CN103924797A - Country prefabricated steel structure residence system and construction method thereof - Google Patents

Country prefabricated steel structure residence system and construction method thereof Download PDF

Info

Publication number
CN103924797A
CN103924797A CN201410190647.5A CN201410190647A CN103924797A CN 103924797 A CN103924797 A CN 103924797A CN 201410190647 A CN201410190647 A CN 201410190647A CN 103924797 A CN103924797 A CN 103924797A
Authority
CN
China
Prior art keywords
steel
assembled unit
column
concrete column
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410190647.5A
Other languages
Chinese (zh)
Other versions
CN103924797B (en
Inventor
董有
赵恩平
鞠树森
潘沂华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Lvke Intelligent Manufacturing Industry Group Co.,Ltd.
Original Assignee
BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd filed Critical BEIJING AEIDO INTERNATIONAL ENGINEERING TECHNOLOGY Co Ltd
Priority to CN201410190647.5A priority Critical patent/CN103924797B/en
Publication of CN103924797A publication Critical patent/CN103924797A/en
Application granted granted Critical
Publication of CN103924797B publication Critical patent/CN103924797B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention relates to a country prefabricated steel structure residence system and a construction method of the country prefabricated steel structure residence system. The country prefabricated steel structure residence system comprises plane assembling units, stereoscopic assembling units, stair assembling units and independent component units. The plane assembling units comprise steel pipe concrete columns and H-steel beams forming rectangular frames, each stereoscopic assembling unit is defined by four plane assembling units, a herringbone support is arranged in at least one plane assembling unit in each stereoscopic assembling unit, and a light structure triangular roof truss is arranged on the top layer. Sleeves are welded to vertical connecting column joints at the lower ends of the steel pipe concrete columns, the sleeves are welded to the H-steel beams, and reinforcing plates are further arranged at the joint points where the steel pipe concrete columns and the H-steel beams are connected. Reinforced concrete foundation columns are connected to the bottoms of the steel pipe concrete columns on the first layer, and independent reinforced concrete foundations are further arranged at the bottoms of the reinforced concrete foundation columns. The system is convenient to assemble, short in using time and capable of being widely applied to rural residences and post-disaster reconstruction projects.

Description

Rural area assembling type steel structure dwelling house system and construction method
Technical field
The present invention relates to a kind of rural area assembling type steel structure dwelling house system and construction method, be particularly useful for the urgent engineering of post-disaster reconstruction equal time requirement, belong to earthquake relief work technical field.
Background technology
Along with scientific and technological high speed development, the continuous change of people's demand and life style, traditional residential structure pattern and residential conception are challenged, for the requirement of house, first be to guarantee to use safety, also have the development of livable property, economy and the industrialization of living.In China for a long time, traditional residential structure pattern is to take brick mix structure as main, and the main material of this structure is sintered clay brick, and the destruction farmland that it is serious, consumes the energy in a large number, poor seismic behavior, thereby completely forbidden and use gradually.Many, the Tall Steel reinforced Concrete Shear-wall Structure form of the general employing of Urban House now, industrialization level is not high, and a kind of replacement form is not more found in vast rural area.Therefore, in the time limit of safe handling, preserve the ecological environment to greatest extent guaranteeing, improve the space development efficiency on soil, unit, meet the housing construction that industrialization economic, practical, attractive in appearance, efficient requirement produces and be more applicable for society now.Along with grange, more and more focus on the aspect requirements such as safety, livable property, economic reliable, conservation of nature environment, speed of application, can predict, this assembling, be convenient to the dwelling house system that industrialization produces and there is very large development prospect.
Summary of the invention
Based on the problems referred to above, the present invention proposes a kind of rural area assembling type steel structure dwelling house system and construction method, the H girder steel composite construction system that it adopts square steel tube concrete column, supports with herringbone, and according to its prefabrication, site-assembled characteristic, its construction method has been proposed.The construction that has solved rural area tradition residence form destroys farmland, consumes ample resources, and anti-seismic performance can not get ensureing, and the problem of long construction period.
Technical scheme of the present invention is as follows:
A rural area assembling type steel structure dwelling house system, comprises the assembled unit of plane, three-dimensional assembled unit, the assembled unit of stair and independent component assembly unit; The assembled unit of described plane comprises steel core concrete column and the H girder steel that forms rectangular frame, four assembled unit of described plane surround the assembled unit of described solid, described at least one in the assembled unit of described solid, in the assembled unit of plane, be also provided with herringbone and support, described solid is also provided with shingle nail, roof panel and door and window in assembled unit; In the assembled unit of a plurality of described solids plane, by independent component assembly unit, be interconnected to one deck, and in this layer, the assembled unit of stair is connected with the assembled unit of described solid and independent component assembly unit; Each layer of upper and lower the interconnecting in the assembled unit of described solid and the assembled unit of stair is integral, and is provided with light section steel structure triangular roof truss described in top layer on three-dimensional assembled unit; Wherein, the vertical joint pin joint of described steel core concrete column lower end is welded with sleeve, sleeve and the welding of H girder steel, the Nodes that described steel core concrete column is connected with H girder steel is also provided with stiffener, one end that described herringbone supports is arranged on this stiffener, and the other end is arranged on the H girder steel on door and window top or is arranged on another stiffener being connected with top H girder steel middle part; First floor concrete filled steel tube column bottom is also connected with reinforced concrete foundation post, and described reinforced concrete foundation column bottom is also provided with independently reinforced concrete foundation.
Described first floor concrete filled steel tube column bottom is also extended and is provided with a steel concrete suspension column, between steel concrete suspension column and reinforced concrete foundation post, by suspension column backing plate and stone bolt, is connected.
Described steel core concrete column is square steel tube concrete column, and sectional dimension is 200mm * 200mm.
Described herringbone is supported for square steel pipe or round steel pipe herringbone supports.Particularly, square steel pipe herringbone supporting section is of a size of 120mm * 120mm.
Described H girder steel depth of section is 300mm~400mm.
On described sleeve, be welded with the junction plate that connects H girder steel and independent component assembly unit, and on junction plate, be provided with bolt hole.
The floor height of described dwelling house system is 2.8m~3m, and depth is 5.1m~5.4m, and the standard width of a room in an old-style house is 3.6m~4.2m, and the number of plies is 2~4 layers, and seismic fortification intensity is not more than 8 degree.
On described steel core concrete column, be also provided with injected hole and steam vent.
The construction method of above-mentioned rural area assembling type steel structure dwelling house system, adopts following steps:
Step 1: the assembled unit of prefabrication plane, independent component assembly unit and the assembled unit of stair; Injected hole and steam vent are set on steel core concrete column, according to the position of H girder steel, sleeve are welded on steel core concrete column, then H girder steel is welded on sleeve; On component assembly unit, bolt hole is being set separately;
Step 2: require location setting-out according to design drawing, at bottom, steel core concrete column position excavation ground, independently reinforced concrete foundation is set, at reinforced concrete foundation construction reinforced bar concrete foundation post, and in reinforced concrete foundation column top pre-buried suspension column backing plate and the stone bolt that is not less than 20mm;
Step 3: the steel concrete suspension column that extension is set in first floor concrete filled steel tube column bottom;
Step 4: all reach 70% when above until the concrete strength of reinforced concrete foundation and reinforced concrete foundation post, the assembled unit of plane of the first floor is installed and is surrounded the assembled unit of solid that forms the first floor, steel core concrete column is corresponding one by one by steel concrete suspension column with reinforced concrete foundation post, and be connected firmly by stone bolt;
Step 5: connect three-dimensional assembled unit and separately with bolts and be aided with and be welded to connect by junction plate between component assembly unit between each three-dimensional assembled unit by independent component assembly unit; The assembled unit of stair is connected with the assembled unit of described solid and independent component assembly unit;
Step 6: assembling each three-dimensional assembled unit of last layer plane, the assembled unit of stair and independent component assembly unit, between levels steel core concrete column, by sleeve, be welded to connect, complete the assembling of floor;
Step 7: cleaning concrete filled steel tube column wall, pouring steel core concrete column inner concrete;
Step 8: shingle nail is installed, roof panel and door and window;
Step 9: adopt light section steel structure triangular roof truss at top, it is supported on steel core concrete column.
Wherein, for post-disaster reconstruction engineering, because of very tight to construction period, do reinforced concrete foundation consuming time long, can make base steel plinth according to specific requirement.Described base steel plinth can be by supporting steel plate, the floor of putting more energy into, and the members such as basic steel column form, and can allow the victims of the disaster first live in peace and move in, then according to requirement for anticorrosion, base steel plinth be carried out to the measure of corrosion-resistant concrete protective.
The assembled unit of described plane, three-dimensional assembled unit and separately component assembly unit should be considered to be convenient to produce and building site is installed and is connected and transports, and also will guarantee livable being suitable for, and should form standardization, modularization, seriation, the applicable industrialization requirement that forms a complete production network.
Beneficial effect:
Advantage of the present invention is to adopt steel core concrete column and the supporting member of the H girder steel composite construction supporting with herringbone as house, this supporting member sectional dimension is less, member can be hidden in fender body completely, has guaranteed the building instructions for use of house, and the while is stressed and deformation performance is better.Filling concrete in steel pipe, steel tube confinement concrete distortion, delayed pressurized cracking, simultaneously in steel pipe, fill concrete has avoided steel pipe pressurized generation cripling to destroy, bi-material is given full play to advantage separately, and the bearing capacity of member is improved.Assembled by prefabricate assembled unit being carried out to building site, saved reinforcing bar binding, the operations such as building site concrete blinding installation, construct more convenient.Its basis can adopt independent reinforced concrete foundation or base steel plinth under frame column as required.
Because this assembled dwelling components adopts prefabrication, on-site consolidation, member is easy to connect, quick construction, has shortened construction period greatly, has saved peasant's construction cost, high-strength light, dwelling environment that anti-seismic performance is good are provided, have there is very strong sustainable developability.Can predict, along with the development of China's economy, technology and going deep into of steel house research, draw the low-rise steel residential structure that existing construction empirical studies is applicable to rural condition, in new rural residence ambient conditions, apply, particularly in post-disaster reconstruction, will there is significant economic benefit and social benefit.
Accompanying drawing explanation
Fig. 1 is that plan view is distinguished in the present invention assembled unit;
Fig. 2 is load-bearing skeleton front elevation view of the present invention;
Fig. 3 is load-bearing skeleton sectional drawing of the present invention;
Fig. 4 is reinforced concrete foundation plan view;
Fig. 5 is the A-A sectional drawing of Fig. 4.
In figure, 1: the assembled unit of plane; 2: three-dimensional assembled unit; 3: independent component assembly unit; 4: steel core concrete column; 5:H girder steel; 6: herringbone supports; 7: bolt; 8: sleeve; 9: welding position; 10: stone bolt; 11: steel tube concrete column feet; 12: reinforced concrete foundation post; 13: reinforced concrete foundation; 14: the assembled unit of stair; 15: door and window.
The specific embodiment
The specific embodiment of the present invention as Figure 1-5.
A kind of assembling rural area system of steel residential structure, referring to shown in Fig. 1 to Fig. 5, comprise the assembled unit 1 of plane, three-dimensional assembled unit 2, the assembled unit 14 of stair and separately component assembly unit 3, referring to Fig. 1, the assembled unit 1 of plane comprises steel core concrete column 4 and the H girder steel 5 that forms rectangular frame, four assembled unit 1 of described plane surround the assembled unit 2 of described solid, described at least one in the assembled unit 2 of described solid, in the assembled unit 1 of plane, be also provided with herringbone and support 6, and by steel core concrete column 4, H girder steel 5 and herringbone support 6 as supporting member, referring to Fig. 2, Fig. 3.Described square steel tube concrete column 4, H girder steel 5 and herringbone support the assembled unit 1 of plane of 6 these dwelling house systems of composition, as vertical, horizontal framework.The member of described assembled unit connects, and factory manufactures to adopt and is welded to connect, and the assembled common employing high-strength bolt 7 in building site, assembled unit connects to be aided with and is welded to connect.
In three-dimensional assembled unit 2, be also provided with shingle nail, roof panel and door and window; In the assembled unit of a plurality of solids 2 planes, by independent component assembly unit 3, be interconnected to one deck, and in this layer, the assembled unit 14 of stair is connected with three-dimensional assembled unit 2 and independent component assembly unit 3; Each layer of upper and lower the interconnecting in the assembled unit 2 of solid and the assembled unit 14 of stair is integral, and top layer is provided with light section steel structure triangular roof truss on three-dimensional assembled unit 2; Wherein, the vertical joint pin joint of described steel core concrete column 4 lower ends is welded with sleeve 8, sleeve 8 and 5 welding of H girder steel, the Nodes that steel core concrete column 4 is connected with H girder steel 5 is also provided with stiffener, herringbone supports one end of 6 and is arranged on this stiffener, and the other end is arranged on the H girder steel 5 on door and window top or is arranged on another stiffener being connected with H girder steel 5 middle parts, top; First floor steel core concrete column 4 bottoms are also connected with reinforced concrete foundation post 12, and reinforced concrete foundation post 12 bottoms are also provided with independently reinforced concrete foundation 13.Foundation columns goes out in face of ground to be designed to reinforced concrete foundation post 12, goes out after grade and should do being connected of steel core concrete column 4 and reinforced concrete foundation post 12 according to design, referring to Fig. 4, Fig. 5.For post-disaster reconstruction engineering, because of very tight to construction period, do reinforced concrete foundation 13 consuming time long, can make base steel plinth according to specific requirement.Wherein dwelling house system floor height 2.8, depth 5.1, the standard width of a room in an old-style house 3.6, the number of plies is 3 layers, the grade of providing fortification against earthquakes is 8 degree, and square steel tube concrete column 4 sectional dimensions are 200mm * 200mm, and H girder steel 5 depth of sections are 350mm, square steel pipe herringbone supports 6 sectional dimensions and is generally 120mm * 120mm, and thickness of section and concrete size are determined by designing and calculating; On described sleeve 8, be welded with as required and connect the junction plate of H girder steel 5 and independent component assembly unit 3 and bolt hole is set as required; Described steel core concrete column 4 should be noted, by the reserved injected hole of slip casting requirement and steam vent, avoiding occurring honeycomb hollowing phenomenon in pipe; First floor steel core concrete column 4 bottoms are also extended and are provided with a steel concrete suspension column 11, between steel concrete suspension column 11 and reinforced concrete foundation post 12, by suspension column backing plate and stone bolt 10, be connected, described steel core concrete column 4 was typically designed to and is articulated and connected with being connected of reinforced concrete foundation post 12, and need carry out the processing of steel tube concrete column feet 11.
The construction method of above-mentioned dwelling house system, specifically adopts following steps:
Step 1: the assembled unit 1 of prefabrication plane, independent component assembly unit 3 and the assembled unit 14 of stair; Injected hole and steam vent are set on steel core concrete column 4, according to the position of H girder steel 5, sleeve 8 are welded on steel core concrete column 4, then H girder steel 5 is welded on sleeve 8; Wherein, on sleeve 8, be welded with junction plate;
Step 2: require location setting-out according to design drawing, at steel core concrete column 4 bottom, position excavation grounds, independently reinforced concrete foundation 13 is set, at reinforced concrete foundation 13 construction reinforced bar concrete foundation posts 12, and at the reinforced concrete foundation post 12 pre-buried suspension column backing plates in top and the stone bolt 10 that is not less than 20mm;
Step 3: the steel concrete suspension column 11 that extension is set in first floor steel core concrete column 4 bottoms;
Step 4: all reach 70% when above until the concrete strength of reinforced concrete foundation 13 and reinforced concrete foundation post 12, the assembled unit 1 of plane of the first floor is installed and is surrounded the assembled unit 2 of solid that forms the first floor, steel core concrete column 4 is corresponding one by one by steel concrete suspension column 11 with reinforced concrete foundation post 12, and be connected firmly by stone bolt 10;
Step 5: between each three-dimensional assembled unit 2, by independent component assembly unit 3, connect, three-dimensional assembled unit 2 with separately between component assembly unit 3, by junction plate, adopt bolt 7 to be connected and to be aided with to be welded to connect; The assembled unit 14 of stair is connected with the assembled unit 2 of described solid and independent component assembly unit 3;
Step 6: assembling each three-dimensional assembled unit 2 of last layer plane, the assembled unit 14 of stair and independent component assembly unit 3, between levels steel core concrete column 4, by sleeve 8, be welded to connect, complete the assembling of floor;
Step 7: cleaning steel core concrete column 4 inwalls, pouring steel core concrete column 4 inner concretes;
Step 8: shingle nail is installed, roof panel and door and window;
Step 9: adopt light section steel structure triangular roof truss at top, it is supported on steel core concrete column 4.
Be more than a specific embodiment of the present invention, enforcement of the present invention is not limited to this.

Claims (10)

1. a rural area assembling type steel structure dwelling house system, is characterized in that: comprise the assembled unit of plane (1), three-dimensional assembled unit (2), the assembled unit of stair (14) and independent component assembly unit (3); The assembled unit of described plane (1) comprises steel core concrete column (4) and the H girder steel (5) that forms rectangular frame, four assembled unit of described plane (1) surround the assembled unit of described solid (2), described at least one in the assembled unit of described solid (2), in the assembled unit of plane (1), be also provided with herringbone and support (6), in the assembled unit of described solid (2), be also provided with shingle nail, roof panel and door and window; In the assembled unit of a plurality of described solids (2) plane, by independent component assembly unit (3), be interconnected to one deck, and in this layer, the assembled unit of stair (14) is connected with the assembled unit of described solid (2) and independent component assembly unit (3); Upper and lower the interconnecting in each layer of assembled unit of described solid (2) and the assembled unit of stair (14) is integral, and is provided with light section steel structure triangular roof truss described in top layer on three-dimensional assembled unit (2); Wherein, the vertical joint pin joint of described steel core concrete column (4) lower end is welded with sleeve (8), sleeve (8) and H girder steel (5) welding, described steel core concrete column (4) is also provided with stiffener with the Nodes that H girder steel (5) is connected, one end that described herringbone supports (6) is arranged on this stiffener, and the other end is arranged on the H girder steel (5) on door and window top and goes up or be arranged on another stiffener being connected with top H girder steel (5) middle part; First floor steel core concrete column (4) bottom is also connected with reinforced concrete foundation post (12), and described reinforced concrete foundation post (12) bottom is also provided with independently reinforced concrete foundation (13).
2. rural area according to claim 1 assembling type steel structure dwelling house system, it is characterized in that: described first floor steel core concrete column (4) bottom is also extended and is provided with a steel concrete suspension column (11), between steel concrete suspension column (11) and reinforced concrete foundation post (12), by suspension column backing plate and stone bolt (10), be connected.
3. rural area according to claim 1 assembling type steel structure dwelling house system, is characterized in that: described steel core concrete column (4) is square steel tube concrete column (4), and sectional dimension is 200mm * 200mm.
4. rural area according to claim 1 assembling type steel structure dwelling house system, is characterized in that: described herringbone supports (6) for square steel pipe or round steel pipe herringbone support (6).
5. rural area according to claim 4 assembling type steel structure dwelling house system, is characterized in that: it is 120mm * 120mm that square steel pipe herringbone supports (6) sectional dimension.
6. rural area according to claim 1 assembling type steel structure dwelling house system, is characterized in that: described H girder steel (5) depth of section is 300mm~400mm.
7. rural area according to claim 1 assembling type steel structure dwelling house system, is characterized in that: on described sleeve (8), be welded with the junction plate that connects H girder steel (5) and independent component assembly unit (3), and on junction plate, be provided with bolt hole.
8. rural area according to claim 1 assembling type steel structure dwelling house system, is characterized in that: the floor height of described dwelling house system is 2.8m~3m, and depth is 5.1m~5.4m, and the standard width of a room in an old-style house is 3.6m~4.2m, and the number of plies is 2~4 layers, and seismic fortification intensity is not more than 8 degree.
9. rural area according to claim 1 assembling type steel structure dwelling house system, is characterized in that: described steel core concrete column is also provided with injected hole and steam vent on (4).
10. according to a construction method for rural area assembling type steel structure dwelling house system described in claim 1-9 any one, it is characterized in that: adopt following steps:
Step 1: the assembled unit of prefabrication plane (1), independent component assembly unit (3) and the assembled unit of stair (14); On steel core concrete column (4), injected hole and steam vent are set, according to the position of H girder steel (5), sleeve (8) are welded to steel core concrete column (4) upper, then H girder steel (5) is welded on sleeve (8); Wherein, on sleeve (8), be welded with junction plate;
Step 2: require location setting-out according to design drawing, at steel core concrete column (4) bottom, position excavation ground, independently reinforced concrete foundation (13) is set, at reinforced concrete foundation (13) construction reinforced bar concrete foundation post (12), and at the pre-buried suspension column backing plate in reinforced concrete foundation post (12) top and the stone bolt (10) that is not less than 20mm;
Step 3: the steel concrete suspension column (11) that extension is set in first floor steel core concrete column (4) bottom;
Step 4: all reach 70% when above until the concrete strength of reinforced concrete foundation (13) and reinforced concrete foundation post (12), the assembled unit of plane (1) of the first floor is installed and is surrounded the assembled unit of solid (2) that forms the first floor, steel core concrete column (4) is corresponding one by one by steel concrete suspension column (11) with reinforced concrete foundation post (12), and be connected firmly by stone bolt (10);
Step 5: between each three-dimensional assembled unit (2), by independent component assembly unit (3), connect, three-dimensional assembled unit (2) with separately between component assembly unit (3), by junction plate, adopt bolt (7) to be connected and to be aided with to be welded to connect; The assembled unit of stair (14) is connected with the assembled unit of described solid (2) and independent component assembly unit (3);
Step 6: assembling each three-dimensional assembled unit (2) of last layer plane, the assembled unit of stair (14) and independent component assembly unit (3), between levels steel core concrete column (4), by sleeve (8), be welded to connect, complete the assembling of floor;
Step 7: cleaning steel core concrete column (4) inwall, pouring steel core concrete column (4) inner concrete;
Step 8: shingle nail is installed, roof panel and door and window;
Step 9: adopt light section steel structure triangular roof truss at top, it is supported on steel core concrete column (4).
CN201410190647.5A 2014-05-06 2014-05-06 Rural area assembling type steel structure dwelling house system and construction method Active CN103924797B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410190647.5A CN103924797B (en) 2014-05-06 2014-05-06 Rural area assembling type steel structure dwelling house system and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410190647.5A CN103924797B (en) 2014-05-06 2014-05-06 Rural area assembling type steel structure dwelling house system and construction method

Publications (2)

Publication Number Publication Date
CN103924797A true CN103924797A (en) 2014-07-16
CN103924797B CN103924797B (en) 2016-08-24

Family

ID=51143174

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410190647.5A Active CN103924797B (en) 2014-05-06 2014-05-06 Rural area assembling type steel structure dwelling house system and construction method

Country Status (1)

Country Link
CN (1) CN103924797B (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105649360A (en) * 2015-12-29 2016-06-08 山东远博建筑科技有限公司 Integral assembling type building system and installing method
CN105821965A (en) * 2016-05-20 2016-08-03 西安建筑科技大学 Multi-cavity concrete filled steel tube combination column supporting frame system installed in supported and inserted mode
CN105821959A (en) * 2016-05-20 2016-08-03 西安建筑科技大学 Multi-cavity concrete filled steel tube combination column supporting frame system assembled in supported and sliding mode
CN105839778A (en) * 2016-05-20 2016-08-10 西安建筑科技大学 Prefabricated beam column node single frame with side plate
CN106245768A (en) * 2016-08-30 2016-12-21 山东建筑大学 A kind of assembled low-rise buildings Special-Shaped Column hinged steel frame door shape supporting construction
CN106958291A (en) * 2017-05-16 2017-07-18 中国矿业大学(北京) A kind of assembled light steel frame crisscross joint and the practice
CN107034990A (en) * 2017-05-15 2017-08-11 中国地震局工程力学研究所 A kind of assembled light steel frame T-section point and the practice
CN107060090A (en) * 2017-05-15 2017-08-18 中国地震局工程力学研究所 A kind of assembled light steel frame L-shaped node and the practice
CN107119797A (en) * 2017-04-25 2017-09-01 天津大学 A kind of public building structural system with frame-shear wall and supporting construction
CN107217741A (en) * 2017-05-16 2017-09-29 中国矿业大学(北京) A kind of assembled light steel frame yi word pattern node and the practice
CN107354998A (en) * 2017-07-19 2017-11-17 姚攀峰 A kind of foundation-free node and its construction method
CN107762161A (en) * 2017-10-17 2018-03-06 新疆农业大学 A kind of energy-saving assembled system of steel residential structure and installation method
CN108104370A (en) * 2017-12-21 2018-06-01 中国恩菲工程技术有限公司 For the hinged column base of reinforced column and the construction method of reinforced column
CN108374489A (en) * 2018-05-04 2018-08-07 中国建筑股份有限公司 A kind of assembly concrete foot joint structure and its construction method
WO2019012427A1 (en) * 2017-07-11 2019-01-17 Nova Building Ltd Concrete building shoppable in small parts
CN110747993A (en) * 2019-11-13 2020-02-04 浙江东南网架股份有限公司 Steel tube fabric reinforced concrete member and construction method thereof
CN113089828A (en) * 2021-04-14 2021-07-09 泰州德添建设有限公司 Prefabricated house building and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0633516A (en) * 1992-07-10 1994-02-08 Maeda Corp Joint part structure of filling type steel pipe concrete column and pc beam and joining method therefor
CN202347870U (en) * 2011-12-16 2012-07-25 太原市耐安特钢结构建筑安装工程有限公司 Steel structure villa
CN102979161A (en) * 2012-09-26 2013-03-20 浙江杭萧钢构股份有限公司 Novel steel structure building system
CN203080965U (en) * 2012-11-27 2013-07-24 邵天星 Intelligent steel structure anti-seismic villa
CN203905531U (en) * 2014-05-06 2014-10-29 北京筑福国际工程技术有限责任公司 Rural assembled steel structure residence system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0633516A (en) * 1992-07-10 1994-02-08 Maeda Corp Joint part structure of filling type steel pipe concrete column and pc beam and joining method therefor
CN202347870U (en) * 2011-12-16 2012-07-25 太原市耐安特钢结构建筑安装工程有限公司 Steel structure villa
CN102979161A (en) * 2012-09-26 2013-03-20 浙江杭萧钢构股份有限公司 Novel steel structure building system
CN203080965U (en) * 2012-11-27 2013-07-24 邵天星 Intelligent steel structure anti-seismic villa
CN203905531U (en) * 2014-05-06 2014-10-29 北京筑福国际工程技术有限责任公司 Rural assembled steel structure residence system

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105649360A (en) * 2015-12-29 2016-06-08 山东远博建筑科技有限公司 Integral assembling type building system and installing method
CN105821965B (en) * 2016-05-20 2018-03-30 西安建筑科技大学 A kind of multi-cavity steel tube concrete coupled column support frame system for supporting insertion installation
CN105821965A (en) * 2016-05-20 2016-08-03 西安建筑科技大学 Multi-cavity concrete filled steel tube combination column supporting frame system installed in supported and inserted mode
CN105821959A (en) * 2016-05-20 2016-08-03 西安建筑科技大学 Multi-cavity concrete filled steel tube combination column supporting frame system assembled in supported and sliding mode
CN105839778A (en) * 2016-05-20 2016-08-10 西安建筑科技大学 Prefabricated beam column node single frame with side plate
CN105839778B (en) * 2016-05-20 2018-07-06 西安建筑科技大学 A kind of one Pin frames of prefabricated bean column node with side plate
CN106245768A (en) * 2016-08-30 2016-12-21 山东建筑大学 A kind of assembled low-rise buildings Special-Shaped Column hinged steel frame door shape supporting construction
CN107119797B (en) * 2017-04-25 2019-11-29 天津大学 A kind of public building structural system with frame-shear wall and support construction
CN107119797A (en) * 2017-04-25 2017-09-01 天津大学 A kind of public building structural system with frame-shear wall and supporting construction
CN107034990A (en) * 2017-05-15 2017-08-11 中国地震局工程力学研究所 A kind of assembled light steel frame T-section point and the practice
CN107060090A (en) * 2017-05-15 2017-08-18 中国地震局工程力学研究所 A kind of assembled light steel frame L-shaped node and the practice
CN107217741A (en) * 2017-05-16 2017-09-29 中国矿业大学(北京) A kind of assembled light steel frame yi word pattern node and the practice
CN106958291A (en) * 2017-05-16 2017-07-18 中国矿业大学(北京) A kind of assembled light steel frame crisscross joint and the practice
WO2019012427A1 (en) * 2017-07-11 2019-01-17 Nova Building Ltd Concrete building shoppable in small parts
CN107354998A (en) * 2017-07-19 2017-11-17 姚攀峰 A kind of foundation-free node and its construction method
CN107354998B (en) * 2017-07-19 2023-04-11 姚攀峰 Foundation-free joint and construction method thereof
CN107762161A (en) * 2017-10-17 2018-03-06 新疆农业大学 A kind of energy-saving assembled system of steel residential structure and installation method
CN107762161B (en) * 2017-10-17 2019-09-10 新疆农业大学 A kind of energy-saving assembled system of steel residential structure and installation method
CN108104370A (en) * 2017-12-21 2018-06-01 中国恩菲工程技术有限公司 For the hinged column base of reinforced column and the construction method of reinforced column
CN108374489A (en) * 2018-05-04 2018-08-07 中国建筑股份有限公司 A kind of assembly concrete foot joint structure and its construction method
CN108374489B (en) * 2018-05-04 2023-07-21 中国建筑股份有限公司 Assembled concrete column foot joint structure and construction method thereof
CN110747993A (en) * 2019-11-13 2020-02-04 浙江东南网架股份有限公司 Steel tube fabric reinforced concrete member and construction method thereof
CN110747993B (en) * 2019-11-13 2023-10-24 浙江东南网架股份有限公司 Steel pipe fabric reinforced concrete member and construction method thereof
CN113089828A (en) * 2021-04-14 2021-07-09 泰州德添建设有限公司 Prefabricated house building and construction method thereof
CN113089828B (en) * 2021-04-14 2022-04-01 泰州德添建设有限公司 Prefabricated house building and construction method thereof

Also Published As

Publication number Publication date
CN103924797B (en) 2016-08-24

Similar Documents

Publication Publication Date Title
CN103924797B (en) Rural area assembling type steel structure dwelling house system and construction method
CN102251607B (en) Reinforced concrete superposed wall joint connecting structure and construction method
CN107313517B (en) Connecting node for laminated wall and laminated floor slab in middle layer
CN101769008A (en) Method for constructing quake-proof masonry house by utilizing prefabricated constructional column ring beams
CN108301531B (en) Assembled built-in heat preservation concrete composite wall-light steel frame-floor slab connection node
CN103993679A (en) Bolt connecting joint structure of low-rise fabricated composite wall house
CN102561717A (en) Method for reinforcing brick-concrete structure by utilizing angle steel frame
CN109083308B (en) Anti-seismic prefabricated assembly type wall and construction method thereof
CN204252324U (en) Prefabricated steel construction integration assembling green building component with window opening or door opening
CN205875394U (en) Antidetonation concrete beam column that dry process is connected
CN113338451A (en) Assembly type structure adaptive to deformed steel pipe column and construction method thereof
CN103352537A (en) Integral load-bearing heat-insulating wall plate and production and construction technology thereof
CN104389363A (en) Prefabricated steel structure integrated assembly type green building component and preparation method thereof
CN106284644B (en) A kind of residential architecture structural system and its method of construction suitable for industrialized production
CN203905531U (en) Rural assembled steel structure residence system
CN103352584A (en) Externally covering strengthening method
CN108625491A (en) Assembled H profile steel column-isolated footing-concrete collar tie beam L-shaped connecting node
CN204252328U (en) A kind of Prefabricated steel construction integration assembling green building component
CN204252325U (en) A kind of in-line Prefabricated steel construction integration assembling green building component
CN204001705U (en) Outer wall of basement single surface formwork constructing structure based on earth anchor truss
CN107354998B (en) Foundation-free joint and construction method thereof
CN202202415U (en) Side node of rectangular steel pipe concrete special-shaped column and steel beam framework
Zhao Features and construction of prefabricated buildings
CN210264016U (en) Assembled antidetonation reinforced structure of brick concrete structure wall body
CN103469892A (en) Primary and secondary module unit combination structure of high-rise module building space and connection method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20180110

Address after: 102600, room 2, building 2212, pop Center, Xinghua street, Beijing, Daxing District

Patentee after: Beijing Yong Bo Science and Technology Ltd.

Address before: 100043 Shijingshan District, Yang Yang Street, No. 69, No. 1, building an international Park, Fu International

Patentee before: Beijing Aeido International Engineering Technology Co., Ltd.

TR01 Transfer of patent right
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: You Suncai

Inventor before: Dong You

Inventor before: Zhao Enping

Inventor before: Ju Shusen

Inventor before: Pan Yihua

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180202

Address after: 364299 No. 351, No. 351, Linjiang Town, Linjiang Town, Shanghang County, Fujian

Patentee after: Fujian greenke Construction Group Co., Ltd.

Address before: 102600, room 2, building 2212, pop Center, Xinghua street, Beijing, Daxing District

Patentee before: Beijing Yong Bo Science and Technology Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: No.13, Huangzhu Road, Nangang Industrial Zone, Lincheng Town, Shanghang County, Longyan City, Fujian Province 364299

Patentee after: Fujian Lvke Intelligent Manufacturing Industry Group Co.,Ltd.

Address before: 364299 4th floor, no.351, Beihuan Road, Linjiang Town, Shanghang County, Longyan City, Fujian Province

Patentee before: FUJIAN LVKE CONSTRUCTION GROUP Co.,Ltd.