CN205178381U - Erect off -load fixer of tower crane and dysprosium lamp cable perpendicularly - Google Patents

Erect off -load fixer of tower crane and dysprosium lamp cable perpendicularly Download PDF

Info

Publication number
CN205178381U
CN205178381U CN201520893740.2U CN201520893740U CN205178381U CN 205178381 U CN205178381 U CN 205178381U CN 201520893740 U CN201520893740 U CN 201520893740U CN 205178381 U CN205178381 U CN 205178381U
Authority
CN
China
Prior art keywords
component
tower crane
cable
socket joint
dysprosium lamp
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520893740.2U
Other languages
Chinese (zh)
Inventor
任铁铭
王圣军
刘�东
左宏亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
Original Assignee
China Construction First Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN201520893740.2U priority Critical patent/CN205178381U/en
Application granted granted Critical
Publication of CN205178381U publication Critical patent/CN205178381U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

The utility model discloses an erect off -load fixer of tower crane and dysprosium lamp cable perpendicularly, including first component, second component and split pin, be equipped with corresponding pinhole on first component and the second component respectively, the split pin is passed through the pinhole will first component and second component are fixed in the tower crane both sides, and the outer downside of second component is equipped with the fixation clamp that is used for fixed cable. The utility model discloses a split pin replaces screw and nut to fasten first member and second member, avoided screw and nut to get rusty after not quick detachable problem, lightened the intensity of labour when installing simultaneously. The utility model discloses simple structure is through the fixed cable of firm ground of the fixation clamp centre gripping on the second component to through -hole on the accessible fixation clamp further with the cable ligature on the fixation clamp, the off -load stable performance makes the cable reliably be connected with the consumer, the assurance consumer is normally worked, has ensured construction safety, and repeatedly usable.

Description

The off-load fixture of vertical erection tower crane and dysprosium lamp cable
Technical field
The utility model relates to the off-load fixture of a kind of vertical erection tower crane and dysprosium lamp cable.
Background technology
A lot of power consumption equipment is installed on the tower crane of construction, comprise hoisting equipment, as bridge motor, and lighting apparatus, as dysprosium lamp, these power consumption equipments need the power supply unit being connected to ground by cable, because cable exists larger deadweight, if be not fixed, long-time use is easy afterwards to come off from the power consumption equipment such as motor and dysprosium lamp.For this reason, need to adopt to be fixed cable by some way, removal cable, from heavy load, makes cable reliably be connected on power consumption equipment all the time.
At present, cable generally adopts screw and nut to be fixed on standard section of tower crane, and on the one hand, the time one is long, and through wind and weather, screw and nut corrosion seriously, are difficult to disassemble, can not recycle; On the other hand, its installation difficulty is also larger, and owing to being work high above the ground, the labour intensity of installation and danger are all very high.What is more, cable by means of only band or rope colligation on tower crane structural member, fixing very insecure, very easily come off from power consumption equipment under wind and weather and motor oscillating effect, cause the unexpected power-off of power consumption equipment, thus lighting apparatus has a power failure when causing the material of lifting from falling from high altitude or carry on construction work at night, potential safety hazard is huge, has a strong impact on normally carrying out of construction.
Utility model content
The purpose of this utility model adopts screw and nut to fix for solving current tower crane power consumption equipment cable, and installation difficulty is large, and easy corrosion causes difficult dismounting and can not reuse, or adopts simple side to prick fixing poor reliability, the technical problem that potential safety hazard is large.
In order to solve the problems of the technologies described above, the utility model provides the off-load fixture of a kind of vertical erection tower crane and dysprosium lamp cable, comprise the first component, second component and split pin, described first component and second component are respectively equipped with corresponding pin-and-hole, and described first component and second component are fixed on tower crane both sides by described pin-and-hole by described split pin.
Further, the outer downside of described second component is provided with the geometrical clamp for attached cable.
Further, described first component comprises an angle steel and two socket joint components, and one end of described two socket joint components is welded in angle steel both sides perpendicular to described angle steel respectively, and the pin-and-hole of described first component has two, lays respectively in the middle part of two socket joint components.
Further, described second component comprises a long angle steel, two socket joint components and two angle clips, one end of described two socket joint components is welded in long angle steel both sides perpendicular to described long angle steel respectively, the other end of described two socket joint components also welds together with described angle clip respectively perpendicular to described two angle clips respectively, the pin-and-hole of described second component has two, lays respectively at two socket joint member upper.
Further, described socket joint component is square tube or coating steel pipe.
Further, the outer downside of described long angle steel is provided with the geometrical clamp for attached cable.
Further, describedly fixedly accompany many, and evenly arrange.
Further, the through hole for banded cable is provided with in the middle part of described geometrical clamp.
Further, described pin-and-hole is circular, and diameter is 4mm.
The utility model adopts split pin to replace screw and nut to carry out fastening to the first component and second component, avoid screw and nut get rusty after not easily detachable problem, alleviate labour intensity during installation simultaneously.The utility model structure is simple, cable is gripped securely by the geometrical clamp on second component, and by the through hole on geometrical clamp further by cable tie on geometrical clamp, unloading performance is stablized, cable reliably can be connected with power consumption equipment, ensure that power consumption equipment normally works, ensured construction safety, and reusable.
Accompanying drawing explanation
Fig. 1 is the first element structure schematic diagram;
Fig. 2 is second component structural representation;
Fig. 3 is the structural representation that the first component and second component are assembled by split pin.
In figure: the first component 1; Angle steel 101; First component socket joint component 102; First component pin-and-hole 1021; Second component 2; Angle clip 201; Second component socket joint component 202; Second component pin-and-hole 2021; Long angle steel 203; Geometrical clamp 204; Geometrical clamp through hole 2041; Split pin 3.
Embodiment
By reference to the accompanying drawings the utility model is described in further detail now.These accompanying drawings are the schematic diagram of simplification, only basic structure of the present utility model are described in a schematic way, and therefore it only shows the formation relevant with the utility model.
As shown in Figure 1, the angle steel 101 of the first component 1 by level and two socket joint components 102 perpendicular to angle steel 101 are welded, two socket joint components 102 are welded on the two ends of angle steel 101 respectively, and the middle part of two socket joint components 102 is provided with the circular pin hole 1021 of diameter 4mm.Preferably, socket joint component 102 is square tube or coating steel pipe.
As shown in Figure 2, second component 2 by two levels angle clip 201, be welded perpendicular to two socket joint components 202 of two angle clips 201 and the long angle steel 203 of level respectively, one end of two socket joint components 202 is welded on one end of two angle clips 201 respectively, the other end of two socket joint components 202 is welded on the two ends of long angle steel 203 respectively, and the top of two socket joint components 202 is provided with the circular pin hole 2021 of diameter 4mm.The outer downside of long angle steel 203 is welded with three geometrical clamps 204 equably, is provided with through hole 2041 in the middle part of geometrical clamp 204.Preferably, socket joint component 202 is square tube or coating steel pipe.
As shown in Figure 3, first component 1 and second component 2 are fixed on the both sides of standard section of tower crane by pulling open afterbody after split pin 3 is each passed through pin-and-hole 1021 and 2021, length by adjustment split pin 3 adjusts the relative distance between the first component 1 and second component 2, thus the clamping degree of adjustment first component 1 and second component 2 pairs of standard section of tower cranes, the length of split pin 3 is shorter, holds tighter.After first component 1 is fixed on tower crane with second component 2, just cable clamping can be fixed in geometrical clamp 204, for strengthening the constant intensity of cable, thus removal cable deadweight further, also cable is helped on geometrical clamp 204 through the through hole 2041 on geometrical clamp 204 by available band.
With above-mentioned according to desirable embodiment of the present utility model for enlightenment, by above-mentioned description, relevant staff in the scope not departing from this utility model technological thought, can carry out various change and amendment completely.The technical scope of this utility model is not limited to the content on specification, must determine its technical scope according to right.

Claims (9)

1. the off-load fixture of vertical erection tower crane and dysprosium lamp cable, it is characterized in that, comprise the first component, second component and split pin, described first component and second component are respectively equipped with corresponding pin-and-hole, and described first component and second component are fixed on tower crane both sides by described pin-and-hole by described split pin.
2. the off-load fixture of vertical erection tower crane according to claim 1 and dysprosium lamp cable, is characterized in that, the outer downside of described second component is provided with the geometrical clamp for attached cable.
3. the off-load fixture of vertical erection tower crane according to claim 1 and dysprosium lamp cable, it is characterized in that, described first component comprises an angle steel and two socket joint components, one end of described two socket joint components is welded in angle steel both sides perpendicular to described angle steel respectively, the pin-and-hole of described first component has two, lays respectively in the middle part of two socket joint components.
4. the off-load fixture of vertical erection tower crane according to claim 1 and dysprosium lamp cable, it is characterized in that, described second component comprises a long angle steel, two socket joint components and two angle clips, one end of described two socket joint components is welded in long angle steel both sides perpendicular to described long angle steel respectively, the other end of described two socket joint components also welds together with described angle clip respectively perpendicular to described two angle clips respectively, the pin-and-hole of described second component has two, lays respectively at two socket joint member upper.
5. the vertical erection tower crane according to claim 3 or 4 and the off-load fixture of dysprosium lamp cable, it is characterized in that, described socket joint component is square tube or coating steel pipe.
6. the off-load fixture of vertical erection tower crane according to claim 4 and dysprosium lamp cable, is characterized in that, the outer downside of described long angle steel is provided with the geometrical clamp for attached cable.
7. the vertical erection tower crane according to claim 2 or 6 and the off-load fixture of dysprosium lamp cable, is characterized in that, describedly fixedly accompanies many, and evenly arrange.
8. the off-load fixture of vertical erection tower crane according to claim 7 and dysprosium lamp cable, is characterized in that, is provided with the through hole for banded cable in the middle part of described geometrical clamp.
9. the off-load fixture of vertical erection tower crane according to claim 1 and dysprosium lamp cable, is characterized in that, described pin-and-hole is circular, and diameter is 4mm.
CN201520893740.2U 2015-11-11 2015-11-11 Erect off -load fixer of tower crane and dysprosium lamp cable perpendicularly Expired - Fee Related CN205178381U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520893740.2U CN205178381U (en) 2015-11-11 2015-11-11 Erect off -load fixer of tower crane and dysprosium lamp cable perpendicularly

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520893740.2U CN205178381U (en) 2015-11-11 2015-11-11 Erect off -load fixer of tower crane and dysprosium lamp cable perpendicularly

Publications (1)

Publication Number Publication Date
CN205178381U true CN205178381U (en) 2016-04-20

Family

ID=55742319

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520893740.2U Expired - Fee Related CN205178381U (en) 2015-11-11 2015-11-11 Erect off -load fixer of tower crane and dysprosium lamp cable perpendicularly

Country Status (1)

Country Link
CN (1) CN205178381U (en)

Similar Documents

Publication Publication Date Title
CN205123185U (en) Non -maintaining insulator wire fixation clamp
CN102856838B (en) Tubular bus support insulator changing tool and method
CN104242152A (en) Lifting device for lifting overhead ground wire on straight concrete pole
CN105275253A (en) Equal-diameter rod erecting device and application method thereof
CN106499201A (en) A kind of dismountable safety rope tool-type holding clamp and its using method
CN202808179U (en) Hoisting clamp and hoisting clamp assembly
CN205178381U (en) Erect off -load fixer of tower crane and dysprosium lamp cable perpendicularly
CN202405695U (en) Lifting tool for overhead ground wire of steel pipe pole
CN204299162U (en) To encorbelment steel I-beam anchor structure
CN104098016A (en) Easy lifting bracket of transformer
CN204156436U (en) A kind of tower crane cable line fixture
CN203466505U (en) Device for vertically pulling cable
CN214755189U (en) Cable laying device suitable for trapezoidal crane span structure
CN203582268U (en) Clamp for unloading front-section column of steel structure on site
CN203699652U (en) Fastening-type steel wire rope sling
CN204609430U (en) Emergent repairing tower tractive hangs connection box
CN204096924U (en) Concrete pumping pipe connector anchor fitting
CN209868519U (en) Driving maintenance auxiliary device
CN203514921U (en) Electricity approaching stay wire replacing tool
CN202259718U (en) Movable-type grounding pile
CN203939815U (en) Be used in the suspension centre fixing device on emergency first-aid repair tower
CN203989576U (en) The high point of portable secured band suspension
CN216142439U (en) Steel construction box girder high altitude construction safety rope fixing device
CN216207615U (en) Lifting test platform for automatic device of distribution live working robot
CN205304104U (en) A anchor clamps for cable laying

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160420