear check calculation. During the excavation, the concrete of the cast-in-place pile protection layer 5 is excavated, and the pre-embedded steel bars are inserted into the supporting steel cage 10 and connected with the supporting beam. The longitudinal reinforcement 6 is connected, the connection method between the pre-embedded reinforcement and the longitudinal reinforcement 6 of the support beam is welding or binding connection, the length of the pre-embedded reinforcement entering the support reinforcement cage 10 is not less than 30D (D is the diameter of the steel bar), and the length is 35D (D is The area of the stressed steel bar with joints within the scope of steel bar diameter) is not more than 50% of the total area; if it is a two-way or multi-directional support intersection, a reinforced concrete ring with a vector diameter of 600~800mm can be set outside the pile to enhance the overall rigidity of the support node , the reinforcement in the ring can meet the minimum reinforcement ratio; the concrete at the junction of the inner support beam 4 and the cast-in-situ pile column 71 is chiseled, and finally the concrete of the inner support beam 4 is poured, so that the inner support beam 4 and the cast-in-situ pile column 71 Connect; as shown in Figure 5, the mode of planting reinforcement 13 at the junction of inner support beam 4 and cast-in-situ pile column 71 can also be adopted instead of pouring concrete. The length entering the cast-in-place pile column 71 and the supporting reinforcement cage 10 is not less than 35D (D is the diameter of the steel bar), and a ring can be set at the intersection of multi-directional supports; as shown in Figure 6, if it is a multi-directional support, reinforced concrete can be added hoop 9;
如图7所示,若内支撑体系采用的是钢管支撑11,则将预制的钢托架用膨胀螺栓12钉在灌注桩桩71身上,从而托住钢管支撑; As shown in Figure 7, if the inner support system adopts the steel pipe support 11, the prefabricated steel bracket is nailed to the cast-in-place pile 71 with the expansion bolt 12, thereby supporting the steel pipe support;
(5)防水:如图8所示,灌注桩立柱71与地下室底板15交汇处,凿开保护层,沿灌注桩周边设置上下两道膨胀止水条14,并将灌注桩立柱71整浇在地下室底板15内,地下室结构完成后破除上部灌注桩立柱71,确保地下室底板15的防水效果不受影响。 (5) Waterproof: As shown in Figure 8, at the intersection of cast-in-place pile column 71 and basement floor 15, the protective layer is dug open, and two expansion water-stop strips 14 are set up and down along the periphery of the cast-in-place pile, and the cast-in-place pile column 71 is completely poured on the In the basement floor 15, after the basement structure is completed, the upper cast-in-situ pile column 71 is removed to ensure that the waterproof effect of the basement floor 15 is not affected.
实例 example
番禺石岗东地段开发项目位于广州市番禺区石岗东路,下设一~二层地下室,建筑±0.00相当于广州城建高程7.600m,基坑周长约660m,基坑开挖深度约6.4~10.2m。基坑挖深范围内依次揭露填土、淤泥、粉砂、可塑~坚硬的砂质粘性土等,基坑底主要位于流塑~软塑状淤泥(淤泥质土)层或粉砂层中,局部位于可塑~硬塑的砂质粘性土层。基坑周边临近市政主干道及管桩基础的6层住宅楼,分布有排污管、给水管、电缆沟等,根据基坑开挖深度及场地地质条件,本工程基坑支护主要采用桩撑支护形式,局部采用桩锚支护,一层地下室区域采用一道支撑,二层地下室区域采用二道支撑,外侧采用单排搅拌桩止水。由于基坑底淤泥层较为深厚,考虑到钢格构立柱稳定性差,为防止支撑体系失稳,支撑立柱均采用Φ1000大直径钢筋混凝土灌注桩作为立柱桩,第一道支撑与立柱桩在桩顶整浇连接,第二道支撑与立柱桩在桩身植筋连接。立柱桩进入强风化岩不小于8m或中微风化岩不小于3m,同时兼做地下室底板抗拔桩。目前该工程已竣工,立柱桩沉降较小,最大沉降量未超过5mm,开挖后支撑体系稳定,基坑累计变形量处于设计允许值范围,收到了良好的社会和经济效益。 Panyu Shigang East Lot Development Project is located on Shigang East Road, Panyu District, Guangzhou City, with basements on the first to second floors, the building ±0.00 is equivalent to the Guangzhou urban construction elevation of 7.600m, the perimeter of the foundation pit is about 660m, and the excavation depth of the foundation pit is about 6.4 ~10.2m. Within the excavation depth of the foundation pit, the filling soil, silt, silt, plastic to hard sandy cohesive soil, etc. are sequentially exposed. Partially located in plastic to hard plastic sandy cohesive soil layer. Around the foundation pit is a 6-storey residential building close to the municipal main road and pipe pile foundation. There are sewage pipes, water supply pipes, cable trenches, etc. According to the excavation depth of the foundation pit and the geological conditions of the site, the foundation pit support of this project is mainly supported by piles. The support form is partially supported by piles and anchors, one support is used in the basement area on the first floor, two supports are used in the basement area on the second floor, and a single row of mixing piles is used on the outside to stop water. Due to the relatively deep mud layer at the bottom of the foundation pit, considering the poor stability of the steel lattice columns, in order to prevent the support system from being unstable, the supporting columns are all made of Φ1000 large-diameter reinforced concrete pouring piles as the column piles. The whole pouring is connected, and the second support is connected with the column pile by planting reinforcement on the pile body. The column piles penetrate into the strongly weathered rock not less than 8m or the medium and slightly weathered rock not less than 3m, and also serve as the uplift piles of the basement floor. At present, the project has been completed, the settlement of the column piles is small, and the maximum settlement does not exceed 5mm. After excavation, the support system is stable, and the accumulated deformation of the foundation pit is within the design allowable range, which has received good social and economic benefits.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410258350.8A CN104005414B (en) | 2014-06-12 | 2014-06-12 | Large-size rebar cast in place concrete pile supports the constructional method of column |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410258350.8A CN104005414B (en) | 2014-06-12 | 2014-06-12 | Large-size rebar cast in place concrete pile supports the constructional method of column |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN104005414A CN104005414A (en) | 2014-08-27 |
| CN104005414B true CN104005414B (en) | 2016-06-08 |
Family
ID=51366303
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201410258350.8A Active CN104005414B (en) | 2014-06-12 | 2014-06-12 | Large-size rebar cast in place concrete pile supports the constructional method of column |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN104005414B (en) |
Families Citing this family (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105178292B (en) * | 2015-07-28 | 2017-03-08 | 济南轨道交通集团有限公司 | A kind of composite pile structure as tunneling garage column and its construction method |
| CN106087991B (en) * | 2016-06-17 | 2018-07-31 | 中国建筑第八工程局有限公司 | Stake top absolute altitude is in natural ground dug pile construction method below |
| CN108506018A (en) * | 2018-03-29 | 2018-09-07 | 中铁第六勘察设计院集团有限公司 | The new supporting structure and its construction method of duct pieces of shield tunnel opening |
| CN111535337B (en) * | 2020-06-03 | 2025-03-21 | 江苏东合南岩土科技股份有限公司 | Steel concrete column pile and its construction method |
| CN113186991B (en) * | 2021-05-25 | 2022-04-12 | 南京长江都市建筑设计股份有限公司 | Anti-floating structure and construction method thereof |
| CN117026992A (en) * | 2023-07-28 | 2023-11-10 | 中铁五局集团华南工程有限责任公司 | Connection structure of temporary concrete pile and support and construction method |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2009114662A (en) * | 2007-11-02 | 2009-05-28 | Kajima Corp | Concrete integrated structure pillar |
| KR20100062395A (en) * | 2008-12-02 | 2010-06-10 | 이동희 | Underground floor construction method using pre-concrete |
| CN102587406A (en) * | 2012-03-13 | 2012-07-18 | 中天建设集团有限公司 | Pouring construction method of concrete-filled tower crane foundation lattice column |
| CN102733395A (en) * | 2012-07-04 | 2012-10-17 | 江苏省华建建设股份有限公司 | Connecting method of supporting beam at second path or under second path and vertical column pile in deep foundation pit of basement of building engineering |
| CN103046542A (en) * | 2012-12-04 | 2013-04-17 | 中建三局建设工程股份有限公司 | Simultaneous construction technology for deep foundation pit inner support steel tube column and cast-in-place concrete pile |
-
2014
- 2014-06-12 CN CN201410258350.8A patent/CN104005414B/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2009114662A (en) * | 2007-11-02 | 2009-05-28 | Kajima Corp | Concrete integrated structure pillar |
| KR20100062395A (en) * | 2008-12-02 | 2010-06-10 | 이동희 | Underground floor construction method using pre-concrete |
| CN102587406A (en) * | 2012-03-13 | 2012-07-18 | 中天建设集团有限公司 | Pouring construction method of concrete-filled tower crane foundation lattice column |
| CN102733395A (en) * | 2012-07-04 | 2012-10-17 | 江苏省华建建设股份有限公司 | Connecting method of supporting beam at second path or under second path and vertical column pile in deep foundation pit of basement of building engineering |
| CN103046542A (en) * | 2012-12-04 | 2013-04-17 | 中建三局建设工程股份有限公司 | Simultaneous construction technology for deep foundation pit inner support steel tube column and cast-in-place concrete pile |
Also Published As
| Publication number | Publication date |
|---|---|
| CN104005414A (en) | 2014-08-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104264688B (en) | Manually digging hole non-uniform pile support construction process | |
| CN104453274B (en) | Method for supporting existing building underground with support structure and underpinning structure | |
| CN102434717B (en) | Construction method of joist steel pipe-jacking work pit | |
| CN107542108B (en) | A reverse construction method of a building basement structure | |
| CN104005414B (en) | Large-size rebar cast in place concrete pile supports the constructional method of column | |
| CN205742213U (en) | Foundation pit supporting construction | |
| CN101215834A (en) | Construction Method of Outrigger Type Diaphragm Wall | |
| CN102995659B (en) | Method for constructing from central area to periphery of ultra-large type underground engineering | |
| CN110080525B (en) | Bidirectional synchronous construction method for high-rise building | |
| CN105714831A (en) | Abnormal-shape double-row pile for supporting foundation pit side wall and construction method of abnormal-shape double-row pile | |
| CN108005399A (en) | Add the construction method for building multi-layer underground space under a kind of existing building group | |
| CN102864946B (en) | Process for supporting existing buildings through structural steel and horizontal rachel rod member and additionally adding multilayer basement | |
| CN110485431A (en) | A kind of interlocking pile combines foundation pit supporting construction with ground-connecting-wall | |
| CN108277996A (en) | The construction method of multi-storey basement is extended under a kind of protection groups of building | |
| CN111501771A (en) | Application method of multi-elliptical-ring combined support in deep large-sludge foundation pit engineering | |
| CN102286982A (en) | Deep foundation pit precast building enclosure for constructing in low environment | |
| CN112095626A (en) | Foundation pit supporting structure serving as corridor underpinning pile foundation and construction method thereof | |
| CN103510526A (en) | Foundation pit stepped supporting method with double-row piles combined with single-row piles | |
| CN209179021U (en) | A foundation pit row pile support system | |
| CN108385693B (en) | Equal-generation anchor bolt supporting method and system for staged basement supporting | |
| CN106065628A (en) | Based on the major diameter running water pipe security protection construction method forever facing the theory of combination | |
| CN102392417B (en) | Dual-cantilever bearing support structure for large steel pipe and installation method | |
| CN107338799A (en) | Large-span foundation pit support structure | |
| CN212270962U (en) | An integrated structure of foundation pit support and construction road | |
| CN205421332U (en) | Contrary coincide underground continuous wall that does of a core section of thick bamboo |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant |