CN204940328U CN201520522041.7U CN201520522041U CN204940328U CN 204940328 U CN204940328 U CN 204940328U CN 201520522041 U CN201520522041 U CN 201520522041U CN 204940328 U CN204940328 U CN 204940328U
Authority
CN
China
Prior art keywords
side plate
tie beam
collar tie
plate
mounted equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520522041.7U
Other languages
Chinese (zh)
Inventor
龚武良
黄有为
张雪峰
姚淼
彭平
柴琳
樊勇
周镇涛
袁立侠
何光军
吕为
谭卫成
赫哲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Power Supply Co ltd
Shenzhen Power Supply Planning Design Institute Co ltd
Original Assignee
Shenzhen Power Supply Co ltd
Shenzhen Power Supply Planning Design Institute Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Power Supply Co ltd, Shenzhen Power Supply Planning Design Institute Co ltd filed Critical Shenzhen Power Supply Co ltd
Priority to CN201520522041.7U priority Critical patent/CN204940328U/en
Application granted granted Critical
Publication of CN204940328U publication Critical patent/CN204940328U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Building Environments (AREA)

Abstract

The utility model provides an assembled equipment basis, including bottom plate, curb plate, circle roof beam, mounting and apron, the curb plate head and the tail concatenation and set firmly in the upper surface of bottom plate, the circle roof beam set firmly in the upper end of curb plate, it includes apron circle roof beam and the equipment circle roof beam of placing side by side, place at least one above the apron circle roof beam the apron, the mounting is used for carrying out fixed connection to adjacent curb plate, and its both ends link firmly with adjacent both sides board respectively. The utility model discloses assembled equipment basis is whole to be assembled by the prefab and is formed, and the construction is simple, swift, and the structure of assembled reduces field construction work load, reduction of erection time, practices thrift the human cost by a wide margin and is little to the influence of all ring edge borders, environmental protection, energy-conservation.

Description

A kind of mounted equipment basis
Technical field
The utility model relates to power engineering equipment technical field, particularly relates to the basis of a kind of installation, holding electrical equipment.
Background technology
Conventional electrical devices foundation construction mode mainly adopts brick or cast in situs mode, speed of application is slow, hand labor intensity is high, quality control is unstable, and the duration affects comparatively large by seasonal weather etc., finished surface is coarse, poor flatness, and construction period is large to traffic, ambient influnence, the raising required power engineering construction along with urban construction, the form of construction work on traditional electric fixtures basis can not meet urban construction requirement.
Utility model content
Technical problem to be solved in the utility model, be to provide a kind of construct simple, the duration is short, affect little mounted equipment basis to building site surrounding enviroment.
The utility model solves the problems of the technologies described above adopted technical scheme:
The utility model provides a kind of mounted equipment basis, comprise base plate, side plate, collar tie beam, fixture and cover plate, described side plate head and the tail splice and are fixedly arranged on the upper surface of described base plate, described collar tie beam is fixedly arranged on the upper end of described side plate, it comprises cover plate collar tie beam placed side by side and equipment collar tie beam, place at least one piece of described cover plate above described cover plate collar tie beam, described fixture is used for being fixed connection to adjacent side plate, and its two ends are connected with adjacent biside plate respectively.
As the further improvement of technique scheme, described side plate is connected by bolt and fixture, and described side plate has one for the first fixing hole of erection bolt, and the two ends correspondence of described fixture is respectively provided with one second fixing hole.
As the further improvement of technique scheme, the soffit of described collar tie beam is provided with some for the projection affixed with described side plate, and the upper end correspondence of described side plate is provided with the blind hole matched with described projection.
As the further improvement of technique scheme, described base plate is provided with a groove coincide with described side plate bottom shape, and described side plate is vertically inserted in described groove.
As the further improvement of technique scheme, the joint of described side plate and side plate is stepped interface.
As the further improvement of technique scheme, described in water-swellable adhesive tape is housed between the side plate that connects.
As the further improvement of technique scheme, two sides that described equipment collar tie beam is relative are provided with ventilation opening.
As the further improvement of technique scheme, described base plate, side plate, collar tie beam and cover plate are all concrete precast element.
The beneficial effects of the utility model are:
The utility model mounted equipment basis is all assembled by prefabricated component, and construction is simple, fast, and fabricated structure significantly reduces site operation workload, reduction of erection time, saving human cost and little on the impact of surrounding enviroment, environmental protection, energy-conservation.
Accompanying drawing explanation
Fig. 1 is the overall structure schematic diagram on the utility model mounted equipment basis;
Fig. 2 is the fractionation structural representation on the utility model mounted equipment basis;
Fig. 3 is the base plate on the utility model mounted equipment basis and the assembly structure schematic diagram of side plate;
Fig. 4 is the base plate on the utility model mounted equipment basis and the assembly structure schematic diagram of two blocks of side plates;
Fig. 5 is the schematic diagram that the fixture on the utility model mounted equipment basis has assembled with side plate;
Fig. 6 is the assembly structure schematic diagram of the cover plate collar tie beam on the utility model mounted equipment basis;
Fig. 7 is the assembly structure schematic diagram of the equipment collar tie beam on the utility model mounted equipment basis.
Detailed description of the invention
Be clearly and completely described below with reference to embodiment and the accompanying drawing technique effect to design of the present utility model, concrete structure and generation, to understand the purpose of this utility model, characteristic sum effect fully.Obviously; described embodiment is a part of embodiment of the present utility model, instead of whole embodiment, based on embodiment of the present utility model; other embodiments that those skilled in the art obtains under the prerequisite not paying creative work, all belong to the scope of the utility model protection.In addition, all connection/annexations related in patent, not singly refer to that component directly connects, and refer to and according to concrete performance, can connect auxiliary by adding or reducing, and form more excellent draw bail.Each technical characteristic in the utility model, can combination of interactions under the prerequisite of not conflicting conflict.
Please refer to Fig. 1 and Fig. 2, the utility model mounted equipment basis comprises: base plate 10, side plate 20, cover plate collar tie beam 30, equipment collar tie beam 40, cover plate 60 and fixture 50.Described base plate 10, side plate 20, cover plate collar tie beam 30, equipment collar tie beam 40, cover plate 60 are all by the prefabricated component of the materials such as steel concrete, composite material or steel according to certain size and intensity of load, factorial praluction, described fixture 50 be for installing, the angle steel of fixing each prefabricated component.
Base plate 10 is a rectangular slab, and it is provided with the groove 11 for side plate described in positioned vertical 20, and the width of groove 11 is identical with the width of side plate 20 or slightly wide.
Side plate 20 head and the tail splice and are fixedly arranged in the groove 11 of described base plate 10 upper surface, in the present embodiment, the joint of adjacent side plates 20 is stepped interface and the mode adopting mismatch to connect, namely from the cross section of interface, seam is broken line, and this connected mode makes the connection of adjacent side plates 20 more fastening and have certain waterproof action.In addition, in order to reach more excellent waterproof effect, preferably, water-swellable adhesive tape is folded with at adjacent side plate connecting sewing place.In the present embodiment, described side plate 20 is connected by bolt and fixture 50, and described side plate 20 has one for the first fixing hole 21 of erection bolt, and the two ends correspondence of described fixture is respectively provided with one second fixing hole 51.
Described cover plate collar tie beam 30 and equipment collar tie beam 40 are arranged side by side the upper end in described side plate 20, namely side plate 20 supports above-mentioned collar tie beam, the soffit of collar tie beam is all provided with some for the projection 41 affixed with described side plate 20, the upper end correspondence of described side plate is provided with and described protruding 41 blind holes matched 22, preferably, protruding 41 is reserved protrusion reinforcing bar, in various embodiments, also side plate 20 can be made to stretch out reinforcing bar, and collar tie beam reserves blind hole, also can reach in the present embodiment and coordinate spacing, fixing object.Described equipment collar tie beam 40 arranges ventilation opening 42 relative two sides, is convenient to heat radiation, anti-condensation.At least one piece of cover plate 60 is settled in the upper end of cover plate collar tie beam 30, and the quantity of cover plate 60 sets flexibly according to the area of cover plate collar tie beam 30, in the present embodiment, is preferably 5 pieces of cover plates 60.
Fig. 3 to Fig. 7 shows the installation process on the utility model mounted equipment basis, Fig. 3 is the base plate on the utility model mounted equipment basis and the assembly structure schematic diagram of side plate, Fig. 4 is the base plate on the utility model mounted equipment basis and the assembly structure schematic diagram of two blocks of side plates, Fig. 5 is the schematic diagram that the fixture on the utility model mounted equipment basis has assembled with side plate, Fig. 6 is the assembly structure schematic diagram of the cover plate collar tie beam on the utility model mounted equipment basis, and Fig. 7 is the assembly structure schematic diagram of the equipment collar tie beam on the utility model mounted equipment basis.
As shown in Figure 3, first according to the foundation ditch on plan excavation equipment basis, and lay stonework road cutting, compacting, levelling, prefabricated panel 10 is lain against bottom foundation ditch, is adjusted to level.
As shown in Figure 3 and Figure 4, vertically inserted in the groove 11 of base plate 10 by prefabricated side plate 20, adjacent side plates 20 is installed successively, is adjusted to vertical with base plate 10.
As shown in Figure 5, fixture 50 is adopted to be fixedly connected with by adjacent side plate 20.Side plate 20 joint is provided with the water-swellable adhesive tape (not drawing) for waterproof sealing.
As shown in Figure 6 and Figure 7, be placed in above side plate 20 by prefabricated collar tie beam (comprising cover plate collar tie beam 30 and equipment collar tie beam 40) level, bottom protrusion 41 is aimed at side plate 20 top blind hole 22 and is inserted, and guarantees that insertion puts in place, collar tie beam top level, adopt waterproof concrete to fill splicing seams again, guarantee waterproof.
Finally, prefabricated cover plate is lain against on cover plate collar tie beam, pit backfill stone flour outside work well, compaction in layers, recover road surface, above equipment hoisting to equipment collar tie beam, aim at erection bolt, fixing.
More than that better enforcement of the present utility model is illustrated, but the utility model is not limited to described embodiment, those of ordinary skill in the art also can make all equivalent variations or replacement under the prerequisite without prejudice to the utility model spirit, and these equivalent distortion or replacement are all included in the application's claim limited range.

Claims (8)

1. a mounted equipment basis, it is characterized in that: comprise base plate, side plate, collar tie beam, fixture and cover plate, described side plate head and the tail splice and are fixedly arranged on the upper surface of described base plate, described collar tie beam is fixedly arranged on the upper end of described side plate, it comprises cover plate collar tie beam placed side by side and equipment collar tie beam, place at least one piece of described cover plate above described cover plate collar tie beam, described fixture is used for being fixed connection to adjacent side plate, and its two ends are connected with adjacent biside plate respectively.
2. mounted equipment basis as claimed in claim 1, is characterized in that: described side plate is connected by bolt and fixture, and described side plate has one for the first fixing hole of erection bolt, and the two ends correspondence of described fixture is respectively provided with one second fixing hole.
3. mounted equipment basis as claimed in claim 1, is characterized in that: the soffit of described collar tie beam is provided with some for the projection affixed with described side plate, and the upper end correspondence of described side plate is provided with the blind hole matched with described projection.
4. mounted equipment basis as claimed in claim 1, is characterized in that: described base plate is provided with a groove coincide with described side plate bottom shape, and described side plate is vertically inserted in described groove.
5. mounted equipment basis as claimed in claim 1, is characterized in that: the joint of described side plate and side plate is stepped interface.
6. mounted equipment basis as claimed in claim 1, is characterized in that: described in water-swellable adhesive tape is housed between the side plate that connects.
7. mounted equipment basis as claimed in claim 1, is characterized in that: two sides that described equipment collar tie beam is relative are provided with ventilation opening.
8. mounted equipment basis as claimed in claim 1, is characterized in that: described base plate, side plate, collar tie beam and cover plate are all concrete precast element.
CN201520522041.7U 2015-07-17 2015-07-17 Assembled equipment foundation Active CN204940328U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520522041.7U CN204940328U (en) 2015-07-17 2015-07-17 Assembled equipment foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520522041.7U CN204940328U (en) 2015-07-17 2015-07-17 Assembled equipment foundation

Publications (1)

Publication Number Publication Date
CN204940328U true CN204940328U (en) 2016-01-06

Family

ID=55007770

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520522041.7U Active CN204940328U (en) 2015-07-17 2015-07-17 Assembled equipment foundation

Country Status (1)

Country Link
CN (1) CN204940328U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107142956A (en) * 2017-07-18 2017-09-08 王伟 A kind of prefabricated assembled elevator basis
CN109183830A (en) * 2018-07-22 2019-01-11 绿山高科建设科技有限公司 A kind of simple splice type prefabricated buildings structure and its building method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107142956A (en) * 2017-07-18 2017-09-08 王伟 A kind of prefabricated assembled elevator basis
CN109183830A (en) * 2018-07-22 2019-01-11 绿山高科建设科技有限公司 A kind of simple splice type prefabricated buildings structure and its building method

Similar Documents

Publication Publication Date Title
CN105064391A (en) Assembled equipment foundation
CN106759420B (en) A kind of prefabricated assembled transformer substation foundation structure
CN104389349B (en) The novel house can quickly remove, assembled and assemble method
CN202190047U (en) Fabricated steel ground cable channel
CN107476471A (en) One kind assembling combined type external wall system and its construction method
CN204940328U (en) Assembled equipment foundation
CN105369828A (en) Prefabricated assembly type cable working well
CN110424447A (en) A kind of assembled substation integration foundation structure and its construction method
CN110306396A (en) A kind of assembly concrete road surface and construction method
CN104863313A (en) Application structure of solar photovoltaic wall tiles on roof
CN104124913A (en) New solar roof integration power generation system
CN203905282U (en) Precast wall-panel and precast wall thereof
CN106436746A (en) Prefabricated box-type substation cement foundation
CN109025084B (en) Lighting skylight for civil air defense engineering and installation and application method thereof
CN218345839U (en) Construction access road capable of being circulated
CN206635786U (en) Prefabricated assembled transformer substation foundation structure
CN203284814U (en) Transformer substation prefabricated concrete water-scattering device
CN207144563U (en) A kind of assembled communication base station room
CN212452751U (en) Direct-rotating assembled retaining wall
CN204849827U (en) Prefabricated assembled cable worker well
CN205000360U (en) Basement structure with waterproof structure
CN208782449U (en) A kind of cable duct bank
CN106193685A (en) Prefabricated assembled communications equipment room structure
CN206143802U (en) Prefabricated formula box -type substation cement foundation
CN204920034U (en) A solar panel waterproof construction for villa roof

Legal Events